CN110672273B - Building outer wall and window limit infiltration testing arrangement for engineering supervision - Google Patents

Building outer wall and window limit infiltration testing arrangement for engineering supervision Download PDF

Info

Publication number
CN110672273B
CN110672273B CN201911112156.8A CN201911112156A CN110672273B CN 110672273 B CN110672273 B CN 110672273B CN 201911112156 A CN201911112156 A CN 201911112156A CN 110672273 B CN110672273 B CN 110672273B
Authority
CN
China
Prior art keywords
outlet pipe
pipe
water
water outlet
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911112156.8A
Other languages
Chinese (zh)
Other versions
CN110672273A (en
Inventor
陈磊
顾建清
邢轩
林伟珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Lida Construction Engineering Project Management Co ltd
Original Assignee
Guangdong Lida Construction Engineering Project Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Lida Construction Engineering Project Management Co ltd filed Critical Guangdong Lida Construction Engineering Project Management Co ltd
Priority to CN201911112156.8A priority Critical patent/CN110672273B/en
Publication of CN110672273A publication Critical patent/CN110672273A/en
Application granted granted Critical
Publication of CN110672273B publication Critical patent/CN110672273B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M3/00Investigating fluid-tightness of structures
    • G01M3/02Investigating fluid-tightness of structures by using fluid or vacuum

Abstract

The invention relates to the technical field of constructional engineering, in particular to a device for testing water seepage of an outer wall and a window edge of a building for engineering supervision, which has the technical scheme that: the spraying device comprises a water tank, wherein a water pump is arranged at the top of the water tank, a first water outlet pipe and a second water outlet pipe are arranged on the water pump, a first spraying pipe is arranged at one end of the second water outlet pipe, second spraying pipes are hinged to two side surfaces of the first spraying pipe, a plurality of spraying ports are formed in the first spraying pipe and each second spraying pipe, the first spraying pipe is communicated with one side of each second spraying pipe through a water guiding pipe, and the other end of each second spraying pipe is sealed; all be provided with the locating lever between second shower and each second outlet pipe, the one end and the second shower bottom of each locating lever are articulated, and the one end that the second shower was kept away from to each locating lever is provided with the slider, and the both sides of second outlet pipe all have the locating piece, and the locating piece is provided with the spout along the length direction of second outlet pipe, and each slider slides with corresponding spout and is connected.

Description

Building outer wall and window limit infiltration testing arrangement for engineering supervision
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a device for testing water seepage of an outer wall and a window edge of a building for engineering supervision.
Background
After building construction is completed, project supervision is needed to check and accept buildings, multiple performance tests of the buildings need to be developed in the checking and accepting process, water seepage tests of the wall surfaces and the window edges of the buildings are included in the multiple performance tests, if the water seepage tests of the outer walls and the window edges of the buildings are not carried out, water seepage can possibly occur to the walls and the window edges to the indoor due to quality reasons under heavy rainfall weather, property loss of owners is caused, and the water seepage tests of the outer walls and the window edges of the buildings are very necessary, so that a water seepage testing device for the outer walls and the window edges of the buildings for the project supervision is needed.
In the prior art, chinese patent with patent publication No. CN204439296U discloses a building outer wall and window side water seepage testing device for engineering supervision, which comprises a fixing piece, a water spraying pipe, a conduit, a switch, a water pump and a construction water source, wherein the water spraying pipe is fixed on a window top or a building outer wall by the fixing piece, the water spraying pipe is provided with a jet hole, the water spraying pipe is connected with the switch by the conduit, the switch is connected with a water outlet of the water pump by a connecting pipe, and a water inlet of the water pump is connected with the construction water source by a connecting pipe.
The water spraying pipe in the device is adhered to the window top or the building outer wall through the fixing piece, and the spraying holes arranged on the water spraying pipe can spray against the building outer wall and the window edge, but some building outer walls and window edges are not arranged in a plane, wherein the building outer wall can be grooved or additionally provided with a wall body or a convex edge, and the window edge can be arc-shaped or additionally provided with a frame and the like; the spraying position, the spraying direction and the spraying angle of the device are fixed, the spraying angle of the spraying pipe cannot be adjusted according to different types of building outer walls and window edges, the device sprays actual conditions of different building outer walls and window edges, a blind area which cannot be sprayed exists, the universality is not strong, and therefore improvement is needed.
Disclosure of Invention
Aiming at the defects of the prior art, the invention aims to provide a building and window edge water seepage testing device for project supervision, which can adjust the spraying angle, is further suitable for water seepage tests of different building outer walls and window edges and has strong universality.
The technical purpose of the invention is realized by the following technical scheme: a water seepage testing device for the outer wall and the window edge of a building for project supervision comprises a water tank, a water pump is arranged at the top of the water tank, a first water outlet pipe is communicated with the water pump along the vertical direction, one end of the first water outlet pipe, which is far away from the water pump, is provided with a second water outlet pipe, the first water outlet pipe is communicated with the second water outlet pipe through a machine seal, one end of the second water outlet pipe, which is far away from the machine seal, is communicated with a first spray pipe, two side surfaces of the first spray pipe are hinged with second spray pipes, two ends of the first spray pipe and two ends of the second spray pipe are sealed, a plurality of spraying openings are arranged on the surfaces of one sides of the first spraying pipes and the second spraying pipes, which are far away from the second water outlet pipe, one side of the first spraying pipe, which is far away from the second water outlet pipe, is communicated with one side of each second spraying pipe through a water guide pipe; positioning rods are arranged between the second spraying pipe and each second water outlet pipe, one end of each positioning rod is hinged to the bottom of the second spraying pipe, a sliding block is arranged at one end, far away from the second spraying pipe, of each positioning rod, positioning blocks are arranged on two sides of each second water outlet pipe, sliding grooves are formed in the positioning blocks along the length direction of the second water outlet pipes, and each sliding block is connected with the corresponding sliding groove in a sliding mode.
Through adopting above-mentioned technical scheme, first shower is articulated with the second shower and through the leading water pipe intercommunication, and steerable second shower pivoted angle under the cooperation of sliding of slider and spout, and then makes the device be applicable to different building outer walls and window limit, and the commonality is good.
Preferably, an adjusting component used for shifting the sliding block to move is arranged between the sliding block and the corresponding positioning block, each adjusting component comprises a guide block arranged on one side wall of the sliding block and a guide groove arranged on one groove wall of the sliding groove and running through the sliding groove along the length direction of the sliding groove, and in each adjusting component, the guide block is connected with the guide groove in a sliding manner and extends out of the guide groove.
Through adopting above-mentioned technical scheme, the guide block slides in the guide way and makes things convenient for the staff to promote the slider, and then makes things convenient for the staff to adjust second shower spray angle.
Preferably, the device still includes and is used for each the locking subassembly that the guide block was locked and was unblock, every group the locking subassembly all includes elasticity fixture block and a plurality of card hole, in every group in the locking subassembly, one side that the guide block was kept away from the slider articulates there is the lug, elasticity fixture block set up in one side that the pin joint was kept away from to the lug, it is a plurality of the card hole all set up in the lateral wall of second outlet pipe, and arrange along its length direction interval, elasticity fixture block is used for along under the drive of guide block the guide way slides, when relative the guide block rotates to with each card hole joint complex position, and with corresponding when the card hole joint is coordinated, to the guide block is locked and is followed when dialling out in the card hole the guide block unblock.
Through adopting above-mentioned technical scheme, after having adjusted the spray angle of second shower, elasticity fixture block and each card hole joint cooperation can make the stable fixing of guide block in the guide way, make the slider no longer slide, and then make the spray angle of second shower fixed.
Preferably, the water conduit includes two first expansion hoses and communicating pipe, the one end of communicating pipe with one the one end intercommunication of first expansion hose, the other end of communicating pipe and the one end intercommunication of another first expansion hose, the other end and the second shower of a first expansion hose deviate from one side intercommunication of second outlet pipe, the other end and the first shower of another first expansion hose depart from one side of first outlet pipe is connected, be provided with on communicating pipe and be used for opening and close the valve of communicating pipe.
By adopting the technical scheme, the valve can control the opening and closing of the communicating pipe, so that water resources are saved; when the second spraying pipe does not need to spray, the valve is closed, and when the second spraying pipe needs to spray, the valve is opened.
Preferably, the machine seal cover is equipped with connecting sleeve, connecting sleeve's both sides are provided with first stopper and second stopper respectively, connecting sleeve with first outlet pipe passes through first stopper fixed connection, the second outlet pipe with connecting sleeve passes through second stopper rotatable coupling.
Through adopting above-mentioned technical scheme, the setting of first stopper and the setting of second stopper can play limiting displacement to the machine seal, have strengthened the stability of being connected between first outlet pipe and the second outlet pipe simultaneously.
Preferably, the second outlet pipe is close to the fixed cover of connecting sleeve's free end is equipped with from the driving wheel, be provided with the action wheel from one side of driving wheel, connecting sleeve's lateral wall is provided with and is used for the drive action wheel pivoted driving piece, the driving piece with the action wheel is connected, the action wheel with be connected with the belt from between the driving wheel.
Through adopting above-mentioned technical scheme, driving piece drive action wheel rotates to drive driven round of rotation under the drive of belt, the second outlet pipe rotates, and first shower rotates under the drive of second outlet pipe with the second shower, and then makes the spraying scope of device more even, and it is better to spray the effect.
Preferably, the driving part is a driving motor, and the driving wheel is fixedly sleeved on an output shaft of the driving motor.
Through adopting above-mentioned technical scheme, driving motor's setting makes things convenient for the staff to drive the action wheel and rotates, and then makes the second outlet pipe rotate, has strengthened the automation ability of device, alleviates staff's manual burden.
Preferably, the free end of the second water outlet pipe, which is far away from the first spray pipe, is provided with a third limiting block, the inner side of the connecting sleeve is circumferentially provided with a limiting groove, and when the second water outlet pipe is driven by the driving motor to rotate, the third limiting block is connected with the limiting groove in a sliding manner.
Through adopting above-mentioned technical scheme, when the second outlet pipe rotated, the third stopper slided in the spacing groove and has played limiting displacement, and then made the difficult not hard up follow connecting sleeve of second outlet pipe at the pivoted in-process break away from and influence the spraying effect.
In conclusion, the invention has the following beneficial effects:
1. the first spraying pipe is hinged with the second spraying pipe and is communicated with the second spraying pipe through the water conduit, and the rotating angle of the second spraying pipe can be controlled under the sliding fit of the sliding block and the sliding groove, so that the device is suitable for outer walls and window edges of different buildings, and has good universality;
2. the second outlet pipe can be rotated by the aid of the rotating assembly, so that the first spraying pipe and the second spraying pipe can be rotated, the spraying range of the device is more uniform, and the spraying effect is better.
Drawings
FIG. 1 is a schematic structural diagram of an embodiment of the present invention;
FIG. 2 is an enlarged view of portion A of FIG. 1;
FIG. 3 is a schematic diagram illustrating an assembly relationship between a dial block and a second water outlet pipe according to an embodiment of the present invention;
FIG. 4 is a schematic diagram of a partial structure of the first outlet pipe according to the embodiment of the present invention;
fig. 5 is a schematic sectional view of a connecting sleeve according to an embodiment of the present invention.
Reference numerals: 1. a water tank; 2. a handle; 3. a water inlet pipe; 4. a universal wheel; 5. a limiting rod; 6. a first water outlet pipe; 7. a fixed block; 8. a reinforcing bar; 9. a connecting sleeve; 10. a second water outlet pipe; 11. a second shower pipe; 12. a first shower pipe; 13. a support; 131. supporting legs; 132. a support plate; 14. a worm; 15. a worm gear; 16. a water pump; 17. a spray port; 18. a first flexible hose; 19. a communicating pipe; 20. a valve; 21. positioning blocks; 22. a chute; 23. a guide groove; 24. a guide block; 25. a slider; 26. positioning a rod; 27. a clamping hole; 28. a bump; 29. an elastic clamping block; 30. positioning a groove; 31. a first stopper; 32. machine sealing; 33. a drive motor; 34. a belt; 35. a driving wheel; 36. a driven wheel; 37. a limiting groove; 38. a second limiting block; 39. a third limiting block; 40. a second flexible hose.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
The utility model provides a building outer wall and window limit infiltration testing arrangement for engineering supervision, refers to FIG. 1, includes water tank 1, and water pump 16 and inlet tube 3 are installed at the top of water tank 1, and inlet tube 3 is located one side of water pump 16. The water pump 16 is provided with a first water outlet pipe 6 along the vertical direction, the first water outlet pipe 6 is communicated with the water pump 16 through a second flexible hose 18, and in this embodiment, the first water outlet pipe 6 is in an L-shaped configuration. One end of the first water outlet pipe 6, which is far away from the water tank 1, is provided with a second water outlet pipe 10, one end of the second water outlet pipe 10, which is far away from the first water outlet pipe 6, is communicated with a first rectangular spraying pipe 12, and two ends of the first spraying pipe 12 are sealed. The surface of one side of the first spraying pipe 12, which is far away from the second water outlet pipe 10, is provided with a plurality of spraying openings 17. In addition, in order to facilitate the movement of the device, four universal wheels 4 are installed at the bottom of the water tank 1, and a U-shaped handle 2 is welded at one side of the water tank 1.
Referring to fig. 1 and 4, simultaneously, support 13 is still installed at the top of water tank 1, and support 13 includes four supporting legs 131 and backup pad 132 that are vertical setting, and four supporting legs 131 evenly distributed are in the bottom of backup pad 132, and one side circumference that first outlet pipe 6 is close to water tank 1 is provided with the external screw thread, and the arbor wheel hole circumference of worm wheel 15 is provided with the internal thread, and first outlet pipe 6 runs through backup pad 132 and worm wheel 15's arbor hole threaded connection. The top of the supporting plate 132 is provided with a worm 14 engaged with the worm wheel 15, and rotating the worm 14 rotates the worm wheel 15, so that the first water outlet pipe 6 rotates and rises. In addition, the welding has the gag lever post 5 of L shape on the backup pad 132, and the lateral wall welding of first outlet pipe 6 has rectangular form fixed block 7, and constant head tank 30 has been seted up along its length direction to fixed block 7, and gag lever post 5 slides with constant head tank 30 and is connected, and then has played limiting displacement to first outlet pipe 6.
Referring to fig. 3, further, the second water outlet pipe 10 is communicated with the first water outlet pipe 6 through the mechanical seal 32, one end of the first water outlet pipe 6 is connected with a stationary ring in the mechanical seal 32, and one end of the second water outlet pipe 10 is connected with a moving ring in the mechanical seal 32. Meanwhile, in order to enhance the communication stability between the first water outlet pipe 6 and the second water outlet pipe 10, a circular connecting sleeve 9 is fixedly sleeved outside the mechanical seal 32, one end of the connecting sleeve 9 is welded with the first water outlet pipe 6 through an annular first limiting block 31, and the first water outlet pipe 6 is welded with the inner side of the first limiting block 31. Meanwhile, the other end of the connecting sleeve 9 is welded with an annular second limiting block 38, and the second water outlet pipe 10 penetrates through an inner ring of the second limiting block 38. In addition, in order that the second water outlet pipe 10 is not easy to deviate and move, an annular third limiting block 39 is welded at one end, far away from the first spraying pipe 12, of the second water outlet pipe 10, an annular limiting groove 37 is formed in one end, far away from the first water outlet pipe 6, of the inner side of the connecting sleeve 9, and the third limiting block 39 is matched with the limiting groove 37 in a sliding mode in a rotating mode. In addition, a reinforcing rod 8 is fixedly welded between the connecting sleeve 9 and the first water outlet pipe 6, so that the firmness of the first water outlet pipe 6 is enhanced.
Referring to fig. 1 and 2, further, both sides of the first spraying pipe 12 are hinged with second spraying pipes 11, and both ends of the second spraying pipes 11 are closed. The surface of one side of the second spraying pipe 11 departing from the second water outlet pipe 10 is also provided with a plurality of spraying openings 17. One side surface of the first spraying pipe 12 departing from the second water outlet pipe 10 is communicated with one side surface of each second spraying pipe 11 departing from the second water outlet pipe 10 through a water guiding pipe, and two ends of each second spraying pipe 11 are sealed. In this embodiment, the water conduit includes two first bellows 18 and communicating pipe 19, the one end of communicating pipe 19 communicates with the one end of a first bellows 18, the other end of communicating pipe 19 communicates with the one end of another first bellows 18, the other end of a first bellows 18 communicates with one side of second shower 11, the other end of another first bellows 18 communicates with one side of first shower 12 that deviates from second outlet pipe 10, each communicating pipe 19 lateral wall all installs the valve 20 that is used for opening and close communicating pipe 19.
Referring to fig. 3, further, an elongated positioning rod 26 is disposed between the second spraying pipe 11 and each second water outlet pipe 10, and one end of each positioning rod 26 is hinged to the bottom of the second spraying pipe 11. Meanwhile, one end, away from the second spraying pipe 11, of each positioning rod 26 is hinged with a sliding block 25, positioning blocks 21 are welded to two sides of the second water outlet pipe 10, sliding grooves 22 are formed in the positioning blocks 21 along the length direction of the second water outlet pipe 10, each sliding block 25 is connected with the corresponding sliding groove 22 in a sliding mode, and the cross sections of the sliding blocks 25 and the sliding grooves 22 are T-shaped. In order to adjust the position of the sliding block 25 in the sliding groove 22, an adjusting component for shifting the sliding block 25 to move is arranged between each sliding block 25 and the corresponding positioning block 21, each group of adjusting components comprises a guide block 24 welded on one side wall of the sliding block 25 and a guide groove 23 arranged on one groove wall of the sliding groove 22 and penetrating along the length direction of the sliding groove 22, and in each group of adjusting components, the guide block 24 is connected with the guide groove 23 in a sliding manner and extends out of the guide groove 23. Meanwhile, the device also comprises two groups of locking assemblies for locking and unlocking the two guide blocks 24, and each group of locking assemblies corresponds to each guide block 24. Each set of locking components comprises a plurality of elastic latch blocks 29 and a plurality of latch holes 27. Between each group of locking components and the corresponding guide block 24, a projection 28 is hinged to one side of the guide block 24 away from the slider 25, an elastic fixture block 29 is welded to one side of the projection 28, and a plurality of fixture holes 27 are all formed in the side wall of the second water outlet pipe 10 and are arranged at intervals along the length direction of the second water outlet pipe. The elastic fixture block 29 is used for locking the guide block 24 and unlocking the guide block 24 when the guide block 24 is pulled out from the card hole 27 under the driving of the guide block 24 sliding along the guide groove 23 and rotates to the position matched with the card holes 27 in a clamping way relative to the guide block 24 and is matched with the corresponding card holes 27 in a clamping way.
Referring to fig. 5, in addition, a driven wheel 36 is fixedly sleeved on the second water outlet pipe 10 near the free end of the connecting sleeve 9, a driving wheel 35 is arranged on one side of the driven wheel 36, and a driving member for driving the driving wheel 35 to rotate is mounted on the side wall of the connecting sleeve 9, and in this embodiment, the driving member is a driving motor 33. An output shaft of the driving motor 33 is connected with a driving wheel 35, the driving wheel 35 is connected with a driven wheel 36 through a belt 34, and when the driving motor 33 is driven to drive the second water outlet pipe 10 to rotate, the first spraying pipe 12 and the second spraying pipe 11 are driven to rotate.
The overall working process is as follows: move the device to the front of building outer wall and window limit, when needs carry out the infiltration test of building outer wall and window limit, according to the actual conditions on building outer wall and window limit, stir guide block 24 and make slider 25 slide in spout 22, and then adjust the angle of second shower 11, open valve 20, can drive driving motor 33 and make second outlet pipe 10 rotate, and then make first shower 12 all rotate with second shower 11 and spray, rotate worm 14 in addition and make worm wheel 15 drive first outlet pipe 6 and go up and down with the height that adjusting device sprayed, and then the device can spray special building outer wall and window limit.
The above-mentioned embodiments are merely illustrative and not restrictive, and those skilled in the art can make modifications to the embodiments without inventive contribution as required after reading the present specification, but only protected by the patent laws within the scope of the claims.

Claims (5)

1. The utility model provides an engineering is managed with building outer wall and window limit infiltration testing arrangement, includes water tank (1), its characterized in that: the water tank is characterized in that a water pump (16) is arranged at the top of the water tank (1), a first water outlet pipe (6) is communicated with the water pump (16) along the vertical direction, a second water outlet pipe (10) is arranged at one end, far away from the water pump (16), of the first water outlet pipe (6), the first water outlet pipe (6) is communicated with the second water outlet pipe (10) through a mechanical seal (32), a first spray pipe (12) is communicated with one end, far away from the mechanical seal (32), of the second water outlet pipe (10), two side faces of the first spray pipe (12) are hinged to second spray pipes (11), two ends of the first spray pipe (12) are sealed with two ends of the second spray pipes (11), the first spray pipe (12) and each second spray pipe (11) deviate from one side surface of the second water outlet pipe (10) is provided with a plurality of spray ports (17), and one side, far away from the second water outlet pipe (10), of the first spray pipe (12) is communicated with the water outlet pipe and the water diversion pipe One side of the second spray pipe (11) is communicated; positioning rods (26) are arranged between the second spraying pipe (11) and each second water outlet pipe (10), one end of each positioning rod (26) is hinged with the bottom of the second spraying pipe (11), a sliding block (25) is arranged at one end, away from the second spraying pipe (11), of each positioning rod (26), positioning blocks (21) are arranged on two sides of each second water outlet pipe (10), a sliding groove (22) is arranged in the length direction of the second water outlet pipe (10) of each positioning block (21), each sliding block (25) is connected with the corresponding sliding groove (22) in a sliding mode, an adjusting assembly used for shifting the sliding block (25) to move is arranged between each sliding block (25) and the corresponding positioning block (21), each adjusting assembly comprises a guide block (24) arranged on one side wall of the sliding block (25) and a guide groove (23) arranged on one groove wall of the sliding groove (22) and penetrating through the sliding groove (22) in the length direction, in each group of adjusting components, the guide block (24) is connected with the guide groove (23) in a sliding manner and extends out of the guide groove (23), the device further comprises locking components used for locking and unlocking each guide block (24), each group of locking components comprises an elastic clamping block (29) and a plurality of clamping holes (27), in each group of locking components, one side, away from the sliding block (25), of each guide block (24) is hinged with a convex block (28), the elastic clamping block (29) is arranged on one side, away from the hinged point, of each convex block (28), the clamping holes (27) are arranged on the side wall of the second water outlet pipe (10) and are arranged at intervals along the length direction of the side wall, the elastic clamping blocks (29) are used for sliding along the guide groove (23) under the driving of the guide block (24), and when the guide block (24) rotates to the position matched with each clamping hole (27) in a clamping manner relatively, and with corresponding when card hole (27) joint is joined in marriage, it is right when dialling in guide block (24) lock and follow card hole (27) guide block (24) unblock, the leading water pipe includes two first bellows (18) and communicating pipe (19), the one end and one of communicating pipe (19) first bellows (18) one end intercommunication, the other end of communicating pipe (19) and the one end intercommunication of another first bellows (18), the other end and the second shower (11) of a first bellows (18) deviate from one side intercommunication of second outlet pipe (10), the other end and the first shower (12) of another first bellows (18) deviate from one side of first outlet pipe (6) is connected, be provided with on communicating pipe (19) and be used for opening and close the valve (20) of communicating pipe (19).
2. The building outer wall and window edge water seepage testing device for project supervision according to claim 1, characterized in that: machine seals (32) cover and is equipped with connecting sleeve (9), the both sides of connecting sleeve (9) are provided with first stopper (31) and second stopper (38) respectively, connecting sleeve (9) with first outlet pipe (6) are through first stopper (31) fixed connection, second outlet pipe (10) with connecting sleeve (9) are through second stopper (38) rotatable coupling.
3. The building outer wall and window edge water seepage testing device for project supervision as claimed in claim 2, wherein: second outlet pipe (10) are close to the fixed cover of free end of connecting sleeve (9) is equipped with from driving wheel (36), one side from driving wheel (36) is provided with action wheel (35), the lateral wall of connecting sleeve (9) is provided with and is used for the drive action wheel (35) pivoted driving piece, the driving piece with action wheel (35) are connected, action wheel (35) with be connected with belt (34) from between driving wheel (36).
4. The building outer wall and window edge water seepage testing device for project supervision according to claim 3, characterized in that: the driving piece is a driving motor (33), and the driving wheel (35) is fixedly sleeved on an output shaft of the driving motor (33).
5. The building outer wall and window edge water seepage testing device for project supervision as claimed in claim 4, wherein: the free end that second outlet pipe (10) kept away from first shower (12) is provided with third stopper (39), connecting sleeve (9) inboard circumference is provided with spacing groove (37), works as second outlet pipe (10) are in when rotating under driving motor (33) drive, third stopper (39) with spacing groove (37) are slided and are connected.
CN201911112156.8A 2019-11-14 2019-11-14 Building outer wall and window limit infiltration testing arrangement for engineering supervision Active CN110672273B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911112156.8A CN110672273B (en) 2019-11-14 2019-11-14 Building outer wall and window limit infiltration testing arrangement for engineering supervision

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911112156.8A CN110672273B (en) 2019-11-14 2019-11-14 Building outer wall and window limit infiltration testing arrangement for engineering supervision

Publications (2)

Publication Number Publication Date
CN110672273A CN110672273A (en) 2020-01-10
CN110672273B true CN110672273B (en) 2021-08-03

Family

ID=69087333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911112156.8A Active CN110672273B (en) 2019-11-14 2019-11-14 Building outer wall and window limit infiltration testing arrangement for engineering supervision

Country Status (1)

Country Link
CN (1) CN110672273B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112067525A (en) * 2020-09-09 2020-12-11 雷成平 Diversified building outer wall and window limit infiltration detection device
CN112525796A (en) * 2020-11-26 2021-03-19 中核华辰工程管理有限公司 Window wall body infiltration detection device for building engineering
CN112985699B (en) * 2021-02-06 2023-03-21 广东至衡工程管理有限公司 Window limit infiltration testing arrangement is used in engineering supervision
CN113075115A (en) * 2021-03-17 2021-07-06 福建祥和工程项目管理有限公司 Building outer wall water seepage testing device for building supervision and detecting method
CN113310870B (en) * 2021-05-20 2023-06-09 丁先喜 Engineering is managed and is used infiltration testing arrangement
CN113295593B (en) * 2021-05-21 2023-07-04 姜兵强 Water seepage testing device for outer wall and window edge of engineering building
CN113758637B (en) * 2021-09-17 2024-03-26 浙江天元项目管理有限公司 Building outer wall seepage testing device for city assembly type residential engineering supervision
CN114112854A (en) * 2021-12-02 2022-03-01 安徽宏祥工程项目管理有限公司 Building outer wall infiltration testing arrangement for building supervision

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6230984B1 (en) * 1998-07-09 2001-05-15 Anton Jager Apparatus for the ejection of liquid
CN207585929U (en) * 2017-12-25 2018-07-06 武汉华威专用汽车检测有限责任公司 Side portion of vehicle spray assemblies and side portion of vehicle spray equipment
CN108851487A (en) * 2018-05-24 2018-11-23 中国人民解放军海军航空大学青岛校区 A kind of naval vessel Multifunctional washing device
CN108926103A (en) * 2018-08-28 2018-12-04 安徽省欧登堡智能门窗有限公司 A kind of window slot cleaner
CN109163853A (en) * 2018-08-24 2019-01-08 北京中联环建设工程管理有限公司 Project supervision external wall and window side water test device
CN110132498A (en) * 2019-05-11 2019-08-16 温州铭洋建设项目管理有限公司 A kind of project supervision window side water test device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6230984B1 (en) * 1998-07-09 2001-05-15 Anton Jager Apparatus for the ejection of liquid
CN207585929U (en) * 2017-12-25 2018-07-06 武汉华威专用汽车检测有限责任公司 Side portion of vehicle spray assemblies and side portion of vehicle spray equipment
CN108851487A (en) * 2018-05-24 2018-11-23 中国人民解放军海军航空大学青岛校区 A kind of naval vessel Multifunctional washing device
CN109163853A (en) * 2018-08-24 2019-01-08 北京中联环建设工程管理有限公司 Project supervision external wall and window side water test device
CN108926103A (en) * 2018-08-28 2018-12-04 安徽省欧登堡智能门窗有限公司 A kind of window slot cleaner
CN110132498A (en) * 2019-05-11 2019-08-16 温州铭洋建设项目管理有限公司 A kind of project supervision window side water test device

Also Published As

Publication number Publication date
CN110672273A (en) 2020-01-10

Similar Documents

Publication Publication Date Title
CN110672273B (en) Building outer wall and window limit infiltration testing arrangement for engineering supervision
CN208880111U (en) A kind of spool assembly device of valve
CN111852336B (en) Drilling tool for horizontal directional drilling and reaming
US4171095A (en) Sprinkler and valve operator
CN113389553A (en) Concrete injection pipe guide auxiliary frame for shaft construction
CN219694450U (en) Pipeline tightness detection device
CN215673666U (en) Use energy-saving flange cast iron gate valve in hydraulic engineering
US4142820A (en) Pivotal connecting device for pivotally connecting an off-shore articulated column structure to a sea bottom
KR101630800B1 (en) A Water Gate for Preventing a Foreign Substance Being Jammed
CN208844505U (en) A kind of hydraulic engineering drainage water channel steering gate
CN113202510A (en) Tunnel secondary lining concrete flow divider and pouring method thereof
CN112025956A (en) Still kettle
CN211779026U (en) Novel special butterfly valve of cement
CN219734546U (en) Butt-clamping pneumatic expansion butterfly valve
KR20070023803A (en) Device for pumping pipe coupling of underground water well
CN216477458U (en) Device for controlling flow rate of adjustment
CN216950463U (en) Dustproof atomizer of mining two-way gang switch
CN213173945U (en) Municipal administration water supply and drainage pipeline stop device
CN219432646U (en) Waterproof sealing structure of basement wall pipe
JP3241074U (en) Concrete control device and concrete placing system
CN214699332U (en) Floating seal reversing valve special for Y-shaped sealed type volume tube
CN211549723U (en) Integrated automatic device for grouting and cleaning grouting pipe
CN219466516U (en) Dry-mixed mortar machine spouts construction machinery structure
CN108006242A (en) A kind of novel hard seal gate valve
CN220025984U (en) Pressure measuring joint for fire hydrant

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant