CN110616818A - Construction method for building shock insulation layer - Google Patents

Construction method for building shock insulation layer Download PDF

Info

Publication number
CN110616818A
CN110616818A CN201910795621.6A CN201910795621A CN110616818A CN 110616818 A CN110616818 A CN 110616818A CN 201910795621 A CN201910795621 A CN 201910795621A CN 110616818 A CN110616818 A CN 110616818A
Authority
CN
China
Prior art keywords
support
plate
shock insulation
concrete
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910795621.6A
Other languages
Chinese (zh)
Inventor
黄秋筠
冯亦文
廖伟东
黄芷敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd
Original Assignee
Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd filed Critical Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd
Priority to CN201910795621.6A priority Critical patent/CN110616818A/en
Publication of CN110616818A publication Critical patent/CN110616818A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/36Bearings or like supports allowing movement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • E04H9/022Bearing, supporting or connecting constructions specially adapted for such buildings and comprising laminated structures of alternating elastomeric and rigid layers

Abstract

The invention discloses a construction method of a building shock insulation layer, which comprises the following steps: s1, mounting a lower embedded plate: the embedded plate is hoisted on the support pier through a hoisting mechanism, S2, and the support pier is concreted: cover pre-buried face through film or plastic cloth when concrete placement, prevent that the concrete from causing the pollution to the surface of pre-buried board, S3, the installation of isolation bearing main part: when the strength of the buttress concrete reaches 70%, firstly cleaning gravels on the surface of the buttress, and S4, installing an upper embedded plate; after the isolation bearing main body is completely fixed, the surface of the isolation bearing main body is cleaned more accurately, and then the embedded steel plate is placed at the top of the isolation bearing, S5, and concrete is poured. The method has the advantages that the embedded plate is hoisted, the embedded plate is guaranteed during pouring, the shock insulation support is installed, and the whole concrete layer is poured finally after the embedded plate is firmly installed.

Description

Construction method for building shock insulation layer
Technical Field
The invention relates to the technical field of building construction, in particular to a construction method of a building shock insulation layer.
Background
Since 2008 after a 5.12 major earthquake, people quickened the research of earthquake-resistant buildings, traditional earthquake-resistant measures considered from the aspect of single structure stress, house buildings were reinforced by a large amount of steel, because the buildings and the foundation are closely connected, although high-rise buildings are built firmly, under the action of strong earthquake waves, huge bending moment still can be generated at the top of the building foundation, the buildings are swung and rocked, the phenomena of building damage and collapse, people's life and property damage and the like are caused, scientists set up earthquake-resistant rubber supports at the top of the foundation through long-term research and exploration, the transverse flexible buffer of the earthquake-resistant rubber supports releases most earthquake waves, and the safety of the structure is ensured.
However, most of the construction methods of the seismic isolation layer in the building in the prior art are complicated, and the adverse phenomena of poor bolt pairs, overlarge horizontal center line deviation, uneven support bottom, cavities and the like are easily caused in the construction process, so that the engineering quality is influenced.
Disclosure of Invention
1. Technical problem to be solved
The invention aims to solve the problems that most construction methods in the prior art are complicated, and poor phenomena such as poor bolt alignment, overlarge horizontal center line deviation, uneven support bottom, cavities and the like are easily caused in construction to influence the engineering quality, and the construction method of the building shock insulation layer is provided.
2. Technical scheme
In order to achieve the purpose, the invention adopts the following technical scheme:
a construction method of a building shock insulation layer comprises the following steps:
s1, mounting a lower embedded plate: hoisting the pre-buried plate on a support pier through a hoisting mechanism, measuring the elevation position of the pre-buried plate by using a level gauge, putting the sleeve and the anchor bars into corresponding holes of the pre-buried plate, pre-screwing the sleeve and the anchor bars by using bolts, adjusting the elevation and the flatness of the steel plate by using wedge-shaped wood blocks, spot-welding the sleeve and the main bars of the lower component by using steel bar heads, extracting the wedge-shaped wood blocks to carry out secondary rechecking on the elevation of the steel plate and checking the flatness by using a leveling rod, screwing the bolts after the steel bar heads are qualified, and firmly welding the steel bar heads;
s2, pouring buttress concrete: the pre-buried plate surface is covered by a film or plastic cloth when concrete is poured, so that the surface of the pre-buried plate is prevented from being polluted by the concrete;
s3, installing the vibration isolation support main body: when the strength of buttress concrete reaches 70%, firstly cleaning sand and stones on the surface of the buttress, installing connecting bolts, enabling the connecting bolts to penetrate through bolt holes of connecting steel plates of the building shock-insulation rubber support and then twisting the connecting bolts into the sleeve and screwing the connecting bolts into the sleeve;
s4, installing an upper embedded plate; after the main body of the shock insulation support is completely fixed, the surface of the main body of the shock insulation support is cleaned more accurately, then the embedded steel plate is placed at the top of the shock insulation support, the bolt penetrates through the bolt hole of the connecting steel plate of the shock insulation rubber support and then is twisted into the sleeve barrel and screwed tightly, and the embedded sleeve extending into the upper buttress part, the embedded anchor bars and the upper reinforcing mesh are firmly bound;
s5, pouring concrete; the method comprises the following steps of rechecking levelness and axis positions of pre-buried steel plates on the shock insulation support, checking whether the appearance of the shock insulation rubber support is normal or not, if the appearance has a paint removal phenomenon, repairing, and pouring concrete after meeting requirements.
Preferably, in the step 1, the levelness error of the top surface of the lower embedded plate is not more than 5 per thousand.
Preferably, in the step 2, a pouring manner is selected according to actual conditions, and a mechanical pouring manner or an artificial cloth manner can be adopted.
Preferably, in the step 4, after the isolation bearing is installed, the levelness error of the top surface of the isolation bearing is not more than 8 per thousand.
Preferably, in the step 4, the deviation between the center elevation of the rubber isolation bearing and the design elevation is not more than 5 mm.
Preferably, the rubber vibration-isolating support connecting plate and the exposed connecting bolt are both sprayed with antirust paint.
Preferably, in step 3, the connecting bolts are all sleeved with gaskets when the connecting bolts are installed.
3. Advantageous effects
Compared with the prior art, the invention has the advantages that:
(1) according to the method, the pre-embedded plate is hoisted, the pre-embedded plate is guaranteed during pouring, the shock insulation support is installed, and the whole concrete layer is poured after the pre-embedded plate is firmly installed.
Drawings
FIG. 1 is a schematic flow chart of a construction method of a building seismic isolation layer provided by the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Example 1:
referring to fig. 1, a construction method of a seismic isolation layer of a building includes the following steps:
s1, mounting a lower embedded plate: hoisting the pre-buried plate on a support pier through a hoisting mechanism, measuring the elevation position of the pre-buried plate by using a level gauge, putting the sleeve and the anchor bars into corresponding holes of the pre-buried plate, pre-screwing the sleeve and the anchor bars by using bolts, adjusting the elevation and the flatness of the steel plate by using wedge-shaped wood blocks, spot-welding the sleeve and the main bars of the lower component by using steel bar heads, extracting the wedge-shaped wood blocks to carry out secondary rechecking on the elevation of the steel plate and checking the flatness by using a leveling rod, screwing the bolts after the steel bar heads are qualified, and firmly welding the steel bar heads;
s2, pouring buttress concrete: the pre-buried plate surface is covered by a film or plastic cloth when concrete is poured, so that the surface of the pre-buried plate is prevented from being polluted by the concrete;
s3, installing the vibration isolation support main body: when the strength of buttress concrete reaches 70%, firstly cleaning sand and stones on the surface of the buttress, installing connecting bolts, enabling the connecting bolts to penetrate through bolt holes of connecting steel plates of the building shock-insulation rubber support and then twisting the connecting bolts into the sleeve and screwing the connecting bolts into the sleeve;
s4, installing an upper embedded plate; after the main body of the shock insulation support is completely fixed, the surface of the main body of the shock insulation support is cleaned more accurately, then the embedded steel plate is placed at the top of the shock insulation support, the bolt penetrates through the bolt hole of the connecting steel plate of the shock insulation rubber support and then is twisted into the sleeve barrel and screwed tightly, and the embedded sleeve extending into the upper buttress part, the embedded anchor bars and the upper reinforcing mesh are firmly bound;
s5, pouring concrete; the method comprises the following steps of rechecking levelness and axis positions of pre-buried steel plates on the shock insulation support, checking whether the appearance of the shock insulation rubber support is normal or not, if the appearance has a paint removal phenomenon, repairing, and pouring concrete after meeting requirements.
In the invention, in step 1, the levelness error of the top surface of the lower embedded plate is not more than 5 per thousand, in step 2, a pouring mode is selected according to actual conditions, a mechanical pouring mode or a manual material distribution mode can be adopted, in step 4, after the shock insulation support is installed, the levelness error of the top surface of the shock insulation support is not more than 8 per thousand, in step 4, the deviation of the central elevation of the rubber shock insulation support and the design elevation is not more than 5mm, the connecting plate of the rubber shock insulation support and the exposed connecting bolt are both sprayed with antirust paint, and in step 3, the connecting bolt is sleeved with a gasket when the connecting bolt is installed.
Example 2:
referring to fig. 1, a construction method of a seismic isolation layer of a building includes the following steps:
s1, mounting a lower embedded plate: hoisting the pre-buried plate on a support pier through a hoisting mechanism, measuring the elevation position of the pre-buried plate by using a level gauge, putting the sleeve and the anchor bars into corresponding holes of the pre-buried plate, pre-screwing the sleeve and the anchor bars by using bolts, adjusting the elevation and the flatness of the steel plate by using wedge-shaped wood blocks, spot-welding the sleeve and the main bars of the lower component by using steel bar heads, extracting the wedge-shaped wood blocks to carry out secondary rechecking on the elevation of the steel plate and checking the flatness by using a leveling rod, screwing the bolts after the steel bar heads are qualified, and firmly welding the steel bar heads;
s2, pouring buttress concrete: the pre-buried plate surface is covered by a film or plastic cloth when concrete is poured, so that the surface of the pre-buried plate is prevented from being polluted by the concrete;
s3, installing the vibration isolation support main body: when the strength of buttress concrete reaches 70%, firstly cleaning sand and stones on the surface of the buttress, installing connecting bolts, enabling the connecting bolts to penetrate through bolt holes of connecting steel plates of the building shock-insulation rubber support and then twisting the connecting bolts into the sleeve and screwing the connecting bolts into the sleeve;
s4, installing an upper embedded plate; after the main body of the shock insulation support is completely fixed, the surface of the main body of the shock insulation support is cleaned more accurately, then the embedded steel plate is placed at the top of the shock insulation support, the bolt penetrates through the bolt hole of the connecting steel plate of the shock insulation rubber support and then is twisted into the sleeve barrel and screwed tightly, and the embedded sleeve extending into the upper buttress part, the embedded anchor bars and the upper reinforcing mesh are firmly bound;
s5, pouring concrete; the method comprises the following steps of rechecking levelness and axis positions of pre-buried steel plates on the shock insulation support, checking whether the appearance of the shock insulation rubber support is normal or not, if the appearance has a paint removal phenomenon, repairing, and pouring concrete after meeting requirements.
In the invention, in step 1, the levelness error of the top surface of the lower embedded plate is not more than 5 per thousand, in step 2, a pouring mode is selected according to actual conditions, a mechanical pouring mode or a manual material distribution mode can be adopted, in step 4, after the shock insulation support is installed, the levelness error of the top surface of the shock insulation support is not more than 8 per thousand, in step 4, the deviation of the central elevation of the rubber shock insulation support and the design elevation is not more than 5mm, the connecting plate of the rubber shock insulation support and the exposed connecting bolt are both sprayed with antirust paint, and in step 3, the connecting bolt is sleeved with a gasket when the connecting bolt is installed.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (7)

1. A construction method of a shock insulation layer of a building is characterized by comprising the following steps:
s1, mounting a lower embedded plate: hoisting the pre-buried plate on a support pier through a hoisting mechanism, measuring the elevation position of the pre-buried plate by using a level gauge, putting the sleeve and the anchor bars into corresponding holes of the pre-buried plate, pre-screwing the sleeve and the anchor bars by using bolts, adjusting the elevation and the flatness of the steel plate by using wedge-shaped wood blocks, spot-welding the sleeve and the main bars of the lower component by using steel bar heads, extracting the wedge-shaped wood blocks to carry out secondary rechecking on the elevation of the steel plate and checking the flatness by using a leveling rod, screwing the bolts after the steel bar heads are qualified, and firmly welding the steel bar heads;
s2, pouring buttress concrete: the pre-buried plate surface is covered by a film or plastic cloth when concrete is poured, so that the surface of the pre-buried plate is prevented from being polluted by the concrete;
s3, installing the vibration isolation support main body: when the strength of buttress concrete reaches 70%, firstly cleaning sand and stones on the surface of the buttress, installing connecting bolts, enabling the connecting bolts to penetrate through bolt holes of connecting steel plates of the building shock-insulation rubber support and then twisting the connecting bolts into the sleeve and screwing the connecting bolts into the sleeve;
s4, installing an upper embedded plate; after the main body of the shock insulation support is completely fixed, the surface of the main body of the shock insulation support is cleaned more accurately, then the embedded steel plate is placed at the top of the shock insulation support, the bolt penetrates through the bolt hole of the connecting steel plate of the shock insulation rubber support and then is twisted into the sleeve barrel and screwed tightly, and the embedded sleeve extending into the upper buttress part, the embedded anchor bars and the upper reinforcing mesh are firmly bound;
s5, pouring concrete; the method comprises the following steps of rechecking levelness and axis positions of pre-buried steel plates on the shock insulation support, checking whether the appearance of the shock insulation rubber support is normal or not, if the appearance has a paint removal phenomenon, repairing, and pouring concrete after meeting requirements.
2. The construction method of the seismic isolation layer of the building as claimed in claim 1, wherein in the step 1, the levelness error of the top surface of the lower embedded plate is not more than 5 per thousand.
3. The construction method of the building seismic isolation layer according to claim 1, wherein in the step 2, a pouring mode is selected according to actual conditions, and a mechanical pouring mode or a manual material distribution mode can be adopted.
4. The construction method of the seismic isolation layer of the building as claimed in claim 1, wherein in the step 4, after the seismic isolation support is installed, the levelness error of the top surface of the seismic isolation support is not more than 8 per thousand.
5. The construction method of the building seismic isolation layer according to claim 1, wherein in the step 4, the deviation between the center elevation of the rubber seismic isolation support and the design elevation is not more than 5 mm.
6. The construction method of the building seismic isolation layer according to claim 1, wherein the rubber seismic isolation support connecting plate and the exposed connecting bolt are sprayed with antirust paint.
7. The construction method of the seismic isolation layer of the building as claimed in claim 1, wherein in the step 3, gaskets are sleeved on the connecting bolts when the connecting bolts are installed.
CN201910795621.6A 2019-08-27 2019-08-27 Construction method for building shock insulation layer Pending CN110616818A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910795621.6A CN110616818A (en) 2019-08-27 2019-08-27 Construction method for building shock insulation layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910795621.6A CN110616818A (en) 2019-08-27 2019-08-27 Construction method for building shock insulation layer

Publications (1)

Publication Number Publication Date
CN110616818A true CN110616818A (en) 2019-12-27

Family

ID=68922089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910795621.6A Pending CN110616818A (en) 2019-08-27 2019-08-27 Construction method for building shock insulation layer

Country Status (1)

Country Link
CN (1) CN110616818A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359996A (en) * 2020-09-25 2021-02-12 周力 Special wind-resistant device in building shock insulation engineering and use method thereof
CN112499469A (en) * 2020-12-30 2021-03-16 河南省安装集团有限责任公司 Track installation process on concrete crane beam
CN112922371A (en) * 2021-02-01 2021-06-08 山东东泰工程咨询有限公司 Method for protecting pre-buried steel plate from concrete pollution
CN115262562A (en) * 2022-06-02 2022-11-01 海洋石油工程股份有限公司 Method for reducing secondary grouting pitted surface rate of embedded plate of seismic isolation support

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08303053A (en) * 1995-04-28 1996-11-19 Hitachi Plant Eng & Constr Co Ltd Clean room building structure
CN201850669U (en) * 2010-11-22 2011-06-01 中建七局第三建筑有限公司 Spatial accurate positioning support of vibration isolating device
CN102767238A (en) * 2012-07-27 2012-11-07 中铁十六局集团有限公司 Construction method of shock-isolation rubber support
CN109252727A (en) * 2018-09-28 2019-01-22 西北民族大学 The integrated assembly node of Seismic Isolation of Isolation Layer rubber support and column, beam slab system and method
CN109610644A (en) * 2018-11-26 2019-04-12 云南省设计院集团工程投资有限公司 A kind of construction method of installation of rubber earthquake isolation support
CN109930710A (en) * 2019-01-28 2019-06-25 成都建工第二建筑工程有限公司 Architectural vibration-insulation layer construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08303053A (en) * 1995-04-28 1996-11-19 Hitachi Plant Eng & Constr Co Ltd Clean room building structure
CN201850669U (en) * 2010-11-22 2011-06-01 中建七局第三建筑有限公司 Spatial accurate positioning support of vibration isolating device
CN102767238A (en) * 2012-07-27 2012-11-07 中铁十六局集团有限公司 Construction method of shock-isolation rubber support
CN109252727A (en) * 2018-09-28 2019-01-22 西北民族大学 The integrated assembly node of Seismic Isolation of Isolation Layer rubber support and column, beam slab system and method
CN109610644A (en) * 2018-11-26 2019-04-12 云南省设计院集团工程投资有限公司 A kind of construction method of installation of rubber earthquake isolation support
CN109930710A (en) * 2019-01-28 2019-06-25 成都建工第二建筑工程有限公司 Architectural vibration-insulation layer construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359996A (en) * 2020-09-25 2021-02-12 周力 Special wind-resistant device in building shock insulation engineering and use method thereof
CN112499469A (en) * 2020-12-30 2021-03-16 河南省安装集团有限责任公司 Track installation process on concrete crane beam
CN112922371A (en) * 2021-02-01 2021-06-08 山东东泰工程咨询有限公司 Method for protecting pre-buried steel plate from concrete pollution
CN115262562A (en) * 2022-06-02 2022-11-01 海洋石油工程股份有限公司 Method for reducing secondary grouting pitted surface rate of embedded plate of seismic isolation support

Similar Documents

Publication Publication Date Title
CN110616818A (en) Construction method for building shock insulation layer
CN106703437B (en) Shock insulation underpinning structure and its construction method
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN108005387B (en) Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN213174260U (en) Laminated rubber shock insulation support mounting structure
CN105442629B (en) A kind of large scale equipment T stage vibration isolation mounts construction
CN107524158B (en) Vibration isolation foundation structure for precision equipment and construction process
CN107143039A (en) Architectural vibration-insulation elastic sliding plate support construction method
CN107476583A (en) A kind of concrete assembled building builds construction method
CN201137151Y (en) Underwater bottom cover-free concrete case box
CN114108917B (en) Height-adjustable assembly type composite floor slab construction method
CN108005255A (en) A kind of construction method of wall
CN206127746U (en) Isolation bearing handles accurate location structure of pre -buried steel sheet in back
CN102434007A (en) Construction process for installing vibration isolation support among floors
CN100353008C (en) Novel embedded part for vibration isolation bearing and mounting method thereof
CN212478159U (en) Pre-buried steel sheet erection joint structure under isolation bearing
CN112922022A (en) Construction method capable of maintaining assembled floating building equipment foundation
CN110878641A (en) Reinforcing structure adopting superimposed hollow floor slab grid system and new construction method
CN110042977B (en) Steel structure wall and construction method thereof
CN103835522B (en) Short wall support energy consumption damping reinforcement structure and construction technology
CN106869387A (en) Multi-ribbed plate Structural Floor System HZ concrete film construction methods
CN110230271A (en) Bridge biased displacement post-reinforcing resets construction method
CN217780474U (en) Large-scale prefabricated case roof beam hoist and mount crack control device
CN214461390U (en) A earthquake-resistant structure for architectural design

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191227