CN110552716A - Assembling method of circular shield tunnel lining structure - Google Patents

Assembling method of circular shield tunnel lining structure Download PDF

Info

Publication number
CN110552716A
CN110552716A CN201910706202.0A CN201910706202A CN110552716A CN 110552716 A CN110552716 A CN 110552716A CN 201910706202 A CN201910706202 A CN 201910706202A CN 110552716 A CN110552716 A CN 110552716A
Authority
CN
China
Prior art keywords
lining
assembling
lining ring
shield tunnel
circular shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910706202.0A
Other languages
Chinese (zh)
Other versions
CN110552716B (en
Inventor
晏启祥
孙明辉
张君臣
李彬嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201910706202.0A priority Critical patent/CN110552716B/en
Publication of CN110552716A publication Critical patent/CN110552716A/en
Application granted granted Critical
Publication of CN110552716B publication Critical patent/CN110552716B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses an assembling method of a lining structure of a circular shield tunnel, which comprises the steps of calculating the position theta of the minimum normal stress according to the outer diameter D of a lining ring and the sectional stress distribution of the lining ring, and taking the position theta of the minimum normal stress as the position for installing a capping block; calculating an initial splicing segment position omega according to the position theta of the minimum positive stress, the blocking angle beta of the capping block and the blocking angle gamma of the adjacent block; placing the initial assembled duct piece at a position omega, and then assembling the duct piece along the lining ring in a one-way mode; after lining segments are assembled into a complete lining ring, assembling the next lining ring at the rear side of the lining ring, wherein the assembling direction of the lining ring is opposite to that of the previous lining ring, and realizing staggered joint assembling; and repeating until the assembly of all lining rings is completed. The method can solve the problems of insufficient construction efficiency and bearing capacity of the shield segment in the prior art, and has the advantages of wide application range, high calculation efficiency and strong design reliability.

Description

一种圆形盾构隧道衬砌结构的拼装方法A method for assembling the lining structure of a circular shield tunnel

技术领域technical field

本发明涉及盾构隧道衬砌技术领域,具体涉及一种圆形盾构隧道衬砌结构 的拼装方法。The invention relates to the technical field of shield tunnel lining, in particular to a method for assembling a circular shield tunnel lining structure.

背景技术Background technique

随着我国经济的快速发展和科技水平的不断提高,越来越多的城市选择采 用轨道交通方案来满足市民出行需求,缓解城市交通压力。盾构法隧道以其建 设速度快,工程质量高以及对周围环境影响小等诸多优点成为各大城市修筑地 铁隧道的首选方案。With the rapid development of my country's economy and the continuous improvement of the level of science and technology, more and more cities choose to adopt rail transit solutions to meet the travel needs of citizens and relieve urban traffic pressure. The shield method tunnel has become the first choice for building subway tunnels in major cities due to its fast construction speed, high engineering quality and low impact on the surrounding environment.

目前国内建设的地铁盾构隧道大多采用圆形断面形式,衬砌环由一块封顶 块、两块邻接块和若干块标准块构成。其中封顶块的分块角度一般比邻接块和 标准块的分块角度小。At present, most of the subway shield tunnels constructed in China adopt the form of circular section, and the lining ring is composed of a capping block, two adjacent blocks and several standard blocks. The block angle of the capping block is generally smaller than that of adjacent blocks and standard blocks.

现有研究发现,盾构隧道全周在等压荷载加载过程中,封顶块两端接缝张 开量最大,隧道结构的破坏最先发生在封顶块处,由此说明封顶块是盾构隧道 结构受力的薄弱环节。Existing studies have found that during the isobaric loading process of the shield tunnel, the joints at both ends of the capping block open the largest, and the damage of the tunnel structure first occurs at the capping block, which shows that the capping block is the shield tunnel structure. Weak link of strength.

由于地下的隧道结构四周受力是不相等的,存在受力最大和受力最小的位 置。当盾构隧道建设在大埋深非自稳且无法形成自然拱的软弱地层中时,若封 顶块放在受力最大的位置,易造成封顶块两端接缝张开过大,进而导致盾构隧 道的漏水问题;因封顶块是盾构隧道衬砌环的薄弱环节,将其放在受力最大的 位置更易导致隧道的破坏。Since the forces around the underground tunnel structure are not equal, there are positions with the largest and smallest forces. When the shield tunnel is built in a weak stratum with a large buried depth that is not self-stable and cannot form a natural arch, if the capping block is placed at the position where the force is the largest, it is easy to cause the joints at both ends of the capping block to open too much, which will lead to shield tunneling. The water leakage problem of the shield tunnel; because the capping block is the weak link of the lining ring of the shield tunnel, it is more likely to cause damage to the tunnel when it is placed at the position with the greatest force.

因此,选用合适的拼装方案,对提高隧道防水和盾构隧道施工运营全生命 期的安全性能是十分必要的。Therefore, it is very necessary to choose a suitable assembly scheme to improve the safety performance of tunnel waterproofing and shield tunnel construction and operation in the whole life cycle.

发明内容Contents of the invention

本发明针对现有技术中的上述不足,提供了一种能够解决现有技术中盾构 衬砌环的拼装方案容易导致封顶块结构受力过大影响使用寿命的问题的圆形盾 构隧道衬砌结构的拼装方法。Aiming at the above-mentioned deficiencies in the prior art, the present invention provides a circular shield tunnel lining structure that can solve the problem that the assembly scheme of the shield lining ring in the prior art is likely to cause excessive force on the capping block structure and affect the service life assembly method.

为解决上述技术问题,本发明采用了下列技术方案:In order to solve the problems of the technologies described above, the present invention adopts the following technical solutions:

提供了一种圆形盾构隧道衬砌结构的拼装方法,其包括如下步骤:A method for assembling a circular shield tunnel lining structure is provided, which includes the following steps:

S1、根据衬砌环外直径D和衬砌环的截面应力分布计算最小正应力所在位 置θ,将最小正应力所在位置θ作为安装封顶块的位置;S1, calculate the position θ of the minimum normal stress according to the cross-sectional stress distribution of the outer diameter D of the lining ring and the lining ring, and use the position θ of the minimum normal stress as the position where the capping block is installed;

S2、根据最小正应力所在位置θ、封顶块分块角度β、邻接块分块角度γ计 算初始拼装管片位置ω;S2. Calculate the initial assembled segment position ω according to the position θ of the minimum normal stress, the block angle β of the capping block, and the block angle γ of the adjacent block;

S3、将初始拼装管片放在位置ω,然后沿衬砌环单向拼装管片;S3. Place the initial assembled segment at position ω, and then assemble the segment along the lining ring in one direction;

S4、将衬砌管片拼装成完整的衬砌环后,在衬砌环后侧拼装下一衬砌环, 且衬砌环的拼装方向与前一衬砌环相反,实现错缝拼装;S4. After the lining segment is assembled into a complete lining ring, the next lining ring is assembled on the rear side of the lining ring, and the assembling direction of the lining ring is opposite to that of the previous lining ring, so as to realize the staggered seam assembly;

S5、重复步骤S4,直至完成全部衬砌环的拼装。S5. Step S4 is repeated until the assembly of all lining rings is completed.

进一步地,最小正应力的计算公式为:Further, the calculation formula of the minimum normal stress is:

θ=122.8031+1.8663D+0.0968p1+0.0332q1-0.1151q2-0.168pk θ=122.8031+1.8663D+0.0968p 1 +0.0332q 1 -0.1151q 2 -0.168p k

其中,p1为竖向载荷,q1为顶部侧向压力,q2为底部侧向压力,pk为地层抗 力,p1、q1、q2和pk为衬砌环的截面应力分布。Among them, p 1 is the vertical load, q 1 is the top lateral pressure, q 2 is the bottom lateral pressure, p k is the formation resistance, p 1 , q 1 , q 2 and p k are the cross-sectional stress distribution of the lining ring.

进一步地,竖向载荷包括上方竖向载荷与下方竖向载荷,竖向载荷p1的计 算方法为:Further, the vertical load includes the upper vertical load and the lower vertical load, and the calculation method of the vertical load p1 is:

p1=pe1+pw1 p 1 =p e1 +p w1

其中,pe1为上部土体压力,pw1为上部水体压力。Among them, p e1 is the upper soil pressure, p w1 is the upper water pressure.

进一步地,顶部侧向压力q1的计算方法为:Further, the calculation method of the top lateral pressure q1 is:

q1=λpe1+pw1 q 1 =λp e1 +p w1

其中,λ为土体侧向压力系数。Among them, λ is the soil lateral pressure coefficient.

进一步地,底部侧向压力q2的计算方法为:Further, the calculation method of the bottom lateral pressure q2 is:

其中,ρ为土体密度,t为管片厚度,pw2为下部水体压力。Among them, ρ is the density of the soil, t is the thickness of the segment, and p w2 is the pressure of the lower water body.

进一步地,地层抗力pk的计算方法为:Further, the calculation method of formation resistance p k is:

其中,k为地层抗力系数,R为管片中心半径,g为重力加速度,η为弯曲 刚度,E为弹性模量,I为管片惯性矩。Among them, k is the formation resistance coefficient, R is the segment center radius, g is the acceleration due to gravity, η is the bending stiffness, E is the modulus of elasticity, and I is the moment of inertia of the segment.

进一步地,初始拼装管片位置ω的计算方法为:Further, the calculation method of the initial assembled segment position ω is:

进一步地,衬砌环包括一个封顶块、两个邻接块和若干个标准块。Further, the lining ring includes a capping block, two adjacent blocks and several standard blocks.

进一步地,相邻的两个衬砌环的两个封顶块所在位置关于过衬砌环中心的 竖直线镜像对称。Further, the positions of the two capping blocks of adjacent two lining rings are mirror symmetrical about the vertical line passing through the center of the lining ring.

本发明提供的上述圆形盾构隧道衬砌结构的拼装方法的主要有益效果在 于:The main beneficial effects of the assembly method of the above-mentioned circular shield tunnel lining structure provided by the present invention are:

本方法通过将封顶块放置在衬砌环的最小正应力所在位置,从而能够最大 程度的降低导致封顶块损坏的不利力学条件,提高盾构隧道施工及运营期的安 全性能;通过根据封顶块的所在位置、封顶块和邻接块的分块角度的位置,选 择初始拼装块的位置,可以保证衬砌环的拼装的稳定性和效率。In this method, by placing the capping block at the position of the minimum normal stress of the lining ring, the unfavorable mechanical conditions that cause damage to the capping block can be reduced to the greatest extent, and the safety performance during the construction and operation period of the shield tunnel can be improved; The location of the block, the position of the block angle of the capping block and the adjacent block, and the selection of the position of the initial assembly block can ensure the stability and efficiency of the assembly of the lining ring.

通过将衬砌管片进行单向拼装,并将衬砌环间进行错缝拼装,提高隧道结 构的纵向刚度。并且拼装方式简单,不增加额外工作量,有助于在保证安全的 前提下提高效率。The longitudinal rigidity of the tunnel structure is improved by assembling the lining segments in one direction and staggering the lining rings. And the assembly method is simple, without adding extra workload, which helps to improve efficiency under the premise of ensuring safety.

附图说明Description of drawings

图1为本发明圆形盾构隧道衬砌结构的拼装方法的示意图。Fig. 1 is a schematic diagram of the assembly method of the circular shield tunnel lining structure of the present invention.

图2为隧道衬砌环的截面应力分布示意图。Figure 2 is a schematic diagram of the cross-sectional stress distribution of the tunnel lining ring.

图3为衬砌环顺时针拼装示意图。Figure 3 is a schematic diagram of clockwise assembly of the lining ring.

图4为衬砌环逆时针拼装示意图。Figure 4 is a schematic diagram of counterclockwise assembly of the lining ring.

图5为地层结构示意图。Figure 5 is a schematic diagram of the stratum structure.

其中,1、封顶块,2、邻接块,3、标准块,4、衬砌环,5、初始拼装管片。Among them, 1. Capping block, 2. Adjacent block, 3. Standard block, 4. Lining ring, 5. Initially assembled segments.

具体实施方式Detailed ways

下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:

如图1所示,其为圆形盾构隧道衬砌结构的拼装方法的示意图。As shown in Figure 1, it is a schematic diagram of the assembly method of the circular shield tunnel lining structure.

本发明的圆形盾构隧道衬砌结构的拼装方法包括如下步骤:The assembling method of circular shield tunnel lining structure of the present invention comprises the following steps:

S1、根据衬砌环4外直径D和衬砌环4的截面应力分布计算最小正应力所 在位置θ,将最小正应力所在位置θ作为安装封顶块1的位置。S1. Calculate the position θ of the minimum normal stress according to the outer diameter D of the lining ring 4 and the cross-sectional stress distribution of the lining ring 4, and use the position θ of the minimum normal stress as the position where the capping block 1 is installed.

最小正应力所在位置θ为设计荷载作用下环向受力最安全的范围内。The location of the minimum normal stress θ is within the safest range of hoop stress under the design load.

具体地,截面应力分布包括竖向载荷p1、顶部侧向压力q1、底部侧向压力 q2和地层抗力pk,如图2所示,截面应力分布的计算方法如下:Specifically, the cross-sectional stress distribution includes vertical load p 1 , top lateral pressure q 1 , bottom lateral pressure q 2 and formation resistance p k , as shown in Fig. 2, the calculation method of cross-sectional stress distribution is as follows:

S1-1、最小正应力所在位置θ的计算方法为:S1-1. The calculation method of the minimum normal stress position θ is:

θ=122.8031+1.8663D+0.0968p1+0.0332q1-0.1151q2-0.168pk θ=122.8031+1.8663D+0.0968p 1 +0.0332q 1 -0.1151q 2 -0.168p k

其中,竖向载荷包括上方竖向载荷p1与下方竖向载荷p2Wherein, the vertical load includes the upper vertical load p 1 and the lower vertical load p 2 .

一般地,上方竖向载荷p1与下方竖向载荷p2的大小相等。因此取上方竖向 载荷p1进行分析。p1的计算方法为:Generally, the upper vertical load p 1 and the lower vertical load p 2 are equal in magnitude. Therefore, take the upper vertical load p1 for analysis. The calculation method of p1 is:

p1=pe1+pw1 p 1 =p e1 +p w1

其中,pe1为上部土体压力,pw1为上部水体压力,pe1和pw1都根据隧道所在 位置的土体和水体环境计算。Among them, p e1 is the upper soil pressure, p w1 is the upper water pressure, both p e1 and p w1 are calculated according to the soil and water environment where the tunnel is located.

在实际计算中,pe1通过根据土体的具体分层累加计算:In the actual calculation, p e1 is calculated according to the specific layering of the soil:

pe1=Pvc=∑hiρi p e1 =P vc =∑h i ρ i

hi为各层土体的厚度,ρi为各层土体的密度。h i is the thickness of each layer of soil, ρ i is the density of each layer of soil.

pw1根据水位深度Hw计算:p w1 is calculated according to the water table depth H w :

其中,t为管片厚度,ρw为水的密度。Among them, t is the thickness of the segment, and ρw is the density of water.

S1-2、顶部侧向压力q1的计算方法为:S1-2. The calculation method of top lateral pressure q1 is:

q1=λpe1+pw1 q 1 =λp e1 +p w1

其中,λ为土体侧向压力系数。Among them, λ is the soil lateral pressure coefficient.

S1-3、底部侧向压力q2的计算方法为:S1-3. The calculation method of bottom lateral pressure q2 is:

其中,ρ为土体密度,pw2为下部水体压力,其计算方法为:Among them, ρ is the density of the soil body, and p w2 is the pressure of the lower water body, and its calculation method is:

S1-4、地层抗力pk的计算方法为:S1-4. The calculation method of formation resistance p k is:

其中,k为地层抗力系数,R为管片中心半径,g为重力加速度,η为弯曲 刚度,参考《隧道标准规范》选取,E为弹性模量,I为管片惯性矩。Among them, k is the formation resistance coefficient, R is the segment center radius, g is the gravitational acceleration, η is the bending stiffness, which is selected by referring to the "Tunnel Standard Specification", E is the elastic modulus, and I is the segment moment of inertia.

S2、根据最小正应力所在位置θ、封顶块1分块角度β、邻接块2分块角度 γ计算初始拼装管片5的位置ω。S2. Calculate the position ω of the initial assembled segment 5 according to the position θ of the minimum normal stress, the block angle β of the capping block 1, and the block angle γ of the adjacent block 2.

初始拼装管片5一般为标准块3。初始拼装管片5的位置ω的计算方法为:The initial assembled segments 5 are generally standard blocks 3 . The calculation method of the position ω of the initial assembled segment 5 is:

S3、将初始拼装管片5放在位置ω,然后沿衬砌环单向拼装管片。S3. Put the initial assembled segment 5 at the position ω, and then assemble the segment along the lining ring in one direction.

利用盾构机内部管片拼装设备将初始拼装管片5准确放置到位,然后沿顺 时针或逆时针的方向单向拼装衬砌环,并最后拼装封顶块1管片。Use the internal segment assembly equipment of the shield machine to accurately place the initial assembled segment 5 in place, then assemble the lining ring in one direction clockwise or counterclockwise, and finally assemble the capping block 1 segment.

S4、将衬砌管片拼装成完整的衬砌环后,在衬砌环后侧拼装下一衬砌环, 且衬砌环的拼装方向与前一衬砌环相反,实现错缝拼装。S4. After the lining segment is assembled into a complete lining ring, the next lining ring is assembled on the rear side of the lining ring, and the assembling direction of the lining ring is opposite to that of the previous lining ring, so as to realize staggered seam assembly.

其中,衬砌环4包括一个封顶块1、两个邻接块2和若干个标准块3。且相 邻的两个衬砌环4的两个封顶块1所在位置关于过衬砌环4中心的竖直线镜像 对称,以保证衬砌管片拼装的准确性。Wherein, the lining ring 4 includes a capping block 1 , two adjacent blocks 2 and several standard blocks 3 . And two capping block 1 positions of adjacent two lining rings 4 are mirror-symmetrical about the vertical line that passes lining ring 4 center, to guarantee the accuracy of lining segment assembling.

S5、重复步骤S4,直至完成全部衬砌环的拼装。S5. Step S4 is repeated until the assembly of all lining rings is completed.

通过重复错缝拼装,提高隧道结构的纵向刚度。并且拼装方式简单,不增 加额外工作量,有助于在保证安全的前提下提高效率。The longitudinal rigidity of the tunnel structure is improved by repeated staggered assembly. And the assembly method is simple, without adding extra workload, which helps to improve efficiency while ensuring safety.

以下面具体算例说明本专利中最小正应力所在位置θ的计算方法:The following specific calculation example illustrates the calculation method of the minimum normal stress position θ in this patent:

地层结构如图5所示,其中,隧道埋深H为13.6m,管片外径D为6.2m, 管片幅宽B为1.2m,管片厚度t为0.35m,管片重度γc为26kN/m3;封顶块对应 的圆心角β为21.5°,邻接块对应的圆心角γ为68°,标准块对应的圆心角为67.5°; 弹性模量E为3.45e4MPa,水位深Hw为8.12m,水重度γw为10kN/m3,管片中 心半径R为2.925m,重力加速度g为10m/s2。其地层物理力学参数见表1。The stratum structure is shown in Fig. 5, where the buried depth H of the tunnel is 13.6m, the segment outer diameter D is 6.2m, the segment width B is 1.2m, the segment thickness t is 0.35m, and the segment weight γ c is 26kN/m 3 ; the central angle β corresponding to the capping block is 21.5°, the central angle γ corresponding to the adjacent block is 68°, and the central angle corresponding to the standard block is 67.5°; the elastic modulus E is 3.45e 4 MPa, and the water level is H w is 8.12m, water gravity γ w is 10kN/m 3 , segment center radius R is 2.925m, and gravitational acceleration g is 10m/s 2 . The physical and mechanical parameters of the formation are shown in Table 1.

表1地层物理力学参数Table 1 Formation physical and mechanical parameters

S1、首先计算衬砌环4的截面应力分布:S1, first calculate the cross-sectional stress distribution of the lining ring 4:

管片惯性矩I为:The segment moment of inertia I is:

因H=13.65m>1D~2D,因此可采用太沙基公式,公路车辆荷载p0取为: p0=10kPa。Since H=13.65m>1D~2D, Terzaghi formula can be used, and the road vehicle load p 0 is taken as: p 0 =10kPa.

S1-1、首先是上方竖向荷载p1。由于土层为多层,所以采用分层的方法, 从第一层到第六层逐层计算,其计算公式为:S1-1. First, the upper vertical load p 1 . Since the soil layer is multi-layered, the method of layering is adopted and calculated layer by layer from the first layer to the sixth layer. The calculation formula is:

以第一层为例,式中,Pvci为松动土压力,B1为松动带宽度,K0为水平土压 与竖直土压之比,一般取为1;为土的内摩擦角,c1为土的粘着力,c=0; γ1为土的单位体积质量,γ=19kN/m3;H1为上覆土厚度,H=2.46m;p0为上部荷 载,即公路车辆荷载,p0=10kPa;R0为管片外半径,R0=3m。Taking the first layer as an example, in the formula, P vci is the loosening earth pressure, B 1 is the width of the loosening zone, K 0 is the ratio of horizontal earth pressure to vertical earth pressure, which is generally taken as 1; is the internal friction angle of the soil, c 1 is the adhesion force of soil, c=0; γ 1 is the unit volume mass of soil, γ=19kN/m 3 ; H 1 is the thickness of overlying soil, H=2.46m; p 0 is the upper load, that is, the road vehicle load , p 0 =10kPa; R 0 is the outer radius of the segment, R 0 =3m.

代入数据上式可得:Substituting the data into the above formula can get:

依次计算各层松动带宽度Bi和松动土压力Pvci,结果如表2所表示:Calculate the loosening zone width B i and loosening earth pressure P vci of each layer in turn, and the results are shown in Table 2:

表2各层松动带宽度和松动土压Table 2 Width of loose belt and loose soil pressure of each layer

因此,自然平衡拱高h0为:由于h0=4.95m<2D=12.4m,故h0取12.4m;故土层总压力Pvc为:Pvc=∑hiγi=182.51kPa。其中:∑hi=h0=12.4m。Therefore, the natural equilibrium arch height h 0 is: Since h 0 =4.95m<2D=12.4m, h 0 is taken as 12.4m; the total pressure P vc of the original soil layer is: P vc =∑h i γ i =182.51kPa. Where: ∑h i =h 0 =12.4m.

由于上部竖向压力p1为:p1=pe1+pw1,其中上部土压力:pe1=pvc=182.51kPa, 上部水压力:故上部竖向压力p1为: p1=pe1+pw1=265.46kPa。Since the upper vertical pressure p 1 is: p 1 =p e1 +p w1 , where the upper earth pressure: p e1 =p vc =182.51kPa, the upper water pressure: Therefore, the upper vertical pressure p1 is: p 1 =p e1 +p w1 =265.46kPa.

S1-2、顶部侧向压力q1为:q1=λpe1+pw1=0.2×182.51+82.95=119.45kPa。S1-2. Top lateral pressure q 1 is: q 1 =λp e1 +p w1 =0.2×182.51+82.95=119.45kPa.

S1-3、底部侧向压力q2S1-3. Bottom lateral pressure q 2 :

S1-4、地层抗力pkS1-4. Formation resistance p k :

将上述截面应力分布代入最小正应力所在位置θ计算公式,得到:Substituting the above cross-sectional stress distribution into the calculation formula of the minimum normal stress position θ, we get:

θ=122.8031+1.8663D+0.0968p1+0.0332q1-0.1151q2-0.168pk=112.26°。θ=122.8031+1.8663D+0.0968p 1 +0.0332q 1 −0.1151q 2 −0.168p k =112.26°.

S2、根据最小正应力所在位置θ、封顶块1分块角度β、邻接块2分块角度 γ计算初始拼装管片5的位置ω:S2. Calculate the position ω of the initial assembled segment 5 according to the position θ of the minimum normal stress, the block angle β of the capping block 1, and the block angle γ of the adjacent block 2:

S3、将初始拼装管片5放在位置,然后沿衬砌环单向拼装管片。S3. Put the initially assembled segment 5 in position, and then assemble the segments unidirectionally along the lining ring.

S4、将衬砌管片拼装成完整的衬砌环4后,在衬砌环4后侧拼装下一衬砌 环4,且衬砌环4的拼装方向与前一衬砌环4相反,实现错缝拼装。S4, after the lining segments are assembled into a complete lining ring 4, the next lining ring 4 is assembled on the rear side of the lining ring 4, and the assembling direction of the lining ring 4 is opposite to that of the previous lining ring 4, so as to realize the staggered seam assembly.

S5、重复步骤S4,直至完成全部衬砌环4的拼装。S5. Step S4 is repeated until the assembly of all the lining rings 4 is completed.

上面对本发明的具体实施方式进行描述,以便于本技术领域的技术人员理 解本发明,但应该清楚,本发明不限于具体实施方式的范围,对本技术领域的 普通技术人员来讲,只要各种变化在所附的权利要求限定和确定的本发明的精 神和范围内,这些变化是显而易见的,一切利用本发明构思的发明创造均在保 护之列。The specific embodiments of the present invention are described above so that those skilled in the art can understand the present invention, but it should be clear that the present invention is not limited to the scope of the specific embodiments. For those of ordinary skill in the art, as long as various changes Within the spirit and scope of the present invention defined and determined by the appended claims, these changes are obvious, and all inventions and creations using the concept of the present invention are included in the protection list.

Claims (9)

1. A splicing method of a circular shield tunnel lining structure is characterized by comprising the following steps:
S1, calculating the position theta of the minimum normal stress according to the outer diameter D of the lining ring and the cross-sectional stress distribution of the lining ring, and taking the position theta of the minimum normal stress as the position for installing the top sealing block;
s2, calculating an initial splicing segment position omega according to the position theta of the minimum normal stress, the blocking block angle beta of the capping block and the blocking block angle gamma of the adjacent block;
s3, placing the initial assembled duct piece at the position omega, and then assembling the duct piece along the lining ring in a one-way mode;
S4, after lining segments are assembled into a complete lining ring, assembling the next lining ring at the rear side of the lining ring, wherein the assembling direction of the lining ring is opposite to that of the previous lining ring, and realizing staggered assembly;
And S5, repeating the step S4 until the assembly of all lining rings is completed.
2. The method for assembling the circular shield tunnel lining structure according to claim 1, wherein the calculation formula of the minimum normal stress is as follows:
θ=122.8031+1.8663D+0.0968p1+0.0332q1-0.1151q2-0.168pk
Wherein p is1For vertical loading, q1Top lateral pressure, q2As bottom lateral pressure, pkas resistance of the formation, p1、q1、q2and pkis the cross-sectional stress distribution of the lining ring.
3. The method for assembling the lining structure of the circular shield tunnel according to claim 2, wherein the vertical loads comprise an upper vertical load and a lower vertical load, and the vertical load p is p1The calculation method comprises the following steps:
p1=pe1+pw1
Wherein p ise1is the pressure of the upper soil body, pw1Is the upper water body pressure.
4. The method for assembling a circular shield tunnel lining structure according to claim 2, wherein the top lateral pressure q is1The calculation method comprises the following steps:
q1=λpe1+pw1
wherein, the lambda is the lateral pressure coefficient of the soil body.
5. The method for assembling the circular shield tunnel lining structure of claim 4, wherein the bottom lateral pressure q2 is calculated by the following method:
Wherein rho is the soil density, t is the thickness of the pipe piece, and pw2The pressure of the lower water body.
6. The method for assembling a circular shield tunnel lining structure according to claim 5, wherein the formation resistance p iskThe calculation method comprises the following steps:
Wherein k is the formation resistance coefficient, R is the central radius of the pipe piece, g is the gravity acceleration, eta is the bending rigidity, E is the elastic modulus, and I is the inertia moment of the pipe piece.
7. The method for assembling the circular shield tunnel lining structure according to claim 6, wherein the method for calculating the initial assembling segment position ω is as follows:
8. The method for assembling a circular shield tunnel lining structure according to claim 1, wherein the lining ring comprises one capping block, two adjacent blocks and a plurality of standard blocks.
9. The method for assembling the circular shield tunnel lining structure of claim 1, wherein the positions of the two capping blocks of the two adjacent lining rings are mirror-symmetrical with respect to a vertical line passing through the centers of the lining rings.
CN201910706202.0A 2019-09-19 2019-09-19 A kind of assembly method of circular shield tunnel lining structure Active CN110552716B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910706202.0A CN110552716B (en) 2019-09-19 2019-09-19 A kind of assembly method of circular shield tunnel lining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910706202.0A CN110552716B (en) 2019-09-19 2019-09-19 A kind of assembly method of circular shield tunnel lining structure

Publications (2)

Publication Number Publication Date
CN110552716A true CN110552716A (en) 2019-12-10
CN110552716B CN110552716B (en) 2020-05-26

Family

ID=68737188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910706202.0A Active CN110552716B (en) 2019-09-19 2019-09-19 A kind of assembly method of circular shield tunnel lining structure

Country Status (1)

Country Link
CN (1) CN110552716B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113073994A (en) * 2020-01-06 2021-07-06 上海申通地铁集团有限公司 Novel subway shield tunnel segment splicing process
CN113551986A (en) * 2021-07-24 2021-10-26 郑州大学 Indoor testing device and testing method for static soil pressure coefficient in complex stress state
CN114562281A (en) * 2022-03-22 2022-05-31 上海隧道工程有限公司 Control method and system for splicing machine capable of synchronously splicing segments in shield propulsion

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9165102B1 (en) * 2014-04-07 2015-10-20 Freescale Semiconductor, Inc. Routing standard cell-based integrated circuits
CN106096162A (en) * 2016-06-21 2016-11-09 西南交通大学 A kind of method determining shield support pressure and mathematical model thereof and construction method
CN106599346A (en) * 2016-11-03 2017-04-26 上海隧道工程有限公司 Method for calculating triangular resistance load of shield tunnel in compound stratum
CN106948837A (en) * 2017-05-26 2017-07-14 西南交通大学 A kind of shield tunnel liner ring for being adapted to quick subway line
CN107143349A (en) * 2017-06-06 2017-09-08 中铁十九局集团轨道交通工程有限公司 Shield duct piece, which binds, the assembled device of block and applies method
CN107798166A (en) * 2017-09-18 2018-03-13 广东省水利水电科学研究院 Load structure collective effect computational methods under Shield tunnel composite lining internal water pressure
CN110130931A (en) * 2019-06-28 2019-08-16 西南交通大学 A Blocking Method for Symmetrical Lining Ring of Circular Shield Tunnel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9165102B1 (en) * 2014-04-07 2015-10-20 Freescale Semiconductor, Inc. Routing standard cell-based integrated circuits
CN106096162A (en) * 2016-06-21 2016-11-09 西南交通大学 A kind of method determining shield support pressure and mathematical model thereof and construction method
CN106599346A (en) * 2016-11-03 2017-04-26 上海隧道工程有限公司 Method for calculating triangular resistance load of shield tunnel in compound stratum
CN106948837A (en) * 2017-05-26 2017-07-14 西南交通大学 A kind of shield tunnel liner ring for being adapted to quick subway line
CN107143349A (en) * 2017-06-06 2017-09-08 中铁十九局集团轨道交通工程有限公司 Shield duct piece, which binds, the assembled device of block and applies method
CN107798166A (en) * 2017-09-18 2018-03-13 广东省水利水电科学研究院 Load structure collective effect computational methods under Shield tunnel composite lining internal water pressure
CN110130931A (en) * 2019-06-28 2019-08-16 西南交通大学 A Blocking Method for Symmetrical Lining Ring of Circular Shield Tunnel

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113073994A (en) * 2020-01-06 2021-07-06 上海申通地铁集团有限公司 Novel subway shield tunnel segment splicing process
CN113551986A (en) * 2021-07-24 2021-10-26 郑州大学 Indoor testing device and testing method for static soil pressure coefficient in complex stress state
CN113551986B (en) * 2021-07-24 2024-01-19 郑州大学 Indoor testing device and method for static soil pressure coefficient under complex stress state
CN114562281A (en) * 2022-03-22 2022-05-31 上海隧道工程有限公司 Control method and system for splicing machine capable of synchronously splicing segments in shield propulsion

Also Published As

Publication number Publication date
CN110552716B (en) 2020-05-26

Similar Documents

Publication Publication Date Title
CN110552716A (en) Assembling method of circular shield tunnel lining structure
CN106988346B (en) Immersed tube tunnel final joint, prefabrication method and installation method
CN109667598B (en) Tunnel composite lining design method based on total safety factor method
CN113361169B (en) An efficient prediction method for the longitudinal deformation of shield tunnel caused by sudden surface loading
CN104047610B (en) Composite lining structure
CN110245401A (en) An evaluation method for the impact of shield tunnel underpass on existing shield tunnels
CN104612724A (en) Splicing structure for pipe pieces of ellipse-like shield tunnel with stand column
CN112329122B (en) Method for determining transverse deformation and internal force of shield tunnel caused by excavation of side foundation pit
CN102392643A (en) Under-building filling, mining and coal pillar recovering method
CN106087742A (en) A kind of suspension bridge pier-stage type prestressing force anchorage
CN108362856A (en) The bath scaled model experimental device of the highly dense area ground long-term settlement in simcity
CN114329680B (en) A stability evaluation method for underground reservoir pillar dam in mining area and its application
CN106285775A (en) Cover goaf filling under a kind of structures and expand bag and construction method
CN106897475A (en) A kind of shallow shield tunnel minimum overburden layer thickness under water that covers determines method and its system
CN204646256U (en) A kind of general ring liner structure of Shield-bored tunnels strengthening gauge surplus capacity
CN104879136A (en) Supporting and protecting system for tunnel penetrating weak and broken formations of karst cave and mounting method of supporting and protecting system
CN113688461A (en) Method and system for determining critical height of reinforced retaining wall
CN116771372B (en) Arrangement method of roadway intersection points for abandoned roadway space compressed air energy storage
CN113221233B (en) Composite soil layer shield tunnel cross section design method and shield tunnel
CN114811186B (en) Submarine pipeline anti-collision seepage-prevention and vibration-suppression device and method
CN117473603A (en) Simulation method for stress characteristics of large-diameter shield tunnel opening expansion segments
CN203639941U (en) Balance weight type retaining wall
CN109635454A (en) A kind of determination method of class rectangle shield tunnel longitudinal direction equivalent bending stiffness
CN101457649A (en) Double upright post lining structure of double-circle shield-tunneling-method tunnel
CN110130931A (en) A Blocking Method for Symmetrical Lining Ring of Circular Shield Tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant