CN110541422A - Construction method for tunnel crossing hole bias landslide zone - Google Patents
Construction method for tunnel crossing hole bias landslide zone Download PDFInfo
- Publication number
- CN110541422A CN110541422A CN201910839131.1A CN201910839131A CN110541422A CN 110541422 A CN110541422 A CN 110541422A CN 201910839131 A CN201910839131 A CN 201910839131A CN 110541422 A CN110541422 A CN 110541422A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- landslide
- arch
- excavation
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 43
- 238000009412 basement excavation Methods 0.000 claims abstract description 29
- 238000005507 spraying Methods 0.000 claims abstract description 6
- 239000002689 soil Substances 0.000 claims abstract description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 20
- 239000010959 steel Substances 0.000 claims description 20
- 230000001680 brushing effect Effects 0.000 claims description 10
- 238000000034 method Methods 0.000 claims description 10
- 238000013461 design Methods 0.000 claims description 4
- 238000005553 drilling Methods 0.000 claims description 2
- 238000011835 investigation Methods 0.000 claims description 2
- 239000004570 mortar (masonry) Substances 0.000 claims description 2
- 230000001012 protector Effects 0.000 claims description 2
- 238000009991 scouring Methods 0.000 claims description 2
- 239000002352 surface water Substances 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 abstract description 2
- 230000001681 protective effect Effects 0.000 abstract 2
- 239000011435 rock Substances 0.000 abstract 2
- 238000011161 development Methods 0.000 description 2
- 230000000903 blocking effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000000275 quality assurance Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/202—Securing of slopes or inclines with flexible securing means
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/04—Pipes or fittings specially adapted to sewers
- E03F3/046—Open sewage channels
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- General Engineering & Computer Science (AREA)
- Paleontology (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Health & Medical Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The invention discloses a construction method for a tunnel to pass through a tunnel portal bias landslide zone, and relates to a tunnel portal bias landslide processing scheme and a tunnel arch protection cover excavation construction method. Before the tunnel passes through the hole and biases the landslide zone, in order to prevent the tunnel construction from disturbing the landslide zone, firstly reinforcing the landslide zone by adopting a duct grouting and anchor spraying mode, and constructing an anti-slide retaining wall to prevent the landslide zone from biasing and sliding; and secondly, before the tunnel portal is excavated, building a protective arch above the tunnel arch part, and covering and excavating the tunnel under the protection of the protective arch to ensure the construction safety. The construction method is suitable for the construction of tunnel engineering in mountain tunnels and urban shallow-buried tunnels in landslide sections, requires poor geological conditions of surrounding rocks at the tunnel opening, is a strongly weathered rock stratum or soil layer, and is suitable for mechanical excavation of tunnel bodies.
Description
Technical Field
The invention relates to a construction scheme for a tunnel to pass through a bias landslide zone, in particular to a tunnel portal bias landslide treatment scheme and a tunnel arch protection cover excavation construction method.
Background
in recent years, according to the development planning of the state 'five longitudinal directions and seven transverse directions', the highway construction in China enters a rapid development period, tunnel engineering is more and more commonly applied to the highway construction and is limited by mountainous terrain, tunnel lines often need to pass through valleys with complex geology, a plurality of tunnel holes are positioned in a shallow-buried bias landslide area, so that the tunnel is very difficult to enter and exit, and the existing tunnel-passing landslide area usually adopts a construction method of unloading, reinforcing and avoiding winding, so that the following problems exist
1. The engineering quantity is large. When a landslide body at a tunnel entrance is unloaded, the slope of a mountain is often required to be slowed down to ensure the stability of the landslide surface under the influence of a landslide fracture surface, so that the unloading work amount of the landslide body is large, the influence range is large, and secondary landslide of the mountain is often caused if the landslide body is not properly treated;
2. the cost is high. When the landslide body is protected and reinforced, the landslide body is large in area and wide in range, and a large amount of grouting, blocking and protecting and the like are needed, so that the engineering cost is greatly increased;
3. The safety quality assurance coefficient is low. When the tunnel cave slope zone is processed, secondary landslide is generated due to disturbance caused by unloading, construction safety is threatened, in addition, in the construction process, due to large engineering quantity, the construction period is long, the exposure time of workers in the landslide zone range is long, and safety problems are easily caused. Even if the tunnel enters the tunnel smoothly, in the operation process of the highway, the phenomena of debris flow and landslide can be generated in rainy seasons under the influence of outdoor weather, and the operation safety of the highway is not facilitated.
Disclosure of Invention
the invention aims to provide a construction scheme of a tunnel through landslide zone, which has the advantages of short construction period, low cost and guaranteed safety quality, aiming at the defects of the background technology and according to the principle that a tunnel entrance is early in and late out.
the technical scheme of the invention is a construction method of a tunnel crossing hole bias landslide zone, which comprises the following construction processes:
s1 digging a masonry intercepting ditch around the bias landslide zone.
S2, temporarily brushing the slope of the slide edge body, wherein the slope brushing rate is 1: 1-1: 1.5.
and protecting the slope surface of S3 by adopting a net hanging and an anchor spraying.
S4, vertically drilling small guide pipes along the slope surface, and grouting.
And S5, driving a steel pipe pile into the landslide on the side, close to the landslide mountain, of the tunnel.
S6 building the anti-slide retaining wall along the side of the tunnel departing from the landslide mountain.
S7, excavating a soil mould, and pouring the concrete arch ring.
and S8, backfilling for the first time, wherein the backfilling height is controlled to be 2m at the vault.
And S9, changing open excavation into underground excavation, wherein the excavation mode adopts an annular excavation soil-retention method.
And S10 carrying out secondary backfilling on the arch.
the method is characterized in that the brushing is carried out before tunnel arch protection excavation, the brushing range cannot be too large, only the range of a landslide body influencing the tunnel arch protection construction is brushed, and a water cut trench needs to be built along the outer side of the landslide body before the brushing.
the steel pipe pile and the ground form an included angle range larger than 45 degrees, the steel pipe pile is driven into the bedrock, if the steel pipe pile does not enter the bedrock, the length of the steel pipe pile needs to be increased, grouting is conducted, and the bearing capacity of the tunnel arch protection foundation is improved.
The inner mold of the arch protector adopts a soil mold, one end of the arch springing is positioned on the steel pipe pile, and the other end is arranged on the anti-slip retaining wall.
From the above description, the construction method for the tunnel to pass through the bias landslide zone has the following advantages: (1) follow the principle that the tunnel advances early and goes out late, through reducing the tunnel open cut tunnel, the slip mass of entrance to a cave is kept away to the dark hole of extension tunnel, reduces the construction risk that unfavorable geology brought. (2) The landslide body is only needed to be brushed and protected simply, large-area unloading and treatment are not needed, the engineering quantity is small, and the construction cost is saved. (3) And the earth mould is used as the inner mould of the arch protection, so that the cost is low and the construction period is short. (4) The tunnel excavation is carried out under the arch protection, the influence of external weather is avoided, and the construction is safe.
Drawings
FIG. 1 is a cross-sectional view of a tunnel through landslide with an arch guard cover excavated;
Detailed Description
Referring to fig. 1, the technical scheme adopted by the invention is a construction method of a tunnel crossing cave entrance bias landslide zone, and the flow of the construction method is as follows:
1) before tunnel construction, the geological condition and the influence range of a tunnel bias landslide zone are subjected to field investigation, and the construction length of changing a tunnel open cut tunnel into a blind hole for excavation is determined.
2) And (4) excavating a masonry intercepting ditch on the periphery of the bias landslide zone to prevent surface water from scouring a mountain slope above the tunnel to cause landslide mass sliding.
3) The landslide body that influences in the tunnel construction scope carries out interim brush slope and protection, and the brush slope rate is 1: 1-1: 1.5, the slope surface of the sliding edge body is protected by adopting net hanging and anchor spraying, C25 concrete is sprayed, the thickness is not 10cm, the steel bar net phi is 6mm, the grid interval is 20 x 20cm, the anchor rod adopts a phi 22mm mortar anchor rod, the length is 4m, the interval is 1.5 x 1.5m, and the plum blossom type arrangement is adopted.
4) And small guide pipes are vertically arranged along the slope, the small guide pipes are made of phi 42 steel flower pipes, the length L is 3.0m, the distance between every two adjacent guide pipes is 1.5 x 1.5m, and the small guide pipes are arranged in a quincunx manner.
5) And (3) driving a steel pipe pile into the landslide at the side of the tunnel close to the landslide mountain, wherein the arched position of the tunnel is provided with an outer diameter phi 89mm, the length 15m and a crossing angle with the ground of 45 degrees.
6) and an anti-slip retaining wall is built on one side, deviating from the landslide mountain body, of the tunnel, the retaining wall is built by M10 grouted rubbles, and an arch protection base of the tunnel is reserved on the back side of the retaining wall.
7) And excavating an earth arch outside the excavation contour line of the tunnel vault, and pouring a concrete arch ring by using an earth mould, wherein one end of the arch ring is supported by a lock pin steel pipe arranged in the landslide mountain body, and the other end of the arch ring is supported on a base reserved behind the anti-skidding retaining wall.
8) And (4) finishing the manufacturing of the arch ring, and after the design strength is reached, primarily backfilling the top of the tunnel, wherein the backfilling height is controlled to be 2m of the arch top.
9) the tunnel is changed from open excavation to underground excavation, mechanical excavation is adopted under the protection of the arch ring, and the excavation mode adopts an annular excavation soil-centered method.
10) and (5) completing the excavation of the tunnel body, and timely constructing a secondary lining and a tunnel portal. And the arch top is backfilled for the second time, the height of the side slope and the upward slope of the tunnel is reduced, and the slip of the landslide body is controlled.
the above description is only an embodiment of the present invention, but the design concept of the present invention is not limited thereto, and any insubstantial modifications made by using the design concept should fall within the scope of infringing the present invention.
Claims (5)
1. a construction method of a tunnel crossing hole bias landslide zone is characterized by comprising the following steps: the construction process of the construction method is as follows,
s1 excavating a masonry intercepting ditch at the periphery of the bias landslide zone;
S2, temporarily brushing the slope of the slide edge body, wherein the slope brushing rate is 1: 1-1: 1.5;
s3 slope protection is carried out by adopting net hanging and anchor spraying;
s4, vertically drilling small guide pipes along the slope surface, and grouting;
S5, driving a steel pipe pile into the landslide on one side of the tunnel close to the landslide mountain;
S6, building an anti-slip retaining wall along one side of the tunnel, which is far away from the landslide mountain;
S7, excavating a soil mold, and pouring a concrete arch ring;
S8, backfilling for the first time, wherein the backfilling height is controlled to be 2m of the vault;
S9, changing open excavation into underground excavation, wherein the excavation mode adopts an annular excavation soil-retention method;
And S10 carrying out secondary backfilling on the arch.
2. the construction method of the tunnel crossing hole bias landslide zone according to claim 1, wherein: the method is characterized in that the brushing is carried out before tunnel arch protection excavation, the brushing range cannot be too large, only the range of a landslide body influencing the tunnel arch protection construction is brushed, and a water cut trench needs to be built along the outer side of the landslide body before the brushing.
3. the construction method of the tunnel crossing hole bias landslide zone according to claim 1, wherein: the steel pipe pile and the ground form an included angle range larger than 45 degrees, the steel pipe pile is driven into the bedrock, and if the steel pipe pile does not enter the bedrock, the length of the steel pipe pile needs to be increased, and grouting is carried out.
4. The construction method of the tunnel crossing hole bias landslide zone according to claim 1, wherein: the inner mold of the arch protector adopts a soil mold, one end of the arch springing is positioned on the steel pipe pile, and the other end is arranged on the anti-slip retaining wall.
5. The construction method of the tunnel crossing hole bias landslide zone according to claim 1, wherein: the construction method comprises the following steps:
1) Before tunnel construction, carrying out field investigation on the geological condition and the influence range of a tunnel bias landslide zone, and determining the construction length of changing a tunnel open cut tunnel into a blind hole for excavation;
2) Excavating a masonry intercepting ditch at the periphery of the bias landslide zone to prevent surface water from scouring a mountain slope above the tunnel to cause landslide mass sliding;
3) the landslide body that influences in the tunnel construction scope carries out interim brush slope and protection, and the brush slope rate is 1: 1-1: 1.5, protecting the slope surface of the edge slipping body by adopting net hanging and anchor spraying, spraying C25 concrete, wherein the thickness is less than 10cm, the steel bar net phi is 6mm, the grid interval is 20 x 20cm, the anchor rod adopts a phi 22mm mortar anchor rod, the length is 4m, the interval is 1.5 x 1.5m, and the arrangement is in a quincunx shape;
4) Vertically arranging small guide pipes along the slope, wherein the small guide pipes are phi 42 steel flower pipes, the length L is 3.0m, the distance is 1.5 x 1.5m, and the small guide pipes are arranged in a quincunx shape;
5) A steel pipe pile is arranged in the landslide at the side of the tunnel close to the landslide mountain, the arch waist of the tunnel, the outer diameter phi 89mm, the length 15m and the intersection angle with the ground are 45 degrees;
6) Building an anti-slip retaining wall along one side of the tunnel, which is far away from the landslide mountain, wherein the retaining wall is built by M10 grouted rubbles, and an arch protection base of the tunnel is reserved on the back side of the retaining wall;
7) Excavating an earth arch outside an excavation contour line of the vault of the tunnel, pouring a concrete arch ring by using an earth mould, wherein one end of the arch ring is supported by a lock pin steel pipe arranged in a landslide mountain body, and the other end of the arch ring is supported on a base reserved behind an anti-skidding retaining wall;
8) After the arch ring is manufactured and the design strength is reached, primarily backfilling the top of the tunnel, wherein the backfilling height is controlled to be 2m of the arch top;
9) The tunnel is changed from open excavation to underground excavation, mechanical excavation is adopted under the protection of an arch ring, and an annular excavation soil-centered method is adopted in the excavation mode;
10) the hole body is excavated and constructed to form a secondary lining and a tunnel portal in time; and the arch top is backfilled for the second time, the height of the side slope and the upward slope of the tunnel is reduced, and the slip of the landslide body is controlled.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910839131.1A CN110541422A (en) | 2019-09-05 | 2019-09-05 | Construction method for tunnel crossing hole bias landslide zone |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910839131.1A CN110541422A (en) | 2019-09-05 | 2019-09-05 | Construction method for tunnel crossing hole bias landslide zone |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110541422A true CN110541422A (en) | 2019-12-06 |
Family
ID=68712627
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910839131.1A Pending CN110541422A (en) | 2019-09-05 | 2019-09-05 | Construction method for tunnel crossing hole bias landslide zone |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110541422A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111322087A (en) * | 2020-04-22 | 2020-06-23 | 四川省商业建设有限责任公司 | Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area |
CN111608701A (en) * | 2020-06-02 | 2020-09-01 | 中铁隧道局集团有限公司 | Method for treating roof collapse of shallow tunnel entrance section |
CN111648790A (en) * | 2020-06-12 | 2020-09-11 | 安徽省公路桥梁工程有限公司 | Shallow-buried bias tunnel entry structure and construction method |
CN111911183A (en) * | 2020-07-01 | 2020-11-10 | 中铁二院重庆勘察设计研究院有限责任公司 | Tunnel hole entering construction method based on end wall type guide wall structure |
CN112127900A (en) * | 2020-09-07 | 2020-12-25 | 中国水利水电第十四工程局有限公司 | Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body |
CN112502188A (en) * | 2020-12-10 | 2021-03-16 | 河南博源电力设备股份有限公司 | Power communication comprehensive pipe rack in easy-to-slide area and construction method thereof |
CN113186842A (en) * | 2021-05-08 | 2021-07-30 | 四川省交通勘察设计研究院有限公司 | Treatment method capable of permanently preventing top of open cut tunnel from being overloaded |
CN113622978A (en) * | 2021-08-26 | 2021-11-09 | 中国水电基础局有限公司 | Construction process of buried deep support of semi-open and semi-concealed bias tunnel |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100656194B1 (en) * | 2006-05-03 | 2006-12-13 | 은산토건(주) | Open cut and cover method applying tunnel cut method |
CN106321106A (en) * | 2015-06-30 | 2017-01-11 | 中交二公局第六工程有限公司 | Construction method for tunnel-entering of tunnel weak surrounding rock and semi-open and semi-underground bias section portal abutment |
CN108625879A (en) * | 2018-05-28 | 2018-10-09 | 中铁第勘察设计院集团有限公司 | Mountain Tunnels half-open and half-hidden structure and its construction method |
-
2019
- 2019-09-05 CN CN201910839131.1A patent/CN110541422A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100656194B1 (en) * | 2006-05-03 | 2006-12-13 | 은산토건(주) | Open cut and cover method applying tunnel cut method |
CN106321106A (en) * | 2015-06-30 | 2017-01-11 | 中交二公局第六工程有限公司 | Construction method for tunnel-entering of tunnel weak surrounding rock and semi-open and semi-underground bias section portal abutment |
CN108625879A (en) * | 2018-05-28 | 2018-10-09 | 中铁第勘察设计院集团有限公司 | Mountain Tunnels half-open and half-hidden structure and its construction method |
Non-Patent Citations (4)
Title |
---|
唐维东: "山岭隧道浅埋段盖挖法施工技术", 《工程建设》 * |
李开军等: "浅埋偏压软弱土层山岭隧道盖挖法施工技术研究", 《基层建设》 * |
段志凡: "半明半暗开挖工法在隧道工程中的实际应用与探讨", 《建筑建材装饰》 * |
苑雪飞: "半明半暗浅埋偏压隧道非对称式护拱施工技术研究", 《铁道建筑技术》 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111322087A (en) * | 2020-04-22 | 2020-06-23 | 四川省商业建设有限责任公司 | Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area |
CN111608701A (en) * | 2020-06-02 | 2020-09-01 | 中铁隧道局集团有限公司 | Method for treating roof collapse of shallow tunnel entrance section |
CN111608701B (en) * | 2020-06-02 | 2022-04-26 | 中铁隧道局集团有限公司 | Method for treating roof collapse of shallow tunnel entrance section |
CN111648790A (en) * | 2020-06-12 | 2020-09-11 | 安徽省公路桥梁工程有限公司 | Shallow-buried bias tunnel entry structure and construction method |
CN111648790B (en) * | 2020-06-12 | 2023-03-14 | 安徽省公路桥梁工程有限公司 | Shallow-buried bias tunnel entry structure and construction method |
CN111911183B (en) * | 2020-07-01 | 2022-03-04 | 中铁二院重庆勘察设计研究院有限责任公司 | Tunnel hole entering construction method based on end wall type guide wall structure |
CN111911183A (en) * | 2020-07-01 | 2020-11-10 | 中铁二院重庆勘察设计研究院有限责任公司 | Tunnel hole entering construction method based on end wall type guide wall structure |
CN112127900A (en) * | 2020-09-07 | 2020-12-25 | 中国水利水电第十四工程局有限公司 | Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body |
CN112502188B (en) * | 2020-12-10 | 2022-03-22 | 河南博源电力设备股份有限公司 | Power communication comprehensive pipe rack in easy-to-slide area and construction method thereof |
CN112502188A (en) * | 2020-12-10 | 2021-03-16 | 河南博源电力设备股份有限公司 | Power communication comprehensive pipe rack in easy-to-slide area and construction method thereof |
CN113186842A (en) * | 2021-05-08 | 2021-07-30 | 四川省交通勘察设计研究院有限公司 | Treatment method capable of permanently preventing top of open cut tunnel from being overloaded |
CN113622978A (en) * | 2021-08-26 | 2021-11-09 | 中国水电基础局有限公司 | Construction process of buried deep support of semi-open and semi-concealed bias tunnel |
CN113622978B (en) * | 2021-08-26 | 2024-05-24 | 中国水电基础局有限公司 | Construction process of semi-bright and semi-dark bias tunnel buried type deep support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110541422A (en) | Construction method for tunnel crossing hole bias landslide zone | |
CN108194102B (en) | The dismounting of limit section and safe stress check calculation construction method are invaded in Tunnel deformation | |
CN103321230B (en) | The deep big foundation pit excavation method in place is passed through in the long distance of operation shallow embedding subway | |
CN104278993B (en) | A kind of bias voltage Skew Tunnel enters the constructional method in hole | |
CN103206219A (en) | Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method | |
CN108979659B (en) | Reinforcing structure and method for underpass structure of soft soil water-rich large-section tunnel group | |
CN102518470B (en) | Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel | |
CN103967504B (en) | A kind of supporting construction and construction method of electric power plant circulating water system tunnel mouth | |
CN110107310A (en) | A kind of construction method at tunnel slope hole | |
CN105134219B (en) | Soft rock strata freezing shaft borehole wall construction technology | |
CN102162250B (en) | Protective construction method of excavating large area deep foundation pit in running sand confined water soil layer | |
CN106121659B (en) | The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one kind | |
CN108625879A (en) | Mountain Tunnels half-open and half-hidden structure and its construction method | |
CN108678753B (en) | Reverse-slope tunnel construction method | |
CN110259490A (en) | A kind of Underground Subway Station construction method | |
CN111852515A (en) | Tunnel stratum pre-reinforcement comprehensive grouting method | |
CN111365020A (en) | Back-pressure backfill construction method suitable for biased hole entry under poor geological conditions | |
CN102808627A (en) | Underground excavation construction method of steel pipe shed | |
CN207033463U (en) | Mine shield handing-over tunnel folded type joint design in the middle part of marine site | |
CN208717894U (en) | One kind entering 30 meters of construction of diaphragm wall structures of rock close to subway | |
CN113931637A (en) | Shallow-buried water-rich softer rock tunnel construction method | |
CN113026757A (en) | Rapid excavation and support construction method for complex stratum pipe-jacking comprehensive well | |
CN111561262A (en) | Hole forming method of rotary drilling rig for large-size pile hole in karst area | |
CN206873466U (en) | One kind is used for footrill flume section safeguard structure | |
CN110500112A (en) | Earth pressure balanced shield, EPBS is parallel with shallow burial hidden digging tunnel to overlap construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191206 |