CN110533908A - A kind of road construction management method based on intelligent road measuring device - Google Patents
A kind of road construction management method based on intelligent road measuring device Download PDFInfo
- Publication number
- CN110533908A CN110533908A CN201910828413.1A CN201910828413A CN110533908A CN 110533908 A CN110533908 A CN 110533908A CN 201910828413 A CN201910828413 A CN 201910828413A CN 110533908 A CN110533908 A CN 110533908A
- Authority
- CN
- China
- Prior art keywords
- measuring device
- construction
- section
- traffic
- road
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G08—SIGNALLING
- G08G—TRAFFIC CONTROL SYSTEMS
- G08G1/00—Traffic control systems for road vehicles
- G08G1/01—Detecting movement of traffic to be counted or controlled
- G08G1/0104—Measuring and analyzing of parameters relative to traffic conditions
- G08G1/0125—Traffic data processing
-
- G—PHYSICS
- G08—SIGNALLING
- G08G—TRAFFIC CONTROL SYSTEMS
- G08G1/00—Traffic control systems for road vehicles
- G08G1/01—Detecting movement of traffic to be counted or controlled
- G08G1/017—Detecting movement of traffic to be counted or controlled identifying vehicles
- G08G1/0175—Detecting movement of traffic to be counted or controlled identifying vehicles by photographing vehicles, e.g. when violating traffic rules
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Quality & Reliability (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Educational Administration (AREA)
- Chemical & Material Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Analytical Chemistry (AREA)
- Traffic Control Systems (AREA)
Abstract
The present invention relates to road construction administrative skill fields, in particular a kind of road construction management method based on intelligent road measuring device, the following steps are included: step S1, intelligent road measuring device is thrown to starting point and the end of construction section before carrying out construction operation by base layer construction personnel;Step S2, base layer construction personnel open intelligent road measuring device before carrying out construction operation, carry out the detection of traffic situation, collect section passage situation data;Step S3 obtains the origin coordinates and end coordinate in maintenance section in real time by intelligent road side equipment location information;Step S4, by section passage situation data and in real time, the information such as the origin coordinates in maintenance section and end coordinate are transmitted to traffic large data center to intelligent road measuring device;Step S5, traffic large data center cooperate section passage situation to carry out Real-Time Scheduling to the time of road construction and section.The present invention can Real-Time Scheduling road construction time and section, the working efficiency of road construction management has been significantly greatly increased.
Description
Technical field
The present invention relates to road construction administrative skill field, especially a kind of road construction pipe based on intelligent road measuring device
Reason method.
Background technique
Expressway Road maintenance influences road, often will cause the congestion in maintenance section, and existing mode lacks
Intelligentized management means, can not be before and after the accurate section of real time automatic update road maintenance, construction speed and maintenance section
Congestion in road situation is unable to satisfy the requirement of fining road maintenance management.
Summary of the invention
The purpose of the present invention is to solve disadvantages existing in the prior art, and the one kind proposed is based on intelligent drive test and sets
Standby road construction management method.
To achieve the goals above, present invention employs following technical solutions:
A kind of road construction management method based on intelligent road measuring device, which comprises the following steps:
Step S1, base layer construction personnel are thrown to rising for construction section before carrying out construction operation, by intelligent road measuring device
Beginning and end;
Step S2, base layer construction personnel open intelligent road measuring device before carrying out construction operation, carry out traffic state
Gesture detection, collects section passage situation data;
Step S3 obtains the origin coordinates in maintenance section in real time and terminates to sit by the location information of intelligent road side equipment
Mark;
Step S4, intelligent road measuring device sit section passage situation data and the in real time origin coordinates in maintenance section and end
The information such as mark are transmitted to traffic large data center;
Step S5, traffic large data center are sat by received section passage situation data and the in real time starting in maintenance section
Mark and end coordinate understand the section passage situation in maintenance section, and cooperate section passage situation to road construction
Time and section carry out Real-Time Scheduling;
Step S6, by by section passage situation data and the origin coordinates and the information such as end coordinate in maintenance section in real time
It is transmitted to traffic large data center, traffic large data center is given section passage situation data publication to traffic key application, provided
Traffic construction early warning, automatic event are reported and submitted, and traffic is quickly sued and laboured, the wisdom construction external member of construction trackside perception.
Preferably, the step S1, intelligent road measuring device is interior to be equipped with video analysis unit, Beidou/GPS positioning unit, is used to
Property navigation elements, input and output processing unit and 4G wireless communication transmissions unit.
Preferably, the step S1, intelligent road measuring device investigative range are≤200 meters.
Preferably, the step S2, the detection of traffic situation are acquisition license plate.
Preferably, the step S4, it is wireless to be transmitted through 4G for data between intelligent road measuring device and traffic large data center
Communication is transmitted.
Preferably, the step S6, traffic key, which is applied, includes traffic navigation software, existing wisdom cloud platform and wisdom
High-velocity cloud control brain.
Compared with prior art, the invention has the following advantages:
1, the present invention with it is a kind of based on the road construction management method of intelligent road measuring device to road construction during, pass through
Intelligent road measuring device detects the traffic situation within the scope of 200 meters of roadside device, and evaluation and test is satisfied the need due to road maintenance
The influence of section passage situation, intelligent road measuring device is interior to be equipped with video analysis unit, Beidou/GPS positioning unit, inertial navigation list
Member, input and output processing unit and 4G wireless communication transmissions unit, traffic large data center can accurately be incuded by equipment
Road conserves the starting in section, terminates state, and the traffic grade in section can be conserved with real-time perception, reduces road maintenance and causes
Congested in traffic fails to report, conceals phenomenon, secondly, passing through the origin coordinates and the end that conserve section by traffic grade and in real time
The information such as coordinate are transmitted to traffic large data center, information can be distributed to traffic key application by traffic large data center,
Offer traffic construction early warning, automatic event are reported and submitted, and traffic is quickly sued and laboured, the wisdom construction external member such as construction trackside perception, Neng Gouwei
Driver provides accurate information, and changes best route in time, being capable of intuitive, image understanding construction by monitoring and analyzing
Process, quality and road conditions, facilitate time and the section of Real-Time Scheduling road construction, to assist carrying out science, effective construction
Management.
2, the present invention passes through the networking for realizing influence real time information acquisition of the road maintenance to section passage situation and can
Depending on change operate, can Real-Time Scheduling road construction time and section, the working efficiency of road construction management has been significantly greatly increased.
3, the intelligent road measuring device of the present invention can be shifted with the change in road construction section, intelligent road measuring device and traffic
Data are transmitted through 4G wireless communication and are transmitted between large data center, facilitate information to transmit, increase intelligent road measuring device
Transferability and reusability.
In the present invention, it is not directed to part in the device and is the same as those in the prior art or can be realized by using the prior art,
The present invention with it is a kind of based on the road construction management method of intelligent road measuring device to road construction during, set by intelligent drive test
It is standby that traffic situation within the scope of 200 meters of roadside device is detected, it evaluates and tests since road maintenance is to section passage situation
Influence, video analysis unit, Beidou/GPS positioning unit, inertial navigation unit, input and output are equipped in intelligent road measuring device
Processing unit and 4G wireless communication transmissions unit, traffic large data center can accurately incude road maintenance section by equipment
Starting terminates state, and the traffic grade in section can be conserved with real-time perception, reduces road maintenance and causes congested in traffic leakage
It reports, conceal phenomenon, secondly, by passing the information such as the origin coordinates and end coordinate in traffic grade and real-time maintenance section
Traffic large data center is transported to, information traffic key application can be distributed to by traffic large data center, traffic construction is provided
Early warning, automatic event are reported and submitted, and traffic is quickly sued and laboured, and the wisdom construction external member such as construction trackside perception can provide standard for driver
True information, and best route is changed in time, it, being capable of intuitive, image understanding construction progress, quality and road by monitoring and analyzing
Condition, facilitates time and the section of Real-Time Scheduling road construction, to assist carrying out science, effective construction management.
Specific embodiment
Below in conjunction with the embodiment of the present invention, technical scheme in the embodiment of the invention is clearly and completely described,
Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based in the present invention
Embodiment, every other embodiment obtained by those of ordinary skill in the art without making creative efforts, all
Belong to the scope of protection of the invention.
A kind of road construction management method based on intelligent road measuring device, which comprises the following steps:
Step S1, base layer construction personnel are thrown to rising for construction section before carrying out construction operation, by intelligent road measuring device
Beginning and end are equipped with video analysis unit, Beidou/GPS positioning unit, inertial navigation unit, defeated in intelligent road measuring device
Enter to export processing unit and 4G wireless communication transmissions unit, intelligent road measuring device investigative range is≤200 meters;
Step S2, base layer construction personnel open intelligent road measuring device before carrying out construction operation, carry out traffic state
Gesture detection, collects section passage situation data, and the detection of traffic situation is acquisition license plate;
Step S3 obtains the origin coordinates in maintenance section in real time and terminates to sit by the location information of intelligent road side equipment
Mark;
Step S4, intelligent road measuring device sit section passage situation data and the in real time origin coordinates in maintenance section and end
Mark etc. information be transmitted to traffic large data center, between intelligent road measuring device and traffic large data center data be transmitted through 4G without
Line communication is transmitted;
Step S5, traffic large data center are sat by received section passage situation data and the in real time starting in maintenance section
Mark and end coordinate understand the section passage situation in maintenance section, and cooperate section passage situation to road construction
Time and section carry out Real-Time Scheduling;
Step S6, by by section passage situation data and the origin coordinates and the information such as end coordinate in maintenance section in real time
It is transmitted to traffic large data center, traffic large data center is given section passage situation data publication to traffic key application, provided
Traffic construction early warning, automatic event are reported and submitted, and traffic is quickly sued and laboured, and the wisdom construction external member of construction trackside perception, traffic key is answered
With including traffic navigation software, existing wisdom cloud platform and wisdom high-velocity cloud control brain.
Road construction management method implementing procedure based on intelligent road measuring device:
1. launching intelligent road measuring device in the starting point of construction section and end.
2. intelligent road measuring device is opened, by being equipped with video analysis unit, inertial navigation unit in intelligent road measuring device
Acquisition license plate and data analysis traffic situation detection in 200 meters are carried out with input and output processing unit, by shooting road
The road conditions panorama of section sends large data center for the image of shooting and video, realizes secondary identification, be determined more accurately
The arrangement situation on road, the video and picture of candid photograph also may be displayed on large data center command system, straight in real time to cammander
The traffic information of sight.
3. carrying out location information acquisition, the origin coordinates in available real-time maintenance section by Beidou/GPS positioning unit
With end coordinate, so that it is determined that current construction section information.
4. then traffic situation information and the in real time starting in maintenance section are sat by 4G wireless communication transmissions unit
Mark and end coordinate from intelligent road measuring device are transmitted to traffic large data center.
5. traffic large data center according to traffic situation, carries out data aggregate and is distributed to traffic navigation software, existing
Wisdom cloud platform and wisdom high-velocity cloud control brain etc., provide traffic construction early warning, automatic event is reported and submitted, traffic is quickly sued and laboured,
The wisdom construction external member such as construction trackside perception, can provide accurate information, and change best route in time, and root for driver
According to construction traffic information, time and the section of road construction are timely dispatched, it is ensured that have a good transport and communication network, to carry out scientific, effective
Construction management.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (6)
1. a kind of road construction management method based on intelligent road measuring device, which comprises the following steps:
Intelligent road measuring device is thrown to the starting point of construction section before carrying out construction operation by step S1, base layer construction personnel
And end;
Step S2, base layer construction personnel open intelligent road measuring device before carrying out construction operation, carry out the spy of traffic situation
It surveys, collects section passage situation data;
Step S3 obtains the origin coordinates and end coordinate in maintenance section in real time by the location information of intelligent road side equipment;
Step S4, intelligent road measuring device conserve origin coordinates and the end coordinate etc. in section by section passage situation data and in real time
Information is transmitted to traffic large data center;
Step S5, traffic large data center by received section passage situation data and in real time maintenance section origin coordinates with
End coordinate understands the section passage situation in maintenance section, and cooperates section passage situation to the time of road construction
Real-Time Scheduling is carried out with section;
Step S6, by transmitting the information such as the origin coordinates and end coordinate in section passage situation data and real-time maintenance section
To traffic large data center, traffic large data center gives section passage situation data publication to traffic key application, provides traffic
Construction early warning, automatic event are reported and submitted, and traffic is quickly sued and laboured, the wisdom construction external member of construction trackside perception.
2. the road construction management method according to claim 1 based on intelligent road measuring device, which is characterized in that the step
Rapid S1, be equipped in intelligent road measuring device video analysis unit, Beidou/GPS positioning unit, inertial navigation unit, at input and output
Manage unit and 4G wireless communication transmissions unit.
3. the road construction management method according to claim 1 based on intelligent road measuring device, which is characterized in that the step
Rapid S1, intelligent road measuring device investigative range are≤200 meters.
4. the road construction management method according to claim 1 based on intelligent road measuring device, which is characterized in that the step
Rapid S2, the detection of traffic situation are acquisition license plate.
5. the road construction management method according to claim 1 based on intelligent road measuring device, which is characterized in that the step
Rapid S4, data are transmitted through 4G wireless communication and are transmitted between intelligent road measuring device and traffic large data center.
6. the road construction management method according to claim 1 based on intelligent road measuring device, which is characterized in that the step
Rapid S6, traffic key, which is applied, includes traffic navigation software, existing wisdom cloud platform and wisdom high-velocity cloud control brain.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910828413.1A CN110533908A (en) | 2019-09-03 | 2019-09-03 | A kind of road construction management method based on intelligent road measuring device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910828413.1A CN110533908A (en) | 2019-09-03 | 2019-09-03 | A kind of road construction management method based on intelligent road measuring device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110533908A true CN110533908A (en) | 2019-12-03 |
Family
ID=68666680
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910828413.1A Pending CN110533908A (en) | 2019-09-03 | 2019-09-03 | A kind of road construction management method based on intelligent road measuring device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110533908A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117057682A (en) * | 2023-10-12 | 2023-11-14 | 深圳市睿拓新科技有限公司 | Traffic safety evaluation method and system during road construction |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202004000918U1 (en) * | 2003-04-25 | 2004-04-29 | Peters, Heiko | Road warning system, especially for warning of jams/diversions, has first signal device on first sign, especially advising of next exit/entrance, second on one immediately indicating exit/entrance |
CN205369083U (en) * | 2015-12-22 | 2016-07-06 | 安徽达尔智能控制系统股份有限公司 | Intelligence way awl |
CN205644968U (en) * | 2016-04-25 | 2016-10-12 | 长安大学 | Road construction highway section judgement system that blocks up |
CN106571052A (en) * | 2016-10-24 | 2017-04-19 | 深圳市元征科技股份有限公司 | Road condition prompting method, device and system |
KR20180016692A (en) * | 2016-08-05 | 2018-02-19 | (재)경북차량용임베디드기술연구원 | Intelligent idle stop and go control method adaptive to road status |
CN108550275A (en) * | 2018-06-01 | 2018-09-18 | 青岛理工大学 | A kind of road construction local vehicle guidance system |
CN110009933A (en) * | 2019-05-07 | 2019-07-12 | 上海力阳道路加固科技股份有限公司 | A kind of device and method thereof of road construction area monitoring and warning |
CN110117938A (en) * | 2019-05-08 | 2019-08-13 | 中国汽车工程研究院股份有限公司 | A kind of road occupying construction risk control early warning system and its method |
-
2019
- 2019-09-03 CN CN201910828413.1A patent/CN110533908A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202004000918U1 (en) * | 2003-04-25 | 2004-04-29 | Peters, Heiko | Road warning system, especially for warning of jams/diversions, has first signal device on first sign, especially advising of next exit/entrance, second on one immediately indicating exit/entrance |
CN205369083U (en) * | 2015-12-22 | 2016-07-06 | 安徽达尔智能控制系统股份有限公司 | Intelligence way awl |
CN205644968U (en) * | 2016-04-25 | 2016-10-12 | 长安大学 | Road construction highway section judgement system that blocks up |
KR20180016692A (en) * | 2016-08-05 | 2018-02-19 | (재)경북차량용임베디드기술연구원 | Intelligent idle stop and go control method adaptive to road status |
CN106571052A (en) * | 2016-10-24 | 2017-04-19 | 深圳市元征科技股份有限公司 | Road condition prompting method, device and system |
CN108550275A (en) * | 2018-06-01 | 2018-09-18 | 青岛理工大学 | A kind of road construction local vehicle guidance system |
CN110009933A (en) * | 2019-05-07 | 2019-07-12 | 上海力阳道路加固科技股份有限公司 | A kind of device and method thereof of road construction area monitoring and warning |
CN110117938A (en) * | 2019-05-08 | 2019-08-13 | 中国汽车工程研究院股份有限公司 | A kind of road occupying construction risk control early warning system and its method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117057682A (en) * | 2023-10-12 | 2023-11-14 | 深圳市睿拓新科技有限公司 | Traffic safety evaluation method and system during road construction |
CN117057682B (en) * | 2023-10-12 | 2024-01-23 | 深圳市睿拓新科技有限公司 | Traffic safety evaluation method and system during road construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108039053B (en) | A kind of intelligent network connection traffic system | |
WO2021031338A1 (en) | Multiple object tracking and identification method and apparatus based on multi-radar cross-regional networking | |
CA2780820C (en) | Monitoring traffic signal preemption | |
CN202443300U (en) | Dynamic quality remote monitoring system for asphalt mixture paving and rolling | |
CN101840634A (en) | Urban real-time road condition interactive system, device and method based on internet of things | |
CN106384517A (en) | Traffic signal control method based on visual sensing, apparatus and system thereof | |
CN102231231A (en) | Area road network traffic safety situation early warning system and method thereof | |
CN103778794B (en) | Method and device for wirelessly sending traffic signal | |
CN107784835A (en) | Traffic behavior model prediction system and its Forecasting Methodology based on traffic data analyzing | |
CN105187790B (en) | Method, device and system for monitoring working state of vehicle-mounted terminal | |
CN108615376A (en) | A kind of integrative design intersection schemes evaluation method based on video detection | |
CN110033630A (en) | Suggestion device, roadside unit and prompt system for road construction | |
CN106504566B (en) | A kind of traffic website identifying system and method | |
CN110012069A (en) | A kind of vehicle data processing unit, method and vehicle monitoring platform | |
KR100429318B1 (en) | Interactive Road Information System | |
CN110533908A (en) | A kind of road construction management method based on intelligent road measuring device | |
CN115762120A (en) | Holographic sensing early warning system based on whole highway section | |
CN109029481A (en) | A kind of driving route optimization method | |
CN103389709A (en) | Vehicle-mounted information service system of construction machinery and vehicle-mounted terminal | |
CN109472732A (en) | A kind of high-speed integrated management-control method of wisdom and control platform | |
CN108198449A (en) | Path method and system are known in a kind of lorry shipping | |
KR100912463B1 (en) | Load managing intergration system based on the Geographic information system and controlling method for the same | |
Ma et al. | Evaluation of the integrated application of intelligent transportation system technologies using stochastic incident generation and resolution modeling | |
CN115457689A (en) | High-speed station detection auxiliary system and method thereof | |
CN107945558A (en) | It is a kind of that path method and system are seen based on Big Dipper location-based service |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191203 |