CN110528531A - A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post - Google Patents

A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post Download PDF

Info

Publication number
CN110528531A
CN110528531A CN201910704694.XA CN201910704694A CN110528531A CN 110528531 A CN110528531 A CN 110528531A CN 201910704694 A CN201910704694 A CN 201910704694A CN 110528531 A CN110528531 A CN 110528531A
Authority
CN
China
Prior art keywords
pit
foundation pit
fender post
excavation
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910704694.XA
Other languages
Chinese (zh)
Inventor
周逊泉
徐立明
马锡海
史婷
徐长节
孙志浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Hanghai Intercity Railway Co Ltd
Zhejiang University ZJU
East China Jiaotong University
Original Assignee
Zhejiang Hanghai Intercity Railway Co Ltd
Zhejiang University ZJU
East China Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Hanghai Intercity Railway Co Ltd, Zhejiang University ZJU, East China Jiaotong University filed Critical Zhejiang Hanghai Intercity Railway Co Ltd
Priority to CN201910704694.XA priority Critical patent/CN110528531A/en
Publication of CN110528531A publication Critical patent/CN110528531A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The method done close to foundation pit enclosure stake to excavation pit fender post is utilized the invention discloses a kind of, it is described to around excavation pit close to the foundation pit for having excavated completion, the foundation pit for having excavated completion and it is described to excavation pit be inner bearing type building enclosure, the fender post capping beam absolute altitude of the foundation pit for having excavated completion is consistent with the capping beam absolute altitude to excavation pit or support absolute altitude, and the foundation pit for having excavated completion does not start the construction of the main structure of ± 0.0m or more.The method of the present invention, which will close on, has excavated the fender post for completing foundation pit as the fender post to excavation pit, this shares fender post and is connected with to excavation pit retaining design by support, with the structural column of excavation pit by supporting cant beam to be connected, so that the present invention has save the cost, facilitate construction, is conducive to the stable feature of deep pit monitor.

Description

A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post
Technical field
The present invention relates to civil construction project technical field of construction, do more particularly to a kind of using close to foundation pit enclosure stake Method to excavation pit fender post.
Background technique
With the rapid development of Underground Space Excavation, foundation pit surrounding environment more sophisticated, multiple Adjacent Pits excavate simultaneously The case where it is more common.Excavation of foundation pit area constantly increases at the same time, and big foundation pit is separated into small foundation pit in construction and is applied respectively Work also becomes current common method.
It is influenced by the factors such as off-load are excavated, these foundation pits can generate significant impact each other in construction.Previous Design and construction in, often take closing foundation ditch the measure of " isolation ", avoid as far as possible to closing foundation ditch generate disturbance, do so It is not only uneconomical but also can also make foundation pit group's stress unreasonable sometimes.
Summary of the invention
The purpose of the present invention is, close to the case where having excavated completion foundation pit is closed on, propose a kind of utilization for excavation pit The method to excavation pit fender post is done close to foundation pit enclosure stake.
A method of it does using close to foundation pit enclosure stake to excavation pit fender post, it is described to tight around excavation pit Neighbour has excavated the foundation pit of completion, the foundation pit for having excavated completion and it is described to excavation pit be inner bearing type building enclosure, institute State the fender post capping beam absolute altitude for having excavated the foundation pit of completion and the capping beam absolute altitude or support absolute altitude to excavation pit Unanimously, the foundation pit for having excavated completion does not start the construction of the main structure of ± 0.0m or more.
Wherein, the fender post is the building enclosure as the foundation pit for having excavated completion, also as enclosing to excavation pit Protection structure.
Wherein, the fender post is connect with the building enclosure to excavation pit by inner support.
Wherein, the fender post is with the structural column of the foundation pit for having excavated completion by supporting cant beam to connect.
Wherein, the method specifically includes:
(1) it treats excavation pit and carries out enclosure wall design;
(2) enclosure wall for having excavated the foundation pit of completion will be closed on as a part to excavation pit enclosure wall;
(3) it treats excavation pit and is supported arrangement;
(4) fender post is shared with the structural column for the foundation pit for having excavated completion by supporting cant beam to connect, and supports cant beam one end It is connected with the capping beam of shared fender post, the other end of cant beam is supported to be connected with structural column;
(5) the foundation pit support changing structure for use for having excavated completion is reinforced, intersection, which is all made of structural beams and extends to support replacement, to be enclosed The way of purlin, using steel channel connection structure plate and support replacement purlin between structural beams, channel steel both ends are using steel plate gasket top jail.
The invention has the benefit that
(1) saving construction cost: stress is carried out using closing foundation ditch fender post, can reduce to excavation pit building enclosure itself Stress, stake spacing can be increased, supporting section product do it is small, to reduce cost.
(2) safety and stability is considered every possible angle two or more foundation pits by using closing foundation ditch fender post stress, can be with Keep stress system more reasonable, foundation pit is more stable.
Detailed description of the invention
Fig. 1 is that the floor map done close to foundation pit enclosure stake to excavation pit fender post is utilized in the embodiment of the present invention;
Fig. 2 is that the diagrammatic cross-section done close to foundation pit enclosure stake to excavation pit fender post is utilized in the embodiment of the present invention;
Fig. 3 is excavation pit support replacement floor map.
Fig. 4 is the cant beam floor map of excavation pit support.
In figure, 1 is excavation pit, and 2 be shared fender post, and 3 be support, and 4 is, to excavation pit, 5 are to support cant beam, 6 It is capping beam for former capping beam, 7,8 be structure floor, and 9 be support replacement purlin, and 10 be channel steel, and 11 bit architecture beams, 12 be support replacement beam, 13 be structural column.
Specific embodiment
To facilitate the understanding of the present invention, a more comprehensive description of the invention is given in the following sections with reference to the relevant attached drawings.In attached drawing Give several embodiments of the invention.But the invention can be realized in many different forms, however it is not limited to this paper institute The embodiment of description.On the contrary, purpose of providing these embodiments is make it is more thorough and comprehensive to the disclosure.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term " and or " used herein includes one or more phases Any and all combinations of the listed item of pass.
Fig. 1 is to be gone along with sb. to guard him to excavation pit in the embodiment of the present invention using doing close to foundation pit enclosure stake referring to FIG. 1 to FIG. 4, The floor map of stake shares fender post 2, the branch to excavation pit it can be seen that the present embodiment includes excavation pit 1 Support 3, to excavation pit 4.In addition, in figure, 1 is excavation pit, and 2 is share fender post, and 3 be support, and 4 is to excavation pits, 5 To support cant beam, 6 be former capping beam, and 7 be capping beam, and 8 be structure floor, and 9 be support replacement purlin, and 10 be channel steel, 11 bit architecture beams, 12 be support replacement beam, and 13 be structural column.
It is connected with to excavation pit retaining design by support 3 as shown in Fig. 2, the present embodiment shares 2 right side of fender post, 2 left side of fender post is shared with the main structure of excavation pit 4 by supporting cant beam 5 to be connected.
As shown in figure 3, the present embodiment to excavation pit building enclosure because needing to be turned by excavation pit fender post It changes, so excavation pit support changing structure for use needs to reinforce.Specific strengthening measure are as follows: intersection is all made of structural beams 11 and extends to support replacement The way of purlin 9, using channel steel link structure plate 8 and support replacement purlin 9 between structural beams 11.
As shown in figure 4, the present embodiment support 5 one end of cant beam is connected with the capping beam of shared fender post 2, support cant beam 5 The other end is connected with structural column 13.
Unshared fender post part connects excavation pit main structure and fender post, every three rhizospheres shield by support replacement beam 12 Stake sets 12 1, support replacement beam, set on the centre of two fender posts.12 one end of support replacement beam anchors into ground with stake top jail, other end main reinforcement is gone along with sb. to guard him Lower room exterior wall.
Support changing structure for use should all be arranged at two layers of underground and basement one floor absolute altitude.
Support cant beam main reinforcement, which anchors into length in structural column and capping beam, should meet related specification requirement.Support the width of cant beam 5 Degree is answered identical with corresponding 13 width of structural column.The local wide smaller part of column supports the width adjustment of cant beam 5 to same widths, high It spends constant.
Specifically by taking certain engineering is 44 layers of building as an example, 3 layers of underground, basement cutting depth is 16.45m, and basement is not The hexagon of rule.Closing on building is 26 layers of building, and 3 layers of underground, basement cutting depth 16.45m, basement is the four of rule Side shape.As shown in Figure 1, three support systems are arranged in the present embodiment, first of support is arranged on basement the plan view of foundation pit Portion, second support are arranged in the middle part of basement, and for the support setting of third road in basement lower part, three supports are reinforced concrete Soil support.
The utilization of the present embodiment is done close to foundation pit enclosure stake to be specifically included to the method for excavation pit fender post:
(1) to 4 Design of Retaining Structure of excavation pit: building enclosure width is 1000mm, depth 32m, and fender post adopted Concrete is C30.
(2) to 4 supported design of excavation pit: as shown in Figure 1, EF designs angle brace while with BD, GF is designed pair while with CD Support, CG design angle brace while with CD.Support is all made of C30 concrete, supports main reinforcement protective layer thickness 25mm.Bed course is supported to use 10cm thickness C15 plain concrete overlays one layer of malthoid again, and every side bed course width, which is that support is wide, adds 20cm, answers when supporting lower earth excavation Support foot mat is removed and is hurted sb.'s feelings in order to avoid falling.
(3) it has excavated and has completed the foundation pit support design of cant beam 5: as shown in Fig. 2, support 5 one end of cant beam anchors into shared fender post Capping beam 7, as shown in figure 4, support 5 other end of cant beam anchors into structural column 13, support cant beam cross-sectional width is 800 × 800mm, office At the wide 700mm of portion's column, support 5 cross-sectional width of cant beam is adjusted to 700 × 800mm.
(4) excavated and completed the design of foundation pit support replacement: as shown in figures 1 and 3, BD and DC intersection take structural beams 11 to extend To the way of support replacement purlin 9,20b steel channel connection structure plate 8 and support replacement purlin 9 are used between structural beams, channel steel both ends use 10mm thickness 300 × 130mm steel plate gasket top jail.Support changing structure for use should all be arranged at two layers of underground and basement one floor absolute altitude.
(5) support post designs: the vertical upright column of cast-in-situ steel reinforced concrete support system is cast-in-situ bored pile, column top For well word truss, well word truss gos deep into 2m in vertical upright column stake, and newly beating stand column pile strength grade of concrete is C25, utilizing works Stake should also meet Construction of Engineering Pile requirement as the stake of column.The superfilled height for newly beating stand column pile is 1200mm.
The present invention carries out stress using closing foundation ditch fender post, can reduce to excavation pit building enclosure itself by Power can increase stake spacing, supporting section product do it is small, to reduce cost.In addition, by the present invention in that being enclosed with closing foundation ditch Fender pile stress considers every possible angle two or more foundation pits, stress system can be made more reasonable, foundation pit is more stable.
One embodiment of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art For, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to guarantor of the invention Protect range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (5)

1. a kind of utilize the method done close to foundation pit enclosure stake to excavation pit fender post, which is characterized in that the base to be excavated Close to the foundation pit for having excavated completion around hole, the foundation pit for having excavated completion and it is described to excavation pit be that inner bearing type encloses Protection structure, the fender post capping beam absolute altitude of the foundation pit for having excavated completion and the capping beam absolute altitude to excavation pit or Support absolute altitude consistent, the foundation pit for having excavated completion does not start the construction of the main structure of ± 0.0m or more.
2. according to claim 1 using the method to excavation pit fender post is done close to foundation pit enclosure stake, feature exists In the fender post is the building enclosure as the foundation pit for having excavated completion, also as the building enclosure to excavation pit.
3. according to claim 2 using the method to excavation pit fender post is done close to foundation pit enclosure stake, feature exists In the fender post is connect with the building enclosure to excavation pit by inner support.
4. according to claim 3 using the method to excavation pit fender post is done close to foundation pit enclosure stake, feature exists In the fender post is with the structural column of the foundation pit for having excavated completion by supporting cant beam to connect.
5. according to claim 4 using the method to excavation pit fender post is done close to foundation pit enclosure stake, feature exists In the method specifically includes:
(1) it treats excavation pit and carries out enclosure wall design;
(2) enclosure wall for having excavated the foundation pit of completion will be closed on as a part to excavation pit enclosure wall;
(3) it treats excavation pit and is supported arrangement;
(4) fender post is shared with the structural column for the foundation pit for having excavated completion by supporting cant beam to connect, and support cant beam one end is together It is connected with the capping beam of fender post, the other end of cant beam is supported to be connected with structural column;
(5) the foundation pit support changing structure for use for having excavated completion is reinforced, intersection is all made of structural beams and extends to support replacement purlin Way, using steel channel connection structure plate and support replacement purlin between structural beams, channel steel both ends are using steel plate gasket top jail.
CN201910704694.XA 2019-07-31 2019-07-31 A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post Pending CN110528531A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910704694.XA CN110528531A (en) 2019-07-31 2019-07-31 A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910704694.XA CN110528531A (en) 2019-07-31 2019-07-31 A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post

Publications (1)

Publication Number Publication Date
CN110528531A true CN110528531A (en) 2019-12-03

Family

ID=68661726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910704694.XA Pending CN110528531A (en) 2019-07-31 2019-07-31 A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post

Country Status (1)

Country Link
CN (1) CN110528531A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236255A (en) * 2020-03-06 2020-06-05 华东建筑设计研究院有限公司 Support structure capable of realizing cross implementation of adjacent foundation pits and application construction method thereof
CN113090066A (en) * 2021-04-16 2021-07-09 华润建筑有限公司 Construction method for newly added entrances and exits of existing buildings and elevator shaft
CN115288155A (en) * 2022-08-19 2022-11-04 中国一冶集团有限公司 Efficient building method of square-round combined ultra-deep permanent foundation pit supporting structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102465534A (en) * 2010-11-11 2012-05-23 上海市第五建筑有限公司 Construction method for adjacent double ditches
CN205712119U (en) * 2016-03-25 2016-11-23 中铁三局集团广东建设工程有限公司 A kind of little excavation structure closing on deep pit excavation
CN106638669A (en) * 2017-01-04 2017-05-10 中铁十六局集团北京轨道交通工程建设有限公司 System and method for reinforcing envelop enclosure for shield tunneling beneath existing subway station
CN107023015A (en) * 2016-02-01 2017-08-08 上海城地建设股份有限公司 A kind of new prefabricated two walls unification foundation pit system and its contrary sequence method
CN107023016A (en) * 2016-02-01 2017-08-08 上海城地建设股份有限公司 Two walls unification foundation pit system is worn under a kind of road and its along the practice
CN206467684U (en) * 2017-01-04 2017-09-05 中铁十六局集团北京轨道交通工程建设有限公司 Existing subway station building enclosure hardened system is worn under a kind of shield
CN109505298A (en) * 2015-10-26 2019-03-22 张继红 A kind of self-balancing foundation pit enclosure method
CN110004919A (en) * 2019-04-30 2019-07-12 中铁十局集团西北工程有限公司 A kind of foundation pit enclosure construction method in pipeline coverage

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102465534A (en) * 2010-11-11 2012-05-23 上海市第五建筑有限公司 Construction method for adjacent double ditches
CN109505298A (en) * 2015-10-26 2019-03-22 张继红 A kind of self-balancing foundation pit enclosure method
CN107023015A (en) * 2016-02-01 2017-08-08 上海城地建设股份有限公司 A kind of new prefabricated two walls unification foundation pit system and its contrary sequence method
CN107023016A (en) * 2016-02-01 2017-08-08 上海城地建设股份有限公司 Two walls unification foundation pit system is worn under a kind of road and its along the practice
CN205712119U (en) * 2016-03-25 2016-11-23 中铁三局集团广东建设工程有限公司 A kind of little excavation structure closing on deep pit excavation
CN106638669A (en) * 2017-01-04 2017-05-10 中铁十六局集团北京轨道交通工程建设有限公司 System and method for reinforcing envelop enclosure for shield tunneling beneath existing subway station
CN206467684U (en) * 2017-01-04 2017-09-05 中铁十六局集团北京轨道交通工程建设有限公司 Existing subway station building enclosure hardened system is worn under a kind of shield
CN110004919A (en) * 2019-04-30 2019-07-12 中铁十局集团西北工程有限公司 A kind of foundation pit enclosure construction method in pipeline coverage

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236255A (en) * 2020-03-06 2020-06-05 华东建筑设计研究院有限公司 Support structure capable of realizing cross implementation of adjacent foundation pits and application construction method thereof
CN113090066A (en) * 2021-04-16 2021-07-09 华润建筑有限公司 Construction method for newly added entrances and exits of existing buildings and elevator shaft
CN115288155A (en) * 2022-08-19 2022-11-04 中国一冶集团有限公司 Efficient building method of square-round combined ultra-deep permanent foundation pit supporting structure
CN115288155B (en) * 2022-08-19 2023-10-27 中国一冶集团有限公司 Efficient construction method of square and round combined ultra-deep permanent foundation pit supporting structure

Similar Documents

Publication Publication Date Title
CN205776249U (en) A kind of combined inner supporting structure
CN101338678B (en) Supporting arch hidden digging top-down construction method
CN110528531A (en) A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post
CN106677189B (en) A kind of taper pile wall supporting type foundation pit supporting construction and its construction method
KR101179770B1 (en) Soil protection against build structure and the method
CN102733827A (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN105155549A (en) Partition support system for large-area deep foundation pit under forward and backward working condition, and construction method thereof
CN210031842U (en) Combined supporting system for adjacent deep foundation pit based on row piles, connecting beams and counter-pulling anchor cables
CN208379610U (en) A kind of broken line alternating expression double-row pile foundation pit support structure
CN104947681A (en) Super large super deep basement ground pit construction method
CN106087746A (en) A kind of cast-in-situ box girder falsework construction method and bridge
CN104631469B (en) For deep big foundation pit without post reinforced concrete support framework and building method thereof
CN105604064A (en) Construction method of comprehensive pipeline protection system supporting system
KR100794677B1 (en) The underground soil retaining wall structure for large-scale activity space securement and this construction technique
CN208517810U (en) A kind of temporary trestle bridge for deep big foundation pit excavation construction
CN203702164U (en) Subsurface excavation tunnel top bracing device adopting lifting jacks for movable support
CN103334451A (en) Underneath-passing channel formed between high-speed rail piers through secant pile walls and method thereof
JP3240438B2 (en) Seismic isolation method for seismically isolated buildings and existing buildings
CN106013174A (en) Oblique supporting method for foundation pit shoring and oblique supporting structure
CN105421488A (en) Constriction method for changing support of foundation slab in underground composite enclosure system
CN108487302A (en) The compound earth-retaining piling wall and construction method of a kind of support pile, retaining wall and pile foundation
JP6276152B2 (en) Construction girder removal method and earth retaining plate for construction girder removal
JP3345598B2 (en) Waste landfill stock equipment
CN106351232A (en) Internal rigid frame support foundation pit supporting structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191203