CN110517872A - A method of eliminating electric energy loss caused by circulation between transformer in substation - Google Patents
A method of eliminating electric energy loss caused by circulation between transformer in substation Download PDFInfo
- Publication number
- CN110517872A CN110517872A CN201910842872.5A CN201910842872A CN110517872A CN 110517872 A CN110517872 A CN 110517872A CN 201910842872 A CN201910842872 A CN 201910842872A CN 110517872 A CN110517872 A CN 110517872A
- Authority
- CN
- China
- Prior art keywords
- transformer
- circulation
- substation
- gear
- electric energy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01F—MAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
- H01F27/00—Details of transformers or inductances, in general
- H01F27/42—Circuits specially adapted for the purpose of modifying, or compensating for, electric characteristics of transformers, reactors, or choke coils
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01F—MAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
- H01F29/00—Variable transformers or inductances not covered by group H01F21/00
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
Abstract
The invention discloses the methods of electric energy loss caused by circulation between transformer in a kind of elimination substation, the method step are as follows: one, the input by substation, outlet side and stand electricity consumption power carry out real-time monitoring, and the power of each transformer consumption is calculated in real time, judge between transformer with the presence of aspergillus ficuum;If two, measuring the parameter of transformation by test method with the presence of circulation between transformer, the gear of transformer is then adjusted, so that its impedance parameter is consistent, so that it may eliminate circulation, and then avoid electric energy loss caused by circulation.After isallobaric device has a power failure, DC resistance of two transformers under each gear is measured respectively using instrument for measuring DC resistance.According to measurement as a result, the gear of transformer is readjusted, keep the DC resistance of two transformers equal or closest.So can existing circulation between eliminating transformer, to achieve the purpose that decreasing loss.
Description
Technical field
The present invention relates to electric energy caused by circulation between transformer in a kind of substation more particularly to a kind of elimination substation
The method of loss belongs to transmission & distribution electro-technical field.
Background technique
The transformer of substation is in the process of running, it may occur that loss.The first kind loss be no-load loss and load loss,
This kind of loss is reasonable loss, unavoidably;Second class loss be since impedance is unequal between transformer, can transformer it
Between form circulation, to consume system capacity, belong to unreasonable loss, it should be eliminated.But it is unreasonable how to eliminate these
Loss, the introduction of this respect currently not yet, in operation power system, long-term this unreasonable loss will cause the energy
A large amount of wastes.
Summary of the invention
The technical problem to be solved by the present invention is providing in a kind of elimination substation electric energy caused by circulation between transformer
The method of loss, in this way, when judging that transformer there are when circulation, is tried in conjunction with the power failure of transformer by monitoring data
It tests, after isallobaric device has a power failure, measures direct current of two transformers under each gear respectively using instrument for measuring DC resistance
Resistance value.According to measurement as a result, the gear of transformer is readjusted, keep the DC resistance of two transformers equal or
It is closest.Since the impedance value of two transformers after readjustment gear is equal, so can be deposited between eliminating transformer
Circulation, to achieve the purpose that decreasing loss, the above-mentioned problem of effective solution.
The technical solution of the present invention is as follows: a kind of side for eliminating electric energy loss caused by circulation between transformer in substation
Method, the method step are as follows: one, the input by substation, outlet side and stand electricity consumption power carry out real-time monitoring, and
The power for calculating each transformer consumption in real time, judges between transformer with the presence of aspergillus ficuum;If two, had between transformer
Circulation exists, and the parameter of transformation is measured by test method, then adjusts the gear of transformer, so that its impedance parameter is consistent,
Circulation can be eliminated, and then avoids electric energy loss caused by circulation.
In the step 2, test method are as follows: when judging transformer there are when circulation, in conjunction with transformation by monitoring data
The power failure of device is tested, and after isallobaric device has a power failure, measures two transformers respectively using instrument for measuring DC resistance in each gear
Under DC resistance make the direct current of two transformers according to measurement as a result, the gear of transformer is readjusted
Resistance value is equal or closest.Since the impedance value of two transformers after readjustment gear is equal, so change can be eliminated
Existing circulation between depressor, to achieve the purpose that decreasing loss.
The beneficial effects of the present invention are: compared with prior art, using technical solution of the present invention, when passing through monitoring data
Judge that transformer there are when circulation, is tested in conjunction with the power failure of transformer, after isallobaric device has a power failure, uses instrument for measuring DC resistance
DC resistance of two transformers under each gear is measured respectively.According to measurement as a result, by the gear of transformer into
Row is readjusted, and keeps the DC resistance of two transformers equal or closest.Due to two transformations after readjustment gear
The impedance value of device is equal, thus can existing circulation between eliminating transformer, to achieve the purpose that decreasing loss.
Detailed description of the invention
Fig. 1 is substation transformer operation wiring schematic diagram of the invention.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below with reference to this specification attached drawing to this hair
It is bright to be described in further detail.
Embodiment 1: as shown in Fig. 1, a kind of side eliminating electric energy loss caused by circulation between transformer in substation
Method, the method step are as follows: one, the input by substation, outlet side and stand electricity consumption power carry out real-time monitoring, and
The power for calculating each transformer consumption in real time, judges between transformer with the presence of aspergillus ficuum;If two, had between transformer
Circulation exists, and the parameter of transformation is measured by test method, then adjusts the gear of transformer, so that its impedance parameter is consistent,
Circulation can be eliminated, and then avoids electric energy loss caused by circulation.
In the step 2, test method are as follows: when judging transformer there are when circulation, in conjunction with transformation by monitoring data
The power failure of device is tested, and after isallobaric device has a power failure, measures two transformers respectively using instrument for measuring DC resistance in each gear
Under DC resistance make the direct current of two transformers according to measurement as a result, the gear of transformer is readjusted
Resistance value is equal or closest.Since the impedance value of two transformers after readjustment gear is equal, so change can be eliminated
Existing circulation between depressor, to achieve the purpose that decreasing loss.
As shown in Fig. 1, in the process of running, there is following equation establishment in substation:
P1=P2+P3+P4+PDamage (1)
Wherein: P1For the received power of substation, P2For the power for pressing outlet side in substation, P3It is defeated for substation's low pressure
The power of side out, P4For the power of substation's interior electric consumption in station, PDamageTo consume the power on substation transformer, the loss
Consist of two parts:
PDamage=PInterior damage+PCirculation (2)
Wherein: PInterior damageTo consume the loss on each transformer when transformer station high-voltage side bus, it is divided into no-load loss and load loss two
A part.Wherein no-load loss is mainly core loss, which is held essentially constant, and can directly be known by transformer nameplate;
Load loss changes with the variation of load, square directly proportional to load current;PCirculationBetween the transformer of paired running
The power consumed due to there are circulation, the reason of causing circulation are that impedance is unequal between transformer.
Therefore, real-time monitoring is carried out by the active power of input to substation, outlet side and electricity consumption of standing, and in real time
The power for calculating each transformer consumption, can judge between transformer with the presence of aspergillus ficuum.Under normal circumstances input with it is defeated
The relationship of active power out are as follows:
P1=P2+P3+P4+PInterior damage (3)
And work as the relationship of power are as follows:
P1> P2+P3+P4+PInterior damage (4)
Then illustrate that there are circulation between transformation at this time.
Solution: cause since circulation is that impedance between the transformer of paired running is unequal, when circulation goes out
Now, the parameter that transformation can be measured by test method, is then adjusted the gear of transformer, so that its impedance parameter
Unanimously, to eliminate circulation, achieve the purpose that decreasing loss.
The process of transformer impedance parameter is measured by test method:
When judging transformer there are when circulation by monitoring data, in conjunction with the power failure test of transformer, isallobaric device stops
After electricity, DC resistance of two transformers under each gear is measured respectively using instrument for measuring DC resistance.According to measurement
As a result, the gear of transformer is readjusted, keep the DC resistance of two transformers equal or closest.Due to weight
The impedance value of two transformers is equal after new adjustment gear, thus can existing circulation between eliminating transformer, thus
Achieve the purpose that decreasing loss.
Place is not described in detail by the present invention, is the well-known technique of those skilled in the art of the present technique.Finally, it is stated that the above reality
It applies example to be only used to illustrate the technical scheme of the present invention and not to limit it, although having carried out specifically the present invention referring to preferred embodiment
It is bright, those skilled in the art should understand that, can with modification or equivalent replacement of the technical solution of the present invention are made, and
The objective and range for not departing from technical solution of the present invention, are intended to be within the scope of the claims of the invention.
Claims (2)
1. a kind of method for eliminating electric energy loss caused by circulation between transformer in substation, it is characterised in that: the method
Step are as follows: one, the input by substation, outlet side and electricity consumption of standing power carry out real-time monitoring, and calculate in real time
The power of each transformer consumption, judges between transformer with the presence of aspergillus ficuum;If two, between transformer with the presence of circulation,
The parameter of transformation is measured by test method, the gear of transformer is then adjusted, so that its impedance parameter is consistent, so that it may eliminate
Circulation, and then avoid electric energy loss caused by circulation.
2. the method according to claim 1 for eliminating electric energy loss caused by circulation between transformer in substation, special
Sign is: in the step 2, test method are as follows: when judging transformer there are when circulation, in conjunction with transformation by monitoring data
The power failure of device is tested, and after isallobaric device has a power failure, measures two transformers respectively using instrument for measuring DC resistance in each gear
Under DC resistance make the direct current of two transformers according to measurement as a result, the gear of transformer is readjusted
Resistance value is equal or closest.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910842872.5A CN110517872A (en) | 2019-09-06 | 2019-09-06 | A method of eliminating electric energy loss caused by circulation between transformer in substation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910842872.5A CN110517872A (en) | 2019-09-06 | 2019-09-06 | A method of eliminating electric energy loss caused by circulation between transformer in substation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110517872A true CN110517872A (en) | 2019-11-29 |
Family
ID=68631495
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910842872.5A Pending CN110517872A (en) | 2019-09-06 | 2019-09-06 | A method of eliminating electric energy loss caused by circulation between transformer in substation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110517872A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114325067A (en) * | 2021-11-19 | 2022-04-12 | 国网新疆电力有限公司电力科学研究院 | Rapid judgment and detection method and detection device for circulation between parallel operation transformers |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201765285U (en) * | 2010-09-07 | 2011-03-16 | 山东达驰电气有限公司 | Device of monitoring real time wastage and load of transformer in operation |
CN203444031U (en) * | 2013-08-01 | 2014-02-19 | 株洲变流技术国家工程研究中心有限公司 | Modularized multi-level current transformer tester |
CN103715765A (en) * | 2013-11-16 | 2014-04-09 | 沈阳工业大学 | Substation fully-enclosed gas insulation combination electric appliance circulation inhibition device and method |
CN203721463U (en) * | 2014-03-17 | 2014-07-16 | 张家港市中亚特种变压器制造有限公司 | Phase-shifting voltage-regulating transformer |
CN204314383U (en) * | 2014-12-15 | 2015-05-06 | 安顺供电局 | DC Resistance of Transformer measures connecting wire switching device |
CN104833895A (en) * | 2015-05-08 | 2015-08-12 | 中广核工程有限公司 | Method for verifying polarity of differential protection current transformer of nuclear power plant transformer |
-
2019
- 2019-09-06 CN CN201910842872.5A patent/CN110517872A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201765285U (en) * | 2010-09-07 | 2011-03-16 | 山东达驰电气有限公司 | Device of monitoring real time wastage and load of transformer in operation |
CN203444031U (en) * | 2013-08-01 | 2014-02-19 | 株洲变流技术国家工程研究中心有限公司 | Modularized multi-level current transformer tester |
CN103715765A (en) * | 2013-11-16 | 2014-04-09 | 沈阳工业大学 | Substation fully-enclosed gas insulation combination electric appliance circulation inhibition device and method |
CN203721463U (en) * | 2014-03-17 | 2014-07-16 | 张家港市中亚特种变压器制造有限公司 | Phase-shifting voltage-regulating transformer |
CN204314383U (en) * | 2014-12-15 | 2015-05-06 | 安顺供电局 | DC Resistance of Transformer measures connecting wire switching device |
CN104833895A (en) * | 2015-05-08 | 2015-08-12 | 中广核工程有限公司 | Method for verifying polarity of differential protection current transformer of nuclear power plant transformer |
Non-Patent Citations (1)
Title |
---|
黄俊: "35kV 某变电站主变容量不能充分利用故障现象的浅析", 《通讯世界》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114325067A (en) * | 2021-11-19 | 2022-04-12 | 国网新疆电力有限公司电力科学研究院 | Rapid judgment and detection method and detection device for circulation between parallel operation transformers |
CN114325067B (en) * | 2021-11-19 | 2023-10-20 | 国网新疆电力有限公司电力科学研究院 | Method and device for rapidly judging and detecting circulating current between parallel operation transformers |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102508950B (en) | Regional dispatching automatic system and method for communication between regional dispatching automatic system and remote monitoring diagnosis centre | |
CN104362637B (en) | A kind of low-voltage platform district based on Forward and backward substitution method intelligence administering method | |
CN102347614A (en) | Voltage stability analyzing method and device based on short circuit capacity | |
CN106786528B (en) | It is a kind of based on the Economical Operation of Main Transformer in Substation control method of D5000 system and application | |
CN106707030B (en) | Method and device for measuring ground impedance and power loss of distribution transformer | |
CN104655990A (en) | Medium and low-voltage power distribution network simulation system based on energy feedback | |
CN103647291A (en) | Control method and device for reactive compensation for power distribution network | |
CN110517872A (en) | A method of eliminating electric energy loss caused by circulation between transformer in substation | |
CN209860353U (en) | Grounding component of power transformation and distribution device | |
CN201270525Y (en) | Electric energy quality monitoring management system for power distribution network | |
CN104678218B (en) | A kind of evaluation method of cable rising test system optimal compensating electric capacity | |
CN101257213A (en) | Reactive-load compensation method for high capacity high electric impedance distributing transformator attrition experiment | |
KR102340636B1 (en) | Reactive Power Compensation type Ground Transformer | |
CN105738691A (en) | Efficacy metering detection platform for high voltage motor | |
Zamora et al. | Simulation by MATLAB/Simulink of active filters for reducing THD created by industrial systems | |
CN104678219A (en) | Capacitance compensation matching method based on high-current test system | |
CN106026166B (en) | Reactive capacity detection method for new energy power station accessed to weak power grid | |
CN204633468U (en) | A kind of area user identification zone device of multimode manner | |
CN105427182A (en) | Transformer area low-voltage cause analysis method and transformer area low-voltage cause analysis device | |
CN204405793U (en) | AC extra high voltage main transformer modulation associating partial discharge test system | |
CN112379176A (en) | Transformer loss acquisition system and method | |
CN207281234U (en) | A kind of DC testing of cables device | |
CN205265256U (en) | Low -voltage power supply network control system | |
CN207393633U (en) | A kind of servo valve test control device | |
CN109444533B (en) | Optimization method for performance detection of reactive compensation device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191129 |
|
RJ01 | Rejection of invention patent application after publication |