CN110512519A - A kind of tool anchor device for facilitating steel strand wires to penetrate - Google Patents
A kind of tool anchor device for facilitating steel strand wires to penetrate Download PDFInfo
- Publication number
- CN110512519A CN110512519A CN201910640389.9A CN201910640389A CN110512519A CN 110512519 A CN110512519 A CN 110512519A CN 201910640389 A CN201910640389 A CN 201910640389A CN 110512519 A CN110512519 A CN 110512519A
- Authority
- CN
- China
- Prior art keywords
- hole
- plate
- steel strand
- strand wires
- clamping piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The present invention relates to a kind of tool anchor device for facilitating steel strand wires to penetrate, including moveable anchor disk, pushes back plate, preceding pushing sleeve, tool clamping piece, pushback pin, is pushed forward spring, spring bearer plate, amount of recovery feeler lever;Moveable anchor disk is equipped with through-hole, and tool clamping piece is mounted in through-hole, and is located at the middle part of through-hole;Spring bearer plate is fixedly mounted on the rear end of moveable anchor disk, and through spring bearer plate and positioned at the rear portion of through-hole, the other end of preceding pushing sleeve is located at outside through-hole and is connected with amount of recovery feeler lever for one end of preceding pushing sleeve;Be pushed forward spring pocket and be located on the one end at through-hole rear portion mounted in preceding pushing sleeve, and be pushed forward spring one end and spring bearer plate it is inconsistent;The front end that plate is located at moveable anchor disk is pushed back, one end of pushback pin is located at the front of through-hole, and the other end of pushback pin is located at outside through-hole, and is connected to and pushes back on plate.The present invention can be with the advance of real-time detection tool clamping piece, backway.
Description
Technical field
The present invention relates to pre-stressed bridge pulling test devices, and in particular to a kind of moveable anchor dress for facilitating steel strand wires to penetrate
It sets.
Background technique
The jack that traditional prestressed bridge girder tensioning uses is centre-hole jack, at work, steel strand wires, work anchor
With work clip sheet after the completion of tensioning, it will be encapsulated in prestressed component;Steel strand wires beyond work clip sheet before packaging, will
5~10mm is stayed except work clip sheet, remaining be removed, be removed the steel strand wires to get off be treated as steel scrap processing, one
Entire engineering waste steel strand wires are completed up to more than 100 ten thousand yuan in railway beam field.
In order to reduce the waste of steel strand wires, each tensioning equipment supplier proposes a variety of tensioning for saving the pre- allowance of steel strand wires
Jack version (preceding clip jack), having a common feature in all schemes is exactly to fall into moveable anchor and tool clamping piece
To inside jack, the spacing between work anchor to moveable anchor is reduced, to realize the effect for reducing the pre- allowance of steel strand wires.
But whether tensioning is generally determined by the elongation of control stretching force and steel strand wires during prestressed stretch-draw
It meets the requirements.By detection jack calibration when traditional stretching force measures, oil pressure converting to force is subjected to stretching force control, and steel
The elongation of steel strand wires is determined when twisted wire elongation by detecting the difference of the overhang of jack piston and the amount of recovery of tool clamping piece
Amount.Obviously moveable anchor and tool clamping piece are trapped in the way inside jack, will be unable to the amount of recovery for detecting tool clamping piece.
Since the testing requirements of detection and steel strand wires elongation to above-mentioned stretching force are not high in highway prestressed stretch-draw,
So current some preceding clip jack are still widely used.But due to railway prestressed stretch-draw, especially high-speed rail
In construction, stretching force is detected and controlled, and the detection of steel strand wires elongation is required higher.Therefore, railway at present
In prestressed stretch-draw in the case where no solution detection instrument intermediate plate amount of recovery, it is necessary to use traditional stretch-draw jack.It is right
In the inaccurate use of preceding clip jack that those cannot detect intermediate plate amount of recovery.In addition, due to the survey with oil pressure detection stretching force
Power scheme, also due to error is larger (0.5%~1.0%) in use, also starting regulation in railway tensioning must be passed with dynamometry
The detection of sensor progress stretching force.
Based on above-mentioned requirements, railway intelligent tensioning equipment is to increase a dynamometry between jack and lengthening set at present
Sensor, for detecting stretching force.The pre- allowance for obviously increasing steel strand wires again in this way, causes steel strand wires more to waste.
In order to save steel strand wires, many people are to a kind of new structure of the Curve guide impeller of traditional centre-hole jack ---
Fore-clamp (card) formula jack.According to the difference of the installation site of the moveable anchor clamping device of clip jack before current can will before
Clip jack is divided into two classes, and one kind is that moveable anchor clamping device is installed on cylinder body, and another kind of is preceding clip clamping device peace
On rear stopper rod.
Clamping device is placed to above inner cylinder, and load cell is installed on piston rod, and this structure mainly has two
A drawback, one is piston rod can prolong axial movement and circumferential rotation is broken so as to cause the cable of load cell by strand,
Second is that being that cylinder body inner cylinder only has oil pressure load originally, and increases and prolong axial pulling force, and force way causes front end to have
Very big stress is concentrated.
Preceding clip clamping device is installed to above piston rod can save steel strand wires well, and adapt to the rotation of steel strand wires
Turning problem --- clamping device is rotated together with piston.
Be in above scheme using oil pressure detect stretching force, while also can not detection instrument intermediate plate amount of recovery.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of preceding clip moveable anchor devices, can detecte tool clamping piece
Amount of recovery.
The technical scheme to solve the above technical problems is that a kind of tool anchor device for facilitating steel strand wires to penetrate,
Including moveable anchor disk, pushes back plate, preceding pushing sleeve, tool clamping piece, pushback pin, is pushed forward spring, spring bearer plate and amount of recovery feeler lever;It is described
Moveable anchor disk is equipped with through-hole, and the tool clamping piece is mounted in the through-hole, and is located at the middle part of the through-hole;The spring
Pressing plate is fixedly mounted on the rear end of the moveable anchor disk, and one end of the preceding pushing sleeve through the spring bearer plate and is located at described logical
The rear portion in hole, and opposite with one end of the tool clamping piece, the other end of the preceding pushing sleeve be located at the through-hole it is outer and with it is described
Amount of recovery feeler lever is connected;It is described to be pushed forward spring pocket and be located on the one end at the through-hole rear portion mounted in the preceding pushing sleeve, and it is described before
One end and the spring bearer plate for pushing away spring are inconsistent;The front end for pushing back plate and being located at the moveable anchor disk, the pushback pin
One end be located at the front of the through-hole, and opposite with the other end of the tool clamping piece, the other end of the pushback pin is located at
Outside the through-hole, and it is connected to described push back on plate;It is described to push back plate, the pushback pin, the tool clamping piece, the preceding pushing sleeve
The steel strand wires through-hole that passes through for steel strand wires is equipped with along axis on the amount of recovery feeler lever.
The beneficial effects of the present invention are: when using a kind of tool anchor device for facilitating steel strand wires to penetrate of the invention, very heavy
Top drives during returning back to top pushes back plate retrogressing, pushes back the dynamic pushback pin of strip and retreats, pushback pin pushes tool clamping piece to open its front end
Angle is magnified, and preceding pushing sleeve withstands tool clamping piece rear end under the action of being pushed forward spring, magnifies its rear end angle of release, conveniently penetrates steel strand
Line;Steel strand wires after pushing back plate tapping and putting on along steel strand wires through-hole, when tensioning very heavy ejection top, push back plate advance, tool
Intermediate plate clamps steel strand wires;Amount of recovery feeler lever and preceding pushing sleeve follow tool clamping piece to move forward and backward together, can be with real-time detection tool holder
Piece advance, backway.
Based on the above technical solution, the present invention can also be improved as follows.
Further, the front size of the through-hole is less than the rear size of the through-hole, and the tool clamping piece is by three pieces point
From intermediate plate composition frustum cone structure, and the variable steel strand wires through-hole of diameter is formed on the axis of rotary table.
Beneficial effect using above-mentioned further scheme is: the rotary table knot that tool clamping piece is made of the intermediate plate that three pieces separate
Structure, and the variable steel strand wires through-hole of diameter is formed on the axis of rotary table, facilitate steel strand wires to penetrate.
Further, the pushback pin, which is located at one end outside the through-hole and is connected to by connecting plate and conduit, described pushes back plate
On;The connecting plate be located at the moveable anchor disk and it is described push back between plate, the pushback pin is located at one end outside the through-hole
Be connected on the connecting plate, the both ends of the conduit be connected to the connecting plate and it is described push back on plate, the conduit
It is connected at the connecting plate with the pushback pin.
Beneficial effect using above-mentioned further scheme is: in pushback pin and increase connecting plate and conduit between plate are pushed back,
It can change the length of tool anchor device, so as to meet different test requirements documents.
Further, the connecting plate and described push back are additionally provided with support rod between plate, and the both ends of the support rod connect respectively
It connects in the connecting plate and described pushes back on plate.
Beneficial effect using above-mentioned further scheme is: the steady of tool anchor device work can be improved in setting support rod
It is qualitative.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram for the tool anchor device for facilitating steel strand wires to penetrate of the present invention.
In attached drawing, parts list represented by the reference numerals are as follows:
1, moveable anchor disk, 2, connecting plate, 3, push back plate, 4, preceding pushing sleeve, 5, tool clamping piece, 6, pushback pin, 7, be pushed forward spring,
8, spring bearer plate, 9, amount of recovery feeler lever, 10, support rod, 11, conduit.
Specific embodiment
The principle and features of the present invention will be described below with reference to the accompanying drawings, and the given examples are served only to explain the present invention, and
It is non-to be used to limit the scope of the invention.
As shown in Figure 1, a kind of tool anchor device for facilitating steel strand wires to penetrate, including moveable anchor disk 1, push back plate 3, preceding pushing sleeve
4, tool clamping piece 5, pushback pin 6, be pushed forward spring 7, spring bearer plate 8 and amount of recovery feeler lever 9;The moveable anchor disk 1 is equipped with through-hole,
The tool clamping piece 5 is mounted in the through-hole, and is located at the middle part of the through-hole;The spring bearer plate 8 is fixedly mounted on institute
The rear end of moveable anchor disk 1 is stated, one end of the preceding pushing sleeve 4 runs through the spring bearer plate 8 and is located at the rear portion of the through-hole, and with
One end of the tool clamping piece 5 is opposite, the other end of the preceding pushing sleeve 4 be located at the through-hole it is outer and with the amount of recovery feeler lever 9
It is connected;It is described be pushed forward spring 7 and be sleeved on the preceding pushing sleeve 4 be located on the one end at the through-hole rear portion, and the spring 7 that is pushed forward
One end and the spring bearer plate 8 are inconsistent;The front end for pushing back plate 3 and being located at the moveable anchor disk 1, the one of the pushback pin 6
End is located at the front of the through-hole, and opposite with the other end of the tool clamping piece 5, and the other end of the pushback pin 6 is located at institute
It states outside through-hole, and is connected to described push back on plate 3;It is described to push back plate 3, the pushback pin 6, the tool clamping piece 5, described be pushed forward
The steel strand wires through-hole passed through for steel strand wires is equipped on set 4 and the amount of recovery feeler lever 9 along axis.
In this embodiment: the front size of the through-hole is less than the rear size of the through-hole, the tool holder
The frustum cone structure that piece 5 is made of the intermediate plate that three pieces separate, and form the variable steel strand wires of diameter on the axis of rotary table and lead to
Hole.
In this embodiment, the pushback pin 6 is located at one end outside the through-hole and is connected by connecting plate 2 and conduit 11
It connects and is pushed back on plate 3 described;The connecting plate 2 be located at the moveable anchor disk 1 and it is described push back between plate 3, the pushback pin 6
It is connected on the connecting plate 2 in one end outside the through-hole, the both ends of the conduit 11 are connected to 2 He of connecting plate
Described to push back on plate 3, the conduit 11 is connected at the connecting plate 2 with the pushback pin 3.
The connecting plate 2 and described push back are additionally provided with support rod 10 between plate 3, the both ends of the support rod 10 are separately connected
In the connecting plate 2 and described push back on plate 3.
The working principle of the invention is: driving during jack returns back to top and pushes back the retrogressing of plate 3, pushes back plate 3 and drive conduit
11, support rod 10, connecting plate 2 and the whole retrogressing of pushback pin 6, pushback pin 6 pushes tool clamping piece 5 to magnify its front end angle of release, preceding
Pushing sleeve 4 withstands 5 rear end of tool clamping piece under the action of being pushed forward spring 7, magnifies its rear end angle of release, conveniently penetrates steel strand wires;Steel
Twisted wire after pushing back 3 tapping of plate and putting on along steel strand wires through-hole, when tensioning very heavy ejection top, push back the advance of plate 3, tool clamping piece
5 clamp steel strand wires;Amount of recovery feeler lever 9 and preceding pushing sleeve 4 follow tool clamping piece 5 to move forward and backward together, can be with real-time detection tool holder
Piece advance, backway.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (4)
1. a kind of tool anchor device for facilitating steel strand wires to penetrate, it is characterised in that: including moveable anchor disk (1), push back plate (3), preceding
Pushing sleeve (4), pushback pin (6), is pushed forward spring (7), spring bearer plate (8) and amount of recovery feeler lever (9) at tool clamping piece (5);The tool
Anchor disk (1) is equipped with through-hole, and the tool clamping piece (5) is mounted in the through-hole, and is located at the middle part of the through-hole;The bullet
Spring pressing plate (8) is fixedly mounted on the rear end of the moveable anchor disk (1), and the spring bearer plate is run through in one end of the preceding pushing sleeve (4)
(8) and it is located at the rear portion of the through-hole, and, the other end position of the preceding pushing sleeve (4) opposite with one end of the tool clamping piece (5)
It is connected in outside the through-hole and with the amount of recovery feeler lever (9);It is described be pushed forward spring (7) and be sleeved on the preceding pushing sleeve (4) be located at
On the one end at the through-hole rear portion, and described one end for being pushed forward spring (7) and the spring bearer plate (8) are inconsistent;It is described to push back
Plate (3) is located at the front end of the moveable anchor disk (1), and one end of the pushback pin (6) is located at the front of the through-hole, and with it is described
The other end of tool clamping piece (5) is opposite, and the other end of the pushback pin (6) is located at outside the through-hole, and is connected to described push back
On plate (3);It is described to push back plate (3), the pushback pin (6), the tool clamping piece (5), the preceding pushing sleeve (4) and the amount of recovery
The steel strand wires through-hole passed through for steel strand wires is equipped on feeler lever (9) along axis.
2. a kind of tool anchor device for facilitating steel strand wires to penetrate according to claim 1, it is characterised in that: the through-hole
Rear size of the front size less than the through-hole, the frustum cone structure that the tool clamping piece (5) is made of the intermediate plate that three pieces separate,
And the variable steel strand wires through-hole of diameter is formed on the axis of rotary table.
3. a kind of tool anchor device for facilitating steel strand wires to penetrate according to claim 1 or 2, it is characterised in that: described time
Push rod (6) is located at one end outside the through-hole and is connected to described push back on plate (3) by connecting plate (2) and conduit (11);It is described
Connecting plate (2) be located at the moveable anchor disk (1) and it is described push back between plate (3), the pushback pin (6) is located at outside the through-hole
One end is connected on the connecting plate (2), and the both ends of the conduit (11) are connected to the connecting plate (2) and described push back
On plate (3), the conduit (11) is connected at the connecting plate (2) with the pushback pin (3).
4. a kind of tool anchor device for facilitating steel strand wires to penetrate according to claim 3, it is characterised in that: the connecting plate
(2) it is additionally provided between plate (3) support rod (10) with described push back, the both ends of the support rod (10) are connected to the connection
It plate (2) and described pushes back on plate (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910640389.9A CN110512519A (en) | 2019-07-16 | 2019-07-16 | A kind of tool anchor device for facilitating steel strand wires to penetrate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910640389.9A CN110512519A (en) | 2019-07-16 | 2019-07-16 | A kind of tool anchor device for facilitating steel strand wires to penetrate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110512519A true CN110512519A (en) | 2019-11-29 |
Family
ID=68623657
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910640389.9A Pending CN110512519A (en) | 2019-07-16 | 2019-07-16 | A kind of tool anchor device for facilitating steel strand wires to penetrate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110512519A (en) |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5755065A (en) * | 1996-04-25 | 1998-05-26 | Sorkin; Felix L. | Method and apparatus for forming an anchorage of a post-tension system |
KR100950265B1 (en) * | 2009-04-24 | 2010-03-31 | 이인귀 | Retension cylinder |
CN202047600U (en) * | 2011-01-28 | 2011-11-23 | 安徽金星预应力工程技术有限公司 | Lengthened sleeve for tool anchor |
CN202116235U (en) * | 2011-05-19 | 2012-01-18 | 中铁十局集团有限公司 | Fore-cramp jack |
CN202401772U (en) * | 2011-12-30 | 2012-08-29 | 柳州泰姆预应力机械有限公司 | Supporting lug with clip top pressing and top loosing functions and clip limit |
CN206267022U (en) * | 2016-07-26 | 2017-06-20 | 王家梁 | The built-in hollow force snesor bite type tensioning system of bridge and oil cylinder |
CN206721682U (en) * | 2017-03-26 | 2017-12-08 | 合肥普林斯交通设备有限公司 | A kind of group's anchor for preceding cassette punching jack |
CN207600653U (en) * | 2017-11-15 | 2018-07-10 | 北京华横新技术开发公司 | measuring system and tensioning system |
CN108457197A (en) * | 2018-02-01 | 2018-08-28 | 重庆恒佳工程技术咨询有限公司 | A kind of intelligent tensioning just wears formula moveable anchor |
CN109269884A (en) * | 2018-08-17 | 2019-01-25 | 武汉希萌科技有限公司 | A kind of prestressed stretch-draw preceding clip type jack and tool anchor arrangement |
CN208780544U (en) * | 2018-08-17 | 2019-04-23 | 武汉希萌科技有限公司 | A kind of preceding clip moveable anchor device |
CN210513948U (en) * | 2019-07-16 | 2020-05-12 | 武汉希萌科技有限公司 | Front clamping type automatic tool anchor device |
-
2019
- 2019-07-16 CN CN201910640389.9A patent/CN110512519A/en active Pending
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5755065A (en) * | 1996-04-25 | 1998-05-26 | Sorkin; Felix L. | Method and apparatus for forming an anchorage of a post-tension system |
KR100950265B1 (en) * | 2009-04-24 | 2010-03-31 | 이인귀 | Retension cylinder |
CN202047600U (en) * | 2011-01-28 | 2011-11-23 | 安徽金星预应力工程技术有限公司 | Lengthened sleeve for tool anchor |
CN202116235U (en) * | 2011-05-19 | 2012-01-18 | 中铁十局集团有限公司 | Fore-cramp jack |
CN202401772U (en) * | 2011-12-30 | 2012-08-29 | 柳州泰姆预应力机械有限公司 | Supporting lug with clip top pressing and top loosing functions and clip limit |
CN206267022U (en) * | 2016-07-26 | 2017-06-20 | 王家梁 | The built-in hollow force snesor bite type tensioning system of bridge and oil cylinder |
CN206721682U (en) * | 2017-03-26 | 2017-12-08 | 合肥普林斯交通设备有限公司 | A kind of group's anchor for preceding cassette punching jack |
CN207600653U (en) * | 2017-11-15 | 2018-07-10 | 北京华横新技术开发公司 | measuring system and tensioning system |
CN108457197A (en) * | 2018-02-01 | 2018-08-28 | 重庆恒佳工程技术咨询有限公司 | A kind of intelligent tensioning just wears formula moveable anchor |
CN109269884A (en) * | 2018-08-17 | 2019-01-25 | 武汉希萌科技有限公司 | A kind of prestressed stretch-draw preceding clip type jack and tool anchor arrangement |
CN208780544U (en) * | 2018-08-17 | 2019-04-23 | 武汉希萌科技有限公司 | A kind of preceding clip moveable anchor device |
CN210513948U (en) * | 2019-07-16 | 2020-05-12 | 武汉希萌科技有限公司 | Front clamping type automatic tool anchor device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208780544U (en) | A kind of preceding clip moveable anchor device | |
CN109269884A (en) | A kind of prestressed stretch-draw preceding clip type jack and tool anchor arrangement | |
CN103645092B (en) | A kind of tension tester clamp | |
CN201548453U (en) | Clamp for high-temperature tensile test of thin-wall pipe | |
CN105973523A (en) | Detection apparatus for yarn tension force | |
CN202582997U (en) | Tensile compressible double-shear clamp for testing shearing strength of material | |
CN103048190A (en) | Tensile test fixture for tensile testing machine | |
CN110512519A (en) | A kind of tool anchor device for facilitating steel strand wires to penetrate | |
CN2864662Y (en) | Wire rod clamping apparatus for material testing machine | |
CN201273030Y (en) | Portable steel stranded wire clamper | |
CN209198205U (en) | A kind of hydraulic clamp with antiskid function | |
CN210513948U (en) | Front clamping type automatic tool anchor device | |
CN110082193A (en) | A kind of separate type Hopkinson pull bar test piece clamp and chucking method | |
CN211235271U (en) | Testing machine for measuring bearing coefficient of processed metal rod | |
CN205636832U (en) | Auxiliary device of test steel strand wires anchor head bond stress | |
CN200992962Y (en) | High ratio energizing rig chuck | |
CN104297075A (en) | A metal wire torsion test method for a steel wire rope | |
CN111350130A (en) | Front clamping type tool anchor device | |
CN209167021U (en) | A kind of tension experimental rig under lateral stressed state | |
CN206223542U (en) | A kind of chuck of steel strand experiment machine prevents miscellaneous device | |
CN207119814U (en) | A kind of fast fastening clamp disk | |
CN210893591U (en) | Radial rigidity test device for prestressed metal corrugated pipe | |
CN202485699U (en) | Fixture for opposite acting force | |
CN215640554U (en) | Prestressed wire anchoring force detection test device | |
CN214749524U (en) | Diversified detection type building material detection device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191129 |
|
RJ01 | Rejection of invention patent application after publication |