CN110508961A - Power transmission steel pipe tower flange welding technique - Google Patents
Power transmission steel pipe tower flange welding technique Download PDFInfo
- Publication number
- CN110508961A CN110508961A CN201910721192.8A CN201910721192A CN110508961A CN 110508961 A CN110508961 A CN 110508961A CN 201910721192 A CN201910721192 A CN 201910721192A CN 110508961 A CN110508961 A CN 110508961A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- ring flange
- welding
- welded
- weld seam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K31/00—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
- B23K31/02—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The invention proposes a kind of power transmission steel pipe tower flange welding techniques, and two weld seams between steel pipe and ring flange are alternately welded, and welding direction is identical, can reduce welding stress, prevents weld seam from cracking failure occurs in later period use process;The welding of steel pipe and ring flange weld seam is executed according to identical direction, it is more efficient;Between multiple gussets by the way of cross-shaped symmetrical welding, welding stress can effectively reduce, positioning is more accurate, prevents from being partially welded, and can prevent weld seam from cracking failure occurs in later period use process;Two weld seams between each gusset and side plate and ring flange alternately weld, and welding direction is identical, can reduce welding stress, prevent weld seam from cracking failure occurs in later period use process.
Description
Technical field
The present invention relates to electric power pylon field more particularly to a kind of power transmission steel pipe tower flange welding techniques.
Background technique
Electric power pylon is towering structure, mainly uses angle steel or steel-tube construction, is welded.Wherein, for
Power transmission steel pipe tower, first completes the blanking and bending of plate, then is welded into steel pipe, next completes steel pipe, ring flange and gusset
Welding.
Current power transmission steel pipe tower flange welding technique, steel pipe is generally first aligned and is welded with ring flange, then complete muscle
The welding of plate and steel pipe and ring flange.In specific welding process, the welding of steel pipe and ring flange inner ring and outer ring is first completed, then
According to sequence clockwise or counter-clockwise, the welding of gusset and steel pipe and ring flange is completed.For each weld seam, divide bottoming
Layer, filled layer and three weld seam of capping layer are completed.In this way, in the weld of steel pipe and ring flange, between inner ring and outer ring
There are welding stresses;And the two sides commissure of gusset and steel pipe and ring flange, also it is easy to produce welding stress.The above welding is answered
Power causes weld seam in later period use process, is easy to happen cracking failure.
Summary of the invention
In view of this, the invention proposes a kind of power transmission steel pipe tower flange welding techniques that welding stress can be effectively reduced.
The technical scheme of the present invention is realized as follows: the present invention provides a kind of power transmission steel pipe tower flange welding technique,
It includes the following steps,
Gusset (3) is first arranged in a mutually vertical manner and is welded and fixed with steel pipe (1) and ring flange (2) surface by S1;
Weld seam and steel pipe (1) bottom outer wall and method between S2, then welded still pipe (1) bottom interior wall and ring flange (2)
Weld seam between blue disk (2);
Step S2 includes,
S2-1, the prime coat between first welded still pipe (1) bottom interior wall and ring flange (2);
Prime coat between S2-2, then welded still pipe (1) bottom outer wall and ring flange (2);
Filled layer between S2-3, then welded still pipe (1) bottom interior wall and ring flange (2);
Filled layer between S2-4, then welded still pipe (1) bottom outer wall and ring flange (2);
S2-5, the capping layer between last welded still pipe (1) bottom interior wall and ring flange (2);
Capping layer between S2-6, then welded still pipe (1) bottom outer wall and ring flange (2).
On the basis of above technical scheme, it is preferred that the step S2-1 and S2-2 welding direction is identical, step S2-3
Identical with S2-4 welding direction, step S2-5 and S2-6 welding direction is identical.
On the basis of above technical scheme, it is preferred that the steel pipe (1) is by 4N side plate (11) head and the tail of same size
It is formed by connecting, steel pipe (1) cross section is in the side 4N shape, and gusset (3) is provided with 4N, each gusset (3) and side plate (11) and flange
Disk (2) surface is mutually perpendicular to and is welded and fixed, and N is positive integer.
It is further preferred that further including step S3, ring flange (2) surface segmentation is 4N section, root by 4N gusset (3)
Welding direction when according to execution step S2, is sequentially completed steel pipe (1) and ring flange (2) in each section clockwise or counter-clockwise
The welding of weld seam.
It is further preferred that further including step S4, four side plates (11) are chosen on steel pipe (1), are divided into two groups, each group
Two interior side plates (11) are parallel to each other, the side plate (11) between two groups vertically, by this corresponding four muscle of four side plates (11)
Plate (3) is welded in the following order: first will wherein be welded in a gusset (3) and side plate (11) and ring flange (2) surface;Again will
An other gusset (3) and side plate (11) and ring flange (2) surface in same group are welded;Again by the gusset (3) in another group
It is welded with side plate (11) and ring flange (2) surface;Finally by another gusset (3) and side plate (11) and ring flange in another group
(2) surface is welded.
Still further preferably, further include step S5, according to the welding sequence of step S4, be sequentially completed 4N gusset (3)
With the welding of side plate (11) and ring flange (2) surface.
Still further preferably, it is right that left and right two is formed between each gusset (3) and side plate (11) and ring flange (2) surface
Claiming weld seam, the welding of the two symmetrical weld seams in left and right includes the following steps,
The prime coat of a wherein weld seam is first welded, then welds the prime coat of an other weld seam;
The filled layer of first weld seam is welded again, then welds the filled layer of an other weld seam;
The capping layer of first weld seam is finally welded, then welds the capping layer of an other weld seam.
Still more preferably, the welding direction of every one of weld seam of the two symmetrical weld seams in left and right is identical.
Power transmission steel pipe tower flange welding technique of the invention has the advantages that compared with the existing technology
(1) two weld seams between steel pipe and ring flange are alternately welded, welding direction is identical, can reduce welding and answer
Power prevents weld seam from cracking failure occurs in later period use process;
(2) welding of steel pipe and ring flange weld seam is executed according to identical direction, it is more efficient;
(3) it between multiple gussets by the way of cross-shaped symmetrical welding, can effectively reduce welding stress, position more smart
Standard prevents from being partially welded, and can prevent weld seam from cracking failure occurs in later period use process;
(4) two weld seams between each gusset and side plate and ring flange alternately weld, and welding direction is identical, can drop
Low welding stress prevents weld seam from cracking failure occurs in later period use process.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is the perspective view of power transmission steel pipe tower of the invention;
Fig. 2 is the top view of power transmission steel pipe tower of the invention;
Fig. 3 is the schematic diagram of the step S2 of power transmission steel pipe tower flange welding technique of the invention;
Fig. 4 is the schematic diagram of the step S3 of power transmission steel pipe tower flange welding technique of the invention;
Fig. 5 is the schematic diagram of the step S4 of power transmission steel pipe tower flange welding technique of the invention;
Fig. 6 is the schematic diagram of the step S4 of power transmission steel pipe tower flange welding technique of the invention.
Specific embodiment
Below in conjunction with embodiment of the present invention, the technical solution in embodiment of the present invention is carried out clearly and completely
Description, it is clear that described embodiment is only some embodiments of the invention, rather than whole embodiments.Base
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts all
Other embodiments shall fall within the protection scope of the present invention.
As shown in Figure 1, in conjunction with Fig. 2, power transmission steel pipe tower of the invention, including steel pipe 1, ring flange 2 and gusset 3, wherein steel
Pipe 1 is formed by connecting by 4N 11 head and the tail of side plate of same size, and 1 cross section of steel pipe is in the side 4N shape, and gusset 3 is provided with 4N, often
A gusset 3 is mutually perpendicular to and is welded and fixed with 1 side plate 11 of steel pipe and 2 surface of ring flange, and steel pipe 1 is mutually perpendicular to and welds with blue disk 2
Fixation is connect, N is positive integer.In the present embodiment, N is equal to 3, i.e. 1 cross section of steel pipe is in 12 side shapes.Specifically, the steel pipe 1 can
With by monolithic steel plate bending at being welded from beginning to end after each side plate 11, can also be by several pieces of steel plate bendings at head and the tail after side plate 11
It is welded, naturally it is also possible to be welded by 4N individual 11 head and the tail of side plate.
Wherein, the power transmission steel pipe tower flange welding technique the following steps are included:
Gusset 3 is first arranged in a mutually vertical manner and is welded and fixed with steel pipe 1 and 2 surface of ring flange by S1.Specifically, can adopt
It is fixed with the mode of spot welding, is convenient for next weld seam welding.
Weld seam and 1 bottom outer wall of steel pipe and ring flange 2 between S2, then 1 bottom interior wall of welded still pipe and ring flange 2
Between weld seam.Specifically, as shown in figure 3, step S2 includes,
S2-1, the prime coat between first 1 bottom interior wall of welded still pipe and ring flange 2;
Prime coat between S2-2, then 1 bottom outer wall of welded still pipe and ring flange 2;
Filled layer between S2-3, then 1 bottom interior wall of welded still pipe and ring flange 2;
Filled layer between S2-4, then 1 bottom outer wall of welded still pipe and ring flange 2;
S2-5, the capping layer between last 1 bottom interior wall of welded still pipe and ring flange 2;
Capping layer between S2-6, then 1 bottom outer wall of welded still pipe and ring flange 2.
Specifically, the step S2-1 and S2-2, step S2-3 and S2-4, step S2-5 and S2-6 welding simultaneously.In this way,
It can prevent steel pipe 1 and 2 commissure of ring flange from being cooled down by heating repeatedly, prevent stress from generating, welding efficiency is higher.Based on same
Consider, the step S2-1 and S2-2 welding direction is identical, and step S2-3 and S2-4 welding direction is identical, step S2-5 and S2-6
Welding direction is identical.So symmetrical welding manner, can substantially reduce the stress of commissure.
S3, as shown in figure 4, in conjunction with Fig. 5,2 surface segmentation of ring flange is 4N section by 4N gusset 3, according to executing step
Welding direction when rapid S2 is sequentially completed the steel pipe 1 in each section and the welding of 2 weld seam of ring flange clockwise or counter-clockwise.
In this way, only welding need to can be completed clockwise or counter-clockwise by one circle of steel pipe 1 and the rotation of ring flange 2, it is more efficient.Steel pipe 1
Often larger with 2 volume of ring flange, heat conduction efficiency is higher, executes again after completing two weld seams in a section next
Weld seam welding in section, tends not to generate biggish stress.Of course, for the steel pipe 1 and ring flange 2 of small volume,
Two weld seams welding in a section by the way of symmetrical welding, i.e., can also be first completed, then executes two of symmetric interval
Weld seam welding, reduces welding stress.
S4 is divided into two groups, two 11 phases of side plate in each group as shown in figure 5, choosing four side plates 11 on steel pipe 1
Mutually parallel, the side plate 11 between two groups is vertical, and 11 corresponding four gussets 3 of this four side plates are welded in the following order
It connects: first will wherein be welded with side plate 11 and 2 surface of ring flange a gusset 3, i.e. step S4-1;Again by the other muscle in same group
Plate 3 and side plate 11 and 2 surface of ring flange are welded, i.e. step S4-2;Again by the gusset 3 and side plate 11 and ring flange in another group
The welding of 2 surfaces, i.e. step S4-3;Another gusset 3 in another group is welded with side plate 11 and 2 surface of ring flange finally, that is, is walked
Rapid S4-4.In this way, can effectively reduce welding stress by the way of cross welding, positioning is more accurate, prevents from being partially welded, and
It can prevent weld seam from cracking failure occurs in later period use process.
Specifically, as shown in fig. 6, forming two balanced weldings in left and right between each gusset 3 and side plate 11 and 2 surface of ring flange
It stitches, the welding of the two symmetrical weld seams in left and right includes the following steps,
The prime coat of a wherein weld seam is first welded, then welds the prime coat of an other weld seam, i.e. step S4a;
The filled layer of first weld seam is welded again, then welds the filled layer of an other weld seam, i.e. step S4b;
The capping layer of first weld seam is finally welded, then welds the capping layer of an other weld seam, i.e. step S4c.
In this way, can prevent from being cooled down at gusset 3 and 2 surface weld of side plate 11 and ring flange by heating repeatedly, prevent stress from producing
Raw, welding efficiency is higher.Based on same consideration, the welding direction of every one of weld seam of the two symmetrical weld seams in left and right is identical.Such as
This symmetrical welding manner can substantially reduce the stress of commissure.
S5 is sequentially completed the weldering of 4N gusset 3 Yu side plate 11 and ring flange (2) surface according to the welding sequence of step S4
It connects.
The foregoing is merely better embodiments of the invention, are not intended to limit the invention, all of the invention
Within spirit and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (8)
1. a kind of power transmission steel pipe tower flange welding technique comprising following steps,
Gusset (3) is first arranged in a mutually vertical manner and is welded and fixed with steel pipe (1) and ring flange (2) surface by S1;
Weld seam and steel pipe (1) bottom outer wall and ring flange between S2, then welded still pipe (1) bottom interior wall and ring flange (2)
(2) weld seam between;
It is characterized by: step S2 includes,
S2-1, the prime coat between first welded still pipe (1) bottom interior wall and ring flange (2);
Prime coat between S2-2, then welded still pipe (1) bottom outer wall and ring flange (2);
Filled layer between S2-3, then welded still pipe (1) bottom interior wall and ring flange (2);
Filled layer between S2-4, then welded still pipe (1) bottom outer wall and ring flange (2);
S2-5, the capping layer between last welded still pipe (1) bottom interior wall and ring flange (2);
Capping layer between S2-6, then welded still pipe (1) bottom outer wall and ring flange (2).
2. power transmission steel pipe tower flange welding technique as described in claim 1, it is characterised in that: the step S2-1 and S2-2 is applied
Weldering direction is identical, and step S2-3 and S2-4 welding direction is identical, and step S2-5 and S2-6 welding direction is identical.
3. power transmission steel pipe tower flange welding technique as described in claim 1, it is characterised in that: the steel pipe (1) is wide by 4N
It spends identical side plate (11) to be formed by connecting from beginning to end, steel pipe (1) cross section is in the side 4N shape, and gusset (3) is provided with 4N, each gusset
(3) it is mutually perpendicular to and is welded and fixed with side plate (11) and ring flange (2) surface, N is positive integer.
4. power transmission steel pipe tower flange welding technique as claimed in claim 3, it is characterised in that: further include step S3,4N muscle
Ring flange (2) surface segmentation is 4N section by plate (3), welding direction when according to execution step S2, the clockwise or inverse time
Needle is sequentially completed the steel pipe (1) in each section and the welding of ring flange (2) weld seam.
5. power transmission steel pipe tower flange welding technique as claimed in claim 3, it is characterised in that: further include step S4, in steel pipe
(1) four side plates (11) are chosen on, are divided into two groups, two side plates (11) in each group are parallel to each other, the side plate between two groups
(11) vertically, this corresponding four gusset (3) of four side plates (11) is welded in the following order: first will a wherein gusset
(3) it is welded with side plate (11) and ring flange (2) surface;Again by same group an other gusset (3) and side plate (11) and flange
The welding of disk (2) surface;The gusset (3) in another group is welded with side plate (11) and ring flange (2) surface again;It finally will be another
Another gusset (3) and side plate (11) and ring flange (2) surface in group weld.
6. power transmission steel pipe tower flange welding technique as claimed in claim 5, it is characterised in that: further include step S5, according to step
The welding sequence of rapid S4, is sequentially completed the welding of 4N gusset (3) Yu side plate (11) and ring flange (2) surface.
7. power transmission steel pipe tower flange welding technique as claimed in claim 5, it is characterised in that: each gusset (3) and side plate
(11) the two symmetrical weld seams in left and right are formed between ring flange (2) surface, the welding of the two symmetrical weld seams in left and right includes following step
Suddenly,
The prime coat of a wherein weld seam is first welded, then welds the prime coat of an other weld seam;
The filled layer of first weld seam is welded again, then welds the filled layer of an other weld seam;
The capping layer of first weld seam is finally welded, then welds the capping layer of an other weld seam.
8. power transmission steel pipe tower flange welding technique as claimed in claim 7, it is characterised in that: control the every of two symmetrical weld seams
The welding direction of one of weld seam is identical.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910721192.8A CN110508961A (en) | 2019-08-06 | 2019-08-06 | Power transmission steel pipe tower flange welding technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910721192.8A CN110508961A (en) | 2019-08-06 | 2019-08-06 | Power transmission steel pipe tower flange welding technique |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110508961A true CN110508961A (en) | 2019-11-29 |
Family
ID=68624558
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910721192.8A Pending CN110508961A (en) | 2019-08-06 | 2019-08-06 | Power transmission steel pipe tower flange welding technique |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110508961A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112658513A (en) * | 2020-12-31 | 2021-04-16 | 广东工业大学 | Welding method for main propeller base of deep water dynamic positioning crude oil conveying device |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102268873A (en) * | 2011-03-01 | 2011-12-07 | 浙江华铁建筑安全科技股份有限公司 | Heavy steel support and processing method thereof |
CN202577317U (en) * | 2012-03-22 | 2012-12-05 | 浙江华铁建筑安全科技股份有限公司 | Reinforced guiding support |
CN105178350A (en) * | 2015-10-09 | 2015-12-23 | 山东鲁能泰山铁塔有限公司 | Flange type polygonal steel tube foundation |
CN105499821A (en) * | 2016-01-27 | 2016-04-20 | 江苏电力装备有限公司 | Anti-deformation welding tool and welding method for steel pipes and flanges |
CN106078093A (en) * | 2016-06-28 | 2016-11-09 | 中国南方航空工业(集团)有限公司 | The processing method of flanged (FLGD) thin-walled tube-type part |
CN106312346A (en) * | 2015-06-26 | 2017-01-11 | 姜蕾 | Welding process of steel pipe and flange |
CN107877020A (en) * | 2017-11-13 | 2018-04-06 | 浙江盛达铁塔有限公司 | Large-scale steel pipe and flange mounting platform |
CN110014241A (en) * | 2019-04-29 | 2019-07-16 | 中电建武汉铁塔有限公司 | Power transmission steel pipe tower flange welding technique |
CN110014240A (en) * | 2019-04-29 | 2019-07-16 | 中电建武汉铁塔有限公司 | Electric power pylon column foot welding procedure |
-
2019
- 2019-08-06 CN CN201910721192.8A patent/CN110508961A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102268873A (en) * | 2011-03-01 | 2011-12-07 | 浙江华铁建筑安全科技股份有限公司 | Heavy steel support and processing method thereof |
CN202577317U (en) * | 2012-03-22 | 2012-12-05 | 浙江华铁建筑安全科技股份有限公司 | Reinforced guiding support |
CN106312346A (en) * | 2015-06-26 | 2017-01-11 | 姜蕾 | Welding process of steel pipe and flange |
CN105178350A (en) * | 2015-10-09 | 2015-12-23 | 山东鲁能泰山铁塔有限公司 | Flange type polygonal steel tube foundation |
CN105499821A (en) * | 2016-01-27 | 2016-04-20 | 江苏电力装备有限公司 | Anti-deformation welding tool and welding method for steel pipes and flanges |
CN106078093A (en) * | 2016-06-28 | 2016-11-09 | 中国南方航空工业(集团)有限公司 | The processing method of flanged (FLGD) thin-walled tube-type part |
CN107877020A (en) * | 2017-11-13 | 2018-04-06 | 浙江盛达铁塔有限公司 | Large-scale steel pipe and flange mounting platform |
CN110014241A (en) * | 2019-04-29 | 2019-07-16 | 中电建武汉铁塔有限公司 | Power transmission steel pipe tower flange welding technique |
CN110014240A (en) * | 2019-04-29 | 2019-07-16 | 中电建武汉铁塔有限公司 | Electric power pylon column foot welding procedure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112658513A (en) * | 2020-12-31 | 2021-04-16 | 广东工业大学 | Welding method for main propeller base of deep water dynamic positioning crude oil conveying device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111360468B (en) | Assembly welding tool for vertical plate and rib plate in fish-belly sill and welding method for fish-belly sill | |
CN110508961A (en) | Power transmission steel pipe tower flange welding technique | |
CN106270929B (en) | The welding method of railway vehicle component | |
CN1103341A (en) | Process for installation of in-situ welded large-size disc type water-wheel generator rotor support | |
CN110014242B (en) | Welding process for tower foot of power transmission tower | |
CN106808062A (en) | Thick-walled structure part electric arc silk filling increasing material manufacturing root area penetration method | |
CN103659015A (en) | Four-section segmented skip welding method | |
CN104617071A (en) | Power terminal group and power electronic module | |
CN208955084U (en) | A kind of power battery tab, busbar connector welding structure and power battery module | |
CN102966033A (en) | Multi-joint chord member of all-welded railway continuous steel truss girder, and manufacturing method of multi-joint chord member | |
CN110014240B (en) | Welding process for tower foot of power transmission tower | |
CN110014241A (en) | Power transmission steel pipe tower flange welding technique | |
US6440182B1 (en) | Method for bonding collector plates to end faces of electrode plates | |
CN107313877B (en) | Liquid-propellant rocket engine platelet injector and attaching method thereof | |
CN111347163A (en) | Y-shaped joint laser-TIG composite welding method | |
CN201685023U (en) | Spot welding device for lower component part of stainless steel car body | |
CN106695063A (en) | Automatic welding technological method of rack of marine diesel engine | |
JPS59101244A (en) | Manufacture of metallic honeycomb body | |
CN100390490C (en) | Plate-type heat exchanger fitted with reinforcing conic-bed at angular hole path bottom | |
CN103644668B (en) | A kind of flexible sealing structure for vacuum flat plate collector | |
CN106141397A (en) | Resistance welding frock | |
JPS6242468A (en) | Electrical connection method for solar cell | |
CN104708178B (en) | A kind of 5M level store-vessel bottom longitudinal seam welding method | |
CN114284647B (en) | Connection structure of unequal tab and pole of lithium battery | |
CN218902391U (en) | Nozzle structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191129 |