CN110468718A - A kind of bridge drain hole pre-embedded device being used in turn - Google Patents

A kind of bridge drain hole pre-embedded device being used in turn Download PDF

Info

Publication number
CN110468718A
CN110468718A CN201910802463.2A CN201910802463A CN110468718A CN 110468718 A CN110468718 A CN 110468718A CN 201910802463 A CN201910802463 A CN 201910802463A CN 110468718 A CN110468718 A CN 110468718A
Authority
CN
China
Prior art keywords
embedded device
drain hole
bridge
turn
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910802463.2A
Other languages
Chinese (zh)
Inventor
曾凡福
徐建宁
卢池
李亚基
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd, Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN201910802463.2A priority Critical patent/CN110468718A/en
Publication of CN110468718A publication Critical patent/CN110468718A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/08Damp-proof or other insulating layers; Drainage arrangements or devices ; Bridge deck surfacings
    • E01D19/086Drainage arrangements or devices
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Abstract

The present invention provides the bridge drain hole pre-embedded devices that one kind can be used in turn, and are formed by steel plate welding production;The shape of the pre-embedded device is consistent with drain hole, and outer dimension is 5-10mm bigger than the size of tapping pipe;The top and bottom of the pre-embedded device axially are respectively sealing face, and handle is welded in the outside positioned at the sealing face of upper end;The outer surface brushing release agent of the pre-embedded device;After the completion of bridge reinforcement binding, the pre-embedded device installation is fixed to bridge top surface;After concreting is completed and is solidified, the pre-embedded device is taken out from the concrete of solidification, and the drain hole is formed in concrete.The above-mentioned bridge drain hole pre-embedded device being used in turn, easy construction, and the device can have enough to meet the need reuse, energy conservation and environmental protection.

Description

A kind of bridge drain hole pre-embedded device being used in turn
Technical field
The present invention relates to building engineering field more particularly to bridge drain holes.
Background technique
To reduce bridge floor ponding, bridge floor needs to be arranged a certain number of tapping pipes, to undertake rainwater discharge task.In bridge Common tapping pipe mainly has cast iron tapping pipe, and the installation of cast iron tapping pipe is usually to reserve to let out when bridge is cast-in-place or prefabricated Water pipe mounting hole.The method that bridge drain hole mainly uses pre-buried pvc pipe is reserved in current domestic construction, it is pre-buried in design position One section is greater than the PVC round tube for designing sluicing pipe outside diameter.Drain hole is reserved using the method, the PVC round tube for needing disposably to put into Quantity is larger, causes waste of material, before the installation of subsequent tapping pipe, it is also necessary to remove to the PVC round tube of pore-forming in advance clear Reason, while bridge floor water inlet is cut according to tapping pipe horn mouth size, working face is reserved for installation tapping pipe, is being installed It needs for pipeline to be fixed temporarily when tapping pipe, and the gap filling of surrounding is closely knit, process is complex, and presentation quality cannot protect Card, tapping pipe installation efficiency are integrally lower.
Summary of the invention
The main technical problem to be solved by the present invention is to provide the bridge drain hole pre-embedded device that can be used in turn of one kind, Easy construction, and the device can have enough to meet the need reuse, energy conservation and environmental protection.
In order to solve the above technical problems, the present invention provides the pre-buried dresses in bridge drain hole that one kind can be used in turn It sets, is formed by steel plate welding production;The shape of the pre-embedded device is consistent with drain hole, ruler of the outer dimension than tapping pipe Very little big 5-10mm;The top and bottom of the pre-embedded device axially are respectively sealing face, seal the outer of face positioned at upper end Weld handle in side;
The outer surface brushing release agent of the pre-embedded device;After the completion of bridge reinforcement binding, the pre-embedded device installation It is fixed to bridge top surface;After concreting is completed and is solidified, the pre-embedded device is taken out from the concrete of solidification, mixed The drain hole is formed in solidifying soil.
Compared to the prior art, technical solution of the present invention have it is following the utility model has the advantages that
The present invention provides the bridge drain hole pre-embedded device that can be used in turn of one kind, bridge is cast-in-place or prefabricated construction Shi Jinhang is pre-buried, drain hole is disposably reserved molding according to design position according to sluicing tube shape, tapping pipe is not necessarily to when installing Extra auxiliary process, easy construction, and the device can have enough to meet the need reuse, energy conservation and environmental protection.
Detailed description of the invention
Fig. 1 is the schematic diagram of pre-embedded device in the preferred embodiment of the present invention;
Fig. 2 is that the schematic diagram after tapping pipe is installed in the preferred embodiment of the present invention.
Specific embodiment
Hereafter just specific implementation method of the invention is further described, but specific implementation method of the invention is not limited to This.
With reference to Fig. 1 and Fig. 2, a kind of bridge drain hole pre-embedded device being used in turn is formed by steel plate welding production;Institute The shape for stating pre-embedded device is consistent with drain hole, and outer dimension is 5-10mm bigger than the size of tapping pipe;The pre-embedded device Top and bottom axially are respectively sealing face 1,2, and handle 3 is welded in the outside positioned at the sealing face 1 of upper end;
The outer surface brushing release agent of the pre-embedded device;After the completion of bridge reinforcement binding, the pre-embedded device installation It is fixed to bridge top surface;After concreting is completed and is solidified, the pre-embedded device is taken out from the concrete of solidification, mixed The drain hole is formed in solidifying soil.Hereafter it only needs to be inserted into tapping pipe in drain hole, so that it may complete the installation of tapping pipe.
The mutually above-mentioned bridge drain hole pre-embedded device being used in turn carries out pre- when bridge is cast-in-place or prefabricated construction It buries, drain hole is disposably reserved according to design position by molding according to sluicing tube shape, extra auxiliary is not necessarily to when tapping pipe is installed Process, easy construction, and the device can have enough to meet the need reuse, energy conservation and environmental protection.
Described above, only the present invention preferably implements example, cannot limit the scope of implementation of the present invention according to this.I.e. according to this Equivalent changes and modifications made by patent of invention range and description, should still be within the scope of the present invention.

Claims (1)

1. the bridge drain hole pre-embedded device that one kind can be used in turn, it is characterised in that formed by steel plate welding production;It is described pre- The shape for burying device is consistent with drain hole, and outer dimension is 5-10mm bigger than the size of tapping pipe;The pre-embedded device along Axial top and bottom are respectively sealing face, and handle is welded in the outside positioned at the sealing face of upper end;
The outer surface brushing release agent of the pre-embedded device;After the completion of bridge reinforcement binding, the pre-embedded device installation is fixed To bridge top surface;After concreting is completed and is solidified, the pre-embedded device is taken out from the concrete of solidification, in concrete It is middle to form the drain hole.
CN201910802463.2A 2019-08-28 2019-08-28 A kind of bridge drain hole pre-embedded device being used in turn Pending CN110468718A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910802463.2A CN110468718A (en) 2019-08-28 2019-08-28 A kind of bridge drain hole pre-embedded device being used in turn

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910802463.2A CN110468718A (en) 2019-08-28 2019-08-28 A kind of bridge drain hole pre-embedded device being used in turn

Publications (1)

Publication Number Publication Date
CN110468718A true CN110468718A (en) 2019-11-19

Family

ID=68512496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910802463.2A Pending CN110468718A (en) 2019-08-28 2019-08-28 A kind of bridge drain hole pre-embedded device being used in turn

Country Status (1)

Country Link
CN (1) CN110468718A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1441120A (en) * 2003-04-07 2003-09-10 沈阳铁路工程建设集团有限公司 Bridge drainage pipe installing construction process
KR100848855B1 (en) * 2007-05-17 2008-07-29 현빈개발 주식회사 Built-up drain groove formed at upper slab for bridge and method for forming built-up drain for bridge using the same
CN201460209U (en) * 2009-07-22 2010-05-12 刘秀立 Mould for concrete wall pocket in building
CN202125074U (en) * 2011-06-24 2012-01-25 江苏双楼建设集团有限公司 Double cone floorslab reserved-hole die
CN104452601A (en) * 2014-12-15 2015-03-25 宁波交通工程建设集团有限公司 Bushing mold for drain pipe of bridge deck and method for applying bushing mold
CN107471428A (en) * 2017-08-22 2017-12-15 中铁十七局集团第三工程有限公司 Manufacture method in a kind of non-standard box beam field
CN210975559U (en) * 2019-08-28 2020-07-10 中铁一局集团厦门建设工程有限公司 Bridge water outlet pre-embedding device capable of being used in turnover mode

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1441120A (en) * 2003-04-07 2003-09-10 沈阳铁路工程建设集团有限公司 Bridge drainage pipe installing construction process
KR100848855B1 (en) * 2007-05-17 2008-07-29 현빈개발 주식회사 Built-up drain groove formed at upper slab for bridge and method for forming built-up drain for bridge using the same
CN201460209U (en) * 2009-07-22 2010-05-12 刘秀立 Mould for concrete wall pocket in building
CN202125074U (en) * 2011-06-24 2012-01-25 江苏双楼建设集团有限公司 Double cone floorslab reserved-hole die
CN104452601A (en) * 2014-12-15 2015-03-25 宁波交通工程建设集团有限公司 Bushing mold for drain pipe of bridge deck and method for applying bushing mold
CN107471428A (en) * 2017-08-22 2017-12-15 中铁十七局集团第三工程有限公司 Manufacture method in a kind of non-standard box beam field
CN210975559U (en) * 2019-08-28 2020-07-10 中铁一局集团厦门建设工程有限公司 Bridge water outlet pre-embedding device capable of being used in turnover mode

Similar Documents

Publication Publication Date Title
CN103498486B (en) A kind of sleeve pipe that adopts implements the method for shutoff to ater-casting precipitation pipe well
CN206376287U (en) Subway station main body and the float Structure of accessory structure interface
CN104988915B (en) A kind of prefabricated installation method of detachable steel casing and under water connection beam
CN102345301A (en) New method for plugging dewatering well in basement
CN207297034U (en) Tunnel double-lining concrete vault backfills grouting device
CN109025899B (en) Well sealing device
CN102285003A (en) Production process of reinforced concrete pipeline with anti-corrosion inner lining
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN208763204U (en) A kind of vertical connecting structure of low layer assembled architecture prefabricated panel
CN210975559U (en) Bridge water outlet pre-embedding device capable of being used in turnover mode
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN110468718A (en) A kind of bridge drain hole pre-embedded device being used in turn
CN108360573B (en) Device for preventing post-cast strip of basement floor from leaking and construction method thereof
CN106592532B (en) The construction method of concrete works deformation joint sealing swaging die with reinforcing fiber
CN203514332U (en) Casing for blocking dewatering tube well of post-cast strip
CN102518129A (en) Post pressure-grouting pre-stressed hollow square pile and manufacturing method thereof
CN104911999A (en) Construction method for deeply burying anchor
CN211342004U (en) Hole reinforcing and leakage preventing construction structure for side wall of old water pool
CN204174629U (en) A kind of light-duty precipitation well point ater-casting, underground building multi-way prevention plugging structure
CN209924089U (en) A well device of riding on horse for pipeline construction
CN208309615U (en) A kind of hole top row ditch of foundation pit
CN202580338U (en) Prestressed concrete cylinder pipe for jacking construction method
CN110593629A (en) Construction method and structure for reinforcing and preventing leakage of old pool side wall through hole opening
CN103774620A (en) Concrete engineering expansion joint vertical sealing up structure fixing member and application thereof
CN205116719U (en) Mould of hole prefabricated section is reserved in preparation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination