CN110424684A - 一种电线半盒的施工方法 - Google Patents
一种电线半盒的施工方法 Download PDFInfo
- Publication number
- CN110424684A CN110424684A CN201910635299.0A CN201910635299A CN110424684A CN 110424684 A CN110424684 A CN 110424684A CN 201910635299 A CN201910635299 A CN 201910635299A CN 110424684 A CN110424684 A CN 110424684A
- Authority
- CN
- China
- Prior art keywords
- electric wire
- box
- half box
- back box
- muscle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/02—Details
- H02G3/08—Distribution boxes; Connection or junction boxes
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
一种电线半盒的施工方法,包括如下步骤:穿筋电线底盒预埋完毕,待剪力墙打点完成后,采用靠尺确定电线半盒出墙厚度;根据该出墙厚度制作出相应高度的电线半盒;该电线半盒的内部尺寸与穿筋电线底盒内部尺寸相匹配,使得电线半盒恰好插入所述穿筋电线底盒内;将电线半盒采用胶水胶粘固定于剪力墙中预埋好的穿筋电线底盒处。本发明采用增加电线半盒高度并改变内部尺寸,然后用胶水粘接到穿筋电线底盒上,避免了安装工人采用水泥砂浆固定电线半盒产生的质量及观感问题,缩短工艺流程,减少工期,节约了大量的人力物力,有着良好的经济效益,同时解决传统方式电线半盒四周较易开裂的问题。
Description
技术领域
本发明属于建筑电气施工技术领域,具体涉及一种电线半盒的施工方法。
背景技术
近年来随着建筑市场竞争的日趋激烈、政府部门加强建筑市场行为监管,促使企业争创精品工程的意识增强,企业一方面对工程施工质量加强管理的同时,另一方面顺应建筑工业化的趋势,积极寻求新工艺新方法提高传统施工工艺的效率。
在房建项目中,各种电气线路的终端为墙体中的线盒,其施工质量的好坏影响到毛坯房的观感质量,危及业主房子整体质量,进而影响到房子的销售业绩。工程项目剪力墙中预埋的线盒数量十分庞大,因此电线半盒的添加效率直接影响到装修阶段电气工程的工期,同时也直接牵涉到后续工作的开始时间。传统电线半盒为带铁扣,深度为2cm的四方形无底盒。
传统施工流程中,添加电线半盒的施工工序是在内墙打点后及内墙粉刷前进行,因此留给安装人员添加电线半盒的工期十分紧迫,往往是任务重、时间紧、效率低。传统添加电线半盒工艺效率低、成品效果差,其施工工艺为:安装工人自拌水泥砂浆,用砂浆将电线半盒固定于剪力墙中预埋线盒处,并用靠尺置于电线半盒及打点处,调整电线半盒的出墙厚度,使得其与粉刷面相平。
现有的采用自拌水泥砂浆添加电线半盒的方法存在如下缺点:1、安装人员从自拌水泥砂浆到电线半盒安装完成的整个施工周期长,且安装效率低,容易影响到土建内墙粉刷工序的进行。2、固定电线半盒需要自拌水泥砂浆,费工费时费料。3、安装人员自拌砂浆与土建内粉人员拌制的内粉砂浆配合比及掺加剂不同,在靠近电线半盒四周的粉刷面较易开裂。
发明内容
本发明所要解决的技术问题在于提供一种简单方便、施工效果好的电线半盒的施工方法。
本发明是这样实现的:
一种电线半盒的施工方法,包括如下步骤:
步骤S1:穿筋电线底盒预埋:
在穿筋电线底盒中放入防浆保护盖,用胶带固定牢固,在穿筋电线底盒两侧穿入钢筋;
依据电气施工图纸,在现场相应位置墙体中放入穿筋电线底盒,并拿靠尺进行定位复测,使得防浆保护盖面与封模板面持平;
然后将穿筋电线底盒旁钢筋焊接于墙体钢筋中;
步骤S2:安装电线半盒:
待剪力墙打点完成后,采用靠尺确定电线半盒出墙厚度;
根据该出墙厚度制作出相应高度的电线半盒;该电线半盒的内部尺寸与穿筋电线底盒内部尺寸相匹配,使得电线半盒恰好插入所述穿筋电线底盒内;
将电线半盒采用胶水胶粘固定于剪力墙中预埋好的穿筋电线底盒处。
进一步地,所述步骤S2,还包括:在所述电线半盒的开口处设置成品保护盖。
本发明的优点在于:电线半盒增加高度并改变内部尺寸,然后采用胶水粘接到穿筋电线底盒上,避免了安装工人采用水泥砂浆固定电线半盒产生的质量及观感问题。本发明的电线半盒施工方法无任何遗留,较为方便、简单。不需要安装工人自拌水泥砂浆,缩短工艺流程,减少工期,节约了大量的人力物力,有着良好的经济效益;同时取消水泥砂浆固定电线半盒的方式,解决传统方式电线半盒四周粉刷面较易开裂的问题。
附图说明
下面参照附图结合实施例对本发明作进一步的描述。
图1是本发明的穿筋电线底盒和电线半盒的位置关系示意图。
具体实施方式
一种电线半盒的施工方法,包括如下步骤:
步骤S1:穿筋电线底盒1预埋:
在86HS70穿筋电线底盒1中放入防浆保护盖,用胶带固定牢固,在穿筋电线底盒两侧穿入钢筋;
依据电气施工图纸,在现场相应位置墙体中放入穿筋电线底盒1,并拿靠尺进行定位复测,使得防浆保护盖面与封模板面持平;
然后将穿筋电线底盒1旁钢筋焊接于墙体钢筋中;
步骤S2:安装电线半盒2:
待剪力墙打点完成后,采用靠尺确定电线半盒2出墙厚度;
根据该出墙厚度制作出相应高度的电线半盒2;该电线半盒2的内部尺寸与穿筋电线底盒1内部尺寸相匹配,使得电线半盒2恰好插入所述穿筋电线底盒1内,如图1所示;
将电线半盒2采用胶水胶粘固定于剪力墙中预埋好的穿筋电线底盒2处。
在所述电线半盒2的开口处设置成品保护盖(图未示)。
本发明增加了电线半盒的高度并改变内部尺寸,然后用胶水粘接到穿筋电线底盒上,避免了安装工人采用水泥砂浆固定电线半盒产生的质量及观感问题。本发明的电线半盒施工方法无任何遗留,较为方便、简单。不需要安装工人自拌水泥砂浆,缩短工艺流程,减少工期,节约了大量的人力物力,有着良好的经济效益;同时取消水泥砂浆固定电线半盒的方式,解决传统方式电线半盒四周粉刷面较易开裂的问题。
上述实施例和图式并非限定本发明的产品形态和式样,任何所属技术领域的普通技术人员对其所做的适当变化或修饰,皆应视为不脱离本发明的专利范畴。
Claims (2)
1.一种电线半盒的施工方法,其特征在于:包括如下步骤:
步骤S1:穿筋电线底盒预埋:
在穿筋电线底盒中放入防浆保护盖,用胶带固定牢固,在穿筋电线底盒两侧穿入钢筋;
依据电气施工图纸,在现场相应位置墙体中放入穿筋电线底盒,并拿靠尺进行定位复测,使得防浆保护盖面与封模板面持平;
然后将穿筋电线底盒旁钢筋焊接于墙体钢筋中;
步骤S2:安装电线半盒:
待剪力墙打点完成后,采用靠尺确定电线半盒出墙厚度;
根据该出墙厚度制作出相应高度的电线半盒;该电线半盒的内部尺寸与穿筋电线底盒内部尺寸相匹配,使得电线半盒恰好插入所述穿筋电线底盒内;
将电线半盒采用胶水胶粘固定于剪力墙中预埋好的穿筋电线底盒处。
2.如权利要求1所述的一种电线半盒的施工方法,其特征在于:所述步骤S2,还包括:在所述电线半盒的开口处设置成品保护盖。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910635299.0A CN110424684A (zh) | 2019-07-15 | 2019-07-15 | 一种电线半盒的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910635299.0A CN110424684A (zh) | 2019-07-15 | 2019-07-15 | 一种电线半盒的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110424684A true CN110424684A (zh) | 2019-11-08 |
Family
ID=68410645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910635299.0A Pending CN110424684A (zh) | 2019-07-15 | 2019-07-15 | 一种电线半盒的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110424684A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2036535A1 (en) * | 1990-05-14 | 1991-11-15 | Szabolcs G. Lengyel | Electrical outlet box assembly for power and communication wires |
US20020042990A1 (en) * | 2000-03-03 | 2002-04-18 | Rorey Kuhn | Electrical junction assembly and related splicing method |
US9258919B1 (en) * | 2014-01-03 | 2016-02-09 | Elmer Rose | Firewall insert box |
CN206211452U (zh) * | 2016-11-17 | 2017-05-31 | 中建五局第三建设有限公司 | 墙体二次预埋加长型无底调节盒 |
CN208046161U (zh) * | 2018-04-23 | 2018-11-02 | 陈亚阳 | 组合式接线盒 |
-
2019
- 2019-07-15 CN CN201910635299.0A patent/CN110424684A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2036535A1 (en) * | 1990-05-14 | 1991-11-15 | Szabolcs G. Lengyel | Electrical outlet box assembly for power and communication wires |
US20020042990A1 (en) * | 2000-03-03 | 2002-04-18 | Rorey Kuhn | Electrical junction assembly and related splicing method |
US9258919B1 (en) * | 2014-01-03 | 2016-02-09 | Elmer Rose | Firewall insert box |
CN206211452U (zh) * | 2016-11-17 | 2017-05-31 | 中建五局第三建设有限公司 | 墙体二次预埋加长型无底调节盒 |
CN208046161U (zh) * | 2018-04-23 | 2018-11-02 | 陈亚阳 | 组合式接线盒 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106193514B (zh) | 不规则双曲面竹铝复合板施工方法 | |
CN104196012B (zh) | 一种基于bim的溶洞处理方法 | |
CN105298307A (zh) | 一种用于成品平开门窗框预应力紧固结构 | |
Jun et al. | BIM-based carbon dioxide emission quantity assessment method in Korea | |
CN207277623U (zh) | 一种整体模块装配式隔墙 | |
MX2016002055A (es) | Suspensiones de cuentas elaboradas para su uso en suspensiones de cemento de bajo peso y metodos relativos a estas. | |
CN110424684A (zh) | 一种电线半盒的施工方法 | |
CN108286341A (zh) | 一种不同基底材料交接处防裂钢网模板结构及利用其进行施工的方法 | |
Nowotarski et al. | Waste reduction by lean construction-office building case study | |
CN108797954A (zh) | 结构体预埋线盒的限位施工方法 | |
MX2022015685A (es) | Adaptacion en tiempo real de lechada de cemento para tiempo de espesamiento de fondo de pozo. | |
CN204531268U (zh) | 钢骨架干粘石材墙体 | |
CN107642183A (zh) | 一种整体模块装配式隔墙 | |
CN108468388A (zh) | 一种预埋件及其施工方法 | |
CN209353613U (zh) | 一种钢结构建筑防火墙面板 | |
CN101343855B (zh) | 场道道面混凝土施工的纹理施工方法 | |
CN110439312A (zh) | 点挂式保温一体板外墙改造的施工方法 | |
CN102587543A (zh) | 一种建筑遮阳现浇混凝土花格墙及施工方法 | |
CN110206254A (zh) | 一种基于热电效应的保温装饰一体板及其安装方法 | |
CN204676889U (zh) | 塑料建筑浇灌门窗转角模板 | |
CN103469978A (zh) | 一种墙面施工工艺 | |
CN105625670B (zh) | 一种石材点挂工艺 | |
CN205296806U (zh) | 建筑外防护架的连墙结构 | |
CN205153189U (zh) | 一种钢结构整体装配式楼体及其墙体结构 | |
Schlagbauer et al. | Cost Calculation in Prefabricated Timber Construction: Methodology of Assessment and General Requirements |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20200927 Address after: 350000, 36 floor, landmark 89, 54 Road, Gulou District, Fujian, Fuzhou Applicant after: FUJIAN JIANGONG GROUP Co.,Ltd. Applicant after: Fujian Construction Engineering Group Co., Ltd Address before: 350000, 36 floor, landmark 89, 54 Road, Gulou District, Fujian, Fuzhou Applicant before: FUJIAN JIANGONG GROUP Co.,Ltd. |
|
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20191108 |