CN110414776A - Branch trade electrical characteristics quick response analysis system - Google Patents

Branch trade electrical characteristics quick response analysis system Download PDF

Info

Publication number
CN110414776A
CN110414776A CN201910514955.1A CN201910514955A CN110414776A CN 110414776 A CN110414776 A CN 110414776A CN 201910514955 A CN201910514955 A CN 201910514955A CN 110414776 A CN110414776 A CN 110414776A
Authority
CN
China
Prior art keywords
data
year
load
electrical characteristics
saturation degree
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910514955.1A
Other languages
Chinese (zh)
Other versions
CN110414776B (en
Inventor
朱东坡
谢彬
黄凯
王超
王心怡
王宏茹
王晓博
赵建贞
王国亮
樊江川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Zhengzhou Power Supply Co of Henan Electric Power Co
Original Assignee
State Grid Corp of China SGCC
Zhengzhou Power Supply Co of Henan Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Zhengzhou Power Supply Co of Henan Electric Power Co filed Critical State Grid Corp of China SGCC
Priority to CN201910514955.1A priority Critical patent/CN110414776B/en
Publication of CN110414776A publication Critical patent/CN110414776A/en
Application granted granted Critical
Publication of CN110414776B publication Critical patent/CN110414776B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of branch trade electrical characteristics quick response analysis systems, the present invention collects data by power information acquisition system, PMS2.0 system and same period line loss system, data available is obtained using sampling and interpolation method processing missing values and exceptional value, and then pass through curve iteration, study industry-specific electricity consumption characteristic curve, it was found that its possession electrical characteristics rule, electricity consumption characteristic curve is patterned displaying by visual interface, realize Load Characteristic Analysis visualization, normalization, reply part throttle characteristics is changing and is being difficult to the predicament grasped in real time;It solves existing method or tool and is difficult to support the problems such as changing because of part throttle characteristics brought by electrification again and energy transition and upgrade.

Description

Branch trade electrical characteristics quick response analysis system
Technical field:
The present invention relates to intelligence for field of power transformation, analyzes system more particularly to a kind of branch trade electrical characteristics quick response System.
Background technique:
The development of electric power and the level of economic development are closely related.The further in-depth of electric system reform, market warp The further development of Ji, the implementation of energy-saving and emission-reduction policy and related economic policy, the Load Characteristic Analysis work made is increasingly It is important.And part throttle characteristics constantly changes with the various influence factors relevant to load prediction such as economic development, Load Characteristic Analysis Difficulty also accordingly increase.
By reading, the analysis to existing literature, summary show that Load Characteristic Analysis method specifically includes that load curve Method, method of expertise, correlation analysis, regression analysis, time series method, Principal Component Analysis, factor analysis or ash The artificial intelligent analysis methods such as color model method, artificial neural network, wavelet analysis method and fuzzy theory method.The client of power supply enterprise The scale of construction is big, type is more, complicated with electrical characteristics, higher to Electric Power Network Planning level requirement.User of different nature is in different development ranks Section, the load rule of development is different, and existing method or tool are difficult to support because of electrification and energy transition and upgrade institute band again The problems such as part throttle characteristics come is changing.
Summary of the invention:
The technical problems to be solved by the present invention are: overcoming the deficiencies of the prior art and provide according to cell name, land used Division condition of the matter as regionality power supply, and industry-specific electricity consumption characteristic curve is obtained year according to building up, find its possession With the branch trade electrical characteristics quick response analysis system of electrical characteristics rule.
The technical scheme is that a kind of branch trade electrical characteristics quick response analysis system, is adopted by power information Collecting system, PMS2.0 system and same period line loss system collect data, utilize sampling and interpolation method processing missing values and exceptional value Data available is obtained, and then by curve iteration, generates industry-specific electricity consumption characteristic curve, and obtain its possession electrical characteristics Rule the steps include: the first step, obtain every class land character basic data;Second step calculates the load growth of each cell year by year Rate;Third step, the load growth rate averaged by homogeneous cells corresponding year, each year that every class land character is calculated are negative Lotus growth rate;4th step is converted to such saturation degree by every class land character load growth rate;5th step shows that interface is straight Output analysis is connect as a result, updating the plot load prediction results based on branch trade electrical characteristics simultaneously.
Further, the land character basic data is weekly periodically from power utilization information collection system, PMS2.0 system and same Phase line loss system obtain, the land character basic data include cell name, land character, build up year and acquisition the time limit in by Annual peak load.
Further, in the acquisition time limit peak load year by year data manipulation step are as follows: i) in the acquisition time limit Certain times, there may be shortage of data, then this time fills in 0.
Ii) Growth Rate Calculation needs the continuity of data, and the cell data that lacking occurs in the intermediate time be should give rejecting, be made Valid data keep continuity.
Iii) each horizontal annual data of cell cannot lack too much, and valid data account for the data that acquisition time limit ratio is lower than 1/4 It should give rejecting.
Iv) the customer charge data acquired should increase year by year, should give rejecting for the user data of load decline.
Further, when the saturation computation, cell load data are unifiedly calculated according to the time is built up, missing portion Divide and is supplied with 0.
Further, cell load Growth Rate Calculation method are as follows:
Assuming that the cell number that every class land character gets data after investigating is M(k)(k indicates land character number), bears Lotus growth rate is defined as:
Wherein, i indicates the cell in kth class land character investigational data, i=1,2 ... M(k);The j expression of years, j=1, 2,...N-1;Indicate kth class land character, i-th of user, the annual peak load in jth year, unit MW.
For cell in certain times there may be shortage of data, according to the quality of data require in agreement, make corresponding Processing: whenOrWhen equal to 0,It does not calculate, referred to as invalid growth rate (being labeled as "-"), remainingIt is known as having Imitate growth rate;Remember kth class, jth year effective increasing rateThe collection of subscript i composition is combined into Indicate element in set Number, i.e. effective increasing rate number.
Further, the calculation method of every class land character load average growth rate are as follows:
N-1 load average growth rate of kth class land character is represented by
Wherein,Indicate kth class land character, the average load growth rate in jth year.
Further, each forcasted years saturation computation method of every class land character are as follows:
Based on the thinking that load adds up, load growth rate is reduced to the saturation degree of each forcasted years, further according to boundary condition Correct saturation degree coefficient;Boundary condition is that saturation year saturation degree is 1.
Assuming that kmaxIndicate that the land-use style that need to generate typical curve is total,Indicate kth class, the saturation degree in jth year, respectively Each forcasted years saturation degree of class land character acquires in the following way:
I) all land characters are traversed, k=1 is initialized;
Ii) consider the quality of data, in fact it could happen that such land character all cells starting the several years or the most end several years without Data, it is assumed that such is fromNian ZhiThere are data in year,And
Iii the initial saturation degree of next year) is obtained according to load average growth rate is cumulative,
Iv) ifReturn step iii);Otherwise it performs the next step;
V) saturation year initial saturation degree is obtained,
Vi) the regulation for being 1 according to saturation year saturation degree obtains each forcasted years saturation degree by normalization,
Vii) if k≤kmax, k=k+1, return step ii);Otherwise, calculating terminates.
As kth class, the saturation degree in jth year, remaining does not have calculated saturation degree that can be labeled as due to shortage of data 0。
The beneficial effects of the present invention are: the present invention passes through power information acquisition system, PMS2.0 system and same period line loss system System collects data, obtains data available using sampling and interpolation method processing missing values and exceptional value, and then pass through curve iteration, Study industry-specific electricity consumption characteristic curve, find its possession electrical characteristics rule, electricity consumption characteristic curve by visual interface into Row graphical representation, realizes Load Characteristic Analysis visualization, normalization, and reply part throttle characteristics is changing and is being difficult in real time The predicament of grasp;Existing method or tool is solved to be difficult to support because of part throttle characteristics brought by electrification again and energy transition and upgrade The problems such as changing.
Detailed description of the invention:
Fig. 1 is the flow diagram of branch trade electrical characteristics quick response analysis system.
Fig. 2 is customer charge data acquisition tables.
Fig. 3 is customer charge data by starting time sorting table.
Specific embodiment:
Embodiment: referring to figure 1, figure 2 and figure 3.
Branch trade electrical characteristics quick response analysis system, passes through power information acquisition system, PMS2.0 system and the same period Line loss system collects data, obtains data available using sampling and interpolation method processing missing values and exceptional value, and then pass through song Line interation generates industry-specific electricity consumption characteristic curve, and obtains its possession electrical characteristics rule, the steps include: the first step, obtains Take every class land character basic data;Second step calculates the load growth rate of each cell year by year;Third step, by homogeneous cells phase Each year load growth rate of every class land character is calculated in the load growth rate averaged for answering year;4th step, by every class Land character load growth rate is converted to such saturation degree;5th step shows that interface directly exports analysis as a result, updating simultaneously Plot load prediction results based on branch trade electrical characteristics.
Further, the land character basic data is weekly periodically from power utilization information collection system, PMS2.0 system and same Phase line loss system obtain, the land character basic data include cell name, land character, build up year and acquisition the time limit in by Annual peak load.
Further, in the acquisition time limit peak load year by year data manipulation step are as follows: i) in the acquisition time limit Certain times, there may be shortage of data, then this time fills in 0.
Ii) Growth Rate Calculation needs the continuity of data, and the cell data that lacking occurs in the intermediate time be should give rejecting, be made Valid data keep continuity.
Iii) each horizontal annual data of cell cannot lack too much, and valid data account for the data that acquisition time limit ratio is lower than 1/4 It should give rejecting.
Iv) the customer charge data acquired should increase year by year, should give rejecting for the user data of load decline.
Further, when the saturation computation, cell load data are needed same starting line (building up year), and practical On, cell data is generally with record of practical time (such as: 2012), it is therefore desirable to by unified starting time (building up year) weight New to arrange, lack part is supplied with 0.Data acquisition is limited to N, 0~N-1 of each forcasted years serial number year, by taking Fig. 2 as an example, arranges Afterwards as shown in Figure 3.
Further, cell load Growth Rate Calculation method are as follows:
Assuming that the cell number that every class land character gets data after investigating is M(k)(k indicates land character number), bears Lotus growth rate is defined as:
Wherein, i indicates the cell in kth class land character investigational data, i=1,2 ... M(k);The j expression of years, j=1, 2,...N-1;Indicate kth class land character, i-th of user, the annual peak load in jth year, unit MW.
For cell in certain times there may be shortage of data, according to the quality of data require in agreement, make corresponding Processing: whenOrWhen equal to 0,It does not calculate, referred to as invalid growth rate (being labeled as "-"), remainingReferred to as Effective increasing rate;Remember kth class, jth year effective increasing rateThe collection of subscript i composition is combined into Indicate element in set Number, i.e. effective increasing rate number.
Further, the calculation method of every class land character load average growth rate are as follows:
N-1 load average growth rate of kth class land character is represented by
Wherein,Indicate kth class land character, the average load growth rate in jth year.
Further, each forcasted years saturation computation method of every class land character are as follows:
Based on the thinking that load adds up, load growth rate is reduced to the saturation degree of each forcasted years, further according to boundary condition Correct saturation degree coefficient;Boundary condition is that saturation year saturation degree is 1.
Assuming that kmaxIndicate that the land-use style that need to generate typical curve is total,Indicate kth class, the saturation degree in jth year, respectively Each forcasted years saturation degree of class land character acquires in the following way:
I) all land characters are traversed, k=1 is initialized;
Ii) consider the quality of data, in fact it could happen that such land character all cells starting the several years or the most end several years without Data, it is assumed that such is fromNian ZhiThere are data in year,And
Iii the initial saturation degree of next year) is obtained according to load average growth rate is cumulative,
Iv) ifReturn step iii);Otherwise it performs the next step;
V) saturation year initial saturation degree is obtained,
Vi) the regulation for being 1 according to saturation year saturation degree obtains each forcasted years saturation degree by normalization,
Vii) if k≤kmax, k=k+1, return step ii);Otherwise, calculating terminates.
As kth class, the saturation degree in jth year, remaining does not have calculated saturation degree that can be labeled as due to shortage of data 0。
Data are collected by power information acquisition system, PMS2.0 system and same period line loss system, using sampling and are inserted Value method processing missing values and exceptional value obtain data available, and then by curve iteration, study industry-specific electricity consumption characteristic curve, It was found that its possession electrical characteristics rule, electricity consumption characteristic curve is patterned displaying by visual interface, by personnel according to Electrical feature curve predicts the plot load of branch trade electrical characteristics.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, it is all It is any simple modification, equivalent change and modification to the above embodiments according to the technical essence of the invention, still falls within In the range of technical solution of the present invention.

Claims (7)

1. a kind of branch trade electrical characteristics quick response analysis system, pass through power information acquisition system, PMS2.0 system and same Phase line loss system collects data, obtains data available using sampling and interpolation method processing missing values and exceptional value, and then pass through Curve iteration generates industry-specific electricity consumption characteristic curve, and obtains its possession electrical characteristics rule, the steps include: the first step, Obtain every class land character basic data;Second step calculates the load growth rate of each cell year by year;Third step, by homogeneous cells The load growth rate averaged in corresponding year, is calculated each year load growth rate of every class land character;4th step, by every Class land character load growth rate is converted to such saturation degree;5th step shows that interface directly exports analysis as a result, simultaneously more Newly based on the plot load prediction results of branch trade electrical characteristics.
2. branch trade according to claim 1 electrical characteristics quick response analysis system, it is characterized in that: the land character Basic data is periodically obtained from power utilization information collection system, PMS2.0 system and same period line loss system weekly, the land character base Plinth data include cell name, land character, build up peak load year by year in year and the acquisition time limit.
3. branch trade according to claim 1 electrical characteristics quick response analysis system, it is characterized in that: the acquisition time limit The inside data manipulation step of peak load year by year are as follows: i) certain times in the acquisition time limit, there may be shortage of data, then this Time fills in 0.
Ii) Growth Rate Calculation needs the continuity of data, and the cell data that lacking occurs in the intermediate time should give rejecting, makes effectively Data keep continuity.
Iii) each horizontal annual data of cell cannot lack too much, and valid data account for data of the acquisition time limit ratio lower than 1/4 should To reject.
Iv) the customer charge data acquired should increase year by year, should give rejecting for the user data of load decline.
4. branch trade according to claim 1 electrical characteristics quick response analysis system, it is characterized in that: the saturation degree meter When calculation, cell load data are unifiedly calculated according to the time is built up, and lack part is supplied with 0.
5. branch trade according to claim 1 electrical characteristics quick response analysis system, it is characterized in that: cell load increases Rate calculation method are as follows:
Assuming that the cell number that every class land character gets data after investigating is M(k)(k indicates land character number), load increases Long rate is defined as:
Wherein, i indicates the cell in kth class land character investigational data, i=1,2 ... M(k);The j expression of years, j=1,2, ...N-1;Indicate kth class land character, i-th of user, the annual peak load in jth year, unit MW.
For cell in certain times there may be shortage of data, according to the quality of data require in agreement, make respective handling: WhenOrWhen equal to 0,It does not calculate, referred to as invalid growth rate (being labeled as "-"), remainingReferred to as effectively increase Long rate;Remember kth class, jth year effective increasing rateThe collection of subscript i composition is combined into Indicate element number in set, That is effective increasing rate number.
6. branch trade according to claim 1 electrical characteristics quick response analysis system, it is characterized in that: every class land character The calculation method of load average growth rate are as follows:
N-1 load average growth rate of kth class land character is represented by
Wherein,Indicate kth class land character, the average load growth rate in jth year.
7. branch trade according to claim 1 electrical characteristics quick response analysis system, it is characterized in that: every class land character Each forcasted years saturation computation method are as follows:
Based on the thinking that load adds up, load growth rate is reduced to the saturation degree of each forcasted years, is corrected further according to boundary condition Saturation degree coefficient;Boundary condition is that saturation year saturation degree is 1.
Assuming that kmaxIndicate that the land-use style that need to generate typical curve is total,Indicate kth class, the saturation degree in jth year, all kinds of use Property each forcasted years saturation degree in ground acquires in the following way:
I) all land characters are traversed, k=1 is initialized;
Ii the quality of data) is considered, in fact it could happen that all cells starting several years of such land character or most end several years no data, Assuming that such is fromNian ZhiThere are data in year,And
Iii the initial saturation degree of next year) is obtained according to load average growth rate is cumulative,
Iv) ifReturn step iii);Otherwise it performs the next step;
V) saturation year initial saturation degree is obtained,
Vi) the regulation for being 1 according to saturation year saturation degree obtains each forcasted years saturation degree by normalization,
Vii) if k≤kmax, k=k+1, return step ii);Otherwise, calculating terminates.
As kth class, the saturation degree in jth year, remaining does not have calculated saturation degree can be labeled as 0 due to shortage of data.
CN201910514955.1A 2019-06-14 2019-06-14 Quick response analysis system for power utilization characteristics of different industries Active CN110414776B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910514955.1A CN110414776B (en) 2019-06-14 2019-06-14 Quick response analysis system for power utilization characteristics of different industries

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910514955.1A CN110414776B (en) 2019-06-14 2019-06-14 Quick response analysis system for power utilization characteristics of different industries

Publications (2)

Publication Number Publication Date
CN110414776A true CN110414776A (en) 2019-11-05
CN110414776B CN110414776B (en) 2022-11-29

Family

ID=68359064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910514955.1A Active CN110414776B (en) 2019-06-14 2019-06-14 Quick response analysis system for power utilization characteristics of different industries

Country Status (1)

Country Link
CN (1) CN110414776B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112700069A (en) * 2021-01-15 2021-04-23 国家电网有限公司 Method for predicting short-term load of regional power distribution network containing energy storage
CN117543563A (en) * 2023-11-23 2024-02-09 国网河南省电力公司郑州供电公司 Short-term power load prediction method and system based on machine learning

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070260336A1 (en) * 2004-10-29 2007-11-08 Kazuaki Iwamura Long Infrastructure Management System and Program
CN104091227A (en) * 2014-06-17 2014-10-08 华南理工大学 Method for analyzing load density of power consumers in city
CN104123595A (en) * 2014-07-22 2014-10-29 国家电网公司 Power distribution network load prediction method and system
CN104252652A (en) * 2014-10-17 2014-12-31 广东电网公司电网规划研究中心 Space load predicting method in electricity system
CN107292480A (en) * 2017-04-25 2017-10-24 国网江西省电力公司赣州供电分公司 A kind of county domain power network long-term load characteristic prediction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070260336A1 (en) * 2004-10-29 2007-11-08 Kazuaki Iwamura Long Infrastructure Management System and Program
CN104091227A (en) * 2014-06-17 2014-10-08 华南理工大学 Method for analyzing load density of power consumers in city
CN104123595A (en) * 2014-07-22 2014-10-29 国家电网公司 Power distribution network load prediction method and system
CN104252652A (en) * 2014-10-17 2014-12-31 广东电网公司电网规划研究中心 Space load predicting method in electricity system
CN107292480A (en) * 2017-04-25 2017-10-24 国网江西省电力公司赣州供电分公司 A kind of county domain power network long-term load characteristic prediction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112700069A (en) * 2021-01-15 2021-04-23 国家电网有限公司 Method for predicting short-term load of regional power distribution network containing energy storage
CN112700069B (en) * 2021-01-15 2024-04-19 国网湖北省电力有限公司经济技术研究院 Short-term load prediction method for regional power distribution network containing energy storage
CN117543563A (en) * 2023-11-23 2024-02-09 国网河南省电力公司郑州供电公司 Short-term power load prediction method and system based on machine learning

Also Published As

Publication number Publication date
CN110414776B (en) 2022-11-29

Similar Documents

Publication Publication Date Title
Rajesh et al. Least cost generation expansion planning with wind power plant incorporating emission using differential evolution algorithm
CN103455852A (en) Power transmission and distribution cost allocation method based on DEA cooperative game
CN110109971A (en) A kind of low-voltage platform area user power utilization Load Characteristic Analysis method
CN106844594A (en) A kind of electric power Optimal Configuration Method based on big data
CN103956732B (en) A kind of method of carrying out associating power supply based on the average peak-valley ratio of industry
CN110796307A (en) Distributed load prediction method and system for comprehensive energy system
CN110414776A (en) Branch trade electrical characteristics quick response analysis system
CN108695859A (en) A kind of capacitor group addressing constant volume method of access active distribution network
CN107730399B (en) Theoretical line loss evaluation method based on wind power generation characteristic curve
Yin et al. Equilibrium stability of asymmetric evolutionary games of multi-agent systems with multiple groups in open electricity market
CN112508287A (en) Energy storage optimization configuration method based on user side BESS full life cycle
CN106570774A (en) Progressive learning grid regulation and control method based on learning theory
CN112651544B (en) Incremental power distribution multi-main-body coordination optimization method
CN105354761B (en) Safety and efficiency evaluation method and system for accessing wind power into power grid
CN114662922B (en) Resident demand response potential evaluation method and system considering photovoltaic uncertainty
CN106991516A (en) A kind of investment planning method and system based on power network resources
CN107832928B (en) Equivalent comprehensive line loss evaluation method based on wind power generation characteristic curve
CN116128154A (en) Energy optimal configuration method and device for agricultural park comprehensive energy system
CN115829141A (en) Energy storage system optimal configuration method based on short-term intelligent ammeter data
CN116111596A (en) Regional dynamic electric carbon factor calculation method
CN210573916U (en) Hydropower station group long-term optimization scheduling system
CN111626509B (en) Method and system for evaluating effective supply capacity of regional new energy
CN113673141A (en) Energy router modeling and optimization control method based on data driving
CN111614086A (en) Filtering estimation and prediction estimation method for multi-state variables of power system
CN112865101A (en) Linear transaction method considering uncertainty of output of renewable energy

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant