CN110413340A - Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment - Google Patents

Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment Download PDF

Info

Publication number
CN110413340A
CN110413340A CN201910582384.5A CN201910582384A CN110413340A CN 110413340 A CN110413340 A CN 110413340A CN 201910582384 A CN201910582384 A CN 201910582384A CN 110413340 A CN110413340 A CN 110413340A
Authority
CN
China
Prior art keywords
engineering equipment
data
target job
work data
configuration parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910582384.5A
Other languages
Chinese (zh)
Inventor
石向星
曹东辉
马云飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sany Heavy Machinery Ltd
Original Assignee
Sany Heavy Machinery Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sany Heavy Machinery Ltd filed Critical Sany Heavy Machinery Ltd
Priority to CN201910582384.5A priority Critical patent/CN110413340A/en
Publication of CN110413340A publication Critical patent/CN110413340A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/44Arrangements for executing specific programs
    • G06F9/445Program loading or initiating
    • G06F9/44505Configuring for program initiating, e.g. using registry, configuration files
    • G06F9/4451User profiles; Roaming

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Software Systems (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Power Sources (AREA)

Abstract

The present invention provides method for parameter configuration, device, equipment and the readable storage medium storing program for executing of a kind of engineering equipment, is related to technical field of engineering machinery.The described method includes: determining target job data from multiple groups work data, work data described in every group includes operation configuration parameter;The operation configuration parameter in the target job data is sent to engineering equipment to be configured, so that the engineering equipment to be configured is configured according to the operation configuration parameter in the target job data.By sending the operation configuration parameter in target job data to each engineering equipment to be configured, engineering equipment to be configured can the operation configuration parameters of the target job data based on the received configured, the target job data are the work datas selected from multiple groups work data, so configured according to the operation configuration parameter in the target job data to carry out operation, it ensure that the flexible configuration of the operation configuration parameter of engineering equipment, to guarantee the operation effectiveness of engineering equipment.

Description

Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment
Technical field
The present invention relates to technical field of engineering machinery, method for parameter configuration, dress in particular to a kind of engineering equipment It sets, equipment and readable storage medium storing program for executing.
Background technique
With the continuous development of engineering equipment, excavator in construction industry using more and more extensive, and excavator Working scene is also more and more.
In the related technology, since excavator can configure excavator, then according to preset operation configuration parameter By carrying out operation with the operation configuration parameter postponed.
But in practical applications, preset operation configuration parameter is usually fixed constant, then preset based on this Operation configuration parameter is configured, and may will affect the operation effectiveness of excavator.
Summary of the invention
It is an object of the present invention in view of the deficiency of the prior art, provide a kind of parameter configuration of engineering equipment Method, apparatus, equipment and readable storage medium storing program for executing, to solve the problems, such as to influence the operation effectiveness of excavator.
To achieve the above object, technical solution used in the embodiment of the present invention is as follows:
In a first aspect, the embodiment of the invention provides a kind of method for parameter configuration of engineering equipment, which comprises
Target job data are determined from multiple groups work data, work data described in every group includes operation configuration parameter;
The operation configuration parameter in the target job data is sent to engineering equipment to be configured, so that the work to be configured Journey equipment is configured according to the operation configuration parameter in the target job data.
Optionally, the work data further include: operation power consumption and/or workload, work data described in every group corresponding one A working scene;
It is described that target job data are determined from multiple groups work data, comprising:
From work data described in multiple groups, using the work data of same working scene as same scrnario operation data;
According to multiple groups with described in every group in scrnario operation data with the operation power consumption of scrnario operation data and/or operation Amount, will meet the same scrnario operation data of preset condition as the target job data.
Optionally, sent described to engineering equipment to be configured operation configuration parameter in the target job data it Before, the method also includes:
It is set according to the corresponding engineering of work data described in the corresponding target job scene of the target job data and multiple groups Standby working scene, from the corresponding engineering equipment of work data described in multiple groups, selection matches with the target job scene Engineering equipment as the engineering equipment to be configured.
Optionally, sent described to engineering equipment to be configured operation configuration parameter in the target job data it Before, the method also includes:
Whether the corresponding engineering equipment of work data described in judging every group has pay mark, obtains judging result, described Pay mark be used to indicate every group described in the corresponding engineering equipment of work data there is the permission for obtaining the target job data;
According to the judging result, from the corresponding engineering equipment of work data described in multiple groups, there will be the payment to mark The engineering equipment of knowledge is as the engineering equipment to be configured.
Optionally, described before determining target job data in multiple groups work data, the method also includes:
Receive the tune sent after multiple engineering equipments are adjusted operation configuration parameter according to the adjustment operation detected Operation configuration parameter after whole.
Optionally, the work data further includes operation power consumption and/or workload;
Described before determining target job data in multiple groups work data, the method also includes:
Receive the operation power consumption and/or the workload of multiple engineering equipment periodicity sendings.
Second aspect, the embodiment of the invention also provides a kind of method for parameter configuration of engineering equipment, which comprises
The target job data that server is sent are received, the target job data are the server from multiple groups operation number According to the work data of middle determination, work data described in every group includes operation configuration parameter;
It is configured according to the operation configuration parameter in the target job data.
Optionally, the method also includes:
It operates, is obtained through the operation configuration parameter after the adjustment operation adjustment in response to adjustment;
The operation configuration parameter adjusted is sent to the server.
Optionally, the work data further includes operation power consumption and/or workload, the method also includes:
Periodically obtain the operation power consumption and/or the workload;
The operation power consumption and/or the workload are sent to the server.
Optionally, before the target job data that the reception server is sent, the method also includes:
In response to delivery operation, Xiang Suoshu server sends payment instruction, and the payment instruction is used to indicate the service Device generates pay mark, and the pay mark, which is used to indicate the engineering equipment, has the power for obtaining the target job data Limit;
The target job data for receiving server and sending, comprising:
Receive server target job data according to transmitted by the pay mark.
The third aspect, the embodiment of the invention also provides a kind of parameter configuration device of engineering equipment, described device includes:
Determining module, for determining target job data from multiple groups work data, work data described in every group includes Operation configuration parameter;
Sending module makes for sending the operation configuration parameter in the target job data to engineering equipment to be configured The engineering equipment to be configured is obtained to be configured according to the operation configuration parameter in the target job data.
Optionally, the work data further include: operation power consumption and/or workload, work data described in every group corresponding one A working scene;
The determining module is specifically used for from work data described in multiple groups, and the work data of same working scene is made For same scrnario operation data;With the operation power consumption described in every group in scrnario operation data with scrnario operation data according to multiple groups And/or workload, the same scrnario operation data of preset condition will be met as the target job data.
Optionally, described device further include:
First choice module is used for the operation according to the corresponding target job scene of the target job data and multiple groups The working scene of the corresponding engineering equipment of data is chosen and the mesh from the corresponding engineering equipment of work data described in multiple groups The engineering equipment that mark working scene matches is as the engineering equipment to be configured.
Optionally, described device further include:
Whether judgment module has pay mark for the corresponding engineering equipment of work data described in judging every group, obtains Judging result, the pay mark be used to indicate every group described in the corresponding engineering equipment of work data have and obtain the target and make The permission of industry data;
Second selecting module is used for according to the judging result, from the corresponding engineering equipment of work data described in multiple groups, Using the engineering equipment with the pay mark as the engineering equipment to be configured.
Optionally, described device further include:
First receiving module, for receive multiple engineering equipments according to detect adjustment operation to operation configuration parameter into The operation configuration parameter adjusted sent after row adjustment.
Optionally, the work data further includes operation power consumption and/or workload;
Described device further include:
Second receiving module, for receive multiple engineering equipment periodicity sendings the operation power consumption and/or the work Industry amount.
Fourth aspect, the embodiment of the invention also provides a kind of parameter configuration device of engineering equipment, described device includes:
Receiving module, for receiving the target job data of server transmission, the target job data are the service The work data that device is determined from multiple groups work data, work data described in every group includes operation configuration parameter;
Configuration module, for being configured according to the operation configuration parameter in the target job data.
Optionally, described device further include:
First obtains module, for operating in response to adjustment, obtains and is configured by the operation after the adjustment operation adjustment Parameter;
First sending module, for sending the operation configuration parameter adjusted to the server.
Optionally, the work data further includes operation power consumption and/or workload, described device further include:
Second obtains module, for periodically obtaining the operation power consumption and/or the workload;
Second sending module, for sending the operation power consumption and/or the workload to the server.
Optionally, described device further include:
Third sending module, in response to delivery operation, Xiang Suoshu server to send payment instruction, the payment instruction It is used to indicate the server and generates pay mark, the pay mark, which is used to indicate the engineering equipment, has the acquisition mesh Mark the permission of work data;
The receiving module is made specifically for receiving server target according to transmitted by the pay mark Industry data.
5th aspect, the embodiment of the invention also provides a kind of servers, comprising: processor, storage medium and bus, institute It states storage medium and is stored with the executable machine readable instructions of the processor, when server operation, the processor By the bus communication between the storage medium, the processor executes the machine readable instructions, holds when executing The step of method for parameter configuration of engineering equipment of the row as described in first aspect is any.
6th aspect, it is described computer-readable to deposit the embodiment of the invention also provides a kind of computer readable storage medium It is stored with computer program on storage media, is executed as described in first aspect is any when the computer program is run by processor The step of method for parameter configuration of engineering equipment.
7th aspect, the embodiment of the invention also provides a kind of electronic equipment, comprising: processor, storage medium and bus, The storage medium is stored with the executable machine readable instructions of the processor, when electronic equipment operation, the place It manages by the bus communication between device and the storage medium, the processor executes the machine readable instructions, to execute The step of method for parameter configuration of any engineering equipment of Shi Zhihang such as second aspect.
Eighth aspect, it is described computer-readable to deposit the embodiment of the invention also provides a kind of computer readable storage medium It is stored with computer program on storage media, is executed as described in second aspect is any when the computer program is run by processor The step of method for parameter configuration of engineering equipment.
The beneficial effects of the present invention are:
The embodiment of the present application includes making by determining target job data, every group job data from multiple groups work data Industry configuration parameter, then the operation configuration parameter in target job data is sent to engineering equipment to be configured, so that engineering to be configured Equipment is configured according to the operation configuration parameter in target job data.By sending target to each engineering equipment to be configured Operation configuration parameter in work data, engineering equipment to be configured can based on the received the target job data operation configuration Parameter is configured, which is the work data selected from multiple groups work data, then being made according to the target Operation configuration parameter in industry data is configured to carry out operation, ensure that the flexible of the operation configuration parameter of engineering equipment Configuration, to guarantee the operation effectiveness of engineering equipment.
Detailed description of the invention
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to needed in the embodiment attached Figure is briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not construed as pair The restriction of range for those of ordinary skill in the art without creative efforts, can also be according to this A little attached drawings obtain other relevant attached drawings.
Fig. 1 is the parameter configuration of engineering equipment involved in a kind of method for parameter configuration of engineering equipment provided by the invention The structural schematic diagram of system;
Fig. 2 is the flow diagram of the method for parameter configuration for the engineering equipment that one embodiment of the invention provides;
Fig. 3 be another embodiment of the present invention provides engineering equipment method for parameter configuration flow diagram;
Fig. 4 is the flow diagram of the method for parameter configuration for the engineering equipment that further embodiment of this invention provides;
Fig. 5 is the schematic diagram of the parameter configuration device for the engineering equipment that one embodiment of the invention provides;
Fig. 6 be another embodiment of the present invention provides engineering equipment parameter configuration device schematic diagram;
Fig. 7 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Fig. 8 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Fig. 9 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Figure 10 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Figure 11 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Figure 12 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Figure 13 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides;
Figure 14 is the schematic diagram of the parameter configuration device for the engineering equipment that one embodiment of the invention provides.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.
Fig. 1 is the parameter configuration of engineering equipment involved in a kind of method for parameter configuration of engineering equipment provided by the invention The structural schematic diagram of system, as shown in Figure 1, the system includes: server 110 and multiple engineering equipments 120, server 110 with The equal link connection of each engineering equipment 120.
Wherein, engineering equipment 120 may include processor, memory and communication component, and processor can will be in memory The data of storage are sent to server 110 by communication component, can also receive the number that server 110 is sent by communication component According to, and in memory by the storage of received data.
For example, communication component in engineering equipment 120 can for GPRS (General Packet Radio Service, General packet radio service technology) component, or wireless communication module can also be other with data transmit-receive function Component, the embodiment of the present application do not limit this.
It, can be using the side of the operation configuration parameter of adjustment engineering equipment 120 in order to guarantee the operation effectiveness of engineering equipment Formula ensure that the operation effectiveness of engineering equipment to the flexible configuration of the operation configuration parameter of engineering equipment.For example, can be improved Operating efficiency reduces operation power consumption.
Wherein, operation configuration parameter may include: that the gain of swing arm, the gain of dipper and scraper bowl turn round one action gain At least one of, said one or multiple gains can be adjusted in conjunction with different working scenes.Certainly, operation configures Parameter can also include other parameters, and the embodiment of the present application does not limit this.
For example, in the working scene for excavating revolution entrucking, can the yield value to boom arm lift and revolution gain into Row adjustment, and in the working scene on level land, then the gain of swing arm and dipper can be adjusted.
Therefore, operation configuration parameter can be sent to multiple engineering equipments 120 by server 110, so that receiving operation The engineering equipment 120 of configuration parameter operation configuration parameter can be configured based on the received, thus by with the operation postponed Configuration parameter carries out operation.
Specifically, server 110 can determine that target job data, every group job data are wrapped from multiple groups work data Operation configuration parameter is included, then can send the operation configuration parameter in target job data to engineering equipment 120 to be configured.Accordingly , engineering equipment 120 to be configured can receive the target job data of the transmission of server 110, and according in target job data Operation configuration parameter configured.
Wherein, the working scene of engineering equipment 120 to be configured can corresponding with target job data engineering equipment 120 Working scene is consistent, and engineering equipment 120 to be configured may be the engineering equipment 120 that payment has purchased target job data, this Application embodiment treats allocation project equipment 120 without limitation.
It should be noted that in practical applications, engineering equipment 120 can be excavator, or other are in engineering Used mechanical equipment in construction, such as road roller or bull-dozer, the embodiment of the present application also do not limit engineering equipment 120 It is fixed.
Further, if engineering equipment 120 is excavator, excavator, can be according to a variety of during actual job The work pattern that operating condition (working scene) and every kind of operating condition are included in advance sets the operation configuration parameter of excavator It sets.Correspondingly, user on the basis of several work mode, operation configuration parameter can also be adjusted according to operating habit It is whole, it that is to say, can also include the customized operating condition of user and mode on the basis of above-mentioned several work mode.
For example, excavator may include 5 kinds of operating conditions such as in gravel, clay, weak soil, pan soil and mine, 12 kinds of works are corresponded to altogether The operation configuration parameter of industry mode.
Fig. 2 is the flow diagram of the method for parameter configuration for the engineering equipment that one embodiment of the invention provides, and is applied to such as Server shown in FIG. 1, as shown in Fig. 2, this method comprises:
Step 201 determines that target job data, every group job data include operation configuration ginseng from multiple groups work data Number.
Wherein, the operation configuration parameter is for configuring engineering equipment, allows engineering equipment according to postponing Operation configuration parameter carry out operation.
In order to guarantee the operation effectiveness of engineering equipment, the target job of flexible configuration can be chosen from multiple groups work data Data, so that the operation configuration parameter to engineering equipment carries out flexible configuration, to guarantee the operation effectiveness of engineering equipment.
For example, reducing operation consumption, server can be from each engineering to improve the operating efficiency of each engineering equipment In the multiple groups work data that equipment is sent, operating efficiency highest or operation target job data least in power-consuming are searched.Certainly, The server can also select the work data for meeting other conditions as target job data from multiple groups work data.
Specifically, server can be from multiple groups work data, according to the workload and operation of every group job data record The data such as power consumption, selection obtain the highest work data of operating efficiency, obtain operation operation number least in power-consuming alternatively, choosing According to thus using the work data of selection as target job data.
Step 202 sends the operation configuration parameter in target job data to engineering equipment to be configured, so that work to be configured Journey equipment is configured according to the operation configuration parameter in target job data.
Server, then can be by the operation configuration parameter in the target job data of selection after determining target job data It is issued to each engineering equipment to be configured, so that each engineering equipment to be configured is configured according to operation configuration parameter.
Specifically, server can be chosen according to the corresponding engineering equipment of multiple groups work data and need to configure target job The engineering equipment to be configured of data, then the operation configuration parameter in target job data is sent to each engineering equipment to be configured, Then each engineering equipment to be configured can receive the operation configuration parameter, and be configured according to the operation configuration parameter.
In conclusion the method for parameter configuration of engineering equipment provided by the embodiments of the present application, by from multiple groups work data Middle determining target job data, every group job data include operation configuration parameter, then send target to engineering equipment to be configured Operation configuration parameter in work data so that engineering equipment to be configured according to the operation configuration parameter in target job data into Row configuration.By sending the operation configuration parameter in target job data to each engineering equipment to be configured, engineering to be configured is set It is standby can the operation configuration parameters of the target job data based on the received configured, which made from multiple groups The work data selected in industry data, then being configured according to the operation configuration parameter in the target job data to carry out Operation, ensure that the flexible configuration of the operation configuration parameter of engineering equipment, to guarantee the operation effectiveness of engineering equipment.
Fig. 3 be another embodiment of the present invention provides engineering equipment method for parameter configuration flow diagram, be applied to Engineering equipment as shown in Figure 1, as shown in figure 3, this method comprises:
Step 301 receives the target job data that server is sent.
Wherein, which is the work data that server is determined from multiple groups work data, every group job number According to including operation configuration parameter.
In order to guarantee the operation effectiveness of engineering equipment, can the operation configuration parameter to engineering equipment be adjusted so that The operation configuration parameter of engineering equipment can be with flexible configuration, to guarantee the operation effectiveness of engineering equipment.
Therefore, engineering equipment can receive the target job data chosen in the slave multiple groups work data that server is sent, To be configured.
It should be noted that target job data may include in operation configuration parameter, operation power consumption and workload extremely One item missing.And during being configured to engineering equipment, it is carried out according to the operation configuration parameter in the target job data Configuration.It therefore, can only include operation configuration parameter in the target job data that server is sent.Certainly, target job It may also include other information in data, details are not described herein.
Step 302 is configured according to the operation configuration parameter in target job data.
Engineering equipment operation configuration parameter, the operation configuration parameter current to engineering equipment can carry out more based on the received Newly, so that the parameter value of the current operation configuration parameter of engineering equipment, is updated to the parameter value of received operation configuration parameter, from And operation is carried out by updated operation configuration parameter.
In conclusion the method for parameter configuration of engineering equipment provided by the embodiments of the present application, is sent by receiving server Slave multiple groups work data in the target job data that determine, and matched according to the operation configuration parameter in target job data It sets.It is configured by the operation configuration parameter in target job data based on the received, allows engineering equipment will be current Operation configuration parameter be updated to the operation configuration parameters of target job data, to be configured according to the operation of target job data Parameter carries out operation, and target job data are the work datas selected from multiple groups work data, then being made according to the target Operation configuration parameter in industry data is configured to carry out operation, ensure that the flexible of the operation configuration parameter of engineering equipment Configuration, to guarantee the operation effectiveness of engineering equipment.
Fig. 4 is the flow diagram of the method for parameter configuration for the engineering equipment that further embodiment of this invention provides, and is applied to Server and engineering equipment as shown in Figure 1, as shown in figure 4, this method comprises:
Step 401, engineering equipment obtain work data.
In order to guarantee the operation effectiveness of engineering equipment, the target job of flexible configuration can be chosen from multiple groups work data Data, so that the operation configuration parameter to engineering equipment carries out flexible configuration, to guarantee the operation effectiveness of engineering equipment.
For example, the embodiment of the present application in order to improve engineering equipment operating efficiency or reduce engineering equipment operation energy For the purpose of consumption, efficiency highest or the minimum target job data of energy consumption are chosen from the multiple groups work data of multiple engineering equipments, And by the target job data configuration of selection to each engineering equipment, so that the operating efficiency to engineering equipment improves, or The operation consumption of person's reduction engineering equipment.But in practical applications, the different operation effectivenesses that can according to need are chosen Different work datas is not limited this as target job data, the embodiment of the present application.
Therefore, server needs first to acquire the multiple groups work data of multiple engineering equipments.Correspondingly, engineering equipment can not Disconnected Collecting operation data, and the multiple groups work data collected is sent to server.
Since the work data of engineering equipment not only may include operation configuration parameter, also may include operation power consumption and/ Or workload, for the operation configuration parameter for configuring to engineering equipment, operation power consumption is engineering equipment in operation process The power consumption of generation, workload are used to indicate the workload that engineering equipment is completed.
Wherein, operation power consumption is for indicating engineering equipment consumed energy in the unit time in operation process, for example, It can be indicated, can also be indicated in other ways, the embodiment of the present application pair with the oil mass for consuming how many liter per hour This is without limitation.
Moreover, the workload is for indicating the workload that engineering equipment is completed in the unit time in operation process, example Such as, it during excavator carries out digging, can be indicated with shoveling how many cubic meter or how many ton of cutting the earth, It can be indicated in other ways, the embodiment of the present application does not limit this.
And the acquisition mode of every kind of work data is different, then step 401 may include in step 401a and step 401b It is at least one.Certainly, other modes can also be used and obtain work data, step 401a and step 401b are only possible reality Example, the application is not to this limitation.
Step 401a, it is operated in response to adjustment, engineering equipment obtains by adjusting the operation configuration parameter after operation adjustment.
Since engineering equipment is previously stored with preset operation configuration parameter, the current operation configuration of engineering equipment that is to say Parameter.When user is when carrying out operation by engineering equipment, operation configuration parameter that can be current to engineering equipment is adjusted, Allow engineering equipment according to the better operation of operation configuration parameter adjusted.
Therefore, in the adjustment operation for detecting user's triggering, it can acquire and obtain user's operation configuration ginseng adjusted Number.
Specifically, engineering equipment can operate, to current in the adjustment operation for detecting user's triggering according to the adjustment Operation configuration parameter in parameters value be adjusted.If user finishes the adjustment of operation configuration parameter, can acquire Operation configuration parameter adjusted is obtained, in the next steps, to send operation configuration parameter adjusted to server.
For example, if engineering equipment be excavator, and in mine set up the stage 90 degree revolution car loading operation working scene in, then User can be set up the stage from set up the stage 45 degree of revolution entruckings, mines of pre-set mine by pre-set human-computer interaction interface 90 degree of revolution entruckings are pacifically in multiple working scenes such as 90 degree of revolution entruckings, and it is corresponding to choose mine 90 degree of revolution entruckings of setting up the stage Working scene can if user has found that the corresponding operation configuration parameter of working scene chosen is not suitable for the operating habit of oneself To be adjusted again to operation configuration parameter, such as can gain to the swing arm of excavator, the gain of dipper, scraper bowl revolution increasing At least one parameter in benefit is adjusted, and can also control the parameters such as main pump flow and power, is realized to operation configuration parameter Adjustment.
Correspondingly, user can be acted during operating excavator progress operation by electric control handle execution, and dig The movement of execution can be converted to digital signal by analog-to-digital conversion by the processor in pick machine, and be dug according to Digital Signals The electromagnetic proportional valve and main valve of pick machine work, so that controlling excavator carries out operation.
It should be noted that causing operation to configure in order to avoid user is adjusted pre-set operation configuration parameter Parameter is chaotic, can provide a user the function of One-key recovery, to restore the operation configuration parameter of user's adjustment to preparatory The operation configuration parameter of setting.
Step 401b, engineering equipment periodically obtains operation power consumption and/or workload.
It is different from step 401a, it, then can not in operation process since operating equipment can continuously carry out operation Stopping pregnancy raw operation power consumption and/or the corresponding data of workload.Therefore, acquisition operation can periodically be acquired in engineering equipment Power consumption and/or workload.
For example, engineering equipment can acquire one-stop operation power consumption and/or workload every 5ms (millisecond).
Step 402, engineering equipment send work data to server.
It is corresponding with step 401, different work datas can be acquired in step 401, then in this step 402, Different work datas can also be sent to server.
Different data acquisition modes may correspond to different data sender's formulas, and step 402 may include step 402a At least one of with step 402b.Certainly, the operation configuration that other modes are got to server transport device can also be used Parameter, the application is not to this limitation.
Step 402a, engineering equipment sends operation configuration parameter adjusted to server.
It is corresponding with step 401a, current operation configuration parameter is adjusted in the adjustment operation triggered according to user After whole and acquisition, the operation configuration parameter of acquisition can be sent to server in real time by engineering equipment.
Step 402b, engineering equipment sends operation power consumption and/or workload to server.
Corresponding with step 402a, engineering equipment, can also week periodically after Collecting operation power consumption and/or workload The operation power consumption and/or workload of acquisition are sent to phase property to server.For example, work corresponding with the citing of step 401b Journey equipment can also send one-stop operation power consumption and/or workload to server every 5mS.
It should be noted that engineering equipment when sending work data to server, can also send engineering to server The identification information of equipment can establish the corresponding relationship between identification information and work data so as to server.Wherein, the mark Information is used to indicate engineering equipment, for example, the identification information can be the number of engineering equipment, or opertions engineering equipment User number, can also be used to identify the information of engineering equipment for other, the embodiment of the present application not limit this.
In addition, in practical applications, user can buy the target job data that server selects, will pass through purchase Target job data engineering equipment is configured, to improve the operating efficiency of engineering equipment, alternatively, reducing engineering equipment Operation power consumption.
Optionally, the delivery operation that engineering equipment can also be triggered according to user, the target job number that server is chosen According to carrying out payment purchase.
Optionally, engineering equipment sends payment instruction to server, wherein the payment instruction is used in response to delivery operation Indicate that server generates pay mark, which, which is used to indicate engineering equipment, has the permission for obtaining target job data.
Specifically, if detecting the delivery operation of user's triggering, illustrate that user triggers and target job data are carried out The operation of purchase is paid, then payment instruction can be generated according to the delivery operation, and send the payment instruction to server, to accuse Know that the engineering equipment has the permission for obtaining target job data.
Correspondingly, server can receive the payment instruction, and according to the payment instruction, generate the mark with the engineering equipment Know the corresponding pay mark of work data of information and/or the engineering equipment, thus establish pay mark, identification information and/ Or the corresponding relationship between work data.
It should be noted that in practical applications, engineering equipment, can also be to clothes when sending payment instruction to server Business device sends the identification information of engineering equipment, so that server establishes pay mark, identification information and/or work according to identification information Corresponding relationship between industry data.
Correspondingly, target job data can be not only bought, it can also be to the engineering equipment pair of offer target job data The user answered rewards.Other target job data are freely used for example, can reward the engineering equipment of the user.When So, user can also be rewarded using other modes, the embodiment of the present application does not limit this.
Step 403, server receive work data.
Corresponding with step 402, engineering equipment can be sent to server different at different times in step 402 Work data, then server can also receive the different work datas of engineering equipment transmission at different times.
Therefore, step 403 may include at least one of step 403a and step 403b.If engineering equipment is using other Mode transmit work data, then server use the corresponding reception mode of the other way, receive work data, herein no longer It repeats.
Step 403a, after the multiple engineering equipments of reception are adjusted operation configuration parameter according to the adjustment operation detected The operation configuration parameter adjusted sent.
Corresponding with step 402a, server can receive engineering equipment and detect adjustment operation to current operation The operation configuration parameter adjusted that configuration parameter is sent after being adjusted.
Further, since server stores multiple groups work data, every group job data are matched according to different operations Set what parameter and corresponding operation power consumption and/or workload generated.Therefore, server is receiving operation configuration ginseng adjusted After number, a group job data are generated again.
Step 403b, the operation power consumption and/or workload of multiple engineering equipment periodicity sendings are received.
It is corresponding with step 402b, engineering equipment can constantly to server send engineering equipment operation power consumption and/ Or workload, server then can constantly receive operation power consumption and/or workload, and by received operation power consumption and/or operation Amount is added in corresponding each group work data, to constantly update each group work data of storage.
But it is corresponding with step 403a, if server receives operation configuration parameter, new one group can be generated Work data, then server received operation power consumption and/or workload can will be added again after generating new work data New work data, to indicate received operation power consumption and/or workload be after being adjusted to operation configuration parameter, Operation power consumption and/or workload caused by subjob again.
Optionally, wherein every group job data can correspond to a working scene.
Corresponding, this method may also include that
Step 404, server are from multiple groups work data, using the work data of same working scene as same scrnario operation Data.
Wherein, the corresponding working scene of every group job data.
Since multiple engineering equipments may work under different working scenes, and the engineering in different work scene The efficiency and power consumption of equipment are different.Therefore, it in order to determine target job data, needs first according to every group job data pair The working scene answered divides each group work data.
Specifically, server can first determine the corresponding working scene of every group job data, and to each group working scene into Row traversal, determines certain corresponding working scene of group job data, if operation field corresponding with other traversed work datas Scape is consistent, to will belong to the work data of same working scene as same scrnario operation data.
In addition, server is during determining every group job data corresponding working scene, it can be according to work data The location information in the geographical location where middle expression engineering equipment, judges whether each engineering equipment is in same working scene, It can also determine whether each engineering equipment is in same working scene according to the work pattern of engineering equipment in work data.
For example, the geographical location where the first engineering equipment and the distance between the geographical location where the second engineering equipment Less than pre-set distance threshold, then it can determine that the first engineering equipment and the second engineering equipment are located at identical operation field Scape, and the first engineering equipment and the corresponding work data of the second engineering equipment belong to same scrnario operation data.
Optionally, server is according to the location information in the geographical location where engineering equipment and the operation mould of engineering equipment Whether the working scene of formula, each engineering equipment of comprehensive descision is consistent, judges whether each group work data is same scrnario operation number According to.
It should be noted that in practical applications, corresponding multiple working scenes can be determined according to multiple groups work data Multiple groups are with scrnario operation data, and the embodiment of the present application is illustrated by taking a working scene as an example, the embodiment of the present application Without limitation to the number of working scene.
Step 405, server according to multiple groups with every group in scrnario operation data with the operation power consumption of scrnario operation data and/ Or workload, the same scrnario operation data of preset condition will be met as target job data.
After determining each group with scrnario operation data, then every group can be analyzed with scrnario operation data, be determined not The corresponding target job data with working scene are made so as to send different targets to the engineering equipment of different work scene Industry data.
Specifically, for every group with scrnario operation data, server can first determine the group with the work of scrnario operation data Industry power consumption and/or workload, and from each operation power consumption and/or workload, selection obtains the smallest operation power consumption of parameter value And/or the maximum workload of parameter value, thus using same scrnario operation data corresponding to the smallest operation power consumption of parameter value as Target job data, and also it regard same scrnario operation data corresponding to the maximum workload of parameter value as target job data.
Step 406, server determine engineering equipment to be configured.
Server can send target job data to engineering equipment to be configured, so that engineering equipment to be configured can basis Operation configuration parameter in target job data is configured.But since the working scene where each engineering equipment is different, And each engineering equipment is also different to the payment purchase situation of target job data, then needs to sieve each engineering equipment Choosing, obtains the engineering equipment to be configured for meeting corresponding conditions.
Optionally, step 406 may include at least one of following step 406a and step 406b:
Step 406a, it is set according to the corresponding target job scene of target job data and the corresponding engineering of multiple groups work data Standby working scene is chosen the engineering to match with target job scene and is set from the corresponding engineering equipment of multiple groups work data It is standby to be used as engineering equipment to be configured.
Server can be according to the target job scene where the corresponding operating equipment of target job data, from multiple groups operation In the corresponding working scene of data, selection and work data corresponding to the consistent working scene of target job scene, thus will Engineering equipment corresponding with each group work data of selection is as engineering equipment to be configured.
It should be noted that during determining engineering equipment to be configured, it can also be according to determination in step 405 With scrnario operation data, engineering equipment to be configured is determined, the embodiment of the present application does not do the mode of determination engineering equipment to be configured It limits.
Step 406b, judge whether the corresponding engineering equipment of every group job data has pay mark, obtain judging result, According to judging result, from the corresponding engineering equipment of multiple groups work data, using the engineering equipment with pay mark as wait match Set engineering equipment.
Corresponding with the delivery operation that user in step 402 triggers, each group work data stored in server can be with It is corresponding with the identification information of engineering equipment, and identification information and work data can be corresponding with pay mark, for identifying this The engineering equipment payment of identification information instruction has purchased the permission for obtaining target job data.
Therefore, server can be according to every group job data and/or identification information corresponding with work data, determination It is no that there is corresponding pay mark, so that it is determined that whether engineering equipment indicated by identification information, which pays, has purchased acquisition target The permission of work data, and then by engineering equipment corresponding to the work data and/or identification information that are identified with counterpart expenditure, As engineering equipment to be configured.
Step 407, server send the operation configuration parameter in target job data to engineering equipment to be configured, so as to Allocation project equipment is configured according to the operation configuration parameter in target job data.
Step 408, engineering equipment receive server target job data according to transmitted by pay mark, target job number According to the work data determined from multiple groups work data for server, every group job data include operation configuration parameter.
Step 409, engineering equipment are configured according to the operation configuration parameter in target job data.
In conclusion the method for parameter configuration of engineering equipment provided by the embodiments of the present application, is sent by receiving server Slave multiple groups work data in the target job data that determine, and matched according to the operation configuration parameter in target job data It sets.By sending the operation configuration parameter in target job data to each engineering equipment to be configured, engineering equipment to be configured can It is configured with the operation configuration parameter of the target job data based on the received, which is from multiple groups operation number According to the work data of middle selection, then being configured according to the operation configuration parameter in the target job data to be made Industry, ensure that the flexible configuration of the operation configuration parameter of engineering equipment, to guarantee the operation effectiveness of engineering equipment.
Further, since target job data are that operating efficiency highest or operation are least in power-consuming in multiple groups work data Work data, therefore improve the operating efficiency of engineering equipment or reduce the operation power consumption of engineering equipment.
Fig. 5 is the schematic diagram of the parameter configuration device for the engineering equipment that one embodiment of the invention provides, as shown in figure 5, answering For server as shown in Figure 1, which is specifically included:
Determining module 501, for determining target job data from multiple groups work data, every group of work data includes Operation configuration parameter;
Sending module 502 makes for sending the operation configuration parameter in the target job data to engineering equipment to be configured The engineering equipment to be configured is obtained to be configured according to the operation configuration parameter in the target job data.
Optionally, work data further include: operation power consumption and/or workload, the corresponding work of every group of work data Industry scene;
The determining module 501, be specifically used for from the multiple groups work data, using the work data of same working scene as With scrnario operation data;According to multiple groups this with every group in the scrnario operation data operation power consumption with scrnario operation data and/or Workload will meet the same scrnario operation data of preset condition as the target job data.
Optionally, referring to Fig. 6, the device further include:
First choice module 503, for according to the corresponding target job scene of the target job data and the multiple groups operations The working scene of the corresponding engineering equipment of data is chosen and is made with the target from the corresponding engineering equipment of the multiple groups work datas The engineering equipment that industry scene matches is as the engineering equipment to be configured.
Optionally, referring to Fig. 7, the device further include:
Judgment module 504 is obtained for judging whether the corresponding engineering equipment of every group of work data has pay mark Judging result, which, which is used to indicate the corresponding engineering equipment of every group of work data, has the acquisition target job data Permission;
Second selecting module 505, for according to the judgment result, from the corresponding engineering equipment of the multiple groups work datas, Using the engineering equipment with the pay mark as the engineering equipment to be configured.
Optionally, referring to Fig. 8, the device further include:
First receiving module 506 is joined for receiving multiple engineering equipments and being configured according to the adjustment operation detected to operation The operation configuration parameter adjusted that number is sent after being adjusted.
Optionally, which further includes operation power consumption and/or workload;
Referring to Fig. 9, the device further include:
Second receiving module 507, for receiving the operation power consumption and/or the work of multiple engineering equipment periodicity sendings Industry amount.
In conclusion the parameter configuration device of engineering equipment provided by the embodiments of the present application, by from multiple groups work data Middle determining target job data, every group job data include operation configuration parameter, then send target to engineering equipment to be configured Operation configuration parameter in work data so that engineering equipment to be configured according to the operation configuration parameter in target job data into Row configuration.By sending the operation configuration parameter in target job data to each engineering equipment to be configured, engineering to be configured is set It is standby can the operation configuration parameters of the target job data based on the received configured, which made from multiple groups The work data selected in industry data, then being configured according to the operation configuration parameter in the target job data to carry out Operation, ensure that the flexible configuration of the operation configuration parameter of engineering equipment, to guarantee the operation effectiveness of engineering equipment.
Figure 10 is the schematic diagram of the parameter configuration device for the engineering equipment that further embodiment of this invention provides, such as Figure 10 institute Show, applied to engineering equipment as shown in Figure 1, which is specifically included:
Receiving module 1001, for receiving the target job data of server transmission, which is the service The work data that device is determined from multiple groups work data, every group of work data includes operation configuration parameter;
Configuration module 1002, for being configured according to the operation configuration parameter in the target job data.
Optionally, referring to Figure 11, the device further include:
First obtains module 1003, and for operating in response to adjustment, acquisition is matched by the operation after the adjustment operation adjustment Set parameter;
First sending module 1004, for sending the operation configuration parameter adjusted to the server.
Optionally, which further includes operation power consumption and/or workload, referring to Figure 12, the device further include:
Second obtains module 1005, for periodically obtaining the operation power consumption and/or the workload;
Second sending module 1006, for sending the operation power consumption and/or the workload to the server.
Optionally, referring to Figure 13, the device further include:
Third sending module 1007, for sending payment instruction, the payment instruction to the server in response to delivery operation It is used to indicate the server and generates pay mark, which, which is used to indicate the engineering equipment, has the acquisition target job number According to permission;
The receiving module 1001, specifically for receiving server target job number according to transmitted by the pay mark According to.
In conclusion the parameter configuration device of engineering equipment provided by the embodiments of the present application, is sent by receiving server Slave multiple groups work data in the target job data that determine, and matched according to the operation configuration parameter in target job data It sets.It is configured by the operation configuration parameter in target job data based on the received, allows engineering equipment will be current Operation configuration parameter be updated to the operation configuration parameters of target job data, to be configured according to the operation of target job data Parameter carries out operation, and target job data are the work datas selected from multiple groups work data, then being made according to the target Operation configuration parameter in industry data is configured to carry out operation, ensure that the flexible of the operation configuration parameter of engineering equipment Configuration, to guarantee the operation effectiveness of engineering equipment.
The method that above-mentioned apparatus is used to execute previous embodiment offer, it is similar that the realization principle and technical effect are similar, herein not It repeats again.
The above module can be arranged to implement one or more integrated circuits of above method, such as: one Or multiple specific integrated circuits (Application Specific Integrated Circuit, abbreviation ASIC), or, one Or multi-microprocessor (digital singnal processor, abbreviation DSP), or, one or more field programmable gate Array (Field Programmable Gate Array, abbreviation FPGA) etc..For another example, when some above module passes through processing elements When the form of part scheduler program code is realized, which can be general processor, such as central processing unit (Central Processing Unit, abbreviation CPU) or it is other can be with the processor of caller code.For another example, these modules can integrate Together, it is realized in the form of system on chip (system-on-a-chip, abbreviation SOC).
One embodiment of the invention also provides a kind of server, comprising: processor, storage medium and bus, the storage are situated between Matter is stored with the executable machine readable instructions of the processor, and when server operation, the processor is deposited with described By the bus communication between storage media, the processor executes the machine readable instructions, execute when executing such as Fig. 2 and The step of method for parameter configuration of the corresponding any engineering equipment of Fig. 4.
One embodiment of the invention also provides a kind of electronic equipment, comprising: processor, storage medium and bus, the storage The machine readable instructions that media storage has the processor executable, when electronic equipment operation, the processor and institute It states by the bus communication between storage medium, the processor executes the machine readable instructions, executes such as when executing The step of method for parameter configuration of the corresponding any engineering equipment of Fig. 3 and Fig. 4.
Wherein, the electronic equipment can for the control device of engineering equipment, controller or other connect with engineering equipment Electronic equipment, such as mobile phone, plate or other controlling terminals, the embodiment of the present application do not limit this.
Figure 14 is the schematic diagram of the parameter configuration device for the engineering equipment that one embodiment of the invention provides, which can collect At in the chip of terminal device or terminal device, the calculating which can be the parameter configuration function for having engineering equipment is set It is standby.
The device includes: memory 1401, processor 1402.
For memory 1401 for storing program, the program that processor 1402 calls memory 1401 to store is above-mentioned to execute Embodiment of the method.Specific implementation is similar with technical effect, and which is not described herein again.
Optionally, the present invention also provides a kind of program product, such as computer readable storage medium, including program, the journeys Sequence is when being executed by processor for executing above method embodiment.
The present invention also provides a kind of computer readable storage medium, calculating is stored on the computer readable storage medium Machine program, when the computer program is run by processor execute Fig. 2 and Fig. 4 it is corresponding it is any as described in engineering equipment ginseng The step of number configuration method.
The present invention also provides a kind of computer readable storage medium, calculating is stored on the computer readable storage medium Machine program, when the computer program is run by processor execute Fig. 3 and Fig. 4 it is corresponding it is any as described in engineering equipment ginseng The step of number configuration method.
In several embodiments provided by the present invention, it should be understood that disclosed device and method can pass through it Its mode is realized.For example, the apparatus embodiments described above are merely exemplary, for example, the division of the unit, only Only a kind of logical function partition, there may be another division manner in actual implementation, such as multiple units or components can be tied Another system is closed or is desirably integrated into, or some features can be ignored or not executed.Another point, it is shown or discussed Mutual coupling, direct-coupling or communication connection can be through some interfaces, the INDIRECT COUPLING or logical of device or unit Letter connection can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of hardware adds SFU software functional unit.
The above-mentioned integrated unit being realized in the form of SFU software functional unit can store and computer-readable deposit at one In storage media.Above-mentioned SFU software functional unit is stored in a storage medium, including some instructions are used so that a computer Equipment (can be personal computer, server or the network equipment etc.) or processor (English: processor) execute this hair The part steps of bright each embodiment the method.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only memory (English: Read-Only Memory, abbreviation: ROM), random access memory (English: Random Access Memory, letter Claim: RAM), the various media that can store program code such as magnetic or disk.
Upper is only the specific embodiment of the application, but the protection scope of the application is not limited thereto, any to be familiar with sheet Those skilled in the art within the technical scope of the present application, can easily think of the change or the replacement, and should all cover at this Within the protection scope of application.Therefore, the protection scope of the application should be subject to the protection scope in claims.

Claims (24)

1. a kind of method for parameter configuration of engineering equipment, which is characterized in that the described method includes:
Target job data are determined from multiple groups work data, work data described in every group includes operation configuration parameter;
The operation configuration parameter in the target job data is sent to engineering equipment to be configured, so that the engineering to be configured is set It is standby to be configured according to the operation configuration parameter in the target job data.
2. the method as described in claim 1, which is characterized in that the work data further include: operation power consumption and/or operation Amount, the corresponding working scene of work data described in every group;
It is described that target job data are determined from multiple groups work data, comprising:
From work data described in multiple groups, using the work data of same working scene as same scrnario operation data;
With the operation power consumption and/or workload described in every group in scrnario operation data with scrnario operation data according to multiple groups, The same scrnario operation data of preset condition will be met as the target job data.
3. the method as described in claim 1, which is characterized in that send the target job to engineering equipment to be configured described Before operation configuration parameter in data, the method also includes:
According to the corresponding engineering equipment of work data described in the corresponding target job scene of the target job data and multiple groups Working scene chooses the work to match with the target job scene from the corresponding engineering equipment of work data described in multiple groups Journey equipment is as the engineering equipment to be configured.
4. the method as described in claim 1, which is characterized in that send the target job to engineering equipment to be configured described Before operation configuration parameter in data, the method also includes:
Whether the corresponding engineering equipment of work data described in judging every group has pay mark, obtains judging result, the payment Identifying the corresponding engineering equipment of work data described in being used to indicate every group has the permission for obtaining the target job data;
It, will be with the pay mark from the corresponding engineering equipment of work data described in multiple groups according to the judging result Engineering equipment is as the engineering equipment to be configured.
5. the method as described in Claims 1-4 is any, which is characterized in that determine target from multiple groups work data described Before work data, the method also includes:
After receiving the adjustment sent after multiple engineering equipments are adjusted operation configuration parameter according to the adjustment operation detected Operation configuration parameter.
6. the method as described in Claims 1-4 is any, which is characterized in that the work data further include operation power consumption and/or Workload;
Described before determining target job data in multiple groups work data, the method also includes:
Receive the operation power consumption and/or the workload of multiple engineering equipment periodicity sendings.
7. a kind of method for parameter configuration of engineering equipment, which is characterized in that the described method includes:
The target job data that server is sent are received, the target job data are the server from multiple groups work data Determining work data, work data described in every group include operation configuration parameter;
It is configured according to the operation configuration parameter in the target job data.
8. the method for claim 7, which is characterized in that the method also includes:
It operates, is obtained through the operation configuration parameter after the adjustment operation adjustment in response to adjustment;
The operation configuration parameter adjusted is sent to the server.
9. the method for claim 7, which is characterized in that the work data further includes operation power consumption and/or workload, The method also includes:
Periodically obtain the operation power consumption and/or the workload;
The operation power consumption and/or the workload are sent to the server.
10. the method for claim 7, which is characterized in that it is described reception server send target job data it Before, the method also includes:
In response to delivery operation, Xiang Suoshu server sends payment instruction, and it is raw that the payment instruction is used to indicate the server At pay mark, the pay mark, which is used to indicate the engineering equipment, has the permission for obtaining the target job data;
The target job data for receiving server and sending, comprising:
Receive server target job data according to transmitted by the pay mark.
11. a kind of parameter configuration device of engineering equipment, which is characterized in that described device includes:
Determining module, for determining target job data from multiple groups work data, work data described in every group includes operation Configuration parameter;
Sending module, for sending the operation configuration parameter in the target job data to engineering equipment to be configured, so that institute Engineering equipment to be configured is stated to be configured according to the operation configuration parameter in the target job data.
12. device as claimed in claim 11, which is characterized in that the work data further include: operation power consumption and/or operation Amount, the corresponding working scene of work data described in every group;
The determining module is specifically used for from work data described in multiple groups, using the work data of same working scene as same Scrnario operation data;According to multiple groups with described in every group in scrnario operation data with the operation power consumption of scrnario operation data and/ Or workload, the same scrnario operation data of preset condition will be met as the target job data.
13. device as claimed in claim 11, which is characterized in that described device further include:
First choice module is used for the work data according to the corresponding target job scene of the target job data and multiple groups The working scene of corresponding engineering equipment is chosen and is made with the target from the corresponding engineering equipment of work data described in multiple groups The engineering equipment that industry scene matches is as the engineering equipment to be configured.
14. device as claimed in claim 11, which is characterized in that described device further include:
Whether judgment module has pay mark for the corresponding engineering equipment of work data described in judging every group, is judged As a result, the pay mark be used to indicate every group described in the corresponding engineering equipment of work data have and obtain the target job number According to permission;
Second selecting module, for will be had from the corresponding engineering equipment of work data described in multiple groups according to the judging result There is the engineering equipment of the pay mark as the engineering equipment to be configured.
15. the device as described in claim 11 to 14 is any, which is characterized in that described device further include:
First receiving module adjusts operation configuration parameter according to the adjustment operation detected for receiving multiple engineering equipments The operation configuration parameter adjusted sent after whole.
16. the device as described in claim 11 to 14 is any, which is characterized in that the work data further includes operation power consumption And/or workload;
Described device further include:
Second receiving module, for receiving the operation power consumption and/or the workload of multiple engineering equipment periodicity sendings.
17. a kind of parameter configuration device of engineering equipment, which is characterized in that described device includes:
Receiving module, for receive server transmission target job data, the target job data be the server from The work data determined in multiple groups work data, work data described in every group includes operation configuration parameter;
Configuration module, for being configured according to the operation configuration parameter in the target job data.
18. device as claimed in claim 17, which is characterized in that described device further include:
First obtains module, for operating in response to adjustment, obtains through the operation configuration parameter after the adjustment operation adjustment;
First sending module, for sending the operation configuration parameter adjusted to the server.
19. device as claimed in claim 17, which is characterized in that the work data further includes operation power consumption and/or operation Amount, described device further include:
Second obtains module, for periodically obtaining the operation power consumption and/or the workload;
Second sending module, for sending the operation power consumption and/or the workload to the server.
20. device as claimed in claim 17, which is characterized in that described device further include:
Third sending module, in response to delivery operation, Xiang Suoshu server to send payment instruction, and the payment instruction is used for Indicate that the server generates pay mark, the pay mark is used to indicate the engineering equipment, and there is the acquisition target to make The permission of industry data;
The receiving module, specifically for receiving server target job number according to transmitted by the pay mark According to.
21. a kind of server characterized by comprising processor, storage medium and bus, the storage medium storage is The executable machine readable instructions of processor are stated, when server operation, between the processor and the storage medium By the bus communication, the processor executes the machine readable instructions, and such as claim 1 to 6 times is executed when executing The step of method for parameter configuration of engineering equipment described in one.
22. a kind of computer readable storage medium, which is characterized in that be stored with computer on the computer readable storage medium Program, the parameter that the engineering equipment as described in claim 1 to 6 is any is executed when the computer program is run by processor are matched The step of setting method.
23. a kind of electronic equipment characterized by comprising processor, storage medium and bus, the storage medium are stored with The executable machine readable instructions of the processor, when electronic equipment operation, the processor and the storage medium Between by the bus communication, the processor executes the machine readable instructions, executed when executing as claim 7 to The step of method for parameter configuration of 10 any engineering equipments.
24. a kind of computer readable storage medium, which is characterized in that be stored with computer on the computer readable storage medium Program, the computer program execute the parameter of engineering equipment the method according to any one of claims 7 to 10 when being run by processor The step of configuration method.
CN201910582384.5A 2019-06-28 2019-06-28 Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment Pending CN110413340A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910582384.5A CN110413340A (en) 2019-06-28 2019-06-28 Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910582384.5A CN110413340A (en) 2019-06-28 2019-06-28 Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment

Publications (1)

Publication Number Publication Date
CN110413340A true CN110413340A (en) 2019-11-05

Family

ID=68359999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910582384.5A Pending CN110413340A (en) 2019-06-28 2019-06-28 Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment

Country Status (1)

Country Link
CN (1) CN110413340A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112417041A (en) * 2020-11-19 2021-02-26 清华大学 Parameter configuration method and device, electronic equipment and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104899648A (en) * 2015-05-19 2015-09-09 国家电网公司 Induction filtering converter transformer optimizing method based on operation index combined monitoring
CN108131126A (en) * 2018-02-09 2018-06-08 徐工集团工程机械有限公司 Control system, drill jumbo and the control method of rock drill
CN108490893A (en) * 2018-02-13 2018-09-04 烽台科技(北京)有限公司 A kind of industrial control method, device and equipment
CN109327505A (en) * 2018-09-03 2019-02-12 深圳和而泰数据资源与云技术有限公司 The means of communication, server, household appliance and storage medium
CN109358549A (en) * 2018-11-01 2019-02-19 三重机有限公司 A kind of intelligent control method and device of excavator

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104899648A (en) * 2015-05-19 2015-09-09 国家电网公司 Induction filtering converter transformer optimizing method based on operation index combined monitoring
CN108131126A (en) * 2018-02-09 2018-06-08 徐工集团工程机械有限公司 Control system, drill jumbo and the control method of rock drill
CN108490893A (en) * 2018-02-13 2018-09-04 烽台科技(北京)有限公司 A kind of industrial control method, device and equipment
CN109327505A (en) * 2018-09-03 2019-02-12 深圳和而泰数据资源与云技术有限公司 The means of communication, server, household appliance and storage medium
CN109358549A (en) * 2018-11-01 2019-02-19 三重机有限公司 A kind of intelligent control method and device of excavator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112417041A (en) * 2020-11-19 2021-02-26 清华大学 Parameter configuration method and device, electronic equipment and storage medium
CN112417041B (en) * 2020-11-19 2022-12-02 清华大学 Parameter configuration method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
CN114190095B (en) Method and system for performing worksite planning to modify a work surface at a worksite
Vahdatikhaki et al. Framework for near real-time simulation of earthmoving projects using location tracking technologies
US11994397B2 (en) Shovel and assist device for shovel
CN101864780B (en) Intelligent control method for hydraulic excavator
CN105940721A (en) Dynamically influencing the choice of a mobile network operator profile used by a user equipment comprising an embedded identity module
WO2021086619A1 (en) Systems and methods for autonomous movement of material
CN107015892A (en) A kind of method for testing pressure, device and system
EP1273719B1 (en) Method and apparatus for transmitting machine operation data
CN106836364A (en) The automatic control system and optimal trajectory planning method of intelligent excavator
CN103422527A (en) Self-adaptive control method and device
CN110397108A (en) Excavator control method, device, server, mobile unit and storage medium
CN110413340A (en) Method for parameter configuration, device, equipment and the readable storage medium storing program for executing of engineering equipment
CN101316967A (en) Machine operational data collection and reporting system
CN110289867A (en) A kind of method, electronic device and storage medium reducing inter-antenna interference
KR101775628B1 (en) System for information providing of excavator combination and method for thereof
CN109614168A (en) Memory Optimize Method and device
CN108699812B (en) Construction machine, portable information terminal for acquiring work data from construction machine, information communication system for construction machine, and program installed on portable information terminal
CN106953656A (en) A kind of intelligent terminal control intercom carries out the method and apparatus of information transfer
CN106034040B (en) The control method of scan node, apparatus and system
CN109032954A (en) A kind of user's choosing method, device, storage medium and the terminal of A/B test
CN114514355A (en) Determination of unified production index
KR20210040121A (en) Construction management system
CN104039008A (en) Hybrid positioning method
Han et al. Productivity evaluation of the conventional and GPS-based earthmoving systems using construction simulation
CN216379737U (en) Device for identifying work cycle and positive flow excavator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination