CN110411702A - The high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel - Google Patents
The high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel Download PDFInfo
- Publication number
- CN110411702A CN110411702A CN201910624771.0A CN201910624771A CN110411702A CN 110411702 A CN110411702 A CN 110411702A CN 201910624771 A CN201910624771 A CN 201910624771A CN 110411702 A CN110411702 A CN 110411702A
- Authority
- CN
- China
- Prior art keywords
- air
- pressure
- deicing
- valve
- wind tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01M—TESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
- G01M9/00—Aerodynamic testing; Arrangements in or on wind tunnels
- G01M9/02—Wind tunnels
- G01M9/04—Details
Landscapes
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- General Physics & Mathematics (AREA)
- Aerodynamic Tests, Hydrodynamic Tests, Wind Tunnels, And Water Tanks (AREA)
Abstract
The invention discloses a kind of high-pressure air source supply air lines of the anti-deicing air supply system of icing wind tunnel, the gas supply process of the high-pressure air source supply air line is as follows: the high-pressure air source drawn from high pressure air distribution system, pass through fore filter, pneumatic ball valve, after post-filter, it is once depressurized by high pressure relief regulating valve, outlet imports air buffer, the outlet of air buffer is through Venturi meter, digital valve, it is divided into two-way after three-way control valve, pass through air heater all the way, another way is bypassed as cold air, it is blended by cold and hot gas and quickly adjusts feed air temperature, reduce the influence that heater heat stagnation controls to adjust the time to temperature, anti- deicing test heating air-flow is formed after cold and hot gas blending.
Description
Technical field
The present invention relates to the high-pressure air source supply air lines of the anti-deicing air supply system of icing wind tunnel.
Background technique
The aircraft industries such as America and Europe developed country pay much attention to status of the icing wind tunnel in the anti-deicing system research of aircraft with
Effect, it is desirable that each aircraft type has to pass through the verification experimental verification of stringent anti-deicing system, this is also icing seaworthiness specification
It is required that one of indispensable content.External long-term icing research shows that: carry out the anti-deicing system of aircraft using icing wind tunnel and set
Meter and verifying are very reliable and effective means.
The anti-deicing air supply system of icing wind tunnel provides the main flow type pump with injection of simulation for the wing hot gas anti-icing system in test section
Air-flow is heated, heating air-flow is heated by heater, and heater heat stagnation will affect temperature and control to adjust the time.
Summary of the invention
The purpose of the present invention is to provide a kind of high-pressure air source supply air lines of the anti-deicing air supply system of icing wind tunnel, lead to
Hot gas blending is subcooled and quickly adjusts feed air temperature, reduces the influence that heater heat stagnation controls to adjust the time to temperature, cold and hot gas is mixed
Anti- deicing test heating air-flow is formed after mixed.
To achieve the above object, the technical scheme is to design a kind of high pressures of the anti-deicing air supply system of icing wind tunnel
The gas supply process of gas source feed pipeline, the high-pressure air source supply air line is as follows: the high-pressure air source drawn from high pressure air distribution system is led to
It after crossing fore filter, pneumatic ball valve, post-filter, is once depressurized by high pressure relief regulating valve, outlet imports air
The outlet of buffer, air buffer is divided into two-way after Venturi meter, digital valve, three-way control valve, passes through sky all the way
Hot-air heater, another way are bypassed as cold air, are blended by cold and hot gas and are quickly adjusted feed air temperature, reduce heater heat stagnation to temperature
Degree controls to adjust the influence of time, and anti-deicing test heating air-flow is formed after cold and hot gas blending.
Preferably, the air pressure of the high-pressure air source is 12~22MPa.
Preferably, the pneumatic ball valve is pneumatic band handwheel regulation ball valve, and loses gas power failure state valve and be automatically closed.
Preferably, the high pressure relief regulating valve is the pressure reducing valve that pneumatic stagnation pressure self-excitation aciculiform is adjusted, and is fed back to after valve always
Pressure combines feedback and flow rate feedback, and operating pressure selects the gas source of 3~6MPa, loses gas power failure state valve and quickly closes automatically
It closes, has lock pressure function.
Preferably, the venturi flow is calculated as room temperature flowmeter.
Preferably, the three-way control valve uses electrical servo, and it is true according to short-term air flow temperature regulating range to shunt size
It is fixed.
Preferably, the high-pressure air source supply air line uses gapless stainless steel tube, and wraps up insulating layer, keeps the temperature layer material
Select aluminium silicate wool.
Advantages and advantages of the present invention are to provide a kind of high-pressure air source of anti-deicing air supply system of icing wind tunnel supplies
Air pipe quickly adjusts feed air temperature by the blending of cold and hot gas, reduces the shadow that heater heat stagnation controls to adjust the time to temperature
It rings, forms anti-deicing test heating air-flow after cold and hot gas blending.
Detailed description of the invention
Fig. 1 is schematic diagram of the invention.
Specific embodiment
With reference to the accompanying drawings and examples, further description of the specific embodiments of the present invention.Following embodiment is only
For clearly illustrating technical solution of the present invention, and not intended to limit the protection scope of the present invention.
As shown in Figure 1, the present invention provides a kind of high-pressure air source supply air line of anti-deicing air supply system of icing wind tunnel, the height
The gas supply process of pressurized air source supply air line is as follows: the high-pressure air source drawn from high pressure air distribution system 1 passes through fore filter 2, gas
It after dynamic ball valve 3, post-filter 4, is once depressurized by high pressure relief regulating valve 5, outlet imports air buffer 6, air
The outlet of buffer 6 is divided into two-way after Venturi meter 7, digital valve 8, three-way control valve 9, passes through air heater all the way
10, another way is bypassed as cold air, is blended by cold and hot gas and is quickly adjusted feed air temperature, is reduced heater heat stagnation and is controlled temperature
The influence of regulating time forms anti-deicing test heating air-flow after cold and hot gas blending.
The air pressure of the high-pressure air source is 12~22MPa.
The pneumatic ball valve 3 is pneumatic band handwheel regulation ball valve, and loses gas power failure state valve and be automatically closed.
The high pressure relief regulating valve 5 is the pressure reducing valve that pneumatic stagnation pressure self-excitation aciculiform is adjusted, and is fed back to stagnation pressure after valve, comprehensive
Feedback and flow rate feedback, operating pressure select the gas source of 3~6MPa, lose gas power failure state valve automatic quick closedown, have
Lock pressure function.
The Venturi meter 7 is room temperature flowmeter.
The three-way control valve 9 uses electrical servo, shunts size and is determined according to short-term air flow temperature regulating range.
The high-pressure air source supply air line uses gapless stainless steel tube, and wraps up insulating layer, and heat preservation layer material selects silicon
Sour aluminum wool.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, several improvements and modifications can also be made, these improvements and modifications
Also it should be regarded as protection scope of the present invention.
Claims (7)
1. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel, which is characterized in that the high-pressure air source supply air line
Gas supply process it is as follows: from high pressure air distribution system draw high-pressure air source, pass through fore filter, pneumatic ball valve, postposition filtering
It after device, is once depressurized by high pressure relief regulating valve, outlet imports air buffer, and the outlet of air buffer is through venturi
It is divided into two-way after flowmeter, digital valve, three-way control valve, all the way by air heater, another way bypasses as cold air, passes through
Cold and hot gas blending quickly adjusts feed air temperature, reduces the influence that heater heat stagnation controls to adjust the time to temperature, cold and hot gas blending
After form anti-deicing test heating air-flow.
2. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel according to claim 1, which is characterized in that
The air pressure of the high-pressure air source is 12~22MPa.
3. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel according to claim 1, which is characterized in that
The pneumatic ball valve is pneumatic band handwheel regulation ball valve, and loses gas power failure state valve and be automatically closed.
4. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel according to claim 1, which is characterized in that
The high pressure relief regulating valve be pneumatic stagnation pressure encourage oneself aciculiform adjust pressure reducing valve, be fed back to stagnation pressure after valve, combine feedback and
Flow rate feedback, operating pressure select the gas source of 3~6MPa, lose the automatic quick closedown of gas power failure state valve, have lock pressure function.
5. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel according to claim 1, which is characterized in that
The venturi flow is calculated as room temperature flowmeter.
6. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel according to claim 1, which is characterized in that
The three-way control valve uses electrical servo, shunts size and is determined according to short-term air flow temperature regulating range.
7. the high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel according to claim 1, which is characterized in that
The high-pressure air source supply air line uses gapless stainless steel tube, and wraps up insulating layer, and heat preservation layer material selects aluminium silicate wool.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910624771.0A CN110411702A (en) | 2019-07-11 | 2019-07-11 | The high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910624771.0A CN110411702A (en) | 2019-07-11 | 2019-07-11 | The high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110411702A true CN110411702A (en) | 2019-11-05 |
Family
ID=68361021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910624771.0A Pending CN110411702A (en) | 2019-07-11 | 2019-07-11 | The high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110411702A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110848572A (en) * | 2019-11-20 | 2020-02-28 | 华陆工程科技有限责任公司 | For supercritical CO2Anti-icing system and method for safe discharge of power generation system |
CN110947964A (en) * | 2019-12-18 | 2020-04-03 | 安徽科元三维技术有限公司 | Uniform-speed air supply circulating device of metal 3D printer |
CN111795796A (en) * | 2020-09-08 | 2020-10-20 | 中国空气动力研究与发展中心低速空气动力研究所 | Icing wind tunnel ice prevention and removal test method and system |
CN112611567A (en) * | 2020-11-27 | 2021-04-06 | 中国航发四川燃气涡轮研究院 | Automatic model selection method for regulating valve of high-altitude simulation test bed of aero-engine |
CN116448376A (en) * | 2023-06-16 | 2023-07-18 | 中国空气动力研究与发展中心低速空气动力研究所 | Spray air supply system for icing wind tunnel and adjusting method |
CN118376380A (en) * | 2024-06-24 | 2024-07-23 | 中国空气动力研究与发展中心低速空气动力研究所 | Air inlet channel pressure test device and method based on three-way valve |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103048109A (en) * | 2012-11-28 | 2013-04-17 | 中国商用飞机有限责任公司 | Wing type test piece for icing wind tunnel test of aircraft wing anti-icing system |
EP2703291A2 (en) * | 2012-08-29 | 2014-03-05 | The Boeing Company | Inlet icing protection simulation system |
CN203858089U (en) * | 2014-04-02 | 2014-10-01 | 康福斯(苏州)航空工业有限公司 | Aircraft anti-icing system testing device |
CN104764578A (en) * | 2015-04-10 | 2015-07-08 | 中国空气动力研究与发展中心低速空气动力研究所 | Icing-deicing process force measurement test device |
CN107271134A (en) * | 2017-06-28 | 2017-10-20 | 中国空气动力研究与发展中心低速空气动力研究所 | A kind of icing wind tunnel hot air anti-icing tests high-precision analog method and apparatus |
CN206990187U (en) * | 2017-06-28 | 2018-02-09 | 中国空气动力研究与发展中心低速空气动力研究所 | A kind of high-precision icing wind tunnel hot air anti-icing experiment simulator |
CN107745828A (en) * | 2017-11-28 | 2018-03-02 | 中国航空工业集团公司沈阳空气动力研究所 | A kind of anti-deicing experiment air entraining device of hot gas |
-
2019
- 2019-07-11 CN CN201910624771.0A patent/CN110411702A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2703291A2 (en) * | 2012-08-29 | 2014-03-05 | The Boeing Company | Inlet icing protection simulation system |
CN103048109A (en) * | 2012-11-28 | 2013-04-17 | 中国商用飞机有限责任公司 | Wing type test piece for icing wind tunnel test of aircraft wing anti-icing system |
CN203858089U (en) * | 2014-04-02 | 2014-10-01 | 康福斯(苏州)航空工业有限公司 | Aircraft anti-icing system testing device |
CN104764578A (en) * | 2015-04-10 | 2015-07-08 | 中国空气动力研究与发展中心低速空气动力研究所 | Icing-deicing process force measurement test device |
CN107271134A (en) * | 2017-06-28 | 2017-10-20 | 中国空气动力研究与发展中心低速空气动力研究所 | A kind of icing wind tunnel hot air anti-icing tests high-precision analog method and apparatus |
CN206990187U (en) * | 2017-06-28 | 2018-02-09 | 中国空气动力研究与发展中心低速空气动力研究所 | A kind of high-precision icing wind tunnel hot air anti-icing experiment simulator |
CN107745828A (en) * | 2017-11-28 | 2018-03-02 | 中国航空工业集团公司沈阳空气动力研究所 | A kind of anti-deicing experiment air entraining device of hot gas |
Non-Patent Citations (2)
Title |
---|
肖春华 等: "结冰环境下结冰/除冰过程的气动参数测量实验技术", 《航空动力学报》 * |
雷桂林 等: "航空发动机进气支板电热防冰试验", 《航空学报》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110848572A (en) * | 2019-11-20 | 2020-02-28 | 华陆工程科技有限责任公司 | For supercritical CO2Anti-icing system and method for safe discharge of power generation system |
CN110947964A (en) * | 2019-12-18 | 2020-04-03 | 安徽科元三维技术有限公司 | Uniform-speed air supply circulating device of metal 3D printer |
CN110947964B (en) * | 2019-12-18 | 2022-03-18 | 安徽科元三维技术有限公司 | Uniform-speed air supply circulating device of metal 3D printer |
CN111795796A (en) * | 2020-09-08 | 2020-10-20 | 中国空气动力研究与发展中心低速空气动力研究所 | Icing wind tunnel ice prevention and removal test method and system |
CN112611567A (en) * | 2020-11-27 | 2021-04-06 | 中国航发四川燃气涡轮研究院 | Automatic model selection method for regulating valve of high-altitude simulation test bed of aero-engine |
CN116448376A (en) * | 2023-06-16 | 2023-07-18 | 中国空气动力研究与发展中心低速空气动力研究所 | Spray air supply system for icing wind tunnel and adjusting method |
CN116448376B (en) * | 2023-06-16 | 2023-08-18 | 中国空气动力研究与发展中心低速空气动力研究所 | Spray air supply system for icing wind tunnel and adjusting method |
CN118376380A (en) * | 2024-06-24 | 2024-07-23 | 中国空气动力研究与发展中心低速空气动力研究所 | Air inlet channel pressure test device and method based on three-way valve |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110411702A (en) | The high-pressure air source supply air line of the anti-deicing air supply system of icing wind tunnel | |
CN110411703A (en) | The anti-deicing air supply system of icing wind tunnel | |
CN109114418A (en) | A kind of gasification station with plunger pump | |
RU2010151854A (en) | AREA VENTILATION SYSTEM IN THE AIRCRAFT | |
CN106755678A (en) | Oxygen enrichment system before a kind of blast furnace machine | |
CN106680128B (en) | Cold and hot impact testing system for detecting service life of air intercooler | |
CN109442817B (en) | Water power balance system of plant chilled water supply network | |
CN110395406A (en) | The anti-deicing of icing wind tunnel supplies control system | |
CN204693042U (en) | The high-pressure natural gas depressurized system that a kind of heat supply is not delayed | |
CN207395117U (en) | Variable fresh air volume CPC control system | |
CN107300233A (en) | A kind of hot water apparatus of environmental protection and energy saving | |
CN103615792A (en) | Water circulation central air-conditioning uniform flow distributor | |
CN201281224Y (en) | High-pressure compressed gas discharging device | |
CN106091376A (en) | The broken empty heat blower of vacuum glass equipment | |
CN110595790A (en) | Heater oxygenating flow adjusting and rectifying device | |
CN203533814U (en) | Flow homogenizer of water cycle central air conditioner | |
CN110360450A (en) | The middle pressurized air source supply air line of the anti-deicing air supply system of icing wind tunnel | |
CN105709655A (en) | Atmosphere united gas distributing device for hot-dip plating experiment and method of atmosphere united gas distributing device | |
CN205956444U (en) | Automatic thermostatic water mixing valve | |
CN206207002U (en) | A kind of electric heating carburetor | |
CN214093981U (en) | Defrosting system of gasification station | |
CN111841667B (en) | Circulating type double-regulation simulation heat flow system | |
CN204438544U (en) | A kind of combined type water heater | |
CN203814289U (en) | Greenhouse indoor temperature-regulating device | |
CN102564165A (en) | Steam heating oil filtering device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191105 |