CN110390430A - A kind of frequency conversion type water circulating pump optimizing operation method avoiding frequent start-stop - Google Patents

A kind of frequency conversion type water circulating pump optimizing operation method avoiding frequent start-stop Download PDF

Info

Publication number
CN110390430A
CN110390430A CN201910645200.5A CN201910645200A CN110390430A CN 110390430 A CN110390430 A CN 110390430A CN 201910645200 A CN201910645200 A CN 201910645200A CN 110390430 A CN110390430 A CN 110390430A
Authority
CN
China
Prior art keywords
circulating pump
frequency conversion
water circulating
conversion type
type water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910645200.5A
Other languages
Chinese (zh)
Other versions
CN110390430B (en
Inventor
肖俊峰
夏林
胡孟起
连小龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Thermal Power Research Institute Co Ltd
Original Assignee
Xian Thermal Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Thermal Power Research Institute Co Ltd filed Critical Xian Thermal Power Research Institute Co Ltd
Priority to CN201910645200.5A priority Critical patent/CN110390430B/en
Publication of CN110390430A publication Critical patent/CN110390430A/en
Application granted granted Critical
Publication of CN110390430B publication Critical patent/CN110390430B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Control Of Non-Positive-Displacement Pumps (AREA)
  • Control Of Positive-Displacement Pumps (AREA)

Abstract

The invention discloses a kind of frequency conversion type water circulating pump optimizing operation methods for avoiding frequent start-stop, comprising steps of 1) taking the sea level fluctuations of system of sea cooling water is the annual sea level fluctuations of history meteorological data statistics, seawater water temperature is each monthly average seawater water temperature of history meteorological data statistics, carries out the calculating of the key profit points such as frequency conversion type water circulating pump operation number of units variation;2) when unit is run in the unit load variation range that may face, the equal key profit points of frequency conversion type water circulating pump optimization operation number of units variation in annual 12 months are determined;3) according to the equal key profit points of the frequency conversion type water circulating pump optimization operation number of units variation determined in current month situation, unit load and step 2), determine that optimal frequency conversion type water circulating pump runs number of units;4) it is calculated according to the optimization that real-time unit load, sea level fluctuations and seawater water temperature carry out water circulating pump revolving speed, determines the revolving speed of optimal frequency conversion type water circulating pump, realize the number of units of frequency conversion type water circulating pump and the optimization operation of revolving speed.

Description

A kind of frequency conversion type water circulating pump optimizing operation method avoiding frequent start-stop
Technical field
The invention belongs to thermal power plant's system of sea cooling water fields, and in particular to a kind of frequency conversion for avoiding frequent start-stop Formula water circulating pump optimizing operation method.
Background technique
The optimization operation of Cooling Water From Thermal Power Plants system is an important link of reduction unit generation coal consumption, and fire at present Motor group carries out one of the most potential technological approaches of energy-saving operation.Cooling water system optimization operation is set in given Under standby parameter and boundary condition, the optimal solution in economy is found in the influence of each factor in research system, that is, determines optimal condenser pressure Power and corresponding cooling water flow.And optimal condenser pressure and corresponding cooling water flow are by adjusting frequency conversion type recirculated water The method of operation (operation number of units, revolving speed) Lai Shixian's of pump.System of sea cooling water is a kind of using seawater as the straight of water source Cooling water system is flowed, running boundary condition includes: unit load, seawater water temperature and sea level fluctuations.By adjusting frequency conversion type in time The water circulating pump method of operation (operation number of units, revolving speed), it is ensured that under certain unit load, seawater water temperature and sea level fluctuations, coagulate Vapour device is optimal pressure, realizes the optimization operation of frequency conversion type water circulating pump, to reduction Station Service Electrical-Energy rate, promotes energy conservation drop Consumption, raising unit economy have great importance.
For being not involved in the fired power generating unit of peaking operation, in the running boundary condition of system of sea cooling water, sea Water water level is influenced by flood tide and ebb tide, and continually variation by a relatively large margin is had within one day;Seawater water temperature with season then It has a greater change;Unit load monthly or in long period of time change it is smaller.Therefore cold using traditional seawater direct current But water system efficiency method carries out the optimization operation of frequency conversion type water circulating pump, due to by larger in the sea level fluctuations short time The influence of the variation of amplitude easily leads to the frequent variation of the optimal frequency conversion type water circulating pump method of operation (operation number of units, revolving speed).Become The variation of frequency formula water circulating pump revolving speed is easy to accomplish, but the variation of frequency conversion type water circulating pump operation number of units but need by opening, Stop the mode of water circulating pump to realize.It frequently opens, stop water circulating pump and not only be easy to cause the damage of equipment, be unfavorable for unit Safe operation, and the opening of water circulating pump, the process of stopping are also required to the economical operation for expending longer time, being also unfavorable for unit.
Summary of the invention
The technical problems to be solved by the present invention are: for the fired power generating unit for being not involved in peaking operation, to reduce unit hair For the purpose of electric coal consumption, propose that one kind avoids frequent start-stop, and can practical, effectively instruct the operation platform of frequency conversion type water circulating pump Number, rotational speed optimization facilitate the economy for promoting unit operation.
The present invention adopts the following technical scheme that realize:
A kind of frequency conversion type water circulating pump optimizing operation method avoiding frequent start-stop, comprising the following steps:
Step 1, take the sea level fluctuations of system of sea cooling water for the annual seawater water of history meteorological data statistics Position, seawater water temperature are each monthly average seawater water temperature of history meteorological data statistics, carry out frequency conversion type water circulating pump operation number of units and become The calculating of the key profit points such as change;
Step 2, in the unit load variation range that may be faced when unit is run, frequency conversion in annual 12 months is determined The equal key profit points of formula water circulating pump optimization operation number of units variation;
Step 3, operation is optimized according to the frequency conversion type water circulating pump determined in current month situation, unit load and step 2 The equal key profit points of number of units variation determine that optimal frequency conversion type water circulating pump runs number of units;
Step 4, under the frequency conversion type water circulating pump operation number of units that step 3 determines, according to real-time unit load, seawater water The optimization that position and seawater water temperature carry out water circulating pump revolving speed calculates, and determines the revolving speed of optimal frequency conversion type water circulating pump, realizes frequency conversion The number of units of formula water circulating pump and the optimization operation of revolving speed.
A further improvement of the present invention lies in that during calculating, not considering the real-time change of sea level fluctuations in step 1 Change.
A further improvement of the present invention lies in that waiting key profit points is to make under setting sea level fluctuations, seawater water temperature in step 1 It obtains two kinds of frequency conversion type water circulating pumps and runs the equal unit load value of the net profit power under number of units.
A further improvement of the present invention lies in that the calculation formula of net profit power are as follows:
In formula, Δ P is unit net profit power, kW;PtFor micro- increasing power of unit, kW;PpiFor i-th recirculated water of unit The power consumption of pump, kW;I=1,2,3 ... n;N is that water circulating pump runs number of units.
A further improvement of the present invention lies in that in step 3, the optimal frequency conversion type water circulating pump operation number of units of each moon will only by Unit load determines, for being not involved in the fired power generating unit of peaking operation, according to the substantially unit load monthly or in a period of time Situation determines the operation number of units of the optimal frequency conversion type water circulating pump monthly or in a period of time, and then optimal frequency conversion type is avoided to recycle Water pump optimization operation number of units is influenced by sea level fluctuations real-time change.
The present invention has following beneficial technical effect:
By applying above method, the present invention can avoid the frequent start-stop of frequency conversion type water circulating pump, meanwhile, the frequency conversion of optimization Formula water circulating pump operation number of units has also fully considered the influence of sea level fluctuations, seawater water temperature and unit load, and is become by optimization The revolving speed of frequency formula water circulating pump reacts the influence of sea level fluctuations, seawater water temperature and unit load three's real-time change, realizes frequency conversion The optimization of formula water circulating pump is run.
Detailed description of the invention
Fig. 1 is the equal key profit points calculating side that system of sea cooling water difference frequency conversion type water circulating pump runs number of units variation Method.
Fig. 2 is system of sea cooling water frequency conversion type water circulating pump rotational speed optimization method optimizing operation method.
Fig. 3 is system of sea cooling water frequency conversion type water circulating pump optimizing operation method.
Specific embodiment
The present invention will be described in detail below with reference to the accompanying drawings:
As shown in Figure 1, to take sea level fluctuations be annual sea level fluctuations value, seawater water temperature is annual each monthly average seawater water temperature (such as average sea in January water temperature) inputs unit load initial value (such as 100%), runs number of units side in two kinds of frequency conversion type water circulating pumps The optimization that water circulating pump revolving speed is carried out under case (such as scheme 1 is two machines three pump, and scheme 2 is two machines four pump), which calculates, (to be optimized to calculate and calculate Method is as shown in Fig. 2, will introduce below), steam turbine net profit power 1 and net profit power 2 under optimized rotating speed is calculated. The calculation formula of net profit power are as follows:
In formula: Δ P is unit net profit power, kW;PtFor micro- increasing power of unit, kW;PpiFor i-th recirculated water of unit The power consumption of pump, kW;I=1,2,3 ... n;N is that water circulating pump runs number of units.
Compare the steam turbine net profit power 1 and net profit power 2 being calculated, such as the two is equal, then the unit load The equal key profit points under number of units are run for two kinds of frequency conversion type water circulating pumps;Otherwise, by iterating to calculate unit load, make net profit function Rate 1 and net profit power 2 are equal.The different frequency conversion type water circulating pumps in certain unit system of sea cooling water January run number of units Equal key profit points be 84%;I.e. in January, when unit load is less than 84%, select two machines three pump follows pump operation number of units, otherwise Select two machines four pump follows pump operation number of units.According to the algorithm in Fig. 1, annual 12 months frequency conversion type water circulating pumps are calculated to obtain The equal key profit points under number of units are run, the operation number of units of frequency conversion type water circulating pump can be conveniently optimized and revised.For being not involved in peak regulation fortune Capable fired power generating unit can determine the change monthly or in a period of time according to the substantially unit load situation monthly or in a period of time The operation number of units of frequency formula water circulating pump.
The rotational speed optimization method of frequency conversion type water circulating pump is as shown in Figure 2.When the operation number of units of frequency conversion type water circulating pump determines After, according to real-time unit load, seawater water temperature and sea level fluctuations, in water circulating pump minimum speed nminTo rated speed nr In range, it is sequentially increased water circulating pump revolving speed, and the calculating of system of sea cooling water Study on Variable Condition Features is carried out to each revolving speed, it should Variable condition calculation includes condenser thermodynamic computing, and the micro- increasing power calculation of steam turbine, water circulating pump wasted work calculates and net profit power It calculates.According to the system of sea cooling water Study on Variable Condition Features calculated result under each water circulating pump revolving speed, seawater direct current is carried out Cooling water system optimization operation calculates, preferably the optimal water circulating pump revolving speed under the conditions of current border and maximum net profit function out Rate.
The optimization operational process of complete frequency conversion type water circulating pump is as shown in Figure 3.I.e. according to unit load and the current moon Part situation determines the operation number of units of optimal frequency conversion type water circulating pump;Negative according to real-time sea level fluctuations, seawater water temperature and unit Lotus determines the revolving speed of optimal frequency conversion type water circulating pump, realizes the optimization operation of frequency conversion type water circulating pump.
Application effect:
The optimization operation calculated result of the frequency conversion type water circulating pump of certain power plant shows: in terms of annual economic well-being of workers and staff, this hair The method that bright patent proposes can reach real-time optimization frequency conversion type water circulating pump number of units, revolving speed method about 90%.But it is of the invention The method that patent proposes is not necessarily to frequent start-stop water circulating pump, is conducive to the safe operation of unit.

Claims (5)

1. a kind of frequency conversion type water circulating pump optimizing operation method for avoiding frequent start-stop, which comprises the following steps:
Step 1, take the sea level fluctuations of system of sea cooling water for the annual sea level fluctuations of history meteorological data statistics, sea Water water temperature is each monthly average seawater water temperature of history meteorological data statistics, and it is equivalent to carry out the operation number of units variation of frequency conversion type water circulating pump The calculating of benefit point;
Step 2, in the unit load variation range that may be faced when unit is run, determine that annual 12 months frequency conversion types follow The equal key profit points of ring water pump optimization operation number of units variation;
Step 3, according to the frequency conversion type water circulating pump optimization operation number of units determined in current month situation, unit load and step 2 The equal key profit points of variation determine optimal frequency conversion type water circulating pump operation number of units;
Step 4, step 3 determine frequency conversion type water circulating pump operation number of units under, according to real-time unit load, sea level fluctuations and The optimization that seawater water temperature carries out water circulating pump revolving speed calculates, and determines the revolving speed of optimal frequency conversion type water circulating pump, realizes that frequency conversion type follows The number of units of ring water pump and the optimization operation of revolving speed.
2. a kind of frequency conversion type water circulating pump optimizing operation method for avoiding frequent start-stop according to claim 1, feature It is, in step 1, during calculating, does not consider the real-time change of sea level fluctuations.
3. a kind of frequency conversion type water circulating pump optimizing operation method for avoiding frequent start-stop according to claim 1, feature It is, in step 1, waiting key profit points is under setting sea level fluctuations, seawater water temperature, so that two kinds of frequency conversion type water circulating pumps run platform The equal unit load value of net profit power under several.
4. a kind of frequency conversion type water circulating pump optimizing operation method for avoiding frequent start-stop according to claim 3, feature It is, the calculation formula of net profit power are as follows:
In formula, Δ P is unit net profit power, kW;PtFor micro- increasing power of unit, kW;PpiFor i-th water circulating pump of unit Power consumption, kW;I=1,2,3 ... n;N is that water circulating pump runs number of units.
5. a kind of frequency conversion type water circulating pump optimizing operation method for avoiding frequent start-stop according to claim 1, feature It is, in step 3, the optimal frequency conversion type water circulating pump operation number of units of each moon will be determined only by unit load, be adjusted for being not involved in The fired power generating unit of peak operation, determines monthly or in a period of time according to the substantially unit load situation monthly or in a period of time The operation number of units of optimal frequency conversion type water circulating pump, and then avoid optimal frequency conversion type water circulating pump optimization operation number of units by sea level fluctuations The influence of real-time change.
CN201910645200.5A 2019-07-17 2019-07-17 Frequency conversion type circulating water pump optimized operation method capable of avoiding frequent start and stop Active CN110390430B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910645200.5A CN110390430B (en) 2019-07-17 2019-07-17 Frequency conversion type circulating water pump optimized operation method capable of avoiding frequent start and stop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910645200.5A CN110390430B (en) 2019-07-17 2019-07-17 Frequency conversion type circulating water pump optimized operation method capable of avoiding frequent start and stop

Publications (2)

Publication Number Publication Date
CN110390430A true CN110390430A (en) 2019-10-29
CN110390430B CN110390430B (en) 2022-04-26

Family

ID=68285075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910645200.5A Active CN110390430B (en) 2019-07-17 2019-07-17 Frequency conversion type circulating water pump optimized operation method capable of avoiding frequent start and stop

Country Status (1)

Country Link
CN (1) CN110390430B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112163723A (en) * 2020-11-02 2021-01-01 西安热工研究院有限公司 Hydropower station medium and long term runoff prediction method, medium and equipment based on scenario division
CN112228329A (en) * 2020-10-22 2021-01-15 西安热工研究院有限公司 System, device and method for automatically optimizing and adjusting running frequency of circulating water pump

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2562628A1 (en) * 2011-08-26 2013-02-27 Sony Ericsson Mobile Communications AB Image scale alteration arrangement and method
CN103778478A (en) * 2013-12-24 2014-05-07 国家电网公司 Method for forecasting optimal operation mode of circulating water in combination with tidal characteristic of sea water
CN206755913U (en) * 2017-04-25 2017-12-15 华能罗源发电有限责任公司 A kind of condenser cooling water feeding mechanism of frequency conversion according to tidal fluctuations

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2562628A1 (en) * 2011-08-26 2013-02-27 Sony Ericsson Mobile Communications AB Image scale alteration arrangement and method
CN103778478A (en) * 2013-12-24 2014-05-07 国家电网公司 Method for forecasting optimal operation mode of circulating water in combination with tidal characteristic of sea water
CN206755913U (en) * 2017-04-25 2017-12-15 华能罗源发电有限责任公司 A kind of condenser cooling water feeding mechanism of frequency conversion according to tidal fluctuations

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
夏林: ""考虑潮汐影响的凝汽器变工况特性及最佳真空"", 《动力工程学报》 *
李大才: ""潮汐变化下1000MW海水直冷机组循环水泵运行优化研究"", 《中国电力》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112228329A (en) * 2020-10-22 2021-01-15 西安热工研究院有限公司 System, device and method for automatically optimizing and adjusting running frequency of circulating water pump
CN112163723A (en) * 2020-11-02 2021-01-01 西安热工研究院有限公司 Hydropower station medium and long term runoff prediction method, medium and equipment based on scenario division
CN112163723B (en) * 2020-11-02 2023-09-12 西安热工研究院有限公司 Hydropower station medium-long-term runoff prediction method, medium and equipment based on scene division

Also Published As

Publication number Publication date
CN110390430B (en) 2022-04-26

Similar Documents

Publication Publication Date Title
CN104795846A (en) Optimized operation method of pumped-storage power station and wind power combined system
CN103216282B (en) Thermal power generating unit loading control system and method based on continuously adjustable back pressure
CN110912207B (en) Hydropower station in-plant economic operation method and system considering multi-branch-plant constraint
CN111206970B (en) Peak regulating system utilizing steam jet and steam extractor in thermal power plant and control method
CN110957717A (en) Multi-target day-ahead optimal scheduling method for multi-power-supply power system
CN109546689B (en) Two-stage unit combined operation control method suitable for large-scale system
CN110390430A (en) A kind of frequency conversion type water circulating pump optimizing operation method avoiding frequent start-stop
CN110454373A (en) Optimized operation method for variable frequency pump of seawater direct-current cooling water system
CN109611270A (en) A kind of Control of decreasing load method of wind power generating set primary frequency modulation
CN113217131A (en) Electric heating load scheduling method of multi-energy complementary cogeneration system based on carbon emission reduction
CN114033713B (en) Pump station control method considering start-stop loss based on orthogonal test-dynamic programming combination algorithm
CN106443278B (en) First-time starting test method for pumped storage power station
CN102352780B (en) Optimal control method of cold end of thermal power generating unit
CN207004782U (en) Environmental Power Plant circulating water energy-saving device
CN108062606A (en) A kind of virtual plant method for optimizing scheduling based on Riemann integral
CN114089793B (en) Water regulation method utilizing spontaneous wind power and lake regulation
CN107132806A (en) A kind of control method of cold, heat and power triple supply system
CN110659803A (en) Method for calculating peak regulation capacity and heat supply capacity improvement effect of cogeneration unit based on zero output of low-pressure cylinder
CN110378805A (en) Step power station power generation dispatching is classified peak regulating method
CN114035432A (en) Pump station control method considering startup and shutdown loss based on linear integer-dynamic programming combination algorithm
CN210887401U (en) But deep frequency conversion's of closed circulative cooling unit river limit water supply system
CN212204487U (en) Heat accumulation peak regulation system under heat accumulation and release working condition
CN212227002U (en) Heat accumulation peak regulation system
Cong et al. Study on peak shaving strategy of pumped storage power station combined with wind and photovoltaic power generation
CN113944639A (en) Single unit control method of blade full-regulation pump station based on R-IPSO algorithm and considering start-up and shutdown loss

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant