CN110387828A - CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating method - Google Patents
CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating method Download PDFInfo
- Publication number
- CN110387828A CN110387828A CN201910747588.XA CN201910747588A CN110387828A CN 110387828 A CN110387828 A CN 110387828A CN 201910747588 A CN201910747588 A CN 201910747588A CN 110387828 A CN110387828 A CN 110387828A
- Authority
- CN
- China
- Prior art keywords
- rope
- positioning rope
- guide pile
- chain block
- length
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000011017 operating method Methods 0.000 title claims abstract description 11
- 238000009434 installation Methods 0.000 claims abstract description 5
- 238000007689 inspection Methods 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 12
- 238000010276 construction Methods 0.000 abstract description 11
- 239000004677 Nylon Substances 0.000 abstract description 3
- 229920001778 nylon Polymers 0.000 abstract description 3
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 240000009087 Crescentia cujete Species 0.000 description 1
- 235000005983 Crescentia cujete Nutrition 0.000 description 1
- 235000009797 Lagenaria vulgaris Nutrition 0.000 description 1
- 235000014676 Phragmites communis Nutrition 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/16—Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating methods;Blanking tool includes positioning rope, guide pile, guide pile rotating wheel, ground carrying roller and tightening chain block;The following steps are included: (1) determines the length of beginning and end, installation locating rod and nylon roller (2) make a mark operating method between beginning and end;(3) it runs and checks.Previous rope fixed length is generally using the method directly measured with a yardstick, and the method is mainly for, quantity lesser rope shorter in length.It is simpler while shorter, more efficient than the construction method operation directly measured with a yardstick with this fixed length tooling construction method when more for longer or quantity, and cause different in size will not be caused because of human factor.Its utility value can be more embodied when especially quantity is larger.
Description
Technical field
The present invention relates to field of civil engineering, in particular to a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blankers
Dress and operating method.
Background technique
Currently, the fixed length of the domestic double positioning ropes of suspension bridge Rope bearing equipment is generally using the method directly measured with a yardstick, the method
Mainly for, quantity lesser rope shorter in length.When more for longer or quantity, the workload that directly measures with a yardstick
Greatly, while as the mistake of operator and cause positioning rope length inconsistent.With this fixed length tooling construction method than straight
It is simpler while shorter, more efficient to connect the construction method operation measured with a yardstick, and length will not be led to because of human factor
It is inconsistent.Its utility value can be more embodied when especially quantity is larger.
Summary of the invention
The object of the present invention is to provide a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating methods;It can
The blanking of more efficient progress positioning rope, while can effectively ensure that the length of positioning rope is consistent.
The invention is realized in this way constructing a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool, feature exists
In: including positioning rope, guide pile, guide pile rotating wheel, ground carrying roller and tightening chain block;
Guide pile rotating wheel is arranged by guide pile, and positioning rope is connect after bypassing corresponding guide pile with chain block;Ground support
Roller is that multiple groups are arranged on ground respectively.
A kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool operating method, it is characterised in that: the following steps are included:
Step 1: the corresponding landmark point of length after positioning rope doubling is determined, installation guide pile, rotating wheel are just and tightening pulls calabash
Reed;
Step 2: releasing positioning rope, around after corresponding guide pile, connect with chain block;
Step 3: positioning rope is straightened in tightening chain block, each at positioning rope head and the tail both ends then at the guide pile of starting point
It marks a little;
Step 4: when needing to carry out different length positioning rope blanking, it is only necessary to which positioning rope is bypassed to the guide pile of corresponding position
Rotating wheel;
Step 5: operation and inspection.
The present invention has the advantages that the invention discloses a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and behaviour
Make method;Wherein blanking tool includes positioning rope, guide pile, guide pile rotating wheel, ground carrying roller and tightening chain block.
Operating method is the following steps are included: (1) determines the length of beginning and end, installation locating rod and nylon roller (2)
It makes a mark between beginning and end;(3) it runs and checks.Previous rope fixed length generally uses the method directly measured with a yardstick,
The method is mainly for, quantity lesser rope shorter in length.When more for longer or quantity, constructed with this fixed length tooling
Method is simpler while shorter, more efficient than the construction method operation directly measured with a yardstick, and will not be because of human factor
Lead to cause different in size.Its utility value can be more embodied when especially quantity is larger.Implementation through the invention: (1) it realizes
The standardization of steel cable fixed length construction;(2) avoid conventional method because operator mistake and caused by rope length it is inconsistent
Problem;(3) when more for longer or quantity, this fixed length tooling is simpler than the construction method operation directly measured with a yardstick, together
When it is shorter, more efficient.
Detailed description of the invention
Fig. 1 is positioning rope fixed length tooling elevation;
Fig. 2 is positioning rope fixed length tooling plan view.
Wherein: positioning rope 1, guide pile 2, rotating wheel 3, ground carrying roller 4, chain block 5, ground 6.
Specific embodiment
Below in conjunction with attached drawing 1, the present invention is described in detail, and technical solution in the embodiment of the present invention carries out clear
Chu is fully described by, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Based on the embodiments of the present invention, obtained by those of ordinary skill in the art without making creative efforts all
Other embodiments shall fall within the protection scope of the present invention.
The purpose of the present invention is to provide the methods of the double positioning rope fixed length toolings of large-span suspension bridge Rope bearing equipment, make steel cable
Time used in fixed length is short, high-efficient, and can safely and effectively construct.
Specific embodiment that the present invention is further explained with reference to the accompanying drawing:
A kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool, as Figure 1-Figure 2, including it is positioning rope 1, guide pile 2, fixed
Position stake rotating wheel 3, ground carrying roller 4 and tightening chain block 5;
Guide pile rotating wheel 3 is arranged by guide pile 2, and positioning rope 1 is connect after bypassing corresponding guide pile 2 with chain block 5;Ground
Face carrying roller 4 is that multiple groups are arranged in respectively on ground 6.
A kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool operating method, the specific steps are as follows:
Step 1: determining the corresponding landmark point of length after 1 doubling of positioning rope, and installation guide pile 2, rotating wheel 3 and tightening pull
Cucurbit 5;
Step 2: releasing positioning rope 1, around after corresponding guide pile 2, connect with chain block 5;
Step 3: positioning rope is straightened in tightening chain block 5, then at the guide pile of starting point 2, in 1 head and the tail two of positioning rope
End respectively marks a little;
Step 4: when needing to carry out different length 1 blanking of positioning rope, it is only necessary to which positioning rope 1 is bypassed to the positioning of corresponding position
Stake rotating wheel 3;
Step 5: operation and inspection.
In conclusion the invention discloses a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating methods;
The following steps are included: (1) determines the length of beginning and end, locating rod is installed and nylon roller (2) is done between beginning and end
It marks out;(3) it runs and checks.Previous rope fixed length generally using the method directly measured with a yardstick, the method mainly in
Length is shorter, the lesser rope of quantity.When more for longer or quantity, ruler is directly used with this fixed length tooling construction method ratio
The construction method operation of amount is simpler while shorter, more efficient, and will not lead to cause different in size because of human factor.
Its utility value can be more embodied when especially quantity is larger.Implementation through the invention: (1) mark of steel cable fixed length construction is realized
Standardization;(2) avoid conventional method because the mistake of operator and caused by the inconsistent problem of rope length;(3) for longer
Or quantity it is more when, this fixed length tooling than directly measure with a yardstick construction method operation it is simpler while shorter, more efficient.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention.
Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention
It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one
The widest scope of cause.
Claims (2)
1. a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool, it is characterised in that: including positioning rope (1), guide pile
(2), guide pile rotating wheel (3), ground carrying roller (4) and tightening chain block (5);
Guide pile rotating wheel (3) is arranged by guide pile (2), positioning rope (1) around corresponding guide pile (2) afterwards and chain block
(5) it connects;Ground carrying roller (4) is that multiple groups are arranged in respectively on ground (6).
2. a kind of CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool operating method, it is characterised in that: the following steps are included:
Step 1: the corresponding landmark point of length after positioning rope (1) doubling, installation guide pile (2), rotating wheel (3) and receipts are determined
Tight chain block (5);
Step 2: releasing positioning rope (1), around after corresponding guide pile (2), connect with chain block (5);
Step 3: positioning rope (1) is straightened in tightening chain block (5), then at the guide pile of starting point (2), in positioning rope
(1) head and the tail both ends respectively mark a little;
Step 4: when needing to carry out different length positioning rope blanking, it is only necessary to which positioning rope (1) is bypassed to the positioning of corresponding position
Stake rotating wheel (3);
Step 5: operation and inspection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910747588.XA CN110387828A (en) | 2019-08-14 | 2019-08-14 | CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910747588.XA CN110387828A (en) | 2019-08-14 | 2019-08-14 | CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110387828A true CN110387828A (en) | 2019-10-29 |
Family
ID=68288753
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910747588.XA Pending CN110387828A (en) | 2019-08-14 | 2019-08-14 | CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110387828A (en) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06171501A (en) * | 1992-11-25 | 1994-06-21 | Kajima Corp | Circulating cableway device |
JPH09240466A (en) * | 1996-03-06 | 1997-09-16 | Nippon Cable Co Ltd | Curved operation method for automatic circulating type cable road. |
CN202687627U (en) * | 2012-07-20 | 2013-01-23 | 武汉钢铁(集团)公司 | Steel wire rope sizing arrangement device |
CN204569150U (en) * | 2015-04-16 | 2015-08-19 | 上海振华重工集团(南通)有限公司 | A kind of tyre crane driver's cab hoisting fixture |
CN107974946A (en) * | 2017-12-08 | 2018-05-01 | 中交路桥华东工程有限公司 | A kind of long hoist cable installation auxiliary device of suspension bridge and preparation method thereof and application method |
CN207497533U (en) * | 2017-10-26 | 2018-06-15 | 首钢京唐钢铁联合有限责任公司 | A kind of roller-type conveyer |
CN108988102A (en) * | 2017-05-31 | 2018-12-11 | 科迈士瑞士股份有限公司 | Method and apparatus for processing cable |
CN109095280A (en) * | 2018-09-29 | 2018-12-28 | 中国科学院长春光学精密机械与物理研究所 | A kind of lead length measuring line taking device |
CN208429700U (en) * | 2018-07-10 | 2019-01-25 | 江苏立达电梯有限公司 | A kind of wirerope meter is long, blanking device |
CN109914252A (en) * | 2019-03-20 | 2019-06-21 | 中交路桥建设有限公司 | A kind of long hoist cable installation method of straddle-type |
CN210797288U (en) * | 2019-08-14 | 2020-06-19 | 四川路桥华东建设有限责任公司 | Cable hoisting system holds cable ware location rope unloading frock |
-
2019
- 2019-08-14 CN CN201910747588.XA patent/CN110387828A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06171501A (en) * | 1992-11-25 | 1994-06-21 | Kajima Corp | Circulating cableway device |
JPH09240466A (en) * | 1996-03-06 | 1997-09-16 | Nippon Cable Co Ltd | Curved operation method for automatic circulating type cable road. |
CN202687627U (en) * | 2012-07-20 | 2013-01-23 | 武汉钢铁(集团)公司 | Steel wire rope sizing arrangement device |
CN204569150U (en) * | 2015-04-16 | 2015-08-19 | 上海振华重工集团(南通)有限公司 | A kind of tyre crane driver's cab hoisting fixture |
CN108988102A (en) * | 2017-05-31 | 2018-12-11 | 科迈士瑞士股份有限公司 | Method and apparatus for processing cable |
CN207497533U (en) * | 2017-10-26 | 2018-06-15 | 首钢京唐钢铁联合有限责任公司 | A kind of roller-type conveyer |
CN107974946A (en) * | 2017-12-08 | 2018-05-01 | 中交路桥华东工程有限公司 | A kind of long hoist cable installation auxiliary device of suspension bridge and preparation method thereof and application method |
CN208429700U (en) * | 2018-07-10 | 2019-01-25 | 江苏立达电梯有限公司 | A kind of wirerope meter is long, blanking device |
CN109095280A (en) * | 2018-09-29 | 2018-12-28 | 中国科学院长春光学精密机械与物理研究所 | A kind of lead length measuring line taking device |
CN109914252A (en) * | 2019-03-20 | 2019-06-21 | 中交路桥建设有限公司 | A kind of long hoist cable installation method of straddle-type |
CN210797288U (en) * | 2019-08-14 | 2020-06-19 | 四川路桥华东建设有限责任公司 | Cable hoisting system holds cable ware location rope unloading frock |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106395628B (en) | A kind of method of the aerial group pair of heavy tower equipment segmental hoisting | |
CN103147400A (en) | One-time tensioning construction method of super-long prestressed tendon for cast-in-place box girder bridge web | |
CN106436576A (en) | Constructing method of main tower of cable-stayed bridge through circumferential prestressing force | |
CN209050036U (en) | A kind of automatic adjustment steel reinforcement cage processing diameter device | |
CN102561204B (en) | Construction method for inserting super-long steel stranded wires before pouring of bridge body | |
CN106744311A (en) | A kind of nuclear power plant containment shell steel lining module hanging method | |
CN208220671U (en) | Telescopic wire rope handling guide pulley device | |
CN108221694B (en) | The method for installing long-span arch bridge tie-rod | |
CN105113414A (en) | Method for quickly setting up main ropes of suspension bridge | |
CN110387828A (en) | CABLEWAY ERECTION SYSTEM Rope bearing equipment positioning rope blanking tool and operating method | |
CN105781205B (en) | A kind of guider in place of the aerial group pair of heavy tower equipment segmental hoisting | |
CN110172919A (en) | A kind of low-pylon cable-stayed bridge is reeved method and system | |
CN106744290A (en) | A kind of steel part conveys transfer tooling | |
CN210797288U (en) | Cable hoisting system holds cable ware location rope unloading frock | |
CN107161879A (en) | Attached wall provision for disengagement and its method for dismounting on rear side of derrick crane | |
CN207243306U (en) | Tower crane two sides jacks stock | |
CN206693031U (en) | A kind of large-span suspension bridge cable crane load bearing system of head-rope parallel structure | |
CN214697911U (en) | Lining cutting platform truck air pipe fixing system | |
CN104724615A (en) | Penetrating and winding method of large-diameter variable-amplitude steel wire rope of large moving-arm type tower crane | |
CN108545645B (en) | Auxiliary threading device for hoisting | |
CN108374931A (en) | A kind of push pipe is hampered quick supporting method of getting rid of poverty | |
CN112302350A (en) | Construction scheme of engineering helicopter in transportation aspect of high-voltage line tower | |
CN209637771U (en) | The shield duct piece of service channel removes equipment in a kind of tunnel | |
CN202687627U (en) | Steel wire rope sizing arrangement device | |
CN208308334U (en) | A kind of lifting auxiliary threader |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |