CN110380982A - A kind of flow control methods and relevant apparatus - Google Patents

A kind of flow control methods and relevant apparatus Download PDF

Info

Publication number
CN110380982A
CN110380982A CN201910701532.0A CN201910701532A CN110380982A CN 110380982 A CN110380982 A CN 110380982A CN 201910701532 A CN201910701532 A CN 201910701532A CN 110380982 A CN110380982 A CN 110380982A
Authority
CN
China
Prior art keywords
flow control
operation system
processing capacity
system processing
assessment cycle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910701532.0A
Other languages
Chinese (zh)
Other versions
CN110380982B (en
Inventor
陈炽卉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inspur Power Commercial Systems Co Ltd
Original Assignee
Inspur Power Commercial Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inspur Power Commercial Systems Co Ltd filed Critical Inspur Power Commercial Systems Co Ltd
Priority to CN201910701532.0A priority Critical patent/CN110380982B/en
Publication of CN110380982A publication Critical patent/CN110380982A/en
Application granted granted Critical
Publication of CN110380982B publication Critical patent/CN110380982B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L47/00Traffic control in data switching networks
    • H04L47/10Flow control; Congestion control
    • H04L47/24Traffic characterised by specific attributes, e.g. priority or QoS
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L47/00Traffic control in data switching networks
    • H04L47/10Flow control; Congestion control
    • H04L47/29Flow control; Congestion control using a combination of thresholds

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Data Exchanges In Wide-Area Networks (AREA)

Abstract

This application discloses a kind of flow control methods, the response time including monitoring service request, update flow control assessment cycle based on the response time and predetermined period, and update operation system processing capacity based on updated flow control assessment cycle;Judge to control in assessment cycle in present flow rate, whether the server-side meets operation system processing capacity update condition;If the server-side meets operation system processing capacity update condition, the operation system processing capacity is updated again;Flow control is carried out according to preset flow control strategy when the server-side meets flow control entry condition, and exits flow control when the server-side meets flow control exit criteria.The flow control methods can be improved the adaptive ability of flow control, ensure the precision of flow control.Disclosed herein as well is a kind of volume control device and computer readable storage mediums, all have above-mentioned technical effect.

Description

A kind of flow control methods and relevant apparatus
Technical field
This application involves field of computer technology, in particular to a kind of flow control methods;Further relate to a kind of flow control Device and computer readable storage medium.
Background technique
In operation system, when the quantity of service request constantly rises and exceeds the design maximum capacity of operation system, Operation system enters overload.The overload of short time may cause service request and overstock, and service response is slack-off;Prolonged mistake Load then may cause operation system and paralyse extremely, cause operation system can not normal response service request.For service request mistake The case where load, currently, the flow control methods based on traffic handing capacity first pass through benchmark test assessment operation system most in advance Big processing capacity, and then in the actual moving process of operation system, when the quantity of service request is more than maximum processing capability Just start flow control, refuse the service request exceeded, and after starting flow control, when service request quantity is lower than maximum When reason ability, flow control is exited.
However, the adaptive ability of the above-mentioned existing flow control methods based on traffic handing capacity is poor, work as business When configuration change occurs for system, such as work as server-side and hardware dilatation occur, software upgrading, part software and hardware break down software and hardware When change, the maximum processing capability of operation system may change, and the existing flow control side based on traffic handing capacity Method but can not flexibly and effectively cope with the change of maximum processing capability, to seriously affect the precision of flow control.
In view of this, how to improve the adaptive ability of flow control, ensure that the precision of flow control has become ability Field technique personnel technical problem urgently to be resolved.
Summary of the invention
The purpose of the application is to provide a kind of flow control methods, can be improved the adaptive ability of flow control, ensures The precision of flow control;The another object of the application is to provide a kind of volume control device and computer-readable storage medium Matter all has above-mentioned technical effect.
In order to solve the above technical problems, this application provides a kind of flow control methods, comprising:
The response time for monitoring service request updates flow control assessment cycle based on the response time and predetermined period And operation system processing capacity is updated based on updated flow control assessment cycle;
Judge in present flow rate control assessment cycle, whether the server-side, which meets operation system processing capacity, updates item Part;
If the server-side meets the operation system processing capacity update condition, updated at the operation system again Reason ability;
Flow control is carried out according to preset flow control strategy when the server-side meets flow control entry condition, and Flow control is exited when the server-side meets flow control exit criteria.
It is optionally, described that flow control assessment cycle is updated based on the response time and predetermined period, comprising:
According to Tnew=α * ERT
ERT=A+ β * D
A=A+g*Err
Err=M-A
D=D+h (| Err |-D) it obtains the updated value of the flow control assessment cycle and institute is updated based on the updated value State flow control assessment cycle;
Wherein, the TnewIndicate the updated value of the flow control assessment cycle, the A indicates response time mean value Estimated value, the g indicate that increment, the M indicate the response time, and the D indicates that mean bias, the h indicate gain, institute Stating the α and β indicates that coefficient, the ERT indicate estimation transaction time.
Optionally, operation system processing capacity is updated based on updated flow control assessment cycle, comprising:
According toObtain the first updated value of the operation system processing capacity and based on the business First updated value of system processing capacity updates the operation system processing capacity;
Wherein, the TnewIndicate the updated value of the flow control assessment cycle, ToldIndicate the flow control before updating The numerical value of assessment cycle processed, the Cnew1Indicate the first updated value of the traffic handing capacity, the ColdIndicate institute before updating State the numerical value of traffic handing capacity.
Optionally, if the server-side meets operation system processing capacity update condition, the industry is updated again Business system processing capacity, comprising:
If the server-side meets Δ R >=γ Δ P or S > C, according to Cnew2=λ C+ (1- λ) S obtains the business system Second updated value of processing capacity of uniting simultaneously updates the operation system processing capacity based on second updated value again;
Wherein, the Δ R indicates received service request quantity and a upper flow in present flow rate control assessment cycle The difference of received service request quantity in assessment cycle is controlled, the Δ P indicates processing in present flow rate control assessment cycle Service request quantity and the service request quantity handled in a upper flow control assessment cycle difference, the γ indicates system Number, the λ indicate that smoothing factor, the S indicate actual treatment speed, and the C indicates the operation system processing before updating again Ability, the Cnew2Indicate the second updated value of the operation system processing capacity.
Optionally, the flow control entry condition is there is Δ in continuous preset quantity flow control assessment cycle R≥γΔP;The flow control exit criteria is to exist in continuous preset quantity flow control assessment cycleWherein, the γ with it is describedIndicate coefficient.
Optionally, described to be carried out when the server-side meets flow control entry condition according to preset flow control strategy Flow control, comprising:
When the server-side meets flow control entry condition, the priority according to the service request carries out flow control System.
Optionally, flow control is carried out according to the priority of the service request, comprising:
If Δ R≤0.25*C*T, loss priority is the service request of third priority;
If Δ R > 0.5*C*T, loss priority is the service request of third priority and the second priority;
If Δ R > C*T, loss priority is the industry of third priority, the second priority and the first priority Business request;
Wherein, the T indicates that present flow rate controls assessment cycle, and the C indicates current business system processing capacity.
Optionally, further includes:
Overload error code is controlled to client transmitted traffic after starting flow control, so that the client is receiving Current limited Control is carried out after stating flow control overload error code.
In order to solve the above technical problems, present invention also provides a kind of volume control devices, comprising:
First update module is based on the response time and predetermined period more for monitoring the response time of service request New flow controls assessment cycle, and updates operation system processing capacity based on updated flow control assessment cycle;
Judgment module, for judging in present flow rate control assessment cycle, whether the server-side meets at operation system Manage ability update condition;
Second update module updates again if meeting operation system processing capacity update condition for the server-side The operation system processing capacity then updates the operation system processing capacity again;
Control module, for when the server-side meets flow control entry condition according to preset flow control strategy into Row flow control, and flow control is exited when the server-side meets flow control exit criteria.
In order to solve the above technical problems, the computer can present invention also provides a kind of computer readable storage medium It reads storage medium and is stored with computer program, the computer program is realized as described in any one of the above embodiments when being executed by processor The step of flow control methods.
Flow control methods provided herein, the response time including monitoring service request, when being based on the response Between with predetermined period update flow control assessment cycle and based on updated flow control assessment cycle update operation system at Reason ability;Judge in present flow rate control assessment cycle, whether the server-side meets operation system processing capacity update condition; If the server-side meets the operation system processing capacity update condition, the operation system processing capacity is updated again; Flow control is carried out according to preset flow control strategy when the server-side meets flow control entry condition, and works as the clothes Flow control is exited when meeting flow control exit criteria in business end.As it can be seen that flow control methods provided herein, it can basis Maximum processing capability, that is, operation system processing capacity of the response condition assessment operation system of service request, realization are accurately flowed Amount control, has stronger adaptive ability, can preferably cope with operation system configuration change, and stream provided herein Amount control method adjusts flow control assessment cycle according to the response condition of service request, can effectively avoid flow control starting It is too fast or too slow.
Volume control device and computer readable storage medium provided herein, all has above-mentioned technical effect.
Detailed description of the invention
It in order to more clearly explain the technical solutions in the embodiments of the present application, below will be to institute in the prior art and embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the application Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of flow diagram of flow control methods provided by the embodiment of the present application;
Fig. 2 is a kind of schematic diagram of volume control device provided by the embodiment of the present application.
Specific embodiment
The core of the application is to provide a kind of flow control methods, can be improved the adaptive ability of flow control, ensures The precision of flow control;Another core of the application is to provide a kind of volume control device and computer-readable storage medium Matter all has above-mentioned technical effect.
To keep the purposes, technical schemes and advantages of the embodiment of the present application clearer, below in conjunction with the embodiment of the present application In attached drawing, the technical scheme in the embodiment of the application is clearly and completely described, it is clear that described embodiment is Some embodiments of the present application, instead of all the embodiments.Based on the embodiment in the application, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall in the protection scope of this application.
Referring to FIG. 1, Fig. 1 is a kind of flow diagram of flow control methods provided by the embodiment of the present application;With reference to Shown in Fig. 1, which includes:
S101: monitoring the response time of service request, updates flow control assessment week based on response time and predetermined period Phase, and operation system processing capacity is updated based on updated flow control assessment cycle;
Specifically, flow control methods provided herein are applied to the business middleware of the server-side of operation system, In operation system operational process, business middleware can real-time monitoring service request response time, the so-called response time, that is, industry It is engaged in the processing time requested, for from time difference of the service request to finishing service request-reply is received, unit can be the second. On the basis of the response time of real-time monitoring service request, it is primarily based on response time and predetermined period and updates flow control and comment Estimate the period.Wherein, the specific value of above-mentioned predetermined period can carry out adaptable setting according to the actual application, to this Unique restriction is not done in application, for example, in view of OLTP (On-line Transaction Processing, at online things transaction Reason process) type load the transaction response time usually at 0.1 second or hereinafter, therefore in order to avoid flow control assessment cycle update excessively Frequently, predetermined period can be set to 10 seconds, i.e., every 10 seconds flow control assessment cycles of update.In addition, being flowed in starting In the case where amount control, for the service requesting information being dropped, its response time is not monitored.
It is above-mentioned that flow control assessment cycle is updated based on response time and predetermined period in a kind of specific embodiment It may include according to Tnew=α * ERT, ERT=A+ β * D, A=A+g*Err, Err=M-A, D=D+h (| Err |-D) obtain flow It controls the updated value of assessment cycle and flow control assessment cycle is updated based on updated value;Wherein, TnewIndicate flow control assessment The updated value in period, A indicate the estimated value of response time mean value, and g indicates that increment, M indicate the response time, and D indicates mean bias, H indicates gain, and α and β indicate that coefficient, ERT indicate estimation transaction time.
Specifically, the present embodiment using iterative calculation flow control assessment cycle updated value by the way of, in predetermined period It is interior, it is every to receive a service request response, the updated value of a flow control assessment cycle is just calculated based on above-mentioned each formula, and At the end of predetermined period, such as at the end of the predetermined period of 10s, using the updated value that is calculated for the last time as final Flow control assessment cycle updated value, and flow control is updated based on this final updated value after predetermined period and is commented Estimate the period.Terminating current 10s, into after next 10s, is being again based on above-mentioned each formula and calculates updated value and flowed The update of amount control assessment cycle updates a flow control assessment cycle every 10s to realize.Wherein, factor alpha and coefficient The numerical value of β can carry out otherness setting according to the actual application, for example, factor alpha is 10, factor beta 4.When A indicates response Between mean value estimated value, the initialization value of A can be the initialization value+0.5 of response time M;D indicates mean bias, and D's is initial Change value can be the half of the initialization value of A;Increment g and gain h may respectively be 0.125 and 0.25.
On the basis of updating flow control assessment cycle, further, more based on updated flow control assessment cycle New business system processing capacity.I.e. every update for completing a flow control assessment cycle, just updates a business system accordingly System processing capacity.
It is above-mentioned to be updated at operation system based on updated flow control assessment cycle in a kind of specific embodiment Reason ability may include basisObtain the first updated value of operation system processing capacity and based on business system First updated value of processing capacity of uniting updates operation system processing capacity;Wherein, wherein TnewIndicate flow control assessment cycle Updated value, ToldIndicate the numerical value of flow control assessment cycle before updating, Cnew1Indicate that the first of traffic handing capacity updates Value, ColdIndicate the numerical value of traffic handing capacity before updating.
S102: judging in present flow rate control assessment cycle, and whether server-side, which meets operation system processing capacity, updates item Part;
S103: if server-side meets operation system processing capacity update condition, operation system processing capacity is updated again;
Specifically, judging whether to business after the first time that this step has been intended to rear operation system processing capacity updates The update again of processing capacity, specifically, judging in present flow rate control assessment cycle, whether server-side meets operation system Ability update condition, and work as server-side and meet operation system processing capacity update condition, operation system processing capacity is updated again. On the contrary, no longer updating industry at the end of present flow rate controls assessment cycle if server-side is unsatisfactory for operation system processing capacity Business system processing capacity.
Wherein, in a kind of specific embodiment, if above-mentioned server-side meets operation system processing capacity update condition, If then updating operation system processing capacity again may include that server-side meets Δ R >=γ Δ P or S > C, according to Cnew2=λ C + (1- λ) S obtains the second updated value of operation system processing capacity and updates operation system processing energy again based on the second updated value Power;Wherein, Δ R indicates received service request quantity and upper flow control assessment week in present flow rate control assessment cycle The difference of received service request quantity in phase, Δ P indicate the service request quantity handled in present flow rate control assessment cycle With the difference of the service request quantity handled in a upper flow control assessment cycle, γ indicates that coefficient, λ indicate smoothing factor, S Indicate actual treatment speed, C indicates the operation system processing capacity before updating again, Cnew2Indicate operation system processing capacity Second updated value.
Specifically, operation system processing capacity update condition includes Δ R >=γ Δ P and S > C, server-side in the present embodiment When meeting above-mentioned any one operation system processing capacity update condition, just at the end of present flow rate controls assessment cycle again Update operation system processing capacity.Wherein, coefficient gamma can be 1.5, and smoothing factor λ can be 0.9.Actual treatment speed S= Δ P/ Δ t, Δ t are the difference that present flow rate controlled assessment cycle and a upper flow control assessment cycle.
S104: carrying out flow control according to preset flow control strategy when server-side meets flow control entry condition, And flow control is exited when server-side meets flow control exit criteria.
Specifically, during operation system operation, once server-side meets flow control entry condition, just according to pre- If flow control policy carries out flow control, and after starting flow control, when server-side meets flow control exit criteria Exit flow control.
Wherein, in a kind of specific embodiment, above-mentioned flow control entry condition can be continuous preset quantity There is Δ R >=γ Δ P in flow control assessment cycle;Flow control exit criteria is that continuous preset quantity flow control is commented Estimate in the period and existsWherein, γ withIndicate coefficient.
Specifically, the specific value of above-mentioned preset quantity can be configured according to the actual application, for example, can be 3, coefficient lambda withMay respectively be 1.5 withThen flow control entry condition is specially continuous 3 flow controls assessment week There is the Δ P of Δ R >=1.5 in phase, flow control exit criteria is to exist in continuous 3 flow control assessment cycles
In addition, the above-mentioned foundation when server-side meets flow control entry condition is pre- in a kind of specific embodiment If it may include when server-side meets flow control entry condition, according to service request that flow control policy, which carries out flow control, Priority carry out flow control.
Specifically, can the factors such as importance, resource consumption according to service request, priority is carried out to service request and is drawn Point, so that the priority according to service request carries out flow control after starting flow control, to realize the same of flow control When, improve the performance of operation system.
Further, on the basis of the above embodiments, above-mentioned according to service request as a kind of specific embodiment If it may include: Δ R≤0.25*C*T that priority, which carries out flow control, loss priority is that the business of third priority is asked It asks;If Δ R > 0.5*C*T, loss priority is the service request of third priority and the second priority;If Δ R > C*T, Then loss priority is the service request of third priority, the second priority and the first priority;Wherein, T indicates current stream Amount control assessment cycle, C indicate current business system processing capacity.
Specifically, there are three types of priority for the present embodiment setting, i.e. the first priority, the second priority and third are preferential Grade, the first priority therein are high priority, and the second priority is high medium priority, and third priority is high priority.Into And as Δ R≤0.25*C*T, loss priority is the service request of third priority;It is abandoned as Δ R > 0.5*C*T excellent First grade is the service request of third priority and the second priority;As Δ R > C*T, loss priority is third priority, the The service request of two priority and the first priority abandons all service requests.
Further, the executing subject of flow control methods provided by the various embodiments described above is server-side, in order into one Step improves the control performance of flow, and in a kind of specific embodiment, which further includes starting flow control Backward client transmitted traffic control overload error code, so that client is limited after receiving flow control overload error code Flow control.
Specifically, the present embodiment while server-side carries out flow control, increases client and carries out flow control, work as clothes It is engaged in after the starting flow control of end, server-side can control overload error code via the interface transmitted traffic of server-side and client, into And client is set to carry out preliminary current limliting processing after detecting flow control overload error code, such as client is by the industry of sending The quantity control of business request is at twice or so of the service response received.
In conclusion flow control methods provided herein, can assess business according to the response condition of service request The maximum processing capability of system, that is, operation system processing capacity, realize it is accurate carry out flow control, have it is stronger it is adaptive should be able to Power can preferably cope with operation system configuration change, and flow control methods provided herein, according to service request Response condition adjusts flow control assessment cycle, and it is too fast or too slow to can effectively avoid flow control starting.
Present invention also provides a kind of volume control device, the device described below can be with method as described above phase Mutually to should refer to.It please refers to shown in Fig. 2, which includes:
First update module 10 is updated for monitoring the response time of service request based on response time and predetermined period Flow control assessment cycle, and operation system processing capacity is updated based on updated flow control assessment cycle;
Judgment module 20, for judging in present flow rate control assessment cycle, whether server-side meets operation system processing Ability update condition;
Second update module 30 updates industry if meeting operation system processing capacity update condition for server-side again Business system processing capacity, then update operation system processing capacity again;
Control module 40, for being carried out when server-side meets flow control entry condition according to preset flow control strategy Flow control, and flow control is exited when server-side meets flow control exit criteria.
On the basis of the above embodiments, optionally, the first update module 10 is specifically used for according to Tnew=α * ERT, ERT =A+ β * D, A=A+g*Err, Err=M-A, D=D+h (| Err |-D) it obtains the updated value of flow control assessment cycle and is based on Updated value updates flow control assessment cycle;Wherein, TnewIndicate the updated value of flow control assessment cycle, A indicates the response time The estimated value of mean value, g indicate that increment, M indicate the response time, and D indicates that mean bias, h indicate gain, and α and β indicate coefficient, ERT Indicate estimation transaction time.
On the basis of the above embodiments, the first update module 10 is specifically used for basisObtain business First updated value of system processing capacity and the first updated value based on operation system processing capacity update operation system and handle energy Power;Wherein, TnewIndicate the updated value of flow control assessment cycle, ToldIndicate the numerical value of flow control assessment cycle before updating, Cnew1Indicate the first updated value of traffic handing capacity, ColdIndicate the numerical value of traffic handing capacity before updating.
On the basis of the above embodiments, optionally, if the second update module 30 is specifically used for server-side and meets Δ R >=γ Δ P or S > C, then according to Cnew2=λ C+ (1- λ) S obtains the second updated value of operation system processing capacity and updates based on second Value updates operation system processing capacity again;Wherein, Δ R indicates received service request number in present flow rate control assessment cycle The difference of amount and received service request quantity in a upper flow control assessment cycle, Δ P indicate present flow rate control assessment The difference of the service request quantity handled in the service request quantity handled in period and a upper flow control assessment cycle, γ Indicating that coefficient, λ indicate that smoothing factor, S indicate actual treatment speed, C indicates the operation system processing capacity before updating again, Cnew2Indicate the second updated value of operation system processing capacity.
On the basis of the above embodiments, optionally, control module 40 is specifically used for opening when server-side meets flow control When dynamic condition, the priority according to service request carries out flow control.
On the basis of the above embodiments, further includes:
Sending module controls overload error code to client transmitted traffic after flow control for starting, so that client Current limited Control is carried out after receiving flow control overload error code.
Present invention also provides a kind of computer readable storage medium, calculating is stored on the computer readable storage medium Machine program, the computer program realize following step when being executed by processor:
The response time for monitoring service request updates flow control assessment cycle based on response time and predetermined period, and Operation system processing capacity is updated based on updated flow control assessment cycle;Judge in present flow rate control assessment cycle, Whether server-side meets operation system processing capacity update condition;If server-side meets operation system processing capacity update condition, Operation system processing capacity is then updated again;When server-side meets flow control entry condition according to preset flow control strategy Flow control is carried out, and exits flow control when server-side meets flow control exit criteria.
The computer readable storage medium may include: USB flash disk, mobile hard disk, read-only memory (Read-OnlyMemory, ROM), random access memory (Random Access Memory, RAM), magnetic or disk etc. are various can store program The medium of code.
Above method embodiment is please referred to for the introduction of computer readable storage medium provided by the present invention, the present invention This will not be repeated here.
Each embodiment is described in a progressive manner in specification, the highlights of each of the examples are with other realities The difference of example is applied, the same or similar parts in each embodiment may refer to each other.For device disclosed in embodiment, set For standby and computer readable storage medium, since it is corresponded to the methods disclosed in the examples, so the comparison of description is simple Single, reference may be made to the description of the method.
Professional further appreciates that, unit described in conjunction with the examples disclosed in the embodiments of the present disclosure And algorithm steps, can be realized with electronic hardware, computer software, or a combination of the two, in order to clearly demonstrate hardware and The interchangeability of software generally describes each exemplary composition and step according to function in the above description.These Function is implemented in hardware or software actually, the specific application and design constraint depending on technical solution.Profession Technical staff can use different methods to achieve the described function each specific application, but this realization is not answered Think beyond scope of the present application.
The step of method described in conjunction with the examples disclosed in this document or algorithm, can directly be held with hardware, processor The combination of capable software module or the two is implemented.Software module can be placed in random access memory (RAM), memory, read-only deposit Reservoir (ROM), electrically programmable ROM, electrically erasable programmable ROM, register, hard disk, moveable magnetic disc, CD-ROM or technology In any other form of storage medium well known in field.
Flow control methods provided herein, device and computer readable storage medium have been carried out in detail above It introduces.Specific examples are used herein to illustrate the principle and implementation manner of the present application, the explanation of above embodiments It is merely used to help understand the present processes and its core concept.It should be pointed out that for the ordinary skill people of the art Member for, under the premise of not departing from the application principle, can also to the application, some improvement and modification can also be carried out, these improve and Modification also falls into the protection scope of the claim of this application.

Claims (10)

1. a kind of flow control methods, which is characterized in that be applied to server-side, comprising:
The response time for monitoring service request updates flow control assessment cycle based on the response time and predetermined period, and Operation system processing capacity is updated based on updated flow control assessment cycle;
Judge in present flow rate control assessment cycle, whether the server-side meets operation system processing capacity update condition;
If the server-side meets the operation system processing capacity update condition, the operation system processing energy is updated again Power;
Flow control is carried out according to preset flow control strategy when the server-side meets flow control entry condition, and works as institute It states when server-side meets flow control exit criteria and exits flow control.
2. flow control methods according to claim 1, which is characterized in that described based on the response time and default week Phase updates flow control assessment cycle, comprising:
According to Tnew=α * ERT
ERT=A+ β * D
A=A+g*Err
Err=M-A
D=D+h (| Err |-D) it obtains the updated value of the flow control assessment cycle and the stream is updated based on the updated value Amount control assessment cycle;
Wherein, the TnewIndicate the updated value of the flow control assessment cycle, the A indicates the estimation of response time mean value Value, the g indicate that increment, the M indicate the response time, and the D indicates that mean bias, the h indicate gain, the α Indicate that coefficient, the ERT indicate estimation transaction time with the β.
3. flow control methods according to claim 2, which is characterized in that be based on updated flow control assessment cycle Update operation system processing capacity, comprising:
According toObtain the first updated value of the operation system processing capacity and based on the operation system First updated value of processing capacity updates the operation system processing capacity;
Wherein, the TnewIndicate the updated value of the flow control assessment cycle, ToldIndicate that the flow control is commented before updating Estimate the numerical value in period, the Cnew1Indicate the first updated value of the traffic handing capacity, the ColdIndicate the industry before updating The numerical value for processing capacity of being engaged in.
4. flow control methods according to claim 3, which is characterized in that if the server-side meets operation system Processing capacity update condition then updates the operation system processing capacity again, comprising:
If the server-side meets Δ R >=γ Δ P or S > C, according to Cnew2=λ C+ (1- λ) S obtains the operation system processing Second updated value of ability simultaneously updates the operation system processing capacity based on second updated value again;
Wherein, the Δ R indicates received service request quantity and a upper flow control in present flow rate control assessment cycle The difference of received service request quantity in assessment cycle, the Δ P indicate the industry handled in present flow rate control assessment cycle The difference of the service request quantity handled in number of requests of being engaged in and a upper flow control assessment cycle, the γ indicate coefficient, The λ indicates that smoothing factor, the S indicate actual treatment speed, and the C indicates that the operation system before updating again handles energy Power, the Cnew2Indicate the second updated value of the operation system processing capacity.
5. flow control methods according to claim 4, which is characterized in that the flow control entry condition is continuous pre- If there is Δ R >=γ Δ P in quantity flow control assessment cycle;The flow control exit criteria is continuous preset quantity Exist in a flow control assessment cycleWherein, the γ with it is describedIndicate coefficient.
6. flow control methods according to any one of claims 1 to 5, which is characterized in that described when the server-side is full Flow control is carried out according to preset flow control strategy when sufficient flow control entry condition, comprising:
When the server-side meets flow control entry condition, the priority according to the service request carries out flow control.
7. flow control methods according to claim 6, which is characterized in that the priority according to the service request carries out Flow control, comprising:
If Δ R≤0.25*C*T, loss priority is the service request of third priority;
If Δ R > 0.5*C*T, loss priority is the service request of third priority and the second priority;
If Δ R > C*T, loss priority is that the business of third priority, the second priority and the first priority is asked It asks;
Wherein, the T indicates that present flow rate controls assessment cycle, and the C indicates current business system processing capacity.
8. flow control methods according to claim 7, which is characterized in that further include:
Overload error code is controlled to client transmitted traffic after starting flow control, so that the client is receiving the stream Current limited Control is carried out after amount control overload error code.
9. a kind of volume control device characterized by comprising
First update module is updated based on the response time and predetermined period and is flowed for monitoring the response time of service request Amount control assessment cycle, and operation system processing capacity is updated based on updated flow control assessment cycle;
Judgment module, for judging in present flow rate control assessment cycle, whether the server-side meets operation system processing energy Power update condition;
Second update module, if meeting operation system processing capacity update condition for the server-side, again described in update Operation system processing capacity then updates the operation system processing capacity again;
Control module, for being flowed when the server-side meets flow control entry condition according to preset flow control strategy Amount control, and flow control is exited when the server-side meets flow control exit criteria.
10. a kind of computer readable storage medium, which is characterized in that the computer-readable recording medium storage has computer journey Sequence, the computer program realize the step of flow control methods as claimed in any one of claims 1 to 8 when being executed by processor Suddenly.
CN201910701532.0A 2019-07-31 2019-07-31 Flow control method and related device Active CN110380982B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910701532.0A CN110380982B (en) 2019-07-31 2019-07-31 Flow control method and related device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910701532.0A CN110380982B (en) 2019-07-31 2019-07-31 Flow control method and related device

Publications (2)

Publication Number Publication Date
CN110380982A true CN110380982A (en) 2019-10-25
CN110380982B CN110380982B (en) 2022-10-14

Family

ID=68257281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910701532.0A Active CN110380982B (en) 2019-07-31 2019-07-31 Flow control method and related device

Country Status (1)

Country Link
CN (1) CN110380982B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111966502A (en) * 2020-09-21 2020-11-20 北京百度网讯科技有限公司 Method and device for adjusting number of instances, electronic equipment and readable storage medium
CN113079189A (en) * 2020-01-03 2021-07-06 中国移动通信集团广东有限公司 Capacity control method and device for capacity open platform and electronic equipment
WO2023240506A1 (en) * 2022-06-15 2023-12-21 北京小米移动软件有限公司 Request processing method and apparatus, server, and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1780265A (en) * 2004-11-17 2006-05-31 华为技术有限公司 Flow controlling method for message system
CN103957251A (en) * 2014-04-28 2014-07-30 迈普通信技术股份有限公司 Method and system for achieving server load balancing
CN108282501A (en) * 2017-01-05 2018-07-13 阿里巴巴集团控股有限公司 A kind of Cloud Server resource information synchronous method, device and system
CN108574727A (en) * 2018-03-07 2018-09-25 天津麒麟信息技术有限公司 A kind of improved load balance scheduling system based on platform of soaring
WO2018227157A1 (en) * 2017-06-09 2018-12-13 University Of Southern California Adaptive traffic control
CN110032576A (en) * 2019-03-12 2019-07-19 平安科技(深圳)有限公司 A kind of method for processing business and device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1780265A (en) * 2004-11-17 2006-05-31 华为技术有限公司 Flow controlling method for message system
CN103957251A (en) * 2014-04-28 2014-07-30 迈普通信技术股份有限公司 Method and system for achieving server load balancing
CN108282501A (en) * 2017-01-05 2018-07-13 阿里巴巴集团控股有限公司 A kind of Cloud Server resource information synchronous method, device and system
WO2018227157A1 (en) * 2017-06-09 2018-12-13 University Of Southern California Adaptive traffic control
CN108574727A (en) * 2018-03-07 2018-09-25 天津麒麟信息技术有限公司 A kind of improved load balance scheduling system based on platform of soaring
CN110032576A (en) * 2019-03-12 2019-07-19 平安科技(深圳)有限公司 A kind of method for processing business and device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113079189A (en) * 2020-01-03 2021-07-06 中国移动通信集团广东有限公司 Capacity control method and device for capacity open platform and electronic equipment
CN113079189B (en) * 2020-01-03 2023-04-25 中国移动通信集团广东有限公司 Capacity control method and device of capacity open platform and electronic equipment
CN111966502A (en) * 2020-09-21 2020-11-20 北京百度网讯科技有限公司 Method and device for adjusting number of instances, electronic equipment and readable storage medium
WO2023240506A1 (en) * 2022-06-15 2023-12-21 北京小米移动软件有限公司 Request processing method and apparatus, server, and storage medium

Also Published As

Publication number Publication date
CN110380982B (en) 2022-10-14

Similar Documents

Publication Publication Date Title
CN110380982A (en) A kind of flow control methods and relevant apparatus
CN110099009B (en) Dynamic current limiting method based on interface response time trend and computer readable medium
CN109936511B (en) Token obtaining method, device, server, terminal equipment and medium
US20120173709A1 (en) Seamless scaling of enterprise applications
EP3758325B1 (en) Traffic limiting method, node and system
CN109144700A (en) Determination method, apparatus, server and the data processing method of overtime duration
US8966086B2 (en) License redistributing method, moderator and license controlling system thereof
JP6081812B2 (en) Demand response request device, demand response request method, program, and electric vehicle management system
EP3262587B1 (en) Adaptive quota management system
CN112422440B (en) Flow control method applied to server and related device
CN112068934B (en) Control system and method for shrinking container cloud service instance
CN108984288A (en) Thread pool capacity adjustment method, device and equipment based on system response time
CN106464733A (en) Method and device for adjusting virtual resources in cloud computing
CN104820616A (en) Task scheduling method and device
JP2003084856A (en) Device for changing processing performance of computer
JP5459579B2 (en) Job management system, method and program thereof
CN103442087B (en) A kind of Web service system visit capacity based on response time trend analysis controls apparatus and method
JP2013200615A (en) Virtual machine movement control system, virtual machine movement method, and program
JP4008699B2 (en) Method for service level estimation in an operating computer system
CN108920264A (en) A kind of command timeout processing method and system
JP6031051B2 (en) Job execution planning device
CN112822119B (en) Flow control method, flow control equipment and storage medium based on reverse token bucket
CN110727518B (en) Data processing method and related equipment
CN106131187B (en) Authorization control method and device
CN109495588A (en) Task processing method, device, computer equipment and the storage medium of front end processor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant