CN110362021A - A kind of intelligent automatic monitored control system collecting control operation for power plant - Google Patents

A kind of intelligent automatic monitored control system collecting control operation for power plant Download PDF

Info

Publication number
CN110362021A
CN110362021A CN201810318238.7A CN201810318238A CN110362021A CN 110362021 A CN110362021 A CN 110362021A CN 201810318238 A CN201810318238 A CN 201810318238A CN 110362021 A CN110362021 A CN 110362021A
Authority
CN
China
Prior art keywords
power plant
knowledge base
control system
artificial intelligence
control operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810318238.7A
Other languages
Chinese (zh)
Inventor
陈利锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810318238.7A priority Critical patent/CN110362021A/en
Publication of CN110362021A publication Critical patent/CN110362021A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/048Monitoring; Safety

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to automatic control and artificial intelligence fields, more particularly to a kind of automatic monitored control system for power plant's collection control operation based on artificial intelligence.Problem to be solved by the invention is that current power plant's collection control operation operation fully relies on manpower and dig-ins screen bring fatigue and stress problems.The present invention constructs the knowledge base of a computer programing, by the display picture for obtaining each display terminal, to obtain all operation datas in real time, the operation data obtained by the knowledge of knowledge base and in real time combines, the practical judgment mode of dry run operator on duty, the assessment of Lai Jinhang power plant operating status.When judgment and detection is to scheduled alert if, related personnel immediately issues prompt and alarm signal.It is an advantage of the invention that there is no any dependence and interference to power plant's original system.By using the system, the operating pressure and labor intensity of operations staff can greatly be alleviated, reduce pressure of the power plant in operations staff's arrangement.

Description

A kind of intelligent automatic monitored control system collecting control operation for power plant
Technical field
The present invention relates to automatically control and artificial intelligence field, more particularly to one kind based on artificial intelligence technology directly from Screen obtains the automatic monitored control system for power plant's collection control operation of operation data.
Background technique
Power plant's collection control operation is abbreviation and the common name of power plant's centralized control system operation operation.Power plant is relation belonging to state meter The important energy source enterprise of the people's livelihood is that one kind is integrated with various new and high technologies, the important power generation unit for needing wholesale to invest.It is existing Many automatic technologies are all used and are integrated with for power plant, and core therein is power plant's collection control operation.Power plant's collection control fortune Row usually carries out in centralized control room hall, and there are many terminals with display and operation equipment in hall.
In order to guarantee power supply demand, power plant is usually not shut down operation continuously for a long time for power plant.In the daily of power plant In operation, power plant's production requirement is needed to arrange professional operations staff's continuous work, the mode of break tour in usually 24 hours.For fortune For administrative staff, their action is exactly in the power plant system operation parameters for checking that each terminal is shown at any time, root Guided according to production run regulation and working specification, and combine operations staff's day-to-day operation experience, to system equipment carry out operation and It adjusts, to guarantee generating equipment stabilization, reliable operation.The production responsibility of operations staff is very great, but building ring Border is very dull, uninteresting.On the one hand it wants the moment to concentrate whole attentions in the situation of change of each parameter of screen, is on the other hand responsible for Daily Round Check of the power plant in fortune equipment.Due to the presence of Human Physiology limitation, operations staff cannot be concerned about system change constantly The each details changed.In addition, break tour career patterns are increasingly difficult to give power plant to get the nod with the development of present society The operations staff for cultivating occupation and the stabilization for remaining operational staffs bring many difficulties.
If designing a kind of automatic monitored control system to assist operations staff, to reduce their operating pressure, first It must be able to obtain power plant's operation data.A kind of mode for obtaining power plant's operation data is to be linked by certain communication channel existing Some power plant's operating systems and secure network, to obtain operation data.This mode has many limitations and relies on condition: firstly, Need to know the communication specification of existing system;Secondly, needing to possess the permission for obtaining data;Then, it needs and properly to access Communication port.But the complicated system that power plant system is important as one, management software are that other large manufacturers provide, very Communication specification can not be provided in more situations.And due to safety concerns, power plant can not allow other systems arbitrarily to access simultaneously Obtain data.It is difficult to realize in this way.
Summary of the invention
It is an object of the present invention to directly obtain operation data, all fortune of real-time monitoring from screen using artificial intelligence technology Row data are timely issued and are mentioned to as value operations staff and related management personnel when specific scheduled condition meets Show and alarm, timely and effectively to cope with the generation of abnormal conditions, to mitigate the operating pressure of operations staff, in felicity condition Under can rationally reduce operations staff be equipped with quantity.
The present invention collects control operating standard to power plant and working specification guide is analyzed, and combines operations staff's day-to-day operation Experience constructs the knowledge base of a computer programing, this knowledge base is the Knowledge Base for being monitored and alarming.
The present invention uses artificial intelligence technology, all to obtain in real time by obtaining the display picture of each display terminal Operation data does not need the original collection control operating system of access power plant and secure network.
The present invention uses artificial intelligence technology, the operation data obtained by the knowledge of aforementioned knowledge base [0006] and in real time [0007] combine, the practical operation experience of dry run personnel, the assessment of Lai Jinhang power plant system operating status.
The present invention when prejudging and detecting that specific unsafe condition occurs, immediately to when value operation watch Member and related management personnel issue prompt and alarm.
It includes the voice guard, visual alarm, hair being mounted in equipment that the present invention, which issues prompt and the mode of alarm, The report of the alarm message, the instant communication software (wechat APP) being sent on related personnel's mobile phone that are sent on related personnel's mobile phone Alert information.Alarm logging under automatic safety.
The present invention passes through the function of combining [0006], [0007], [0008], [0009], [0010], forms a whole, Realize the automatic monitoring and alarm system of a kind of pair of power plant's collection control operating system.One advantage of the system is not need access electricity The original control system of factory does not have any influence and interference to power plant's original system.It, can by using the automatic monitored control system The labor intensity of operator is effectively reduced, reduces power plant in operations staff and configures pressure.
Detailed description of the invention
Specific embodiment
Construct knowledge base
The entire control system of power plant is analyzed, corresponding knowledge base is constructed according to analysis, being one huge is System engineering, and the forward position direction of the current artificial intelligence power plant studied in the world.Emphasis of the present invention is to collection control fortune Professional etiquette journey and working specification guide are analyzed, the knowledge base of one computer programing towards collection control operation of building.This The content that knowledge base is covered be it is very specialized, general requirement be meet collection control operation operator regular job Specification.This knowledge base is the Knowledge Base for the condition judgement for being monitored and alarming.
Obtain operation data
The present invention obtains operation data by the way of directly reading data by screen.It does not need to access original electricity Factory's operating system and secure network.
The present invention obtains the picture of the terminal screen of power plant's centralized control room using choosing any one kind of them in two ways.The A kind of mode are as follows: suitable position installs camera before the terminal screen of power plant's centralized control room, obtains screen from camera and draws Face.The second way are as follows: by accessing a signal branch on the display signal line of the terminal screen of power plant's centralized control room Device, signal sends original terminal screen back to all the way, and another way signal is used to obtain screen-picture.
Present invention employs the intelligent algorithms of the vision of simulation people, are analyzed and processed to the screen-picture of acquisition, Carry out all operation datas on real-time recognition screen.
Operating status assessment
The present invention uses the depth learning technology of artificial intelligence field, the fortune obtained by the knowledge of aforementioned knowledge base and in real time Row data combine, the practical judgment mode of dry run personnel, the assessment of Lai Jinhang power plant operating status.The assessment of progress The frequency can be previously set, and assessment is so the various empirical parameters relied on can also be previously set, with the effect being optimal.
Prompt and alarm
The present invention when judgment and detection meets to predetermined alert if, immediately to as value operations staff and correlation Administrative staff issue prompt and alarm.
It includes the voice guard being mounted in equipment, visual alarm that the present invention, which issues prompt and the mode of alarm,.Sound Sound alarm, visual alarm are mounted on the conspicuous position of power plant's collection control operation building, by process control.When predetermined alert if When meeting, different flashing, alarmings and different audible alerts can be started according to danger classes, the volume of audible alert is reachable To 50 decibels or more, guarantee that working region can clearly be heard.
The present invention can be according to setting, and by being sent on related personnel's mobile phone of alarm message, warning message is sent to phase On instant communication software (wechat APP) on the personnel's mobile phone of pass, to guarantee that relevant administrative staff are known at the first time, into One step promotes the validity of safety guarantee and the instantaneity of processing response.

Claims (4)

1. a kind of intelligent automatic monitored control system for collecting control operation for power plant, including collect control operating standard and operation according to power plant Specification, which is guided, is analyzed and is constructed the specialized knowledge base of a computer programing, by camera or signal shunt from electricity The display terminal of factory's collection control operating system obtains display picture, identifies operation data from the picture by artificial intelligence technology, leads to It crosses work intellectual technology and knowledge base and operation data is combined to the assessment for carrying out power plant's operating status, issued according to assessment result Prompt or alarm signal.
2. the automatic monitored control system of power plant's collection control operation according to claim 1, it is characterised in that: pass through camera or letter Number splitter obtains real-time display picture from the display screen of power plant's centralized control room, by artificial intelligence technology from the display picture Face identifies operation data.
3. the automatic monitored control system of power plant's collection control operation according to claim 1, it is characterised in that: collect control operation to power plant Regulation and working specification guide the specialized knowledge base for being analyzed and being constructed a computer programing.
4. the automatic monitored control system of power plant according to claim 1 collection control operation, it is characterised in that: by by claim Operation data described in 2 and knowledge base as claimed in claim 3 combine, and carry out power plant by artificial intelligence technology and run shape The assessment of state issues prompt or alarm signal according to assessment result.
CN201810318238.7A 2018-04-10 2018-04-10 A kind of intelligent automatic monitored control system collecting control operation for power plant Pending CN110362021A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810318238.7A CN110362021A (en) 2018-04-10 2018-04-10 A kind of intelligent automatic monitored control system collecting control operation for power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810318238.7A CN110362021A (en) 2018-04-10 2018-04-10 A kind of intelligent automatic monitored control system collecting control operation for power plant

Publications (1)

Publication Number Publication Date
CN110362021A true CN110362021A (en) 2019-10-22

Family

ID=68214069

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810318238.7A Pending CN110362021A (en) 2018-04-10 2018-04-10 A kind of intelligent automatic monitored control system collecting control operation for power plant

Country Status (1)

Country Link
CN (1) CN110362021A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111539695A (en) * 2020-05-09 2020-08-14 三门核电有限公司 Configuration risk evaluation data automatic acquisition system based on power plant information system
CN113473042A (en) * 2020-03-31 2021-10-01 宝山钢铁股份有限公司 Automatic tracking system and method for hot rolling main rolling line operation monitoring picture based on SDK

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113473042A (en) * 2020-03-31 2021-10-01 宝山钢铁股份有限公司 Automatic tracking system and method for hot rolling main rolling line operation monitoring picture based on SDK
CN111539695A (en) * 2020-05-09 2020-08-14 三门核电有限公司 Configuration risk evaluation data automatic acquisition system based on power plant information system

Similar Documents

Publication Publication Date Title
CN107748546B (en) Intelligent factory inspection system based on LoRa technology
CN109001649A (en) A kind of power supply smart diagnostic system and guard method
CN109147272A (en) Line reminding method is got in violation of rules and regulations by substation based on ultra wide band UWB positioning
KR101944961B1 (en) Supervisory Control And Data Acquisition System Based Internet Of Thing Platform
CN204069358U (en) Constructing tunnel personnel positioning management system
CN108268706B (en) Closed loop test system and method for intelligent alarm application of integrated monitoring system
CN107945049A (en) A kind of wisdom water utilities emergency response method and system based on technology of Internet of things
CN109739183B (en) Large-scale digit control machine tool fault monitoring system based on multisensor
CN109450098A (en) Power regulation integral system warning information optimization method
CN103928071A (en) Nuclear power plant emergency state auxiliary judgment system and method based on emergency action level
CN110362021A (en) A kind of intelligent automatic monitored control system collecting control operation for power plant
CN111035098A (en) Intelligent safety helmet for wind power plant
CN113627897A (en) Method and device for managing and controlling safety of field operating personnel and storage medium
CN109407609A (en) A kind of facility information point detection system
CN116523502A (en) Intelligent production line operation and maintenance management alarm system
CN113673959B (en) Comprehensive management and control method and device for site operation safety and storage medium
CN111030085A (en) Electric power safety multi-engine checking and killing mechanism
CN110262436A (en) Safety production monitoring method and monitoring system
CN112235056B (en) Signal quality monitoring and evaluating system
CN110045699A (en) Data center's power manages system and method
CN211604110U (en) Portable safe operation management and control device
CN115641229A (en) Production safety management and control system of wisdom power plant
CN115294726A (en) Safety control method for electric power operation and safety helmet
CN114519496A (en) New energy collection station equipment health early warning model construction system
CN113011698A (en) Intelligent equipment management and control platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20191022

WD01 Invention patent application deemed withdrawn after publication