CN110360444A - A kind of skid-mounted LNG entrucking and liquid guide system - Google Patents

A kind of skid-mounted LNG entrucking and liquid guide system Download PDF

Info

Publication number
CN110360444A
CN110360444A CN201910678845.9A CN201910678845A CN110360444A CN 110360444 A CN110360444 A CN 110360444A CN 201910678845 A CN201910678845 A CN 201910678845A CN 110360444 A CN110360444 A CN 110360444A
Authority
CN
China
Prior art keywords
pipeline
entrucking
lng
liquid guiding
guiding pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910678845.9A
Other languages
Chinese (zh)
Inventor
张留瑜
薛永攀
周冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Marriott Energy Equipment Co Ltd
Original Assignee
Hefei Marriott Energy Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Marriott Energy Equipment Co Ltd filed Critical Hefei Marriott Energy Equipment Co Ltd
Priority to CN201910678845.9A priority Critical patent/CN110360444A/en
Publication of CN110360444A publication Critical patent/CN110360444A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C13/00Details of vessels or of the filling or discharging of vessels
    • F17C13/02Special adaptations of indicating, measuring, or monitoring equipment
    • F17C13/025Special adaptations of indicating, measuring, or monitoring equipment having the pressure as the parameter
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C13/00Details of vessels or of the filling or discharging of vessels
    • F17C13/04Arrangement or mounting of valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C5/00Methods or apparatus for filling containers with liquefied, solidified, or compressed gases under pressures
    • F17C5/02Methods or apparatus for filling containers with liquefied, solidified, or compressed gases under pressures for filling with liquefied gases
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D3/00Arrangements for supervising or controlling working operations
    • F17D3/01Arrangements for supervising or controlling working operations for controlling, signalling, or supervising the conveyance of a product

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The invention discloses a kind of skid-mounted LNG entrucking and liquid guide systems, it is prized including entrucking arm, and connect the Liquid guiding pump sled of entrucking arm sled, the pipeline one for being connected to LNG tank car is provided in the entrucking arm sled, it is connected to the pipeline two of LNG tank car BOG, for the pipeline BOG pipeline three recycled and for the pipeline four of overpressure relief in system, the pipeline one, pipeline two, pipeline three and pipeline four are formed for utilizing the pipeline branch line that overbottom pressure realization LNG is filled in system, Liquid guiding pump is provided in the Liquid guiding pump sled, the pipeline five of connection BOG recuperator is provided on the Liquid guiding pump.It is integrated that the present invention by the layout facility of pipeline realize entrucking can with drain, filling for LNG is realized using the overbottom pressure of natural gas liquefaction device simultaneously, LNG drain speed is promoted by the compulsory circulation of Liquid guiding pump, LNG can be reduced to fill and drain process BOG yield, the tank car waiting time is shortened, process is reliable and secure.

Description

A kind of skid-mounted LNG entrucking and liquid guide system
Technical field
The present invention relates to LNG to fill technical field, specially a kind of skid-mounted LNG entrucking and liquid guide system.
Background technique
LNG is a kind of low temperature, colourless, tasteless, nontoxic and non-corrosive medium, his volume is about that same amount gaseous state is natural 45%, LNG of a quarter of gas, only androgynous ponding is a kind of safe, high-quality, efficient, clean medium, be may be implemented Transporting safely for long range, enhances city gas peak shaving and emergency capability.
Due to its low-temperature characteristics, usual LNG is during handling, drain, it may appear that a large amount of flashed vapour (BOG) causes More fluid loss.Therefore, a kind of simple, reliable method is found, the liquid during the handling of LNG, drain is reduced and disappears Consumption, reduces the yield of BOG, is hot spot concerned by people always, and there are following defects in existing technology;
1: the prior art unavoidably generates fluid loss with there are a kind of by the way of liquid gasification pressurization;
2: the prior art mainly adopts device autonomous working, entrucking is generally operated separately with drain;
3: the prior art uses cryogenic liquid pump and gasifier combined method, and process is complicated, and does not consider LNG entrucking process;
4: there is the handler that LNG can be achieved in the prior art, but immersed pump is set in LNG storage tank, and process of unloading is only The method that can be pressurized by LNG tank car itself realizes that controlling is poor, while LNG surge tank and pry regulator is arranged, scheme composition It is more complex, it is more difficult to be implemented as sledge.
Summary of the invention
The purpose of the present invention is to provide a kind of skid-mounted LNG entrucking and liquid guide systems, to solve in above-mentioned background technique The problem of proposition.
To achieve the above object, the invention provides the following technical scheme: a kind of skid-mounted LNG entrucking and liquid guide system, packet It includes entrucking arm sled and connects the Liquid guiding pump sled of entrucking arm sled;
Be provided in entrucking arm sled and be connected to the pipeline one of LNG tank car, the pipeline two that is connected to LNG tank car BOG, for managing The pipeline three that road BOG is recycled and the pipeline four for overpressure relief in system, the pipeline one, pipeline two, three and of pipeline Pipeline four is formed for utilizing the pipeline branch line that overbottom pressure realization LNG is filled in system;
It is provided with Liquid guiding pump in the Liquid guiding pump sled, the pipeline five of connection BOG recuperator is provided on the Liquid guiding pump.
It is provided with safety valve on the pipeline one and pipeline two, which is respectively connected with EAG recuperator.
Valve, safety valve, pressure gauge and entrucking arm are provided on the pipeline one.
The pipeline one is provided with two in entrucking arm sled altogether, and is connected to by pipeline branch line, and be connected on pipeline four.
Valve, safety valve, pressure gauge and entrucking arm are provided on the pipeline two.
The pipeline one, pipeline two are connected to pipeline five and are formed with the pipeline branch for generating BOG for collecting entrucking process Line is to pipeline three.
The Liquid guiding pump for tank car to tank car drain is set in the Liquid guiding pump sled, which includes Liquid guiding pump one and lead Liquid pump two.
The pipeline branch line extremely pipe that BOG is generated for collecting drain process is respectively connected on the Liquid guiding pump one and Liquid guiding pump two Road three.
Liquid guiding pump, valve, safety valve, pressure gauge and temperature sensor are provided on pipeline in the Liquid guiding pump sled.
Safety valve in the Liquid guiding pump sled is connected to EAG recuperator.
As shown from the above technical solution, the present invention makes entrucking and drain that can realize one by the layout facility of pipeline Change, while the overbottom pressure of natural gas liquefaction device realizes filling for LNG, LNG drain speed promoted by the compulsory circulation of Liquid guiding pump, LNG can be reduced to fill and drain process BOG yield, shorten the tank car waiting time, process is reliable and secure.
Detailed description of the invention
Fig. 1 is present system schematic diagram.
Specific embodiment
The present invention will be further described with reference to the accompanying drawing:
A kind of skid-mounted LNG entrucking as shown in Figure 1 and liquid guide system, including entrucking arm sled 16 and connect entrucking arm sled 16 Liquid guiding pump sled 17, is below described in further detail entrucking arm sled 16;
The pipeline for being connected to the pipeline 1 of LNG tank car 9 and being connected to tank car gas phase hose 8 is provided in entrucking arm sled 16 22, it is formed on the pipeline 1 and pipeline 22 for that can realize pipeline branch line that LNG be filled after throttling by loine pressure, Current embodiment require that doing emphasis detailed description for the pipeline branch line;
Firstly, the present embodiment is provided with 2 identical pipelines 1 in entrucking arm sled 16 altogether, pipeline is extending to LNG tank car It is disposed with valve 05, pressure gauge, valve 06, safety valve 07, valve 08 and entrucking arm 10 on 9 direction, is managed at two A pipeline branch line is provided between road 1, which is connected between safety valve 07 and valve 08, and connects at bout end Road 44 is taken over, while being provided with by-passing valve 41 on the pipeline branch line;The present embodiment is prized 16 internal strengths in entrucking arm and is provided with simultaneously 2 identical pipelines 22, pipeline be disposed on the direction for extending to tank car gas phase hose 8 safety valve, pressure gauge, Valve, safety valve and entrucking arm 10, while pipeline branch line is communicated between pipeline 1 and pipeline 22, on the pipeline branch line It is again provided with valve, the BOG generated during LNG entrucking can enter combustion by following path in above-mentioned pipeline arrangement Expect gas system 33;
1: the BOG generated during entrucking along pipeline one 1 → entrucking arm 10 → pipeline, 33 → valve, 01 → BOG recuperator 31 → 02 → fuel gas system of valve, 33 path, by entering fuel gas after 10 pipeline of entrucking arm, 31 re-heat to room temperature of BOG recuperator System 33;
2: the BOG that entrucking process generates is along tank car gas phase hose 8 → entrucking arm 10 → pipeline, 33 → valve, 01 → BOG recuperator 31 → valve, 02 → fuel gas system, 33 path, it is laggard to room temperature by another 10 pipeline of entrucking arm, 31 re-heat of BOG recuperator Enter to fuel gas system 33;
3: the BOG that drain process generates divides two-way: a 33 → valve of curb tank car gas phase hose 8 → valve, 12 → pipeline 01 → 02 → fuel gas system of BOG 31 → valve of recuperator, 33 path, is arrived by 8 pipeline of tank car gas phase hose, 31 re-heat of BOG recuperator Fuel gas system 33 is entered after room temperature;Another way is along pipeline 55 → valve, 15 → pipeline, 33 → valve, 01 → BOG recuperator 31 → valve, 02 → fuel gas system, 33 path, the pipeline 55 are immersed pump gas phase hose line, pass through pipeline 55, BOG Fuel gas system 33 is entered after 31 re-heat to room temperature of recuperator;
4: if system pressure occurs more than limit value, the pressure gauge being arranged on pipeline 1 and pipeline 22 can detect real-time number According to, and making safety valve jumping up, the pipeline branch line being connected on safety valve at this time will be connected to EAG recuperator 32, in EAG re-heat The both ends of device 32 are respectively arranged with valve 03 and valve 04, and enter diffusion system 34 eventually by EAG recuperator 32;
It should be noted simultaneously that this programme setting starting security pipeline, is communicated with nitrogen header pipe 7, the nitrogen on pipeline 1 Gas general pipeline's 7 always holds 06 two sides of valve for being formed with two pipeline branch lines and being respectively turned on pipeline one 1 any one, and Valve 09 and valve 11 are respectively arranged on two pipeline branch lines, when device starts and unusual condition occurs, operator can By making device be in safe shape by the way of nitrogen displacement about natural gas system valve, unlatching nitrogen system valve State.
During entrucking, after a tank car is filled, the valve 06 on a wherein pipeline 1 is opened, and close another Valve 06 on one pipeline 1, is filled, and as above alternately fills use, the present embodiment preferably two pipelines 1 are not right Particular number is defined, can according to actual needs to entrucking arm sled 16 in pipeline 1 and pipeline 22 increase, need What is illustrated is that the quantity of pipeline 1 in this programme and pipeline 22 is mutually matched setting.
Secondly, being carried out for Liquid guiding pump sled 17 as described below;
There are two Liquid guiding pumps, respectively Liquid guiding pump 1 and Liquid guiding pump 2 19 for setting in Liquid guiding pump sled 17, in Liquid guiding pump 1 With the pipeline branch line for being provided with connecting pipeline 55 on Liquid guiding pump 2 19, valve 14 and valve are respectively arranged on the pipeline branch line Door 13, while it being provided with pipeline branch line on the arrival end pipeline of on-tube Liquid guiding pump 2 19, which is connected to Liquid guiding pump 2 18, and the outlet end of the Liquid guiding pump 2 18 is connected to pipeline 55, and is provided with valve 20 on the pipeline branch line, needs Bright is extremely provided with valve 15 on pipeline 55, carries out drain through the following steps during drain;
The LNG tank car 9 of more liquid and the entrucking arm 10 on pipeline 22 are connected, the valve 6 on pipeline 22, which is in, closes State opens by-passing valve 41, into Liquid guiding pump sled 17, after the temperature of Liquid guiding pump 1 and Liquid guiding pump 2 18 reaches, to pipeline Slowly boosting, the LNG of certain pressure enter in LNG tank car 9 to be filled, generated during drain BOG in the following manner into Row is collected;
1: pipeline 55 being entered by valve 13 and valve 14, and pipeline 33 is entered by valve 15, into setting in pipe BOG recuperator 31 on road 33 is respectively arranged with valve 01 and valve 02 at the both ends of BOG recuperator 31, when BOG recuperator Fuel gas system 33 is entered after 31 re-heats to room temperature;
2: pipeline 55 being entered by valve 20, and pipeline 33 is entered by valve 15, into being arranged on pipeline 33 BOG recuperator 31 is respectively arranged with valve 01 and valve 02 at the both ends of BOG recuperator 31, when 31 re-heat of BOG recuperator is to often Fuel gas system 33 is entered after temperature;
3: entrucking arm is entered by LNG tank car gas phase hose 8,12 pipeline of valve and prizes BOG recovery line, and is connected to pipeline 33, The BOG recuperator 31 being arranged on pipeline 33 is entered back into, is respectively arranged with valve 01 and valve at the both ends of BOG recuperator 31 02, fuel gas system 33 is entered after 31 re-heat to room temperature of BOG recuperator.
Above scheme prizes block, entrucking arm sled 16 and Liquid guiding pump sled 17 by two sons, realizes entrucking and drain function respectively Can, equipment usage amount is few, and it is easy to operate, and do not used by way of adding gasifier, device LNG section is adequately utilized Pressure after stream realizes filling for LNG, and BOG yield is small, and the consumption of entrucking process liquids is small.
Meanwhile stressing that usual natural gas liquefaction device LNG operating pressure need to be from height for above scheme needs Pressure (4 ~ 5MPa), which is throttled to cryogenic liquid storage facilities design pressure or less and just can enter fluid storage equipment, to be stored, and is more than The design pressure of equipment does not allow access into the fluid storage equipment then;Cryogenic liquid storage facilities routine operating pressure usually exists 0.2MPa or less;LNG enters the condition of fluid storage equipment are as follows: the difference of pressure and fluid storage equipment pressure after LNG throttling > pipe-line system resistance;Pressure is higher than certain value after throttling, and LNG can be flow in storage facilities certainly.
Liquid guiding pump is arranged in this programme: on the one hand, by the raising of pressure after pump, LNG stream is led to ability and is improved, and reduces tank car The time of waiting;On the other hand, due to pressure rise, the LNG after Liquid guiding pump is in supercooled liquid.The LNG of supercooled state is needed first After absorbing external environment heat to saturated liquid, further gasification generates BOG after heat absorption, therefore can to dissolve leaking heat big for this programme, Practical BOG yield is small.According to from pressurization gasifier, a certain amount of LNG need to be consumed, the operating pressure of tank car is made after gasification It is improved, the LNG after this mode is boosted is saturated liquid, is also easy to produce BOG after absorbing external heat.
Immersed pump can be used in this programme Liquid guiding pump, and pump is whole to be immersed in LNG liquid, is in low-temperature condition always, avoids The pre-cooling temperature-fall period of pump, when needing drain, pump can be with quick start, after tank car is full of, termination of pumping;In the process, if hair Raw superpressure or other abnormal conditions are, it can be achieved that chain pump trip.
Embodiment described above only describe the preferred embodiments of the invention, not to model of the invention It encloses and is defined, without departing from the spirit of the design of the present invention, those of ordinary skill in the art are to technical side of the invention The various changes and improvements that case is made should all be fallen into the protection scope that claims of the present invention determines.

Claims (10)

1. a kind of skid-mounted LNG entrucking and liquid guide system, it is characterised in that: prize and connect entrucking arm sled including entrucking arm Liquid guiding pump sled;
Be provided in entrucking arm sled and be connected to the pipeline one of LNG tank car, the pipeline two that is connected to LNG tank car BOG, for managing The pipeline three that road BOG is recycled and the pipeline four for overpressure relief in system, the pipeline one, pipeline two, three and of pipeline Pipeline four is formed for utilizing the pipeline branch line that overbottom pressure realization LNG is filled in system;
It is provided with Liquid guiding pump in the Liquid guiding pump sled, the pipeline five of connection BOG recuperator is provided on the Liquid guiding pump.
2. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: one He of pipeline It is provided with safety valve on pipeline two, which is respectively connected with EAG recuperator.
3. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: on the pipeline one It is provided with valve, safety valve, pressure gauge and entrucking arm.
4. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: the pipeline one exists It is provided with two altogether in entrucking arm sled, and is connected to by pipeline branch line, and be connected on pipeline four.
5. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: on the pipeline two It is provided with valve, safety valve, pressure gauge and entrucking arm.
6. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: the pipeline one, pipe Road two, which is connected to and is formed with pipeline five, generates the pipeline branch line of BOG to pipeline three for collecting entrucking process.
7. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: the Liquid guiding pump sled Interior to be provided with Liquid guiding pump for being connected on the pipeline of LNG tank car, which includes Liquid guiding pump one and Liquid guiding pump two.
8. a kind of skid-mounted LNG entrucking according to claim 7 and liquid guide system, it is characterised in that: the Liquid guiding pump one The pipeline branch line of BOG is generated to pipeline three for collecting drain process with being respectively connected on Liquid guiding pump two.
9. a kind of skid-mounted LNG entrucking according to claim 1 and liquid guide system, it is characterised in that: the Liquid guiding pump sled Liquid guiding pump, valve, safety valve, pressure gauge and temperature sensor are provided on interior pipeline.
10. a kind of skid-mounted LNG entrucking according to claim 9 and liquid guide system, it is characterised in that: the Liquid guiding pump sled Interior safety valve is connected to EAG recuperator.
CN201910678845.9A 2019-07-25 2019-07-25 A kind of skid-mounted LNG entrucking and liquid guide system Pending CN110360444A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910678845.9A CN110360444A (en) 2019-07-25 2019-07-25 A kind of skid-mounted LNG entrucking and liquid guide system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910678845.9A CN110360444A (en) 2019-07-25 2019-07-25 A kind of skid-mounted LNG entrucking and liquid guide system

Publications (1)

Publication Number Publication Date
CN110360444A true CN110360444A (en) 2019-10-22

Family

ID=68222443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910678845.9A Pending CN110360444A (en) 2019-07-25 2019-07-25 A kind of skid-mounted LNG entrucking and liquid guide system

Country Status (1)

Country Link
CN (1) CN110360444A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111237635A (en) * 2020-03-09 2020-06-05 江苏长隆石化装备有限公司 Low-temperature tank car loading and unloading pump skid device
CN114370606A (en) * 2021-12-03 2022-04-19 新地能源工程技术有限公司 Multifunctional LNG loading and unloading device and loading and unloading process

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110097604A (en) * 2010-02-24 2011-08-31 삼성중공업 주식회사 Floating liquefied natural gas charging station
CN204176323U (en) * 2014-09-30 2015-02-25 无锡特汇能源装备有限公司 A kind of LNG low temperature list pump sled
CN204254248U (en) * 2014-11-24 2015-04-08 杭州福斯达实业集团有限公司 LNG entrucking is prized
CN105221924A (en) * 2015-10-28 2016-01-06 连云港杰瑞自动化有限公司 Multi-functional LNG integration handling sledge
CN206459008U (en) * 2016-12-13 2017-09-01 北京燃气绿源达清洁燃料有限公司 Flash recovery device for steam
CN107327699A (en) * 2017-08-12 2017-11-07 连云港市拓普科技发展有限公司 Intelligent integral packaged type LNG unloads sled
CN208779122U (en) * 2018-08-07 2019-04-23 苏州西派格液压科技有限公司 A kind of LNG depot
CN210462445U (en) * 2019-07-25 2020-05-05 合肥万豪能源设备有限责任公司 Skid-mounted LNG loading and liquid guiding system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110097604A (en) * 2010-02-24 2011-08-31 삼성중공업 주식회사 Floating liquefied natural gas charging station
CN204176323U (en) * 2014-09-30 2015-02-25 无锡特汇能源装备有限公司 A kind of LNG low temperature list pump sled
CN204254248U (en) * 2014-11-24 2015-04-08 杭州福斯达实业集团有限公司 LNG entrucking is prized
CN105221924A (en) * 2015-10-28 2016-01-06 连云港杰瑞自动化有限公司 Multi-functional LNG integration handling sledge
CN206459008U (en) * 2016-12-13 2017-09-01 北京燃气绿源达清洁燃料有限公司 Flash recovery device for steam
CN107327699A (en) * 2017-08-12 2017-11-07 连云港市拓普科技发展有限公司 Intelligent integral packaged type LNG unloads sled
CN208779122U (en) * 2018-08-07 2019-04-23 苏州西派格液压科技有限公司 A kind of LNG depot
CN210462445U (en) * 2019-07-25 2020-05-05 合肥万豪能源设备有限责任公司 Skid-mounted LNG loading and liquid guiding system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111237635A (en) * 2020-03-09 2020-06-05 江苏长隆石化装备有限公司 Low-temperature tank car loading and unloading pump skid device
CN114370606A (en) * 2021-12-03 2022-04-19 新地能源工程技术有限公司 Multifunctional LNG loading and unloading device and loading and unloading process

Similar Documents

Publication Publication Date Title
CN102913752B (en) Unloading and liquid adding device for skid-type liquid adding station and unloading and liquid adding method
BRPI0714011A2 (en) system for producing oil and heavier gas fraction from a seabed reservoir, method for producing oil and heavier gas fractions from a seabed reservoir, and, vessel
CN204922500U (en) Liquefied natural gas gasification measurement regulator
CN110360444A (en) A kind of skid-mounted LNG entrucking and liquid guide system
CN205316815U (en) High -efficient liquefaction recovery unit of natural gas
CN104763875B (en) Liquefied natural gas or coal gas unload liquid method
KR20230056561A (en) Vessels including methanol fueling system
CN102913753A (en) Storage and gasification project output system of LNG (Liquefied Natural Gas) receiving terminal as well as method
CN210462445U (en) Skid-mounted LNG loading and liquid guiding system
CN208817083U (en) The lossless fueling station of cryogenic liquid
CN108591814A (en) A kind of liquid carbon dioxide storage tank and its application method
CN206290966U (en) Removable bank base formula LNG loading systems
CN202868303U (en) Storage and gasification engineering output system of liquefied natural gas (LNG) accepting station
CN208222055U (en) A kind of liquid carbon dioxide storage tank
CN201310743Y (en) Underground-liquefied petroleum gas storage tank filling system
CN208620055U (en) A kind of LNG gasification recompression device
CN208457567U (en) The LNG refueling system of low energy consumption with BOG recycling function
CN105508873B (en) A kind of low-temperature (low temperature) vessel vaporizer is from pressure charging system and method
CN207569544U (en) Normal pressure pipe-line system liquid reagent filling apparatus
SU1581958A1 (en) Device for dispensing cryogenic agent
US4204813A (en) LNG Pump anti-slam device
CN205278761U (en) Low temperature medium liquefaction recovery system
CN217816171U (en) LNG gas supply system
CN116045211B (en) Remote large LNG shipping device and shipping method thereof
CN210950778U (en) LNG tank wagon device of unloading

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination