CN110359430A - A kind of Gravity Dam Foundation discharge structure - Google Patents

A kind of Gravity Dam Foundation discharge structure Download PDF

Info

Publication number
CN110359430A
CN110359430A CN201910694723.9A CN201910694723A CN110359430A CN 110359430 A CN110359430 A CN 110359430A CN 201910694723 A CN201910694723 A CN 201910694723A CN 110359430 A CN110359430 A CN 110359430A
Authority
CN
China
Prior art keywords
dam
foundation
vertical drainage
pipe
dam foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910694723.9A
Other languages
Chinese (zh)
Inventor
刘小强
张敬
贺春晖
李金洋
李静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201910694723.9A priority Critical patent/CN110359430A/en
Publication of CN110359430A publication Critical patent/CN110359430A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/08Wall dams
    • E02B7/10Gravity dams, i.e. those in which the weight of the structure prevents overturning
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates

Abstract

The present invention relates to a kind of Gravity Dam Foundation discharge structure and its construction methods, belong to gravity dam field of engineering technology, it includes vertical drainage hole, vertical drainage hole is arranged in the dam foundation, the one end part in vertical drainage hole is on the foundation plane of the dam foundation, it further include vertical drainage pipe, first level drainpipe, the second horizontal drain pipe, vertical drainage pipe, first level drainpipe, the second horizontal drain pipe are arranged in dam body;First level drainpipe is located on the foundation plane of the dam foundation, and vertical drainage pipe one end is connected with vertical drainage hole, and the other end is connected with the second horizontal drain pipe.The discharge structure and its construction method can reduce the setting of gallery in dam body, reduce the requirement to gallery, convenient for constructing and reducing costs, pass through pre-buried vertical drainage pipe, the second horizontal drain pipe, it can be punched to avoid in the concrete dam body poured, to reduce the damage to dam body, reinforcing bar, cooling water pipe and monitoring instrument etc., it is also more convenient construction, saves the duration.

Description

A kind of Gravity Dam Foundation discharge structure
Technical field
The present invention relates to a kind of Gravity Dam Foundation discharge structure and its construction methods, belong to gravity dam field of engineering technology.
Background technique
In order to guarantee the safety of gravity dam, need to discharge the interior infiltration of the dam foundation.The interior infiltration of the dam foundation passes through in the dam foundation It is middle that main drainage hole is set, assisted drainage hole is set in dam body, the interior infiltration of the dam foundation is discharged along main drainage hole, assisted drainage hole. Currently, the form of construction work of main drainage hole, assisted drainage hole are as follows: the vertical and horizontal gallery of setting is first reserved in dam body, to dam body dam After the completion of base consolidation grouting, grout curtain, then to dam body, Dam Foundation Rock brill assisted drainage hole, main drainage hole, operation in gallery After infiltration can drain into gallery internal drainage ditch etc. by main drainage hole, assisted drainage in phase Dam Foundation Rock, then drain into outside dam.This side Formula in dam body firstly the need of being arranged gallery, and gallery cross dimensions is to meet drilling etc. to need certain altitude, width, inside dam body Aperture can deteriorate dam body local stress condition, therefore need to improve gallery and nearby concrete strength and lay the measures such as reinforcing bar, can be because Reinforcing bar increases the duration for storehouse etc., also will increase certain construction investment;Secondly later period dam body inner concrete bore drainage hole when, meeting The integrality for destroying dam concrete and reinforcing bar, may perhaps destroy the temperature control measures such as cooling water pipe in dam or may destroy The monitoring facilities such as dam foundation crack gauge, damage dam body, it is seen then that this sample loading mode higher cost, and very inconvenient construction, to dam There are also damages for body.
Summary of the invention
Technical problem to be solved by the invention is to provide one kind, cost is relatively low, facilitates construction, lesser to dam body damage Gravity Dam Foundation discharge structure.
The technical solution adopted by the present invention to solve the technical problems is: a kind of Gravity Dam Foundation discharge structure, including perpendicular To drainage hole, vertical drainage hole is arranged in the dam foundation, and the one end part in vertical drainage hole further includes erecting on the foundation plane of the dam foundation To drainpipe, first level drainpipe, the second horizontal drain pipe, vertical drainage pipe, first level drainpipe, the second horizontal drainage Pipe is arranged in dam body;
First level drainpipe is located on the foundation plane of the dam foundation, and the outlet of first level drainpipe is located at downstream dam site Outside, vertical drainage pipe one end are connected with vertical drainage hole, and the other end is connected with the second horizontal drain pipe, the second horizontal row The outlet of water pipe is located at the outside of downstream dam site.
Further, first level drainpipe is mutually staggered with the consolidation grouting hole being arranged on the dam foundation.
Further, first level drainpipe is fixed on the foundation plane of the dam foundation by dowel.
Further, the outer surface of vertical drainage pipe, first level drainpipe, the second horizontal drain pipe is provided with guarantor Sheath.
Further, the height of vertical drainage pipe is 1-3m.
In addition, the present invention also technical problems to be solved be to provide it is a kind of cost is relatively low, facilitate construction, to dam body damage compared with The construction method of small Gravity Dam Foundation discharge structure.
The construction method of Gravity Dam Foundation discharge structure, comprising the following steps:
A, first level drainpipe is laid on the foundation plane of the dam foundation, the outlet of first level drainpipe is located at downstream dam site Outside;
B, vertical drainage hole is bored downwards from the foundation plane of the dam foundation;
C, pre-buried vertical drainage pipe, the second horizontal drain pipe, make one end of vertical drainage pipe be connected with vertical drainage hole, The other end is connected with the second horizontal drain pipe, and the outlet of the second horizontal drain pipe is located at the outside of downstream dam site;
D, the casting concrete dam body on the foundation plane of the dam foundation, vertical drainage pipe, first level drainpipe, the second horizontal row Water pipe is arranged in dam body.
Preferably, in step a, the first level drainpipe of laying and the consolidation grouting hole being arranged on the dam foundation are mutually wrong It opens.
Preferably, in step a, the first level drainpipe of laying is fixed on the foundation plane of the dam foundation by dowel, and Matcoveredn is set on first level drainpipe.
Preferably, in step c, pre-buried vertical drainage pipe, the second horizontal drain pipe outer surface be provided with protective layer.
Preferably, in step c, the height of vertical drainage pipe is 1-3m.
The beneficial effects of the present invention are: the discharge structure construction process of the dam foundation of the present invention are as follows: pour coagulation on foundation plane First level drainpipe is first laid with before earth dam body on the foundation plane of the dam foundation, the outlet of first level drainpipe is located at downstream dam site Outside;Then vertical drainage hole is bored downwards from the foundation plane of the dam foundation;Subsequently pre-buried vertical drainage pipe, the second horizontal drainage Pipe, makes one end of vertical drainage pipe be connected with vertical drainage hole, the other end is connected with the second horizontal drain pipe, and the second water The outlet of flat raft water pipe is located at the outside of downstream dam site;The finally casting concrete dam body on the foundation plane of the dam foundation makes vertically to arrange Water pipe, first level drainpipe, the second horizontal drain pipe are arranged in dam body.The surface infiltration of the dam foundation is arranged by first level Water pipe is discharged outside dam body, and successively vertically dam body is discharged in drainage hole, vertical drainage pipe, the second horizontal drain pipe for the interior infiltration of the dam foundation Outside, it is seen then that discharge structure and its construction method of the invention can reduce the setting of gallery in dam body, and gallery is wanted in reduction It asks, reduces the dosage of reinforcing bar, convenient for constructing and reducing costs, the destruction to dam body local stress is also reduced, by pre- Vertical drainage pipe, the second horizontal drain pipe are buried, can be punched to avoid in the concrete dam body poured, thus reduction pair The damage of dam body, reinforcing bar, cooling water pipe and monitoring instrument etc. is also more convenient construction, saves the duration.
Detailed description of the invention
Fig. 1 is the cross-sectional view along water (flow) direction gravity dam;
Fig. 2 is the cross-sectional view along Dam Base Surface;
Fig. 3 is the cross-sectional view along the second horizontal drain pipe;
Components, position and number in figure: the dam foundation 1, dam body 2, vertical drainage hole 3, vertical drainage pipe 4, first level row Water pipe 5, the second horizontal drain pipe 6, downstream dam site 7, consolidation grouting hole 8, dowel 9.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings.
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of Gravity Dam Foundation discharge structure, including vertical drainage hole 3, vertical drainage hole 3 It is arranged in the dam foundation 1, the one end part in vertical drainage hole 3 is on the foundation plane of the dam foundation 1, further including vertical drainage pipe 4, the first water Flat raft water pipe 5, the second horizontal drain pipe 6, vertical drainage pipe 4, first level drainpipe 5, the second horizontal drain pipe 6 are arranged at In dam body 2;
First level drainpipe 5 is located on the foundation plane of the dam foundation 1, and the outlet of first level drainpipe 5 is located at downstream dam The outside of location 7,4 one end of vertical drainage pipe are connected with vertical drainage hole 3, and the other end is connected with the second horizontal drain pipe 6, the The outlet of two horizontal drain pipes 6 is located at the outside of downstream dam site 7.The surface infiltration of the dam foundation 1 is discharged by first level drainpipe 5 Outside dam body 2, successively vertically dam body 2 is discharged in drainage hole 3, vertical drainage pipe 4, the second horizontal drain pipe 6 for the interior infiltration of the dam foundation 1 Outside.
The construction method of above-mentioned Gravity Dam Foundation discharge structure, comprising the following steps:
A, first level drainpipe 5 is laid on the foundation plane of the dam foundation 1, the outlet of first level drainpipe 5 is located at downstream The outside of dam site 7;
B, vertical drainage hole 3 is bored downwards from the foundation plane of the dam foundation 1, until 1 deep rock mass of the dam foundation;
C, pre-buried vertical drainage pipe 4, the second horizontal drain pipe 6, make one end of vertical drainage pipe 4 and 3 phase of vertical drainage hole Connection, the other end are connected with the second horizontal drain pipe 6, and the outlet of the second horizontal drain pipe 6 is located at the outer of downstream dam site 7 Side;
D, the casting concrete dam body 2 on the foundation plane of the dam foundation 1, vertical drainage pipe 4, first level drainpipe 5, the second water Flat raft water pipe 6 is arranged in dam body 2.
As it can be seen that discharge structure and its construction method of the invention can reduce the setting of gallery in dam body 2, reduce to gallery Requirement, reduce the dosage of reinforcing bar, convenient for constructing and reducing costs, also reduce the destruction to 2 local stress of dam body, lead to Pre-buried vertical drainage pipe 4, the second horizontal drain pipe 6 are crossed, can be punched to avoid in the concrete dam body 2 poured, from And the damage to dam body 2, reinforcing bar, cooling water pipe and monitoring instrument etc. is reduced, it is also more convenient construction, saves the duration.
Specifically, before casting concrete dam body 2, need to boring consolidation grouting hole 8 on the dam foundation 1, the later period to the dam foundation 1 into Row is reinforced, and the damage or blocking generated when in order to reduce strengthening construction to vertical drainage hole 3, first level drainpipe 5 should be with The consolidation grouting hole 8 being arranged on the dam foundation 1 mutually staggers.For example, again as shown in Fig. 2, consolidation fills on the foundation plane of the dam foundation 1 Starch hole 8 use square arrangement, first level drainpipe 5 accordingly use square arrangement, only rectangular consolidation grouting hole 8 with it is rectangular First level drainpipe 5 mutually stagger.Meanwhile in order to prevent casting concrete dam body 2 when cause first level drainpipe 5 move Position, first level drainpipe 5 are fixed on the foundation plane of the dam foundation 1 by dowel 9.
When in order to avoid casting concrete dam body 2, cement grout blocks vertical drainage pipe 4, first level drainpipe 5 and the Two horizontal drain pipes 6 are provided with guarantor in the outer surface of vertical drainage pipe 4, first level drainpipe 5, the second horizontal drain pipe 6 Sheath, protective layer preferably use geotextiles at low cost, that is to say and are drained vertical drainage pipe 4, first level by geotextiles Pipe 5, the second horizontal drain pipe 6 wrap, especially joint area, and in addition to being wrapped with geotextiles, galvanized wire progress also can be used It ties up.
By being obtained in a large number of experiments and practice, in order to which more swimmingly the interior infiltration of the dam foundation 1 is successively vertically drained Hole 3, vertical drainage pipe 4, the second horizontal drain pipe 6 are discharged outside dam body 2, and the height of vertical drainage pipe 4 is 1-3m.

Claims (10)

1. a kind of Gravity Dam Foundation discharge structure, including vertical drainage hole (3), vertical drainage hole (3) are arranged in the dam foundation (1), The one end part in vertical drainage hole (3) is on the foundation plane of the dam foundation (1), it is characterised in that: further includes vertical drainage pipe (4), One horizontal drain pipe (5), the second horizontal drain pipe (6), vertical drainage pipe (4), first level drainpipe (5), the second horizontal row Water pipe (6) is arranged in dam body (2);
First level drainpipe (5) is located on the foundation plane of the dam foundation (1), and the outlet of first level drainpipe (5) is located at downstream The outside of dam site (7), vertical drainage pipe (4) one end are connected with vertical drainage hole (3), the other end and the second horizontal drain pipe (6) it is connected, the outlet of the second horizontal drain pipe (6) is located at the outside of downstream dam site (7).
2. a kind of Gravity Dam Foundation discharge structure as described in claim 1, it is characterised in that: first level drainpipe (5) with The consolidation grouting hole (8) being arranged on the dam foundation (1) mutually staggers.
3. a kind of Gravity Dam Foundation discharge structure as described in claim 1, it is characterised in that: first level drainpipe (5) is logical Dowel (9) is crossed to be fixed on the foundation plane of the dam foundation (1).
4. a kind of Gravity Dam Foundation discharge structure as described in claim 1, it is characterised in that: vertical drainage pipe (4), the first water Flat raft water pipe (5), the second horizontal drain pipe (6) outer surface be provided with protective layer.
5. a kind of Gravity Dam Foundation discharge structure as described in Claims 1-4 any one, it is characterised in that: vertical drainage The height for managing (4) is 1-3m.
6. the construction method of Gravity Dam Foundation discharge structure, it is characterised in that: the following steps are included:
A, first level drainpipe (5) are laid on the foundation plane of the dam foundation (1), under the outlet of first level drainpipe (5) is located at Swim the outside of dam site (7);
B, vertical drainage hole (3) are bored downwards from the foundation plane of the dam foundation (1);
C, pre-buried vertical drainage pipe (4), the second horizontal drain pipe (6) make one end and vertical drainage hole of vertical drainage pipe (4) (3) it is connected, the other end is connected with the second horizontal drain pipe (6), and the outlet of the second horizontal drain pipe (6) is located at downstream dam The outside of location (7);
D, casting concrete dam body (2) on the foundation plane of the dam foundation (1), vertical drainage pipe (4), first level drainpipe (5), Two horizontal drain pipes (6) are arranged in dam body (2).
7. the construction method of Gravity Dam Foundation discharge structure as claimed in claim 6, it is characterised in that: in step a, be laid with First level drainpipe (5) mutually staggered with consolidation grouting hole (8) on the dam foundation (1) is arranged.
8. the construction method of Gravity Dam Foundation discharge structure as claimed in claim 6, it is characterised in that: in step a, be laid with First level drainpipe (5) be fixed on the foundation plane of the dam foundation (1) by dowel (9), and set on first level drainpipe (5) It is equipped with protective layer.
9. the construction method of Gravity Dam Foundation discharge structure as claimed in claim 6, it is characterised in that: pre-buried in step c Vertical drainage pipe (4), the second horizontal drain pipe (6) outer surface be provided with protective layer.
10. the construction method of Gravity Dam Foundation discharge structure as claimed in claim 6, it is characterised in that: in step c, erect It is 1-3m to the height of drainpipe (4).
CN201910694723.9A 2019-07-30 2019-07-30 A kind of Gravity Dam Foundation discharge structure Pending CN110359430A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910694723.9A CN110359430A (en) 2019-07-30 2019-07-30 A kind of Gravity Dam Foundation discharge structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910694723.9A CN110359430A (en) 2019-07-30 2019-07-30 A kind of Gravity Dam Foundation discharge structure

Publications (1)

Publication Number Publication Date
CN110359430A true CN110359430A (en) 2019-10-22

Family

ID=68222216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910694723.9A Pending CN110359430A (en) 2019-07-30 2019-07-30 A kind of Gravity Dam Foundation discharge structure

Country Status (1)

Country Link
CN (1) CN110359430A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997080A (en) * 2020-09-09 2020-11-27 郭云美 Gravity dam foundation drainage structure and implementation method thereof
CN112695792A (en) * 2020-12-22 2021-04-23 中国水利水电第三工程局有限公司 Concrete dam section foundation pit drainage and dam foundation pouring method thereof

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1067465A (en) * 1992-04-30 1992-12-30 宁夏回族自治区水利学会 The distribution method of dam body drainage pipe and pipe
JP2007138564A (en) * 2005-11-18 2007-06-07 Kyowa Harmotech Kk Drain structure and construction method of drain structure
CN101250864A (en) * 2008-04-03 2008-08-27 中国水利水电科学研究院 Drainage system in sluicing-siltation dam and uses thereof
CN101429759A (en) * 2008-12-12 2009-05-13 中国葛洲坝集团股份有限公司 Inverse drainage processing method in high concrete panel rock-fill dam construction period
CN101942820A (en) * 2010-10-09 2011-01-12 中国水电顾问集团成都勘测设计研究院 Impervious structure of arch dam and construction method thereof
CN203741787U (en) * 2013-12-20 2014-07-30 中国水电顾问集团贵阳勘测设计研究院有限公司 Dam body drainage structure favorable for roller-compacted concrete rapid construction
US20160201281A1 (en) * 2014-02-11 2016-07-14 Scott Roy Hydrostatic Fluid Containment System
CN206034382U (en) * 2016-09-18 2017-03-22 中国电建集团成都勘测设计研究院有限公司 Cross a river traffic dam
CN106917409A (en) * 2017-03-27 2017-07-04 中国水利水电第四工程局有限公司 A kind of rock lid weight consolidation grouting construction method
CN207392152U (en) * 2017-09-27 2018-05-22 中国电建集团华东勘测设计研究院有限公司 Concrete face rockfill dam dam body water draining structure
CN108265683A (en) * 2018-03-13 2018-07-10 中水北方勘测设计研究有限责任公司 The gallery arrangement of RCC dam
CN210459133U (en) * 2019-07-30 2020-05-05 中国电建集团成都勘测设计研究院有限公司 Gravity dam foundation drainage structures
CN113216246A (en) * 2021-04-21 2021-08-06 中国电建集团华东勘测设计研究院有限公司 Water-immersed retaining wall and construction method thereof

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1067465A (en) * 1992-04-30 1992-12-30 宁夏回族自治区水利学会 The distribution method of dam body drainage pipe and pipe
JP2007138564A (en) * 2005-11-18 2007-06-07 Kyowa Harmotech Kk Drain structure and construction method of drain structure
CN101250864A (en) * 2008-04-03 2008-08-27 中国水利水电科学研究院 Drainage system in sluicing-siltation dam and uses thereof
CN101429759A (en) * 2008-12-12 2009-05-13 中国葛洲坝集团股份有限公司 Inverse drainage processing method in high concrete panel rock-fill dam construction period
CN101942820A (en) * 2010-10-09 2011-01-12 中国水电顾问集团成都勘测设计研究院 Impervious structure of arch dam and construction method thereof
CN203741787U (en) * 2013-12-20 2014-07-30 中国水电顾问集团贵阳勘测设计研究院有限公司 Dam body drainage structure favorable for roller-compacted concrete rapid construction
US20160201281A1 (en) * 2014-02-11 2016-07-14 Scott Roy Hydrostatic Fluid Containment System
CN206034382U (en) * 2016-09-18 2017-03-22 中国电建集团成都勘测设计研究院有限公司 Cross a river traffic dam
CN106917409A (en) * 2017-03-27 2017-07-04 中国水利水电第四工程局有限公司 A kind of rock lid weight consolidation grouting construction method
CN207392152U (en) * 2017-09-27 2018-05-22 中国电建集团华东勘测设计研究院有限公司 Concrete face rockfill dam dam body water draining structure
CN108265683A (en) * 2018-03-13 2018-07-10 中水北方勘测设计研究有限责任公司 The gallery arrangement of RCC dam
CN210459133U (en) * 2019-07-30 2020-05-05 中国电建集团成都勘测设计研究院有限公司 Gravity dam foundation drainage structures
CN113216246A (en) * 2021-04-21 2021-08-06 中国电建集团华东勘测设计研究院有限公司 Water-immersed retaining wall and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭静;杨林;: "毛细透排水管施工技术在混凝土坝基中的应用", 广东水利水电, no. 05, 20 May 2018 (2018-05-20), pages 57 - 59 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997080A (en) * 2020-09-09 2020-11-27 郭云美 Gravity dam foundation drainage structure and implementation method thereof
CN112695792A (en) * 2020-12-22 2021-04-23 中国水利水电第三工程局有限公司 Concrete dam section foundation pit drainage and dam foundation pouring method thereof
CN112695792B (en) * 2020-12-22 2021-10-12 中国水利水电第三工程局有限公司 Concrete dam section foundation pit drainage and dam foundation pouring method thereof

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN109098733B (en) Rapid grouting reinforcement method for large-section tunnel in fracture zone rock stratum
CN104746517B (en) A kind of suspension roof support system of total length below artesian head
CN107542108A (en) A kind of reverse construction method of building basement structure
CN104762955B (en) A kind of Belled Pile construction method based on freezing process
CN107724436B (en) Post-cast strip seepage-proofing construction method
CN108203983A (en) A kind of deep foundation pit supporting structure and method
CN106088094A (en) High mountain strid Method of Arch Dam Foundation segmentation stage grouting method
CN104847365B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method
CN108612110A (en) A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting
CN105926682A (en) Basement baseplate post-cast strip construction method with pressure bearing water and higher water pressure
CN110359430A (en) A kind of Gravity Dam Foundation discharge structure
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN109629845A (en) Concrete structure seam areas leakage treatment device and its construction method
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN201538975U (en) Seepage-proofing joint of underground continuous wall
CN109826635B (en) Construction method for reinforcing shield receiving space peripheral soil body constructed by subsurface excavation method
CN107100206A (en) A kind of prevention and controls of basement leakage
CN104963693B (en) Rectangular parallel push pipe connection channel construction method
CN107869351B (en) A kind of method of high narrow type large size solution cavity Cavity treatment security protection
WO2023202455A1 (en) Single-layer well wall having jointed water-stop structure and grouting system, and construction method therefor
CN104480905B (en) A kind of concrete face rockfill dam upstream face structure preventing face slab dislocation and construction method
CN210459133U (en) Gravity dam foundation drainage structures
KR101974826B1 (en) The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination