CN110329931B - Large-scale tubular pile lifts by crane equipment - Google Patents

Large-scale tubular pile lifts by crane equipment Download PDF

Info

Publication number
CN110329931B
CN110329931B CN201910644476.1A CN201910644476A CN110329931B CN 110329931 B CN110329931 B CN 110329931B CN 201910644476 A CN201910644476 A CN 201910644476A CN 110329931 B CN110329931 B CN 110329931B
Authority
CN
China
Prior art keywords
ring
pile
chute
tubular pile
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201910644476.1A
Other languages
Chinese (zh)
Other versions
CN110329931A (en
Inventor
王作文
刘伯涛
孟晓平
王梦迪
罗瑾
胡飞龙
吴宇航
罗利平
张沛
唐兵
齐志国
袁圣林
杨昆
马洋
王清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Petroleum University
Original Assignee
Southwest Petroleum University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Petroleum University filed Critical Southwest Petroleum University
Priority to CN201910644476.1A priority Critical patent/CN110329931B/en
Publication of CN110329931A publication Critical patent/CN110329931A/en
Application granted granted Critical
Publication of CN110329931B publication Critical patent/CN110329931B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C25/00Cranes not provided for in groups B66C17/00 - B66C23/00

Abstract

The invention relates to large-scale tubular pile hoisting equipment which comprises a pile feeding platform, an arc rail, a base, a waist ring, a bottom ring, a hoisting rail, a first hoisting machine, a second hoisting machine and a hydraulic cylinder, wherein the pile feeding platform is arranged on the upper surface of the pile feeding platform; according to the scheme, the tubular pile feeding work is completed through the pile feeding platform, namely the tubular pile is pushed into the waist ring and the bottom ring to complete the basic fixing of the tubular pile; however, the position of a waist ring of the tubular pile is driven by the first winch to turn over as the original point, so that the tubular pile is erected, finally the tubular pile is erected by the second winch, and finally the whole base is designed on the platform truck to move if horizontal displacement is needed.

Description

Large-scale tubular pile lifts by crane equipment
Technical Field
The invention relates to the technical field of civil engineering construction, in particular to large-scale tubular pile hoisting equipment.
Background
At the end of the last 60 th century, the hogftai bridge factory of the Ministry of railways began to produce pretensioned prestressed concrete pipe piles (abbreviated as PC pipe piles), which were mainly used for the foundation construction of railway bridge engineering; the post-tensioning prestressed concrete pipe pile was developed and produced in the 70 s. Since the 70 s, especially in the construction of Baoshan steel works in Shanghai, a large number of steel pipe piles introduced in Japan were used, which not only had high cost but also had poor durability. In order to meet the requirements of port construction development, a prestressed high-strength concrete tubular pile (PHC tubular pile for short) production line is introduced from Japan in the three navigation departments of Ministry of communications in 1987, the main specification of the PHC tubular pile is from 600mm to 1000mm of vertebra, in the later 80 years, Ningbo Zhedong cement products Limited company cooperates with related scientific research institutions, and a pretensioning method prestressed concrete thin-wall tubular pile (PTC tubular pile for short) is developed by reforming the PC tubular pile according to the characteristics of soft and weak silt geology in coastal areas of China, and the main specification of the PTC tubular pile is from 300mm to 600mm of vertebra. In 1989 to 1992, the original national building materials institute of Suzhou concrete cement products and Panyu yuyu City Qiaofeng cement products Limited company independently develop a localization prestressed high-strength concrete pipe pile by digestion and absorption of an introduced pipe pile production line according to the actual conditions of China, and the achievement is listed as a national key popularization project by the original construction department in 1993.
In the transportation lift by crane in-process tubular pile generally need design two fulcrums, its hoisting point need accord with the mechanics requirement, and the tubular pile piles up to be stocked and need use the cushion, and the tubular pile should be avoided vibrating, offend in lifting by crane the transportation, and present traditional tubular pile lifts by crane generally accomplishes its shortcoming lie in through the crane:
(1) for part of construction sites, the crane has a large size and large approach difficulty;
(2) in the hoisting process of the crane, a plurality of persons are required to cooperate, so that vibration and collision during hoisting are avoided, and a large potential safety hazard exists;
(3) the tubular pile can not be lifted vertically in the lifting and transporting process, so that the tubular pile can only be transversely placed, other buildings are easily touched in the transporting process, and collision with surrounding buildings is caused.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide large tubular pile hoisting equipment, the equipment is miniaturized in size and convenient to enter a field, manual assistance is not needed in the hoisting process, and vertical hoisting can be realized, so that the space in the hoisting process is reduced, and collision is avoided.
The purpose of the invention is realized by the following technical scheme:
a large-scale tubular pile hoisting device comprises an upper pile platform, an arc rail, a base, a waist ring, a bottom ring, a hoisting rail, a first hoisting machine, a second hoisting machine and a hydraulic cylinder;
the hydraulic cylinder is arranged at one end of the upper pile platform, the other end of the upper pile platform is in butt joint with the base, and the hydraulic cylinder is used for pushing the tubular pile to the base;
the base is composed of two cross beams, each of the two cross beams is provided with an arc rail and a hanging rail, the opposite sides of the two arc rails are respectively provided with a section of first sliding chute, and the opposite sides of the two hanging rails are respectively provided with a section of second sliding chute along the axial direction;
a first U-shaped sliding groove and a second U-shaped sliding groove are symmetrically formed in the inner sides of the two cross beams respectively, and the first U-shaped sliding grooves are close to the end of the upper pile platform;
the head end of the first sliding chute is in butt joint with the first U-shaped sliding chute, the tail end of the first sliding chute is communicated with the second sliding chute, and the bottom end of the second sliding chute is in butt joint with the second U-shaped sliding chute;
the waist ring is erected between the two first U-shaped sliding chutes, the bottom ring is erected between the two second U-shaped sliding chutes, and the outer side of the bottom ring is sealed;
the first winch is fixed at the tops of the two arc rails and used for driving the waist ring to move to the second chute along the first chute;
the second winch is fixed at the tops of the two hanging rails and used for driving the bottom ring and the waist ring to be lifted to the top from the bottom of the second sliding groove.
This scheme is used for carrying out the tubular pile material loading through constructing an upper pile platform, when needing to lift by crane, carry the tubular pile to the upper pile platform, push away it to the base by hydraulic cylinder, make one section of tubular pile get into waist ring at first, then reentrant end ring, it is it until tubular pile tip and end ring bottom butt do, first winch work this moment, rise along first spout through cable wire drive waist ring, and end ring then uses second U-shaped spout to rotate as the initial point, thereby accomplish the flow of standing of tubular pile, accomplish the first volume of port after and raise the cable wire between machine and the waist ring, then hoist and mount waist ring and end ring by the second winch, make waist ring and end ring rise along the second spout, thereby accomplish the work of lifting by crane of tubular pile.
Furthermore, the upper pile platform comprises two symmetrically arranged horizontal platforms, and opposite sides of the two horizontal platforms are respectively arranged into slopes;
the slope stretches out place side water platform side, the slope below evenly installed is a plurality of the curved surface roller, the curved surface roller of two horizontal platforms incline in opposite directions are the V-arrangement each other and distribute, are about to place the tubular pile in the V-arrangement inslot and contact with the curved surface roller to make hydraulic cylinder can promote the tubular pile easily and remove.
Furthermore, the two horizontal platforms are poured on the construction ground by adopting concrete;
or the metal plates are used for building and are arranged on the construction ground during use, and the connecting rods are used for fixing the space between the two metal plates so as to be suitable for the tubular piles with different diameters.
Above two kinds of modes respectively have good and bad, and concrete placement formula stable in structure, but unable secondary operation, but the form of using the metal sheet to build then secondary operation can be used for transport many times, and the size is adjustable.
Further, the interval between first U-shaped spout and the second U-shaped spout equals the half of tubular pile height, first U-shaped spout is located crossbeam tip, the purpose of this design is to guarantee that tubular pile removes the in-process, and one end gets into the waist ring earlier, and can not incline after breaking away from the pile platform, still keeps the level so that get into the intra-annular of ending.
Furthermore, a plurality of balls are uniformly arranged on the inner ring of the waist ring, and the friction force applied to the tubular pile in the moving process can be reduced due to the advantage of the balls.
Furthermore, the two sides of the waist ring are connected with the middle part of the bottom ring through steel cables with equal length, and the steel cables with equal length are used, so that the stress in the lifting process is distributed in a triangular shape, and good stability is ensured.
Further, the central angle of the circular arc rail is 180 degrees, and the central angle of the first sliding groove is 90 degrees.
Furthermore, the first winch is connected with the waist ring through an electric buckle, when the waist ring moves to the tail end of the first sliding groove, the electric buckle is unfastened, and meanwhile, the second winch drives the bottom ring and the waist ring to ascend.
Further, base bottom fixed mounting is on ground, perhaps the base is provided with drive division, drive division is the car, sets up automobile drive's advantage and can transport it to the construction point after lifting by crane its tubular pile.
The invention has the beneficial effects that: according to the scheme, the three steps in the lifting process of the tubular pile are completed by designing a corresponding structure, the loading work of the tubular pile is completed through the pile loading platform, namely, the tubular pile is pushed into the waist ring and the bottom ring to complete the basic fixing of the tubular pile; however, the position of a waist ring of the tubular pile is driven by the first winch to turn over as the original point, so that the tubular pile is erected, finally the tubular pile is erected by the second winch, and finally the whole base is designed on the platform truck to move if horizontal displacement is needed.
Drawings
FIG. 1 is an outside view of the present invention;
FIG. 2 is a schematic inside view of the present invention;
FIG. 3 is a schematic end view of the present invention;
FIG. 4 is a schematic view of the pile driving platform structure of the present invention;
FIG. 5 is a schematic end view of a lumbar/bottom ring of the present invention;
FIG. 6 is a side view of the lumbar ring of the present invention;
FIG. 7 is a side view of the bottom ring of the present invention;
FIG. 8 is a schematic view of the present invention in a suspended state.
Detailed Description
The technical solution of the present invention is further described in detail with reference to the following specific examples, but the scope of the present invention is not limited to the following.
As shown in fig. 1 to 3, a large tubular pile hoisting apparatus includes an upper pile platform 100, an arc rail 200, a base 300, a waist ring 400, a bottom ring 500, a hoisting rail 600, a first hoist 700, a second hoist 800 and a hydraulic cylinder 900.
As a preferred example, the upper pile platform 100 includes two embodiments, two horizontal platforms 101 are cast on the construction ground by concrete; or the construction is carried out by adopting metal plates, the construction is carried out on the construction ground when the construction is used, the distance between the two metal plates is fixed by adopting connecting rods so as to be suitable for the tubular piles with different diameters, except for different construction schemes, the main body of the construction is basically consistent, the construction comprises two horizontal platforms 101 which are symmetrically arranged, and the opposite sides of the two horizontal platforms 101 are respectively arranged into slopes 102; the slope 102 extends out of the side water platform 101, a plurality of curved rollers 103 are uniformly arranged below the slope 102, the curved rollers 103 on the opposite sides of the two horizontal platforms 101 are symmetrically distributed in a V shape, the structure of the slope is shown in figure 4, and as can be seen from figure 4, the slope 102 completely covers the upper ends of the curved rollers 103, so that a tubular pile can enter between the curved rollers 103 on the two sides from the horizontal platform 101 along the slope 102, and the tubular pile is prevented from directly impacting the upper parts of the curved rollers 103 to cause deformation in the rolling process.
In order to complete the driving of the pipe pile along the curved roller, one end of the pile feeding platform 100 is provided with a hydraulic cylinder 900, the other end of the pile feeding platform is butted with the base 300, the hydraulic cylinder 900 is used for pushing the pipe pile towards the base 300, wherein the butting of the pile feeding platform 100 and the base 300 is only position butting, and is not fixed after the butting, so that the base 100 can be carried or moved.
As shown in fig. 3, the base 300 is composed of two beams, and the two beams are respectively butted against the ends of the two horizontal stages 101, so that a space is reserved between the two beams. The two cross beams are respectively provided with an arc rail 200 and a hanging rail 600, the installation structure is shown in fig. 1, the central angle of the arc rail 200 is 180 degrees, the bottom of the hanging rail 600 is fixed at the center of the arc rail 200, the opposite sides of the two arc rails 200 are respectively provided with a section of first sliding groove 201, the central angle of the first sliding groove 201 is 90 degrees, the opposite sides of the two hanging rails 600 are respectively provided with a section of second sliding groove 601 along the axial direction, and the structure can be referred to fig. 2.
The inner sides of the two cross beams are respectively and symmetrically provided with a first U-shaped sliding groove 301 and a second U-shaped sliding groove 302, the first U-shaped sliding groove 301 is close to the end of the upper pile platform 100 and meets the requirement that the starting point of the first U-shaped sliding groove 301 is in butt joint with the starting point of the first sliding groove 201, and the second U-shaped sliding groove 302 is located at the circle center of the arc rail 200 and is in butt joint with the second U-shaped sliding groove 302.
A waist ring 400 is disposed between the two first U-shaped sliding slots 301, a bottom ring 500 is disposed between the two second U-shaped sliding slots 302, and the outer side of the bottom ring 500 is sealed, which can be seen from fig. 3.
The bottom ring 500 of the waist ring 400 is basically consistent in structure and is composed of two semicircular rings, the difference is that the bottom ring 500 is sealed, the pipe pile is prevented from being separated in the vertical hoisting process, and the structure can be shown in fig. 6 and 7.
In order to make the structure more clear, the embodiment is described by using the structure of the waist ring 400, as shown in fig. 5, the waist ring 400 includes two semicircular rings 401, the side surfaces of the two semicircular rings 401 are respectively provided with a splicing plate 403, the splicing plate 403 is provided with a screw hole and a through hole, wherein the screw hole is used for completing the splicing of the two semicircular rings 401 through a bolt 404, the through hole is used for fixing a steel cable in the hoisting process, the middle parts of the outer sides of the two semicircular rings 401 are respectively fixed with a rotating shaft 402, and the two rotating shafts 402 are erected in the first U-shaped sliding groove 301.
The mechanical part in this embodiment includes a driving part including a first winding engine 700 and a second winding engine 800. The first winch 700 is fixed on the tops of the two arc rails 200 and used for driving the waist ring 400 to move to the second sliding groove 601 along the first sliding groove 201; the second winch 800 is fixed on the top of the two hanging rails 600 and is used for driving the bottom ring 500 and the waist ring 400 to be lifted to the top from the bottom of the second chute 601.
As a preferred embodiment, the distance between the first U-shaped chute 301 and the second U-shaped chute 302 is equal to one half of the height of the tubular pile, the first U-shaped chute 301 is located at the end of the cross beam, the inner ring of the waist ring 400 is uniformly provided with a plurality of balls 405, both sides of the waist ring 400 are connected with the middle part of the bottom ring 500 through equal length steel cables, and the hoisting process can be referred to fig. 8.
As a preferred embodiment, the first winding machine 700 is electrically connected to the waist ring 400, and when the waist ring 400 moves to the end of the first sliding groove 201, the electric buckle is released, and the second winding machine 800 drives the bottom ring 500 and the waist ring 400 to ascend.
As a preferred embodiment, the bottom of the base 300 is fixedly installed on the ground, or the base 300 is provided with a driving part, and the driving part is a car.
The foregoing is merely a preferred embodiment of the invention, it is to be understood that the invention is not limited to the forms disclosed herein, but is not intended to be exhaustive or to limit the invention to other embodiments, and to various other combinations, modifications, and environments and may be modified within the scope of the inventive concept as described herein by the teachings or the skill or knowledge of the relevant art. And that modifications and variations may be effected by those skilled in the art without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (9)

1. The large tubular pile hoisting equipment is characterized by comprising an upper pile platform (100), an arc rail (200), a base (300), a waist ring (400), a bottom ring (500), a hoisting rail (600), a first hoisting machine (700), a second hoisting machine (800) and a hydraulic cylinder (900);
one end of the upper pile platform (100) is provided with the hydraulic cylinder (900), the other end of the upper pile platform is in butt joint with the base (300), and the hydraulic cylinder (900) is used for pushing the tubular pile to the base (300);
the base (300) is composed of two cross beams, each of the two cross beams is provided with an arc rail (200) and a hanging rail (600), the opposite sides of the two arc rails (200) are respectively provided with a section of first sliding chute (201), and the opposite sides of the two hanging rails (600) are respectively provided with a section of second sliding chute (601) along the axial direction;
a first U-shaped sliding groove (301) and a second U-shaped sliding groove (302) are symmetrically formed in the inner sides of the two cross beams respectively, and the first U-shaped sliding groove (301) is close to the end of the upper pile platform (100);
the head end of the first sliding chute (201) is butted with the first U-shaped sliding chute (301), the tail end of the first sliding chute (201) is communicated with the second sliding chute (601), and the bottom end of the second sliding chute (601) is butted with the second U-shaped sliding chute (302);
the waist ring (400) is erected between the two first U-shaped sliding chutes (301), the bottom ring (500) is erected between the two second U-shaped sliding chutes (302), and the outer side of the bottom ring (500) is sealed;
the first winch (700) is fixed at the tops of the two arc rails (200) and used for driving the waist ring (400) to move to the second sliding groove (601) along the first sliding groove (201);
the second winch (800) is fixed to the tops of the two hanging rails (600) and used for driving the bottom ring (500) and the waist ring (400) to be lifted to the top from the bottom of the second sliding groove (601).
2. The large pipe pile hoisting equipment according to claim 1, wherein the upper pile platform (100) comprises two symmetrically arranged horizontal platforms (101), and opposite sides of the two horizontal platforms (101) are respectively arranged into a slope (102);
the slope (102) extends out of the side face of the side water platform (101), a plurality of curved rollers (103) are uniformly arranged below the slope (102), and the curved rollers (103) on opposite sides of the two horizontal platforms (101) are symmetrically distributed in a V shape.
3. The large pipe pile hoisting equipment according to claim 2, wherein the two horizontal platforms (101) are cast on the construction ground by concrete;
or the metal plates are used for building and are arranged on the construction ground during use, and the connecting rods are used for fixing the space between the two metal plates so as to be suitable for the tubular piles with different diameters.
4. A large pipe pile hoisting apparatus according to claim 1, wherein the distance between the first U-shaped chute (301) and the second U-shaped chute (302) is equal to half of the height of the pipe pile, and the first U-shaped chute (301) is located at the end of the cross beam.
5. A large pipe pile hoisting equipment according to claim 4, wherein the inner ring of the waist ring (400) is uniformly provided with a plurality of balls (405).
6. The large pipe pile hoisting equipment according to claim 5, wherein two sides of the waist ring (400) are connected with the middle part of the bottom ring (500) through steel cables with equal length.
7. The large pipe pile hoisting equipment according to claim 6, wherein the central angle of the arc rail (200) is 180 °, and the central angle of the first chute (201) is 90 °.
8. The large pipe pile hoisting equipment according to claim 7, wherein the first hoisting machine (700) is connected with the waist ring (400) by an electric buckle, when the waist ring (400) moves to the end of the first chute (201), the electric buckle is released, and the second hoisting machine (800) drives the bottom ring (500) and the waist ring (400) to ascend.
9. The large pipe pile hoisting equipment according to claim 8, wherein the bottom of the base (300) is fixedly installed on the ground, or the base (300) is provided with a driving part which is an automobile.
CN201910644476.1A 2019-07-17 2019-07-17 Large-scale tubular pile lifts by crane equipment Expired - Fee Related CN110329931B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910644476.1A CN110329931B (en) 2019-07-17 2019-07-17 Large-scale tubular pile lifts by crane equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910644476.1A CN110329931B (en) 2019-07-17 2019-07-17 Large-scale tubular pile lifts by crane equipment

Publications (2)

Publication Number Publication Date
CN110329931A CN110329931A (en) 2019-10-15
CN110329931B true CN110329931B (en) 2020-05-12

Family

ID=68145455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910644476.1A Expired - Fee Related CN110329931B (en) 2019-07-17 2019-07-17 Large-scale tubular pile lifts by crane equipment

Country Status (1)

Country Link
CN (1) CN110329931B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202031029U (en) * 2011-02-25 2011-11-09 中交四航局第一工程有限公司 Cross-arch rib gantry crane
CN108910687A (en) * 2018-09-25 2018-11-30 陈伟光 A kind of tubular pole suspender

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8141923B2 (en) * 2007-01-19 2012-03-27 Frank's Casing Crew And Rental Tools, Inc. Single joint elevator having deployable jaws

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202031029U (en) * 2011-02-25 2011-11-09 中交四航局第一工程有限公司 Cross-arch rib gantry crane
CN108910687A (en) * 2018-09-25 2018-11-30 陈伟光 A kind of tubular pole suspender

Also Published As

Publication number Publication date
CN110329931A (en) 2019-10-15

Similar Documents

Publication Publication Date Title
US20140053475A1 (en) Method and apparatus for lifting and leveling a concrete panel
CN103821087A (en) Precast bridge deck space steel pipe concrete truss composite beam and construction method
EP1963580B1 (en) Foundation pile driver
CN102852095A (en) Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof
CN109252521B (en) Equipment for pulling out steel pipe pile in water in limited space under steel beam and construction method thereof
CN110805305A (en) Climbing and shifting method for high-rise building
CN110329931B (en) Large-scale tubular pile lifts by crane equipment
CN212175879U (en) Movable foundation pile static load testing device
CN212317544U (en) A post connection structure about newly-built basis for expanding underground space
CN107217669B (en) Pile pulling equipment and quick moving method thereof
CN108821127A (en) The devices and methods therefor of disassembly lifting open type TBM in a kind of hole
CN115853341A (en) Recyclable tubular structure and construction method thereof
CN213871393U (en) Protection structure that portal bracing beam lifted
CN210288479U (en) Prefabricated medium plate transportation and installation device of full-composite assembly type reverse subway station
CN217651795U (en) Prestressed pile construction positioning device
CN108316671B (en) Method for realizing displacement and steering of building by adjusting diameter of roller
CN101476282B (en) Construction method for long, large and heavy component in river
CN213203812U (en) Bridging device for large-span steel beam
CN220523432U (en) Auxiliary penetrating device for penetrating steel pipe in jacking pipe
CN217710377U (en) Simply supported bridge reinforced structure based on reaction frame traction
CN211395315U (en) Interim steel landing stage bearing device
CN214993215U (en) Culvert wall body support and whole sideslip device of template
CN207499143U (en) Steel construction overhangs gallery structure
CN115162218A (en) Rigid frame arch bridge dismantling process
CN112830423A (en) Bridge installation hoisting equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200512

Termination date: 20210717

CF01 Termination of patent right due to non-payment of annual fee