CN110319091A - A kind of construction wall expansion formula anchoring process using anchoring - Google Patents

A kind of construction wall expansion formula anchoring process using anchoring Download PDF

Info

Publication number
CN110319091A
CN110319091A CN201810295781.XA CN201810295781A CN110319091A CN 110319091 A CN110319091 A CN 110319091A CN 201810295781 A CN201810295781 A CN 201810295781A CN 110319091 A CN110319091 A CN 110319091A
Authority
CN
China
Prior art keywords
bar
sliding
holdfast
slide lock
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810295781.XA
Other languages
Chinese (zh)
Inventor
曾敏偲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810295781.XA priority Critical patent/CN110319091A/en
Publication of CN110319091A publication Critical patent/CN110319091A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B13/00Dowels or other devices fastened in walls or the like by inserting them in holes made therein for that purpose
    • F16B13/04Dowels or other devices fastened in walls or the like by inserting them in holes made therein for that purpose with parts gripping in the hole or behind the reverse side of the wall after inserting from the front
    • F16B13/08Dowels or other devices fastened in walls or the like by inserting them in holes made therein for that purpose with parts gripping in the hole or behind the reverse side of the wall after inserting from the front with separate or non-separate gripping parts moved into their final position in relation to the body of the device without further manual operation
    • F16B13/0808Dowels or other devices fastened in walls or the like by inserting them in holes made therein for that purpose with parts gripping in the hole or behind the reverse side of the wall after inserting from the front with separate or non-separate gripping parts moved into their final position in relation to the body of the device without further manual operation by a toggle-mechanism

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Expand formula anchoring process the invention discloses a kind of construction wall using anchoring comprising steps of step 1) is drilled on wall using drill;Step 2) drills after drilling is completed, is replaced with reaming bit;After step 3) completes reaming, the formula anchoring piece of will be enlarged by is put into drilling, expansion formula anchoring piece includes holdfast bar and holdfast connector, the external end head of holdfast bar is arranged in holdfast connector, holdfast bar inner termination is equipped with holdfast conehead, enlarged footing sliding bar on holdfast bar on rear side of holdfast conehead, sliding frustum ring set and sliding annulus set are also arranged on enlarged footing sliding bar, expansion bar is folded around equipped with more than one piece on enlarged footing sliding bar between sliding frustum ring set and sliding annulus set, the front end for folding expansion bar is hinged on sliding frustum ring set, the rear end for folding expansion bar is hinged on sliding annulus and puts on, pressure spring is equipped on the enlarged footing sliding bar on rear side of sliding annulus set, sliding annulus set is pressed by pressure spring to move forward to make to fold to expand bar expansion support.

Description

A kind of construction wall expansion formula anchoring process using anchoring
Technical field
The present invention relates to a kind of anchor studs technical fields, and in particular to a kind of to be anchored using the construction wall expansion formula of anchoring Method.
Background technique
Intumescent anchor studs are to squeeze the anchor studs that anchor hole hole wall forms anchorage effect using expansion piece.Be using centrum with Moving towards for expansion piece, promotes expansion piece to expand, and generates swelling agent pressure with hole wall concrete, and act on by shearing friction It generates withdrawal resistance and realizes a kind of component anchored to connected piece.
In the operation of some civil engineerings and architectural engineering, often uses anchor studs and carry out suspended item or pull Rope;The anchor studs that people use at this stage are mostly the screw or iron nail of large size;And the anchoring property of screw and iron nail It is poor with stability, and bearing capacity is smaller, it is easy to from rock stratum or to make to fall off on wall, therefore the article that hangs and pull Rope be easy to fall, to there are some potential safety problems but also will cause unnecessary economic loss;Because of the invention It is necessary to produce the anchor studs that a kind of anchor force is strong, stability is good and bearing capacity is big.
Structure is complicated for current existing anchor studs, and installation is inconvenient, and anchor studs and anchoring casing pipe must match, and works as wall When body hardness is higher, the expansion piece of anchoring casing pipe cannot achieve expansion, so that anchoring is loosely;In order to solve when wall hardness is higher When, the expansion piece of anchoring casing pipe cannot achieve expansion issues, and existing anchor studs when in use, are matched on wall in advance to brill The tail end in hole carries out reaming, then installs anchor studs again, since the size of reaming is difficult to be fitted close with the enlarged footing of anchor studs, It is shaken after being installed so as to cause anchor studs.
Summary of the invention
The purpose of the present invention is to be to overcome the shortage of prior art, and it is an object of the present invention to provide a kind of construction wall using anchoring Expansion formula anchoring process solves the problems, such as that the size of reaming is difficult to be fitted close with the enlarged footing of anchor studs.
The present invention is achieved through the following technical solutions:
A kind of construction wall expansion formula anchoring process using anchoring, comprising steps of
Step 1) is drilled on wall using drill;
Step 2) drills after drilling is completed, is replaced with reaming bit;
After step 3) completes reaming, the formula anchoring piece of will be enlarged by is put into drilling, and the expansion formula anchoring piece includes holdfast bar With holdfast connector, the external end head of holdfast bar is arranged in the holdfast connector, and the holdfast bar inner termination is equipped with holdfast conehead, Enlarged footing sliding bar on holdfast bar on rear side of holdfast conehead is also arranged with sliding frustum ring set and sliding on enlarged footing sliding bar Annulus set expands bar around equipped with more than one piece folding on the enlarged footing sliding bar between annulus set sliding frustum ring set and sliding, The front end for folding expansion bar is hinged on sliding frustum ring set, and the rear end for folding expansion bar is hinged on sliding annulus set On, sliding annulus set on rear side of enlarged footing sliding bar on be equipped with pressure spring, by pressure spring press sliding annulus set move forward from And makes to fold and expand bar expansion support;
It includes front end folding rod and rear end folding rod that the step 4) folding, which expands bar, and the front end folding rod and rear end are rolled over Folded bar passes through stud connection;Also it is arranged with that slide lock is fixed on the enlarged footing sliding bar, the fixed section of the slide lock For L-type structure;The front end folding rod is linked up with equipped with L-type, the L-type hook and the fixed mutual hanging buckle of slide lock.Described The fixed enlarged footing sliding bar between sliding annulus set of slide lock is equipped with tension spring, by being tensioned spring pressing slide-and-lock set It moves forward, is locked to keep slide lock fixed and link up with mutual hanging buckle with the L-type on the folding rod of front end, in the fixed front end of slide lock Equipped at least one interlocking bar, the interlocking bar is fixedly connected with sliding frustum ring set.
A kind of construction wall using anchoring of the present invention expands formula anchoring process, can be opened by being arranged on holdfast bar Folding expand bar, fold and expand bar in use, folding that expand bar be in closed state, when using wall anchoring dress It sets when being anchored, fixed by being also arranged with slide lock on enlarged footing sliding bar, the fixed section of the slide lock is L-type Structure.Front end folding rod is linked up with equipped with L-type, the L-type hook and the fixed mutual hanging buckle of slide lock.And before slide lock is fixed End is equipped at least one interlocking bar, and the interlocking bar is fixedly connected with sliding frustum ring set.Foot of hole is extend into holdfast bar When reaming, when withstanding on reaming wall by holdfast conehead, since sliding frustum ring set is greater than holdfast conehead outer diameter, frustum ring is slided Set is withstood at first on reaming wall, by the blocking of reaming wall, is slided frustum ring set and is moved backward, synchronous interaction bar also moves back Dynamic, the fixed also synchronization of slide lock is moved backward along enlarged footing sliding bar, falls off, is not having with L-type hook to keep slide lock fixed Under the action of having slide lock fixed not to front end folding rod tightening force, set on the enlarged footing sliding bar on rear side of sliding annulus set There is pressure spring, sliding annulus set is pressed by pressure spring and moves forward to make to fold the inner wall for expanding bar expansion and being firmly supported at reaming On, and then realize the secured anchor of anchor.
Further, the holdfast connector is pull ring, screw rod or hook.
Further, it includes front end folding rod and rear end folding rod that the folding, which expands bar, and the front end folding rod is with after End folding rod passes through stud connection.
Further, also it is arranged with that slide lock is fixed on the enlarged footing sliding bar, the fixed section of the slide lock For L-type structure.
Further, the front end folding rod is linked up with equipped with L-type, the L-type hook and the fixed mutual hanging buckle of slide lock.
Further, it is equipped with tension spring on the fixed enlarged footing sliding bar between sliding annulus set of the slide lock, It is moved forward by tensioning spring pressing slide-and-lock set, so that it is mutual with the L-type hook on the folding rod of front end to keep slide lock fixed Hanging buckle locking is equipped at least one interlocking bar in the fixed front end of slide lock, and the interlocking bar is fixedly connected with sliding frustum ring set.
Compared with prior art, the present invention having the following advantages and benefits:
A kind of construction wall using anchoring of the present invention expands formula anchoring process, can be opened by being arranged on holdfast bar Folding expand bar, fold and expand bar in use, folding that expand bar be in closed state, when using wall anchoring dress It sets when being anchored, fixed by being also arranged with slide lock on enlarged footing sliding bar, the fixed section of the slide lock is L-type Structure.Front end folding rod is linked up with equipped with L-type, the L-type hook and the fixed mutual hanging buckle of slide lock.And before slide lock is fixed End is equipped at least one interlocking bar, and the interlocking bar is fixedly connected with sliding frustum ring set.Foot of hole is extend into holdfast bar When reaming, when withstanding on reaming wall by holdfast conehead, since sliding frustum ring set is greater than holdfast conehead outer diameter, frustum ring is slided Set is withstood at first on reaming wall, by the blocking of reaming wall, is slided frustum ring set and is moved backward, synchronous interaction bar also moves back Dynamic, the fixed also synchronization of slide lock is moved backward along enlarged footing sliding bar, falls off, is not having with L-type hook to keep slide lock fixed Under the action of having slide lock fixed not to front end folding rod tightening force, set on the enlarged footing sliding bar on rear side of sliding annulus set There is pressure spring, sliding annulus set is pressed by pressure spring and moves forward to make to fold the inner wall for expanding bar expansion and being firmly supported at reaming On, and then realize the secured anchor of anchor.
Solve the problems, such as that the size of reaming is difficult to be fitted close with the enlarged footing of anchor studs.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is that the folding that a kind of construction wall using anchoring of the present invention expands on formula anchoring process expands bar closed state Structural schematic diagram;
Fig. 2 is that the folding that a kind of construction wall using anchoring of the present invention expands on formula anchoring process expands bar unfolded state Structural schematic diagram;
Label and corresponding parts title in attached drawing:
1- holdfast bar, 2- holdfast connector, 3- holdfast conehead, 4- enlarged footing sliding bar, 5-, which is folded, expands bar, 6- sliding circle Ring set, 7- pressure spring, the front end 8- folding rod, the rear end 9- folding rod, 10- slide lock is fixed, 11-L type hook, 12- tension spring, 13- Interlocking bar, 14- slide frustum ring set.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment and attached drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation for explaining only the invention, are not made For limitation of the invention.
Embodiment
As shown in Figs. 1-2, a kind of construction wall using anchoring of the present invention expands formula anchoring process, comprising steps of
Step 1 is drilled on wall using drill;
Step 2 drills after drilling is completed, is replaced with reaming bit;
After step 3 completes reaming, the formula anchoring piece of will be enlarged by is put into drilling, and the expansion formula anchoring piece includes holdfast bar 1 With holdfast connector 2, it is characterised in that: the external end head of holdfast bar 1,1 inner end of holdfast bar is arranged in the holdfast connector 2 Head is equipped with holdfast conehead 3, and enlarged footing sliding bar 4 on the holdfast bar 1 of 3 rear side of holdfast conehead is also arranged on enlarged footing sliding bar 4 There are sliding frustum ring set 14 and sliding annulus set 6, in sliding frustum ring set 14 and slides the enlarged footing sliding bar between annulus set 6 Around more than one piece folding expansion bar 5 is equipped on 4, the front end that the folding expands bar 5 is hinged on sliding frustum ring set 14, the folding The folded rear end for expanding bar 5 is hinged on sliding annulus set 6, is equipped with pressure spring on the enlarged footing sliding bar 4 of 6 rear side of sliding annulus set 7, sliding annulus set 6 is pressed by pressure spring 7 and moves forward to make to fold to expand the expansion support of bar 5;
It includes front end folding rod 8 and rear end folding rod 9 that folding described in step 4, which expands bar 5, and the front end folding rod 8 is with after End folding rod 9 passes through stud connection;Slide lock fixed 10, the slide-and-lock are also arranged on the enlarged footing sliding bar 4 The section of set 10 is L-type structure;The front end folding rod 8 is equipped with L-type hook 11, and the L-type hook 11 is fixed with slide lock 10 mutual hanging buckles.It is equipped with tension spring 12 on enlarged footing sliding bar 4 between the slide lock fixed 10 and sliding annulus set 6, It compresses slide lock fixed 10 by tension spring 12 to move forward, so that the L-type on slide lock fixed 10 and front end folding rod 8 be made to hang The locking of the mutual hanging buckle of hook 11 is equipped at least one interlocking bar 13, the interlocking bar 13 and sliding cone in fixed 10 front end of slide lock Platform ring set 14 is fixedly connected.
Holdfast connector 2 is pull ring, screw rod or hook.
It folds expansion bar 5 and includes front end folding rod 8 and rear end folding rod 9, the front end folding rod 8 and rear end folding rod 9 Pass through stud connection.
Slide lock fixed 10 is also arranged on the enlarged footing sliding bar 4, the section of the slide lock fixed 10 is L-type Structure.
Front end folding rod 8 is equipped with L-type hook 11, the L-type hook 11 and the mutual hanging buckle of slide lock fixed 10.
It is equipped with tension spring 12 on enlarged footing sliding bar 4 between the slide lock fixed 10 and sliding annulus set 6, is passed through Tension spring 12 compresses slide lock fixed 10 and moves forward, to make the L-type hook 11 on slide lock fixed 10 and front end folding rod 8 Mutual hanging buckle locking.
It is equipped at least one interlocking bar 13 in fixed 10 front end of slide lock, the interlocking bar 13 and sliding frustum ring set 14 are solid Fixed connection.
A kind of construction wall using anchoring of the present invention expands formula anchoring process, can be opened by being arranged on holdfast bar Folding expand bar, fold and expand bar in use, folding that expand bar be in closed state, when using wall anchoring dress It sets when being anchored, fixed by being also arranged with slide lock on enlarged footing sliding bar, the fixed section of the slide lock is L-type Structure.Front end folding rod is linked up with equipped with L-type, the L-type hook and the fixed mutual hanging buckle of slide lock.And before slide lock is fixed End is equipped at least one interlocking bar, and the interlocking bar is fixedly connected with sliding frustum ring set.Foot of hole is extend into holdfast bar When reaming, when withstanding on reaming wall by holdfast conehead, since sliding frustum ring set is greater than holdfast conehead outer diameter, frustum ring is slided Set is withstood at first on reaming wall, by the blocking of reaming wall, is slided frustum ring set and is moved backward, synchronous interaction bar also moves back Dynamic, the fixed also synchronization of slide lock is moved backward along enlarged footing sliding bar, falls off, is not having with L-type hook to keep slide lock fixed Under the action of having slide lock fixed not to front end folding rod tightening force, set on the enlarged footing sliding bar on rear side of sliding annulus set There is pressure spring, sliding annulus set is pressed by pressure spring and moves forward to make to fold the inner wall for expanding bar expansion and being firmly supported at reaming On, and then realize the secured anchor of anchor.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (6)

1. a kind of construction wall using anchoring expands formula anchoring process, which is characterized in that comprising steps of
Step 1) is drilled on wall using drill;
Step 2) drills after drilling is completed, is replaced with reaming bit;
Step 3) complete reaming after, the formula anchoring piece of will be enlarged by is put into drilling, the expansion formula anchoring piece include holdfast bar (1) and Holdfast connector (2), it is characterised in that: external end head of holdfast connector (2) setting in holdfast bar (1), the holdfast bar (1) inner termination is equipped with holdfast conehead (3), enlarged footing sliding bar (4) on the holdfast bar (1) on rear side of holdfast conehead (3), in enlarged footing Sliding frustum ring set (14) and sliding annulus set (6) are also arranged on sliding bar (4), in sliding frustum ring set (14) and sliding circle Expansion bar (5) is folded around equipped with more than one piece on enlarged footing sliding bar (4) between ring set (6), before the folding expands bar (5) End is hinged in sliding frustum ring set (14), and the rear end for folding expansion bar (5) is hinged in sliding annulus set (6), in cunning Enlarged footing sliding bar (4) on rear side of dynamic annulus set (6) is equipped with pressure spring (7), by pressure spring (7) press sliding annulus set (6) to Preceding movement expands bar (5) expansion support to make to fold;
It includes front end folding rod (8) and rear end folding rod (9), the front end folding rod (8) that the step 4) folding, which expands bar (5), Pass through stud connection with rear end folding rod (9);It is fixed (10) that slide lock is also arranged on the enlarged footing sliding bar (4), institute The section for stating slide lock fixed (10) is L-type structure;The front end folding rod (8) is equipped with L-type hook (11), and the L-type is hung Hook (11) and fixed (10) the mutual hanging buckle of slide lock.Expansion between the slide lock fixed (10) and sliding annulus set (6) Head sliding bar (4) is equipped with tension spring (12), compresses slide lock fixed (10) by tension spring (12) and moves forward, to make to slide L-type hook (11) mutually hanging buckle on dynamic lock sleeve (10) and front end folding rod (8) is locked, and is set in fixed (10) front end of slide lock Have at least one interlocking bar (13), the interlocking bar (13) is fixedly connected with sliding frustum ring set (14).
2. a kind of construction wall using anchoring according to claim 1 expands formula anchoring process, it is characterised in that: described Holdfast connector (2) is pull ring, screw rod or hook.
3. a kind of construction wall using anchoring according to claim 1 expands formula anchoring process, it is characterised in that: described Fold that expand bar (5) include front end folding rod (8) and rear end folding rod (9), the front end folding rod (8) and rear end folding rod (9) pass through stud connection.
4. a kind of construction wall using anchoring according to claim 3 expands formula anchoring process, it is characterised in that: in institute It states and is also arranged with that slide lock is fixed (10) on enlarged footing sliding bar (4), the section of the slide lock fixed (10) is L-type structure.
5. a kind of construction wall using anchoring according to claim 4 expands formula anchoring process, it is characterised in that: described Front end folding rod (8) is equipped with L-type hook (11), the L-type hook (11) and fixed (10) the mutual hanging buckle of slide lock.
6. a kind of construction wall using anchoring according to claim 5 expands formula anchoring process, it is characterised in that: in institute The enlarged footing sliding bar (4) stating slide lock fixed (10) and sliding between annulus set (6) is equipped with tension spring (12), passes through tensioning Spring (12) compresses slide lock fixed (10) and moves forward, so that the L-type on slide lock fixed (10) and front end folding rod (8) be made to hang Hook (11) mutually hanging buckle locking is equipped at least one interlocking bar (13) in fixed (10) front end of slide lock, the interlocking bar (13) It is fixedly connected with sliding frustum ring set (14).
CN201810295781.XA 2018-03-30 2018-03-30 A kind of construction wall expansion formula anchoring process using anchoring Withdrawn CN110319091A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810295781.XA CN110319091A (en) 2018-03-30 2018-03-30 A kind of construction wall expansion formula anchoring process using anchoring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810295781.XA CN110319091A (en) 2018-03-30 2018-03-30 A kind of construction wall expansion formula anchoring process using anchoring

Publications (1)

Publication Number Publication Date
CN110319091A true CN110319091A (en) 2019-10-11

Family

ID=68112429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810295781.XA Withdrawn CN110319091A (en) 2018-03-30 2018-03-30 A kind of construction wall expansion formula anchoring process using anchoring

Country Status (1)

Country Link
CN (1) CN110319091A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685054A (en) * 2021-08-25 2021-11-23 重庆市渝海建设(集团)有限公司 Floor slab crack structure and processing method thereof
CN114165063A (en) * 2021-10-26 2022-03-11 山东高速工程建设集团有限公司 Tool and method for quickly positioning and adjusting precast beam component

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685054A (en) * 2021-08-25 2021-11-23 重庆市渝海建设(集团)有限公司 Floor slab crack structure and processing method thereof
CN113685054B (en) * 2021-08-25 2023-02-17 重庆市渝海建设(集团)有限公司 Floor slab crack structure and processing method thereof
CN114165063A (en) * 2021-10-26 2022-03-11 山东高速工程建设集团有限公司 Tool and method for quickly positioning and adjusting precast beam component

Similar Documents

Publication Publication Date Title
CN110319091A (en) A kind of construction wall expansion formula anchoring process using anchoring
CN110565648B (en) Anchor head expandable anchor rod and construction method thereof
EP2415963A3 (en) Anchor for use with expandable tubular
CA2749593A1 (en) Monobore construction with dual expanders
CN105625971B (en) A kind of expansion hanger and its sit hanging method
CN112647877B (en) Soft coal seam branch drilling and pipe lowering guiding device and efficient extraction method
CN109138880B (en) Bidirectional anchor
CN105114110A (en) Novel slide way type expanding-shell anchor head
CA2895176C (en) High pressure lock assembly
CN110319090A (en) A kind of building wall spike devices convenient for firm installation
CN205475221U (en) A sack expansion structure for assisting expand body anti -floating anchor rod
RU2010107387A (en) TUBE EXPANDER
CN110319089A (en) A kind of wall anchor
US9938787B2 (en) Fully supported c-ring slip retention system
CN110388082A (en) A kind of sealing wall grouting hole plugging method
CN205502000U (en) Extension wing formula anchor rod device
CN211975017U (en) Disposable enlarging anchor head device
CN110388081A (en) One kind leaking seam device convenient for securely blocking roof wallboard
CA2837021C (en) Liner hanger
SG11201810543YA (en) Downhole tubular expansion tool and method for installing a tandem clad liner
CN104088587B (en) For reducing sleeve pipe anti-collapse in drilling process
CN219539293U (en) Safety belt hanging device for greening outer wall construction
CN206143773U (en) Type that strikes directly bores formula crotch anchor nail
CN214787418U (en) Slip casting head dropout prevention means
US20140166315A1 (en) Lock assembly with cageless dogs

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20191011