CN110316689A - Tank container train loading arm - Google Patents

Tank container train loading arm Download PDF

Info

Publication number
CN110316689A
CN110316689A CN201910551885.7A CN201910551885A CN110316689A CN 110316689 A CN110316689 A CN 110316689A CN 201910551885 A CN201910551885 A CN 201910551885A CN 110316689 A CN110316689 A CN 110316689A
Authority
CN
China
Prior art keywords
arm pipe
arm
pipe
tank container
hose
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910551885.7A
Other languages
Chinese (zh)
Other versions
CN110316689B (en
Inventor
梁峰
孙浩
孙明立
王伟
喻晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Qingdao Refining Corp Ltd
Original Assignee
Sinopec Qingdao Refining Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Qingdao Refining Corp Ltd filed Critical Sinopec Qingdao Refining Corp Ltd
Publication of CN110316689A publication Critical patent/CN110316689A/en
Application granted granted Critical
Publication of CN110316689B publication Critical patent/CN110316689B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B67OPENING, CLOSING OR CLEANING BOTTLES, JARS OR SIMILAR CONTAINERS; LIQUID HANDLING
    • B67DDISPENSING, DELIVERING OR TRANSFERRING LIQUIDS, NOT OTHERWISE PROVIDED FOR
    • B67D7/00Apparatus or devices for transferring liquids from bulk storage containers or reservoirs into vehicles or into portable containers, e.g. for retail sale purposes
    • B67D7/04Apparatus or devices for transferring liquids from bulk storage containers or reservoirs into vehicles or into portable containers, e.g. for retail sale purposes for transferring fuels, lubricants or mixed fuels and lubricants
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B67OPENING, CLOSING OR CLEANING BOTTLES, JARS OR SIMILAR CONTAINERS; LIQUID HANDLING
    • B67DDISPENSING, DELIVERING OR TRANSFERRING LIQUIDS, NOT OTHERWISE PROVIDED FOR
    • B67D7/00Apparatus or devices for transferring liquids from bulk storage containers or reservoirs into vehicles or into portable containers, e.g. for retail sale purposes
    • B67D7/06Details or accessories
    • B67D7/78Arrangements of storage tanks, reservoirs or pipe-lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Loading And Unloading Of Fuel Tanks Or Ships (AREA)

Abstract

The present invention proposes a kind of tank container train loading arm, belongs to tank container train handling facilities technical field.This tank container train loading arm includes the components such as supporting mechanism, lower arm pipe, inner arm pipe, middle arm pipe, external arm tube, hose, upper arm pipe and quick coupling.Beneficial effects of the present invention: in the case where train not off-the-line, realize that the end bottom of tank container train is unloaded, should not there are " dead point ", " caecum " phenomenon on conveyance conduit when the design of each arm pipe meets the heaviers oil such as handling fuel oil, whole process substantially increases the efficiency and security reliability of emptying along flow direction of medium aneroid bag;The coordinated of upper arm pipe, metal hose, external arm tube, middle arm pipe, inner arm pipe, lower arm pipe and rotary joint etc., the interface plane of quick coupling may be implemented and unload the interface plane keeping parallelism of liquid mouth, so that quick coupling shows smooth, accurate, sealed connection with liquid cause for gossip is unloaded.

Description

Tank container train loading arm
Technical field
The present invention relates to tank container train handling facilities technical fields, more particularly to a kind of tank container train Loading arm.
Background technique
Train transport for the cost for reducing the transport of fuel oil train, fuel oil is gradually replaced by by existing train tank car Tank container.Cylindrical liquid container transport, is transported compared with train tank car, and expense is greatly reduced, and is the hair of railway liquid transport Open up direction.Cylindrical liquid container unloads liquid valve and is mounted on tank body end bottom, and caliber is generally Dn80, and opening direction and end face are hung down Directly.When transporting heavy oil by cylindrical liquid container train, the scheme of existing train tank car side emptying cannot be used and unloaded Oily equipment.The cylindrical liquid container train emptying mode being currently known is that tank container is hung train, uses Automobile Transportation It unloads to place to use.On automobile, unload liquid mouth and be located at and conveniently unload the automobile tail of liquid, avoid train end face unload it is tired It is difficult.Off-the-line is not found not yet in the case that end face is unloaded directly train at present.By cylindrical liquid container special train by fuel oil etc. Liquid transporting is to destination, in the case where train not off-the-line, by being located at every section train (there are two can loading on a section train Tank container) the liquid mouth that unloads at both ends unloads liquid, the efficiency and security reliability of emptying can be greatly improved, to further decrease expense With.
In the case where train not off-the-line, unloading the difficulty that liquid encounters is mainly following several respects:
First is that tank car unloads liquid mouth in the side of tank car car body, and operator can will unload unlike unloading common tank car The interface position of the side of oily arm or hose access tank car car body smoothly.Tank container unloads liquid mouth at the end of tank container Face, in the surface of train connection hook, operator drags the elastic hose for lifting Dn80, it is difficult to smooth, steadily from ground It is moved to train hook top and connects and unload liquid mouth, Yi Fasheng pipeline is slipped out of the hand the operating safeties such as landing.
Second is that connect even if unloading liquid mouth with end face using the metal hose of Dn80, because hose needs certain turning radius, Larger space need to be occupied.And space is smaller at two section Compartment hooks, and the pot type collection on two section trains is needed when two section vehicles are unloaded simultaneously Vanning connects hose, it is difficult to which liquid mouth is unloaded in normal access, unloads liquid mouth even if can access, is also bound to cause operator without safety Standing and working space, it is difficult to safety operation.
Third is that the land liquid handling arm being currently known, lacks the handling facilities unloaded for cylindrical liquid container, nothing Method accomplishes that the liquid in tank container leans on gravity along loading arm all from pump intake concetrated pipe is flow to, and there are liquid for process of unloading Bag.If a unloading pump is arranged according to automobile equally each tank container of unloading, for being generally the pot type collection of 50 sections one column Case train, unloading pump fabricating yard, in terms of cannot achieve.
Summary of the invention
The purpose of the present invention is to provide a kind of tank container train loading arm, and " the heaviers oil such as fuel oil is adopted for solution Transported with tank container, in the case where train not off-the-line, realize unload the end bottom of tank container train " skill Art problem.
The present invention provides a kind of tank container train loading arm, including supporting mechanism, lower arm pipe, inner arm pipe, middle arm pipe, External arm tube, hose, upper arm pipe and quick coupling;Supporting mechanism is set to the side of train rail, is fixedly connected on supporting mechanism Lower arm pipe, one end of lower arm pipe are connected with pipeline road, and the other end bending of lower arm pipe is upward;One end of inner arm pipe bend to Under, upwards, one end of inner arm pipe is through the other end of rotary joint connection lower arm pipe, inner arm Guan Kexiang for the other end bending of inner arm pipe Lower arm pipe is swung in horizontal plane;Downwards, the other end bending of middle arm pipe is upward for one end bending of middle arm pipe, and the one of middle arm pipe The other end of the end through rotary joint connection inner arm pipe, middle arm pipe can be swung relative to inner arm pipe in horizontal plane;One end of external arm tube Bending downwards, the other end of external arm tube along horizontal extension, one end of external arm tube through rotary joint connect in arm pipe the other end, outside Arm pipe can be swung relative to middle arm pipe in horizontal plane;The one end of the other end of external arm tube through rotary joint connection hose, hose The other end is along horizontal extension, and one end of the other end connection upper arm pipe of hose, upper arm pipe is vertically extending, the other end of upper arm pipe Quick coupling is set, and hose can be rotated relative to external arm tube, and upper arm pipe can be swung with the rotation of hose.
Further, hose supporting element is equipped on external arm tube, upper arm pipe supporting element is arranged in the end of hose supporting element, soft Pipe supporting element is placed on hose supporting element along horizontal extension, the hose, and upper arm pipe supporting element is vertically extending, and upper arm pipe exists When being swung up to vertical position, upper arm pipe can be positioned on upper arm pipe supporting element.
Further, hose supporting element is detachably connected on external arm tube.
Further, handle is provided on the upper arm pipe supporting element.
Further, the supporting mechanism is support post, and the bottom end of support post is fixedly connected with ground, support post Lower support element is arranged in lower part, is fixedly connected with lower arm pipe on lower support element.
Further, upper supporting piece is arranged in the top of support post, is rotatably connected to vertical bull stick on upper supporting piece, vertically The lower end of bull stick is fixedly connected with the outer wall of inner arm pipe.
Further, lockable mechanism is provided on the supporting mechanism, lockable mechanism can the vertical bull stick of interlocking.
Further, the lockable mechanism includes the latch hook being set on supporting mechanism and the lock that is set on vertical bull stick Hole, the pluggable lockhole of latch hook.
Further, fixed ring, inner arm pipe, middle arm pipe and external arm tube are provided on inner arm pipe, middle arm pipe and external arm tube After stacking gradually, each fixed ring is also stacked gradually, and can be inserted into lock pin in each fixed ring.
Further, one end of lower arm pipe connects pipeline road through pipe fitting.
Compared with prior art, tank container train loading arm of the invention has the characteristics that and advantage:
Tank container train loading arm of the invention realizes tank container train in the case where train not off-the-line End bottom unload, should not have on conveyance conduit when the design of each arm pipe meets the heaviers oil such as handling fuel oil " dead point ", " caecum " phenomenon, whole process substantially increase the efficiency and security reliability of emptying along flow direction of medium aneroid bag;Upper arm The coordinated of pipe, metal hose, external arm tube, middle arm pipe, inner arm pipe, lower arm pipe and rotary joint etc. may be implemented quickly The interface plane of connector and the interface plane keeping parallelism for unloading liquid mouth so that quick coupling and unload liquid cause for gossip show it is smooth, accurate, close Envelope connection;The higher balancer of cost in loading arm accessory is eliminated, dry valve is eliminated when unloading liquid, reduces rotary joint Quantity significantly reduces construction cost early period and later period operation and maintenance cost.
After a specific embodiment of the invention is read in conjunction with the figure, the features and advantages of the invention be will become clearer.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is the present invention Some embodiments for those of ordinary skill in the art without creative efforts, can also basis These attached drawings obtain other attached drawings.
Fig. 1 is the perspective view of tank container of embodiment of the present invention train loading arm;
Fig. 2 is the main view of tank container of embodiment of the present invention train loading arm;
Fig. 3 is the top view of tank container of embodiment of the present invention train loading arm;
Fig. 4 is the usage state diagram one of tank container of embodiment of the present invention train loading arm;
Fig. 5 is the usage state diagram two of tank container of embodiment of the present invention train loading arm.
Specific embodiment
As shown in Figures 1 to 5, the present embodiment provides a kind of tank container train loading arm, including supporting mechanism, lower arm The components such as pipe 15, inner arm pipe 3, middle arm pipe 5, external arm tube 6, metal hose 7, upper arm pipe 8 and quick coupling 9.
Supporting mechanism is set to the side of train rail, is fixedly connected with lower arm pipe 15 on supporting mechanism, and the one of lower arm pipe 15 End is along horizontal extension, and one end of lower arm pipe 15 is provided with pipe fitting (being flange 13 in the present embodiment), and one end of lower arm pipe 15 can It is connect by flange 13 with pipeline road, the other end bending of lower arm pipe 15 is upwardly formed 90 ° of elbows, to connect with inner arm pipe 3.
In the present embodiment, supporting mechanism is support post 1, and the bottom end of support post 1 is fixed on ground through buck plate 16, Lower support element 17 is arranged in the lower part of support post 1, is fixedly connected with lower arm pipe 15 on lower support element 17.The top of support post 1 is set Upper supporting piece 18 is set, vertical bull stick 19 is rotatably connected on upper supporting piece 18, the lower end of vertical bull stick 19 is fixedly connected with inner arm pipe 3 Outer wall.
In the present embodiment, lockable mechanism is provided on supporting mechanism, lockable mechanism can the vertical bull stick 19 of interlocking.Specifically, Lockable mechanism includes latch hook 20 and lockhole 21, and latch hook 20 is set on support post 1, and lockhole 21 is set to be connect with inner arm pipe 3 Vertical bull stick 19 on, the pluggable lockhole of latch hook 20, with after inner arm pipe 3, middle arm pipe 5 and external arm tube 6 are stacked gradually, will in Arm pipe 3 is locked at support post 1.Be provided with fixed ring 14 on inner arm pipe 3, middle arm pipe 5 and external arm tube 6, inner arm pipe 3, in After arm pipe 5 and external arm tube 6 stack gradually, each fixed ring 14 is also stacked gradually, and can be inserted into lock pin in each fixed ring 14, will be interior Arm pipe 3, middle arm pipe 5 and the locking of external arm tube 6 are integrated.
One end bending of inner arm pipe 3 is formed down 90 ° of elbows, and the other end bending of inner arm pipe 3 is upwardly formed 90 ° of elbows, One end of inner arm pipe 3 connects the other end of lower arm pipe 15 through rotary joint 4, and one end of inner arm pipe 3 can be relative to lower arm pipe 15 Other end rotation, inner arm pipe 3 can be swung relative to lower arm pipe 15 in horizontal plane.
One end bending of middle arm pipe 5 is formed down 90 ° of elbows, and the other end bending of middle arm pipe 5 is upwardly formed 90 ° of elbows, One end of middle arm pipe 5 connects the other end of inner arm pipe 3 through rotary joint 4, and one end of middle arm pipe 5 can be relative to the another of inner arm pipe 3 One end rotation, middle arm pipe 5 can be swung relative to inner arm pipe 3 in horizontal plane.
One end bending of external arm tube 6 is formed down 90 ° of elbows, the other end of external arm tube 6 along horizontal extension, external arm tube 6 The other end of the one end through arm pipe 5 in the connection of rotary joint 4, one end of external arm tube 6 can be rotated relative to the other end of middle arm pipe 5, External arm tube 6 can be swung relative to middle arm pipe 5 in horizontal plane.
The other end of external arm tube 6 connects one end of metal hose 7 through rotary joint 4, and the other end of metal hose 7 is along horizontal Extend, one end of the other end connection upper arm pipe 8 of metal hose 7, upper arm pipe 8 is vertically extending, the other end setting of upper arm pipe 8 One end of quick coupling 9, metal hose 7 can be rotated relative to the other end of external arm tube 6, and metal hose 7 can be relative to external arm tube 6 Rotation, upper arm pipe 8 can be swung with the rotation of metal hose 7.
The other end of upper arm pipe 8 is provided with dustproof cover, and dustproof cover can close quick coupling 9.To by quick coupling 9 from unloading liquid After under outspoken quick-detach, upper arm pipe 8 is swung up to vertical position, so that each arm pipe fuel oil is downward under the effect of gravity Stream, and fuel oil is avoided to flow out from upper arm pipe 8.At this point, quick coupling 9 is closed by dustproof cover, to avoid sundries from fast quick access First 9 enter upper arm pipe 8.
Hose supporting element 10 is equipped on external arm tube 6, upper arm pipe supporting element 12, hose is arranged in the end of hose supporting element 10 Supporting element 10 is placed on hose supporting element 10 along horizontal extension, metal hose 7.Upper arm pipe supporting element 12 is vertically extending, on When being rocked to vertical position, upper arm pipe 8 can be positioned on upper arm pipe supporting element 12 arm pipe 8.
The tank container train loading arm of the present embodiment needs the flexible deformation based on metal hose 7 to finely tune upper arm The position of quick coupling 9 on pipe 8.The stability of strutting system of metal hose 7 itself is poor, by design hose supporting element 10 to support Metal hose 7 keeps the stability for belonging to hose 7.Upper arm pipe supporting element 12 is vertically extending, and upper arm pipe supporting element 12 plays support Stablize the effect of upper arm pipe 8 and quick coupling 9.
In addition, be swung up in upper arm pipe 8 to vertical position, by upper arm pipe 8, the gravity of quick coupling 9, and Elastic force by metal hose 7 acts on, and upper arm pipe 8 can be made to be extruded in the vertical groove of upper arm pipe supporting element 12.This makes It is not required to that other locking structures are arranged again, it can be so that the holding vertical position of upper arm pipe 8, makes 9 interface of quick coupling on upper arm pipe 8 State upward is kept, the residual fuel oil stream in arm pipe is avoided to go out to pollute environment.
In the present embodiment, hose supporting element 10 is detachably connected on external arm tube 6.Specifically, being put above the outer wall of external arm tube 6 Cladding plate 23 is set, hose supporting element 10 is located at below the outer wall of external arm tube 6, and upper cladding plate 23 is bolted hose supporting element 10. When needing to dismantle the components such as metal hose 7, upper arm pipe 8, first hose supporting element 10 can be disassembled from external arm tube 6, then The components such as metal hose 7, upper arm pipe 8 are dismantled, disassembly, replacement in order to components such as metal hose 7, upper arm pipes 8 are also convenient for tieing up It repairs, replace rotary joint 4 between external arm tube 6 and metal hose 7.
In the present embodiment, vertical groove is provided on upper arm pipe supporting element 12, upper arm pipe 8 is swung up to vertical position When, upper arm pipe 8 is bonded the vertical groove of upper arm pipe supporting element 12, and upper arm pipe 8 can be made to be located in vertical groove.By upper arm pipe 8 It is swung towards the direction for unloading liquid mouth 22, so that upper arm pipe 8 is detached from upper arm pipe supporting element 12, meets quick coupling 9 to liquid mouth of unloading 22 needs.
Handle 11 is provided on upper arm pipe supporting element 12.Operator hold handle 11, with facilitate dragging inner arm pipe 3, in The swing of arm pipe 5 and external arm tube 6 in horizontal plane.
The tank container train loading arm of the present embodiment, operating method of unloading are as follows:
Operator holds handle 11, drags inner arm pipe 3, middle arm pipe 5 and external arm tube 6 in the swing of horizontal plane, so that respectively The expansion of arm pipe unloads liquid for what upper arm pipe 8 was moved to tank container train end face by adjusting the swing angle between each arm pipe Near 22 positions of mouth.Upper arm pipe 8 is swung to be detached from upper arm pipe supporting element 12, based on the flexible deformation of metal hose 7, Ke Yiwei The position of quick coupling 9 on upper arm pipe 8 is adjusted, so that quick coupling 9 is directed at unloading liquid mouth 22 and making for tank container train end face The two installs.The oil circuit valve on the pipeline road connecting with flange 13 is opened, the oil liquid valve for unloading liquid mouth 22 is opened, is started It unloads the fuel oil in tank container.After the completion of unloading, oil liquid valve is closed.Upper arm pipe 8, which is rocked to vertical position, to be made Its vertical groove for being bonded upper arm pipe supporting element 12.Operator holds handle 11, dragging inner arm pipe 3, middle arm pipe 5 and external arm tube 6 horizontal plane swing, stack gradually inner arm pipe 3, middle arm pipe 5 and external arm tube 6, and each arm pipe and train rail is made to keep flat Row.Using lockable mechanism, fixed ring 14, the collective effect of lock pin, each arm pipe is maintained at safety and stability state.Fuel oil exists Under gravity, remaining fuel oil is along upper arm pipe 8, metal hose 7, external arm tube 6, middle arm pipe 5, inner arm pipe 3, lower arm pipe 15 It flows in the pipeline road being connect with flange 13.To after a period of time, after residual fuel oil stream in each arm pipe is clean, Oil circuit valve is closed, completes to unload.
In addition, by valve (such as dry valve) is arranged on the present embodiment upper arm pipe 8, it specifically can be by dry valve and quick coupling 9 It is integrated into the dry valve with quick coupling, then tank container train bottom entrucking function may be implemented.Wherein, quick coupling 9 It is identical with " operation of unloading " as the alignment installation operation for unloading liquid mouth 22, it repeats no more.After filling vehicle to tank container, close The oil liquid valve for unloading liquid mouth 22 is closed, closes the dry valve on upper arm pipe 8, then upper arm pipe 8 will be rocked to vertical position to make its patch Close the vertical groove of arm pipe supporting element 12.Operator holds handle 11, and dragging inner arm pipe 3, middle arm pipe 5 and external arm tube 6 exist The swing of horizontal plane stacks gradually inner arm pipe 3, middle arm pipe 5 and external arm tube 6, and makes each arm pipe and train rail keeping parallelism. Using lockable mechanism, fixed ring 14, the collective effect of lock pin, each arm pipe is maintained at safety and stability state.Fuel oil is in weight Under power effect, remaining fuel oil is flowed along upper arm pipe 8, metal hose 7, external arm tube 6, middle arm pipe 5, inner arm pipe 3, lower arm pipe 15 It moves into the pipeline road being connect with flange 13.To after a period of time, after residual fuel oil stream in each arm pipe is clean, close Oil circuit valve is closed, entrucking is completed.
The tank container train loading arm of the present embodiment realizes tank container column in the case where train not off-the-line The end bottom of vehicle is unloaded, and should not be had " extremely on conveyance conduit when the design of each arm pipe meets the heaviers oil such as handling fuel oil Point ", " caecum " phenomenon, whole process substantially increase the efficiency and security reliability of emptying along flow direction of medium aneroid bag;On The coordinated of arm pipe 8, metal hose 7, external arm tube 6, middle arm pipe 5, inner arm pipe 3, lower arm pipe 15 and rotary joint 4 etc., can The interface plane of quick coupling 9 and the interface plane keeping parallelism of liquid mouth 22 is unloaded to realize, so as to quick coupling 9 and unload liquid mouth 22 Realize smooth, accurate, sealed connection;The higher balancer of cost in loading arm accessory is eliminated, eliminates dry valve when unloading liquid, The quantity for reducing rotary joint significantly reduces construction cost early period and later period operation and maintenance cost.
Certainly, the above description is not a limitation of the present invention, and the present invention is also not limited to the example above, this technology neck The variations, modifications, additions or substitutions that the technical staff in domain is made within the essential scope of the present invention also should belong to of the invention Protection scope.

Claims (10)

1. a kind of tank container train loading arm, it is characterised in that: including supporting mechanism, lower arm pipe, inner arm pipe, middle arm pipe, External arm tube, hose, upper arm pipe and quick coupling;Supporting mechanism is set to the side of train rail, is fixedly connected on supporting mechanism Lower arm pipe, one end of lower arm pipe are connected with pipeline road, and the other end bending of lower arm pipe is upward;One end of inner arm pipe bend to Under, upwards, one end of inner arm pipe is through the other end of rotary joint connection lower arm pipe, inner arm Guan Kexiang for the other end bending of inner arm pipe Lower arm pipe is swung in horizontal plane;Downwards, the other end bending of middle arm pipe is upward for one end bending of middle arm pipe, and the one of middle arm pipe The other end of the end through rotary joint connection inner arm pipe, middle arm pipe can be swung relative to inner arm pipe in horizontal plane;One end of external arm tube Bending downwards, the other end of external arm tube along horizontal extension, one end of external arm tube through rotary joint connect in arm pipe the other end, outside Arm pipe can be swung relative to middle arm pipe in horizontal plane;The one end of the other end of external arm tube through rotary joint connection hose, hose The other end is along horizontal extension, and one end of the other end connection upper arm pipe of hose, upper arm pipe is vertically extending, the other end of upper arm pipe Quick coupling is set, and hose can be rotated relative to external arm tube, and upper arm pipe can be swung with the rotation of hose.
2. tank container train loading arm according to claim 1, it is characterised in that: be equipped with hose branch on external arm tube Upper arm pipe supporting element is arranged in the end of support member, hose supporting element, and hose supporting element is placed in hose along horizontal extension, the hose On supporting element, upper arm pipe supporting element is vertically extending, and when being swung up to vertical position, upper arm pipe can be positioned at upper arm pipe On arm pipe supporting element.
3. tank container train loading arm according to claim 2, it is characterised in that: be detachably connected on external arm tube soft Pipe supporting element.
4. tank container train loading arm according to claim 2, it is characterised in that: set on the upper arm pipe supporting element It is equipped with handle.
5. tank container train loading arm according to claim 1, it is characterised in that: the supporting mechanism is that support is vertical Column, the bottom end of support post are fixedly connected with ground, and the lower part of support post is arranged lower support element, is fixedly connected down on lower support element Arm pipe.
6. tank container train loading arm according to claim 5, it is characterised in that: in the top setting of support post Supporting element is rotatably connected to vertical bull stick on upper supporting piece, and the lower end of vertical bull stick is fixedly connected with the outer wall of inner arm pipe.
7. tank container train loading arm according to claim 6, it is characterised in that: be provided on the supporting mechanism Lockable mechanism, lockable mechanism can the vertical bull sticks of interlocking.
8. tank container train loading arm according to claim 7, it is characterised in that: the lockable mechanism includes setting In the latch hook on supporting mechanism and the lockhole being set on vertical bull stick, the pluggable lockhole of latch hook.
9. tank container train loading arm according to claim 1, it is characterised in that: inner arm pipe, middle arm pipe and outer arm Fixed ring is provided on pipe, after inner arm pipe, middle arm pipe and external arm tube stack gradually, each fixed ring is also stacked gradually, each fixation It can be inserted into lock pin in ring.
10. tank container train loading arm according to claim 1, it is characterised in that: one end of lower arm pipe connects through pipe Head connection pipeline road.
CN201910551885.7A 2019-06-13 2019-06-25 Tank container train loading and unloading arm Active CN110316689B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201910508790 2019-06-13
CN2019105087907 2019-06-13

Publications (2)

Publication Number Publication Date
CN110316689A true CN110316689A (en) 2019-10-11
CN110316689B CN110316689B (en) 2024-06-18

Family

ID=68121143

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910551885.7A Active CN110316689B (en) 2019-06-13 2019-06-25 Tank container train loading and unloading arm

Country Status (1)

Country Link
CN (1) CN110316689B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111908414A (en) * 2020-08-12 2020-11-10 中国石油化工股份有限公司 Height-adjustable tank unloading arm
CN111981313A (en) * 2020-08-13 2020-11-24 梁峰 Gas universal loading and unloading arm

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004338777A (en) * 2003-05-16 2004-12-02 Sanyo Koki Kk Loading arm for liquid feeding in fluid loading apparatus
EP1630100A1 (en) * 2004-07-13 2006-03-01 von Meyerinck, Wolfgang, Dipl.-Ing. Head assembly for refuelling systems
CN203653225U (en) * 2013-11-22 2014-06-18 新乡市新飞专用汽车有限公司 Oil tank truck bottom fuel loading system
CN206266218U (en) * 2016-11-09 2017-06-20 中石化广州工程有限公司 A kind of band unloads oil filling riser under pulling valve
CN210505549U (en) * 2019-06-13 2020-05-12 中国石油化工股份有限公司 Tank container train loading and unloading arm

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004338777A (en) * 2003-05-16 2004-12-02 Sanyo Koki Kk Loading arm for liquid feeding in fluid loading apparatus
EP1630100A1 (en) * 2004-07-13 2006-03-01 von Meyerinck, Wolfgang, Dipl.-Ing. Head assembly for refuelling systems
CN203653225U (en) * 2013-11-22 2014-06-18 新乡市新飞专用汽车有限公司 Oil tank truck bottom fuel loading system
CN206266218U (en) * 2016-11-09 2017-06-20 中石化广州工程有限公司 A kind of band unloads oil filling riser under pulling valve
CN210505549U (en) * 2019-06-13 2020-05-12 中国石油化工股份有限公司 Tank container train loading and unloading arm

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111908414A (en) * 2020-08-12 2020-11-10 中国石油化工股份有限公司 Height-adjustable tank unloading arm
CN111981313A (en) * 2020-08-13 2020-11-24 梁峰 Gas universal loading and unloading arm

Also Published As

Publication number Publication date
CN110316689B (en) 2024-06-18

Similar Documents

Publication Publication Date Title
CN110316689A (en) Tank container train loading arm
CN210505549U (en) Tank container train loading and unloading arm
CN207759036U (en) A kind of plant protection drone
CN113830562B (en) Device for rapidly adding and subtracting pearlites and application method thereof
CN108996095A (en) Container intelligent storage
CN110872094A (en) Crane tube for unloading tank car and using method thereof
JPS6119468B2 (en)
CN105565246B (en) A kind of pitch truck tank entrucking oil filling riser device
CN208816104U (en) A kind of multi-functional liquid supply sledge
CN208710525U (en) It is a kind of for grabbing the mechanical arm of rotating cylinder
CN208790423U (en) Container intelligent storage
CN208868704U (en) A kind of automatic transfer pot of solvent
CN208074571U (en) A kind of LNG low temperature fluid handling arms balancer
CN220976574U (en) Cantilever type full-automatic loading and unloading small crane pipe
CN207307386U (en) A kind of fluid recycling bin for being used to recycle filtering waste oil
CN210855255U (en) Auxiliary discharging device for tank car
CN221217152U (en) Universal fixed unloading crane pipe
CN213199726U (en) Unloading arm for tank container
CN216735768U (en) Liquid filling machine unloading jar body
CN208040693U (en) A kind of oil cylinder pumping unit
CN210127075U (en) Semi-automatic filling equipment of edible oil
CN209012661U (en) Pressure of storage tank container
CN211393837U (en) Novel vertical pipe and swirl-free crane pipe
CN107289318A (en) Cryogenic tank
CN216513411U (en) Prevent sedimentation tank of jam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20191031

Address after: 100728 Beijing, Chaoyangmen, North Street, No. 22, No.

Applicant after: CHINA PETROLEUM & CHEMICAL Corp.

Applicant after: SINOPEC QINGDAO REFINING CHEMICAL Corp.,Ltd.

Address before: 266500 No. 827 Qianshan South Road, Huangdao District, Qingdao City, Shandong Province

Applicant before: SINOPEC QINGDAO REFINING CHEMICAL Corp.,Ltd.

GR01 Patent grant