CN110306606A - Pile foundation quality monitoring method and device for work progress - Google Patents

Pile foundation quality monitoring method and device for work progress Download PDF

Info

Publication number
CN110306606A
CN110306606A CN201910528612.0A CN201910528612A CN110306606A CN 110306606 A CN110306606 A CN 110306606A CN 201910528612 A CN201910528612 A CN 201910528612A CN 110306606 A CN110306606 A CN 110306606A
Authority
CN
China
Prior art keywords
pile
parameter
quality
elastic wave
ram
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910528612.0A
Other languages
Chinese (zh)
Other versions
CN110306606B (en
Inventor
刘杰
张千里
杜翠
陈锋
程远水
郭增强
李中国
王仲锦
王立军
王鹏程
郭浏卉
张兴增
张青波
崔维孝
杨常所
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
Original Assignee
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Railway Sciences Corp Ltd CARS, Railway Engineering Research Institute of CARS filed Critical China Academy of Railway Sciences Corp Ltd CARS
Priority to CN201910528612.0A priority Critical patent/CN110306606B/en
Publication of CN110306606A publication Critical patent/CN110306606A/en
Application granted granted Critical
Publication of CN110306606B publication Critical patent/CN110306606B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B17/00Measuring arrangements characterised by the use of infrasonic, sonic or ultrasonic vibrations
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N29/00Investigating or analysing materials by the use of ultrasonic, sonic or infrasonic waves; Visualisation of the interior of objects by transmitting ultrasonic or sonic waves through the object
    • G01N29/04Analysing solids
    • G01N29/045Analysing solids by imparting shocks to the workpiece and detecting the vibrations or the acoustic waves caused by the shocks
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N29/00Investigating or analysing materials by the use of ultrasonic, sonic or infrasonic waves; Visualisation of the interior of objects by transmitting ultrasonic or sonic waves through the object
    • G01N29/44Processing the detected response signal, e.g. electronic circuits specially adapted therefor
    • G01N29/46Processing the detected response signal, e.g. electronic circuits specially adapted therefor by spectral analysis, e.g. Fourier analysis or wavelet analysis
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2291/00Indexing codes associated with group G01N29/00
    • G01N2291/02Indexing codes associated with the analysed material
    • G01N2291/028Material parameters
    • G01N2291/0289Internal structure, e.g. defects, grain size, texture

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • Pathology (AREA)
  • Health & Medical Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • Signal Processing (AREA)
  • Immunology (AREA)
  • Mathematical Physics (AREA)
  • Spectroscopy & Molecular Physics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Acoustics & Sound (AREA)
  • Investigating Or Analyzing Materials By The Use Of Ultrasonic Waves (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention provides a kind of pile foundation quality monitoring method for work progress, it includes: in the examination pile stage, according to it is default ram parameter and carry out examination pile ram, determine that examination pile rams the correlativity between the middle spectrum signature for generating elastic wave and the mass parameter for reflecting construction quality;In the formal construction stage, according to it is default ram parameter and carry out formal construction ram, it determines that the middle real time spectrum feature for generating elastic wave is rammed in formal construction, real-time quality parameter is calculated according to real time spectrum feature and correlativity, quality-monitoring is carried out to current work progress.The present invention is rammed parameter and is rammed to test pile by default, obtains the correlativity of elastic wave spectrum signature and mass parameter;The formal construction stage calculates mass parameter according to correlativity, carries out bearing capacity monitoring.

Description

Pile foundation quality monitoring method and device for work progress
Technical field
The present invention relates to field of civil engineering, specifically, being related to a kind of pile foundation quality monitoring side for work progress Method and device.
Background technique
The detection method of traditional pile foundation includes static load test, low strain integrity test and high strain monitoring etc..All It is such as test pile detection, engineering pile detection, and to have the shortcomings that respective, be unfavorable for being generalized to and apply for the later detection of pile Implement during work.Dead load method preparation process is more, elapsed time is long, costly.Low strain dynamic method stake top sets sensor, for surveying Pile quality and defect.Large strain method need to use dedicated pile monkey, and sensor installation is complicated for operation, and sensor is perishable, at high cost.
Therefore, the present invention provides a kind of pile foundation quality monitoring methods and device for work progress.
Summary of the invention
To solve the above problems, the present invention provides a kind of pile foundation quality monitoring method for work progress, the side Method comprises the steps of:
In the examination pile stage, according to it is default ram parameter and carry out examination pile ram, determine that the examination pile rams middle generation Correlativity between the spectrum signature of elastic wave and the mass parameter for reflecting construction quality;
In the formal construction stage, according to it is described it is default ram parameter and carry out formal construction ram, determine the formal construction The middle real time spectrum feature for generating elastic wave is rammed, reality is calculated according to the real time spectrum feature and the correlativity When mass parameter, to current work progress carry out quality-monitoring.
According to one embodiment of present invention, determine that the examination pile rams the middle spectrum signature for generating elastic wave and reflection In the step of correlativity between the mass parameter of construction quality, also comprise the steps of:
The elastic wave that the examination pile rams middle generation is received, spectrum analysis is carried out, obtains the spectrum signature;
According to presetting method, measurement obtains the mass parameter of reflection construction quality;
Based on the spectrum signature and the mass parameter, the correlativity is obtained.
According to one embodiment of present invention, reality is calculated according to the real time spectrum feature and the correlativity When mass parameter, to current work progress carry out quality-monitoring the step of in, also comprise the steps of:
It brings the real time spectrum feature into the correlativity, the described real-time of the current construction quality of reflection is calculated Mass parameter;
The real-time quality parameter is compared with standard quality parameters, when the real-time quality parameter reaches the mark When the requirement of quasi- mass parameter, stop ramming.
According to one embodiment of present invention, by be arranged wave detector on the ground receive the examination pile ram and Formal construct rams the elastic wave of middle generation.
According to one embodiment of present invention, in the examination pile stage and/or the formal construction stage, according to reception To elastic wave pile crown depth is calculated.
According to one embodiment of present invention, in the step of pile crown depth being calculated according to the elastic wave received, also It comprises the steps of:
According at least three wave detectors that ground is arranged in, the reception examination pile is rammed and/or the formal construction is rammed At the time of hitting the elastic wave of generation and receive elastic wave;
Three wave detectors are measured respectively at a distance from stake holes, in conjunction with the elastic wave that receives and it is described when It carves, the pile crown depth is calculated by mathematical operation.
According to one embodiment of present invention, the method further includes: according to the pile crown depth, injection is hit in measurement three Degree.
According to one embodiment of present invention, the mass parameter includes bearing capacity.
According to one embodiment of present invention, described default to ram content specified in parameter and include: hammer diameter, the column of column hammer The length of hammer, the quality of column hammer and column hammer fall away from.
According to another aspect of the present invention, a kind of pile foundation quality monitoring device for work progress, institute are additionally provided Stating device includes:
First module, was used in the examination pile stage, according to it is default ram parameter and carry out examination pile ram, determine the examination Pile rams the correlativity between the middle spectrum signature for generating elastic wave and the mass parameter for reflecting construction quality;
Second module, was used in the formal construction stage, according to it is described it is default ram parameter and carry out formal construction ram, really The middle real time spectrum feature for generating elastic wave is rammed in the fixed formal construction, according to the real time spectrum feature and the correlation Real-time quality parameter is calculated in relationship, carries out quality-monitoring to current work progress.
Provided by the present invention for the pile foundation quality monitoring method and device of work progress, it is default ram parameter under, it is right Test pile carries out elastic wave test, mass parameter detection, obtains the correlativity of elastic wave spectrum signature and mass parameter;Formally apply The work stage only carries out elastic wave test, calculates mass parameter according to correlativity, achievees the purpose that bearing capacity monitors.Also, this Invention is using ramming as excitaton source, without additional setting excitaton source.Device simple is light, without it is pre-buried or pile body, hammer body Upper installation sensor, does not interfere work progress, with synchronous progress is rammed, parameters of construction technology can be instructed to select, saving is constructed into Sheet and time.
Other features and advantages of the present invention will be illustrated in the following description, also, partly becomes from specification It obtains it is clear that understand through the implementation of the invention.The objectives and other advantages of the invention can be by specification, right Specifically noted structure is achieved and obtained in claim and attached drawing.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention It applies example and is used together to explain the present invention, be not construed as limiting the invention.In the accompanying drawings:
Fig. 1 shows the pile foundation quality monitoring method process according to an embodiment of the invention for work progress Figure;
Fig. 2 shows in the pile foundation quality monitoring method according to an embodiment of the invention for work progress and determines The flow chart of correlativity;
Fig. 3 shows that the pile foundation quality monitoring field according to an embodiment of the invention for work progress is illustrated Figure;
Fig. 4 shows that the pile foundation quality monitoring method according to an embodiment of the invention for work progress calculates stake Schematic diagram when head depth;
Fig. 5 shows that the pile foundation quality monitoring method according to an embodiment of the invention for work progress carries out frequency Elastic wave spectrogram when spectrum analysis;
Fig. 6 shows frequency spectrum in the pile foundation quality monitoring method according to an embodiment of the invention for work progress The curve graph of feature and mass parameter;
Fig. 7 is shown in the pile foundation quality monitoring method according to an embodiment of the invention for work progress pre- If the graph of relation of spectrum signature and mass parameter under ramming parameter;And
Fig. 8 shows the pile foundation quality monitoring device structural frames according to an embodiment of the invention for work progress Figure.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the embodiment of the present invention is made below in conjunction with attached drawing Further it is described in detail.
For work progress, it is only referred to the monitoring of drive precast piles in specification, the not no defined side of specification of carrier pile Method.According to " JGJ106-2014 architecture foundation pile inspection specifications ", pile measurement can be divided into these following different stages:
1, before constructing: test pile detection provides foundation for design, determines ultimate bearing capacity of single pile.
2, after constructing: acceptance test, engineering pile detection provide foundation to check and accept, determine that bearing capacity of single pile and pile body are complete Property detection.
3, according to requirement of engineering, quality testing and monitoring work progress: are carried out.Drive precast piles, when requiring, Gao Ying Political reform carries out the piling process monitoring of examination piling.Pile body stress and hammering energy transmitting ratio when monitoring prefabricated pile is squeezed into, for choosing Process for sinking parameter and the long offer foundation of stake are provided.
For work progress, it is only referred to the monitoring of drive precast piles in specification, the not no defined side of specification of carrier pile Method.In specification, the pile measurement method mentioned see the table below 1.
The detection method of traditional pile foundation includes static load test, low strain integrity test and high strain monitoring etc..It carries There are carriers at body stake stake end, big using hammering energy required for Large strain, generally do not use this method to be detected, mainly The static load test of carrier pile and low strain integrity test.
Static load test is by preloading or anchoring pile as counterforce device, using jack as load means, classification pair Pile foundation or composite foundation are loaded, and simulate the stress of stake or composite foundation to detect whether it meets engineering design requirements Detection means.Generally comprise engineering test stake detection and engineering pile acceptance test.
The method that low strain integrity test generallys use is reflective wave method, and reflective wave method is propagated in solids using wave Rule analyze and determine by reflection wave at the bottom of pile signal a kind of lossless detection method of pile body and stake base concrete quality.It Tap in stake top using weight and generate shock wave, when shock wave is propagated in solids, when propagation medium changes, or passes When broadcasting section and changing, a part of wave will be reflected back stake top.Mathematics product is carried out by the signal acquired to stake top sensor Point, screening, separation and amplification analyze the defect of pile body.
The piling dynamic monitoring of Large strain method is divided into sensor installation, test macro debugging and data collection and analysis etc. 3 Process.1, the installation site of sensor is determined according to pile monkey length sleeve, it is ensured that sensor is located at pile hammer sleeve lower edge and cuts Pile beacon note is upper intermarginal, so as to effectively monitor stress wave information.Pile extension, weld seam, hammer set lower edge are avoided when installing sensor With the interference positions such as stake cross-section variation.The symmetric borehole on the circumference apart from stake top about 5m is bored using electromagnetism, is respectively used to The fixation of acceleration transducer, strain gauge and wireless transmitter.Before lifting, sensor, wireless transmitter are first installed.2, it adopts Debugging is monitored with test macro.3, after work is ready, data acquisition, analysis processing are carried out during piling.
The detection later both for pile of three of the above method such as test pile detection, engineering pile detection, and exists respective The shortcomings that, it is unfavorable for being generalized in work progress and implements.
1 testing goal of table and detection method
In the prior art, a kind of detection method of carrier pile bearing capacity hammers carrier pile using weight, is hammered by control Energy makes pile body generation vertical displacement determine the vertical of the pile by the shift value of measurement and the soil nature of bearing course at pile end Bearing capacity.
1) pile crown of the carrier pile detected to needs carries out reinforcement protection;
2) above pile crown, free-falling strikes pile crown after promoting certain altitude using weight, by controlling hammering energy So that pile body is generated downward vertical displacement, measures and records the shift value;
3) hammering operation for repeating step 2) when the gross energy repeatedly hammered reaches setting value, stops hammering and remembering Record the total displacement numerical value of pile body;
4) carrier equal calculation area Ae value is determined by the soil nature of total displacement numerical value, bearing course at pile end, then according to Ae value The vertical bearing capacity of the pile is calculated.
The prior art installs displacement sensor in pile crown, perishable, and need to frequently dismantle installation;Hammering energy need to be controlled, is needed The soil nature of measurement displacement and bearing course at pile end, it is complicated for operation;Vertical bearing capacity can only be surveyed;Work progress is interfered, construction party is needed to match It closes.
Fig. 1 shows the pile foundation quality monitoring method process according to an embodiment of the invention for work progress Figure.
As shown in Figure 1, in step s101, when trying pile, according to it is default ram parameter and carry out examination pile ram, determine Examination pile rams the correlativity between the middle spectrum signature and the mass parameter for reacting construction quality for generating elastic wave.
Preferably, correlativity can be determined by method as shown in Figure 2.Firstly, in step s 201, receive examination at The elastic wave of middle generation is rammed in stake, is carried out spectrum analysis, is obtained spectrum signature.Then, in step S202, foundation presetting method, Measurement obtains the mass parameter of reaction construction quality.Finally, being based on spectrum signature and mass parameter in step S203, obtaining To correlativity.
Such as Fig. 1, in step s 102, in the formal construction stage, according to it is default ram parameter and carry out formal construction ram, really The middle real time spectrum feature for generating elastic wave is rammed in fixed formal construction, is calculated according to real time spectrum feature and correlativity Real-time quality parameter carries out quality-monitoring to current work progress.
Preferably, it brings real time spectrum feature into correlativity, the real-time quality for reacting current construction quality is calculated Parameter.Then real-time quality parameter is compared with standard quality parameters, when implement quality parameters reach standard quality parameters Requirement when, stop ramming.
Preferably, it rams and formally constructs by the wave detector reception examination pile of setting on the ground and ram middle generation Elastic wave.
Further, in examination pile stage and/or formal construction stage, pile crown is calculated according to the elastic wave received Depth.
Specifically, pile crown depth is calculated by the following method:
Firstly, according at least three wave detectors that ground is arranged in, receive during examination pile rams and/or formally construct and ram The elastic wave of generation and at the time of receive elastic wave.
Then, three wave detectors are measured respectively at a distance from stake holes, in conjunction with the elastic wave and moment received, pass through number Pile crown depth is calculated in student movement calculation.
In one embodiment, also include: according to pile crown depth, measuring penetration.
Preferably, mass parameter includes bearing capacity.
In one embodiment, preset to ram content specified in parameter and include: the hammer diameter of column hammer, column hammer length, Column hammer quality and column hammer fall away from.
Fig. 3 shows that the pile foundation quality monitoring field according to an embodiment of the invention for work progress is illustrated Figure.
The work progress on-the-spot schematic towards carrier pile piling is shown in Fig. 3.To the 1st pile, elastic wave test is used Spectrum signature E, the survey of dead load the method more directly mass parameter R of reflection construction quality are obtained, the correlation of E and R are established.Rear When continuing other pile driving constructions, frequency measurement spectrum signature E can extrapolate parameter R, thus judge construction quality, auxiliary construction.Quality ginseng Compactness, static sounding etc. in number R, complexity is higher, so surveying an associated variable E, carrys out indirect determination R.It needs It is noted that mass parameter includes bearing capacity.
Such as Fig. 3, need to be arranged on the ground near stake holes wave detector, the quantity of wave detector is according to the difference of monitoring objective And change, it can be 1, be also possible to multiple.
When carrying out test pile elastic wave on-site test, open detection instrument is rammed as emission source using column hammer, generates bullet Property wave, wave detector receives the transmitted wave signal from stake bottom, as column hammer is repeatedly rammed, repeats excitation reception.In addition, trying During stake the ramming of stage, mass parameter R is measured.
It when the quantity of wave detector is at least three, can be analyzed by elastic wave data, pile crown depth is calculated Degree.As shown in Figure 4, it is shown that calculate schematic diagram when pile crown depth.It should be noted that mass parameter includes bearing capacity.
Such as Fig. 4, the data that pile crown depth at least needs 3 wave detectors, the waveform rammed using any single are calculated.It is to be measured Value is pile crown depth H=LMN, data that wave detector can measure are as follows: this 3 wave detectors of wave detector A, wave detector B, wave detector C connect At the time of the waveform received.
It is assumed that the underground space Elastic Wave Velocity of delta-shaped region is uniform, following equation group can be obtained:
V×TNA=LNA
V×TNB=LNB
V×TNC=LNC
Wherein, V indicates velocity of wave, TNA、TNB、TNCRespectively indicate the time that elastic wave is propagated in NA, NB, NC, LNA、LNB、LNC Respectively indicate the linear distance of wave detector A, wave detector B, wave detector C and position N (pile crown).
Because wave detector possibly can not measure accurate triggered time, the correct time T that waveform is propagated in NA, NB, NCNA、 TNB、TNCIt can not obtain, but can obtain 2 time differences according to the reception waveform moment measured.
△ T1=TNB-TNA
△ T2=TNC-TNA
Wherein, △ T1 indicates that wave detector B and wave detector A receive the time difference of elastic wave, and △ T2 indicates wave detector C and inspection Wave device A receives the time difference of elastic wave.
Equation group can be changed to:
V×TNA=LNA
V×(△T1+TNA)=LNB
V×(△T2+TNA)=LNC
By LNA、LNB、LNCIt is indicated with H, e.g.,
Then equation group can be changed to:
Equation group unknown quantity is V, TNA, H, above 3 equations, 3 unknown quantitys can solve H with mathematical operation.
Furthermore it is also possible to carry out the processing such as Fourier transformation to the elastic wave received, spectrum analysis is carried out, calculates and rams every time The spectrum signature E hit.When the changing value △ E that column hammer is rammed twice is less than preset threshold, it is further continued for ramming without practical significance, stops Only ram.
Spectrum signature E is exemplified below, and is not limited to following several situations:
It is unimodal: dominant frequency.
It is bimodal: the absolute value of the difference of two peak values.
In addition, spectrum signature includes: energy variation, dominant frequency and peak value are mobile.
By spectrum signature E and the parameter R measured, R and E correlation curve during being rammed.Assuming that elastic wave connects The waveform received be it is unimodal, spectrum signature is indicated with E.(horizontal axis indicates frequency, and the longitudinal axis indicates amplitude) as shown in Figure 5, dominant frequency Frequency with ram reduce.R with ram increase, E with ram increase, be positively correlated, as shown in Figure 6.According to this correlation Property, can obtain it is default ram parameter under, the correlation curve of the two, as shown in fig. 7, R can be calculated according to E.It should be noted that Mass parameter includes bearing capacity.Wherein, presetting and ramming content specified in parameter includes the hammer diameter of column hammer, the length of column hammer, column Hammer quality and column hammer fall away from etc..
The reason of considering construction shock-effect: due to the compacting effect of column hammer in carrier pile work progress, vibration can be generated Wave, if heavy tamping energy is excessive, it would be possible to be impacted to building.
In formal work progress, dynamic monitoring is may be implemented in the present invention.Parameter is rammed according to default, carries out carrier pile Ram construction.Then, elastic wave test is carried out with work progress.Finally, calculating carrying according to E correlation curve corresponding with R Power R stops ramming when reaching requirement.
In addition, can arrange multiple wave detectors at the construction field (site), multiple carrier pile driving constructions can be monitored simultaneously.But it needs to pay attention to It is that there are two hammer while cannot land.
It should be noted that the present invention can be used for the bottom hole and carrier pile head carrier of pore forming process, it is not limited to carry Body stake, moreover it is possible to which loading test is carried out to other in situ concrete piles, precast concrete pile.Pile foundation includes building construction pile foundation, It also include other architectural engineering foundation piles such as highway, railway, bridge.Wave detector number can change, if pile head depth, until It is 3 few.
In addition, in the construction process, the field of civil engineering specification for needing to abide by includes: " architecture foundation pile detection technique rule Model " (JGJ106-2014), " railway engineering Test Technology of Pile Foundation regulation " (TB 10218-2008) and " highway engineering foundation pile is dynamic Survey technology regulation " (JTG/T F81-01-2004).
As described above, during present invention monitoring is rammed, the bearing capacity of stake end carrier, rather than the detection after pile, because It such as finds the problem after pile, remedial measure is highly difficult, very complicated.Using elastic wave transmission method, but without additional, emission source is set, But it is rammed using column hammer as emission source.Without sensor is arranged in pile body or hammer body, bearing capacity and guidance can be detected Parameter selection and construction progress.
Fig. 8 shows the pile foundation quality monitoring device structural frames according to an embodiment of the invention for work progress Figure.As shown in figure 8, monitoring device 800 includes: the first module 801 and the second module 802.
Wherein, the first module 801 was used in the examination pile stage, according to it is default ram parameter and carry out examination pile ram, determine Examination pile rams the correlativity between the middle spectrum signature for generating elastic wave and the mass parameter for reflecting construction quality.
Second module 802 was used in the formal construction stage, according to it is default ram parameter and carry out formal construction ram, determine just The middle real time spectrum feature for generating elastic wave is rammed in formula construction, is calculated in real time according to real time spectrum feature and correlativity Mass parameter carries out quality-monitoring to current work progress.
In one embodiment, monitoring device may include multiple wave detectors, temporal data library, data transmission module, show Field terminal and server.On-site terminal is connect with server, on-site terminal by data transmission module respectively with wave detector, temporarily The connection of deposit data library, the output end of wave detector are connected to the input terminal in temporal data library.
Wave detector and on-site terminal can guarantee detection by wireless adapter, USB communication module or serial communication module Data in real time, dynamic and do not land transmission, it is ensured that its authenticity;And data buffer storage is made using temporal data library, guarantee that data are complete Whole property, timeliness and transmission stability.
To sum up, provided by the present invention for the pile foundation quality monitoring method and device of work progress, parameter is rammed default Under, elastic wave test, mass parameter detection are carried out to test pile, obtain the correlativity of elastic wave spectrum signature and mass parameter; The formal construction stage only carries out elastic wave test, calculates mass parameter according to correlativity, achievees the purpose that bearing capacity monitors. Also, the present invention is using ramming as excitaton source, without additional setting excitaton source.Device simple is light, without pre-buried or in stake Sensor is installed with body, hammer, does not interfere work progress, with synchronous progress is rammed, parameters of construction technology can be instructed to select, is saved Construction cost and time.
It should be understood that disclosed embodiment of this invention is not limited to specific structure disclosed herein, processing step Or material, and the equivalent substitute for these features that those of ordinary skill in the related art are understood should be extended to.It should also manage Solution, term as used herein is used only for the purpose of describing specific embodiments, and is not intended to limit.
" one embodiment " or " embodiment " mentioned in specification means the special characteristic described in conjunction with the embodiments, structure Or characteristic is included at least one embodiment of the present invention.Therefore, the phrase " reality that specification various places throughout occurs Apply example " or " embodiment " the same embodiment might not be referred both to.
While it is disclosed that embodiment content as above but described only to facilitate understanding the present invention and adopting Embodiment is not intended to limit the invention.Any those skilled in the art to which this invention pertains are not departing from this Under the premise of the disclosed spirit and scope of invention, any modification and change can be made in the implementing form and in details, But scope of patent protection of the invention, still should be subject to the scope of the claims as defined in the appended claims.

Claims (10)

1. a kind of pile foundation quality monitoring method for work progress, which is characterized in that the method comprises the steps of:
In the examination pile stage, according to it is default ram parameter and carry out examination pile ram, it is elastic to determine that the examination pile rams middle generation Correlativity between the spectrum signature of wave and the mass parameter for reflecting construction quality;
In the formal construction stage, according to it is described it is default ram parameter and carry out formal construction ram, determine that the formal construction is rammed The middle real time spectrum feature for generating elastic wave, is calculated real-time matter according to the real time spectrum feature and the correlativity Parameter is measured, quality-monitoring is carried out to current work progress.
2. the method as described in claim 1, which is characterized in that it is special to determine that the examination pile rams the middle frequency spectrum for generating elastic wave In the step of levying the correlativity between the mass parameter of reflection construction quality, also comprise the steps of:
The elastic wave that the examination pile rams middle generation is received, spectrum analysis is carried out, obtains the spectrum signature;
According to presetting method, measurement obtains the mass parameter of reflection construction quality;
Based on the spectrum signature and the mass parameter, the correlativity is obtained.
3. such as method of any of claims 1-2, which is characterized in that according to the real time spectrum feature and described It also include following step in the step of real-time quality parameter is calculated in correlativity, carries out quality-monitoring to current work progress It is rapid:
It brings the real time spectrum feature into the correlativity, the real-time quality for reflecting current construction quality is calculated Parameter;
The real-time quality parameter is compared with standard quality parameters, when the real-time quality parameter reaches the standard matter When measuring the requirement of parameter, stop ramming.
4. method as claimed in any one of claims 1-3, which is characterized in that by the way that wave detector reception on the ground is arranged The examination pile is rammed and formal construct rams the elastic wave of middle generation.
5. method as claimed in claim 4, which is characterized in that the method further includes: in the examination pile stage and/or institute The formal construction stage is stated, pile crown depth is calculated according to the elastic wave received.
6. method as claimed in claim 5, which is characterized in that the step of pile crown depth is calculated according to the elastic wave received In rapid, also comprise the steps of:
According at least three wave detectors that ground is arranged in, receive that the examination pile is rammed and/or formal construct is rammed The elastic wave of generation and at the time of receive elastic wave;
Three wave detectors are measured respectively at a distance from stake holes, in conjunction with the elastic wave and the moment received, are led to It crosses mathematical operation and the pile crown depth is calculated.
7. the method as described in any one of claim 5-6, which is characterized in that the method further includes: according to the pile crown Depth measures penetration.
8. such as method of any of claims 1-7, which is characterized in that the mass parameter includes bearing capacity.
9. such as method of any of claims 1-8, which is characterized in that described preset rams content specified in parameter Include: column hammer hammer diameter, column hammer length, column hammer quality and column hammer into shape fall away from.
10. a kind of pile foundation quality monitoring device for work progress, which is characterized in that described device includes:
First module, was used in the examination pile stage, according to it is default ram parameter and carry out examination pile ram, determine the examination pile Ram the correlativity between the spectrum signature for generating elastic wave and the mass parameter for reflecting construction quality;
Second module, was used in the formal construction stage, according to it is described it is default ram parameter and carry out formal construction ram, determine institute It states formal construction and rams the middle real time spectrum feature for generating elastic wave, according to the real time spectrum feature and the correlativity Real-time quality parameter is calculated, quality-monitoring is carried out to current work progress.
CN201910528612.0A 2019-06-18 2019-06-18 Pile foundation quality monitoring method and device for construction process Active CN110306606B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910528612.0A CN110306606B (en) 2019-06-18 2019-06-18 Pile foundation quality monitoring method and device for construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910528612.0A CN110306606B (en) 2019-06-18 2019-06-18 Pile foundation quality monitoring method and device for construction process

Publications (2)

Publication Number Publication Date
CN110306606A true CN110306606A (en) 2019-10-08
CN110306606B CN110306606B (en) 2020-12-11

Family

ID=68077739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910528612.0A Active CN110306606B (en) 2019-06-18 2019-06-18 Pile foundation quality monitoring method and device for construction process

Country Status (1)

Country Link
CN (1) CN110306606B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114737621A (en) * 2022-04-02 2022-07-12 襄阳东磊检测技术服务有限公司 Nondestructive foundation pile detection method based on outer cross hole of pile

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2459042C1 (en) * 2011-02-28 2012-08-20 Закрытое акционерное общество Соликамский строительный трест Method to determine bearing capacity of driven pile
CN104328776A (en) * 2014-09-23 2015-02-04 同济大学 Method for predicting influence of dynamic compaction on soil body and surrounding environment
CN104878785A (en) * 2015-05-18 2015-09-02 湖北工业大学 Pile-soil interaction and pile-end soil constitutive model and parameter determining method thereof
CN105780772A (en) * 2016-03-24 2016-07-20 三峡大学 Method for optimally designing anchor rod grouting parameters through researching characteristics of expansible binding materials in anchor rod grouting
CN106326552A (en) * 2016-08-24 2017-01-11 青岛理工大学 Dynamic compaction reinforcing method for improving stability of cast-in-place pile collapse hole

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2459042C1 (en) * 2011-02-28 2012-08-20 Закрытое акционерное общество Соликамский строительный трест Method to determine bearing capacity of driven pile
CN104328776A (en) * 2014-09-23 2015-02-04 同济大学 Method for predicting influence of dynamic compaction on soil body and surrounding environment
CN104878785A (en) * 2015-05-18 2015-09-02 湖北工业大学 Pile-soil interaction and pile-end soil constitutive model and parameter determining method thereof
CN105780772A (en) * 2016-03-24 2016-07-20 三峡大学 Method for optimally designing anchor rod grouting parameters through researching characteristics of expansible binding materials in anchor rod grouting
CN106326552A (en) * 2016-08-24 2017-01-11 青岛理工大学 Dynamic compaction reinforcing method for improving stability of cast-in-place pile collapse hole

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114737621A (en) * 2022-04-02 2022-07-12 襄阳东磊检测技术服务有限公司 Nondestructive foundation pile detection method based on outer cross hole of pile

Also Published As

Publication number Publication date
CN110306606B (en) 2020-12-11

Similar Documents

Publication Publication Date Title
Holeyman Keynote lecture: Technology of pile dynamic testing
CN106770643B (en) Method for detecting pile bottom grouting effect of expanded-bottom cast-in-place pile based on sound wave propagation principle
CN210917488U (en) Pile foundation quality monitoring system for construction process
Monaco et al. Interrelationship between small strain modulus G0 and operative modulus
CN106149770B (en) The large-section in-situ concrete pile hole wall rock mass integrality detection method that bored concrete pile pile foundation construction period synchronously carries out
Anusic et al. Influence of installation method on static lateral response of displacement piles in sand
Sahadewa et al. Field testing method for evaluating the small-strain shear modulus and shear modulus nonlinearity of solid waste
Fellenius Pile foundations
CN117552483B (en) Test method for foundation reinforcement influence range of dynamic compaction treatment
CN110306606A (en) Pile foundation quality monitoring method and device for work progress
CN102268886B (en) Method for detecting and evaluating design bearing capacity of pile foundation of offshore oil platform
CN208105265U (en) A kind of Driven Piles machine and pile penetration detection device
Lo et al. MEASUREMENT OF UNKNOWN BRIDGE FOUNDATION DEPTH BY PARALLEL SEISMIC METHOD.
CN109469119A (en) A kind of test method of offshore wind farm steel tube pile embeded in rock
CN110306604A (en) Optimal for work progress rams parameter selection method and device
CN108427142A (en) A kind of prefabricated pile stake bottom CAVE DETECTION system and method
CN108221994A (en) A kind of Driven Piles machine and pile penetration detection device
Flynn et al. Driven cast-in-situ piles installed using hydraulic hammers: Installation energy transfer and driveability assessment
JPH08248142A (en) Method and apparatus for investigation of ground by s-wave generation device and cone penetration device carried on ground investigation vehicle
Zhussupbekov et al. The experience different of piling testing on problematical soil ground of Astana, Kazakhstan
Hussein et al. Deep foundations quality control and quality assurance testing methods
CN216474921U (en) Mechanical property parameter measuring equipment for saturated soil foundation
Tulebekova et al. The Non-destructive testing of bored piles
Sack et al. Combined parallel seismic and cone penetrometer testing of existing bridge foundations and levee sheet piles for length and capacity evaluations
CN215725772U (en) Anchor rod length detection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant