CN110295667A - A kind of assembled architecture room and assembled architecture room construction method - Google Patents

A kind of assembled architecture room and assembled architecture room construction method Download PDF

Info

Publication number
CN110295667A
CN110295667A CN201910528576.8A CN201910528576A CN110295667A CN 110295667 A CN110295667 A CN 110295667A CN 201910528576 A CN201910528576 A CN 201910528576A CN 110295667 A CN110295667 A CN 110295667A
Authority
CN
China
Prior art keywords
sole plate
assembled architecture
overturn
room
spud pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910528576.8A
Other languages
Chinese (zh)
Other versions
CN110295667B (en
Inventor
徐攀
杨多娇
杨德志
龚俊
邓波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201910528576.8A priority Critical patent/CN110295667B/en
Publication of CN110295667A publication Critical patent/CN110295667A/en
Application granted granted Critical
Publication of CN110295667B publication Critical patent/CN110295667B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34315Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34315Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
    • E04B1/34321Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts mainly constituted by panels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/52Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits
    • E04C2/521Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling
    • E04C2/523Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling for ventilating
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02SGENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES
    • H02S20/00Supporting structures for PV modules
    • H02S20/30Supporting structures being movable or adjustable, e.g. for angle adjustment
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/10Photovoltaic [PV]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Foundations (AREA)
  • Photovoltaic Devices (AREA)

Abstract

The application provides a kind of assembled architecture room and assembled architecture room construction method, belongs to building field.It includes sole plate;Multiple the first spud piles for immobilizing foundation bottom plate, multiple first spud piles are mounted on sole plate with being respectively separated, and are extended and be fixed in soil layer;Multiple prefabricated panels, multiple prefabricated panel compartment of terrain are fixed on sole plate;Multiple overturn-preventing ground beams, multiple overturn-preventing ground beams are mounted on the side of sole plate;Multiple for fixing the second spud pile of overturn-preventing ground beam, multiple second spud piles are mounted on overturn-preventing ground beam with being respectively separated, and are extended and be fixed in soil layer.Device assembling is convenient, applied widely, and environmental protection and energy saving, structural stability are good.

Description

A kind of assembled architecture room and assembled architecture room construction method
Technical field
This application involves building field more particularly to a kind of assembled architecture rooms and assembled architecture room construction party Method.
Background technique
In recent years, with the fast development of building trade, urban architecture is more and more, and a large amount of buildings are generated in work progress Rubbish runs in the opposite direction to the increasing level of cultural life, previous temporary building with room generally use cast-in-place foundation beam and Bottom plate combines fabricated cystosepiment, and a large amount of reluctant rubbish are generated in installation and use process, though in installation process So light but part installation site electric pipeline needs interim cutting, to being impacted in use process, when disassembly due to every Plate is slightly insufficient, and when disassembly is easy to damage, and impacts to secondary use, and generates more waste rubbish, influences daily Life.It is also insufficient for the stable degree of strong convective weather total.
Summary of the invention
The first purpose of the application is to provide a kind of assembled architecture room and assembled architecture room construction method, purport Time-consuming and laborious problem is torn open improving temporary building room peace in the prior art.
The technical solution of the application is:
A kind of assembled architecture room, comprising:
Sole plate;
Multiple the first spud piles for being used to fix the sole plate, multiple first spud piles are installed with being respectively separated On the sole plate, and extends and be fixed in soil layer;
Multiple prefabricated panels, multiple prefabricated panel compartment of terrain are fixed on the sole plate;
Multiple overturn-preventing ground beams, multiple overturn-preventing ground beams are mounted on the side of the sole plate;
Multiple the second spud piles for being used to fix the overturn-preventing ground beam, multiple second spud piles are pacified with being respectively separated On the overturn-preventing ground beam, and extends and be fixed in soil layer.
As a kind of technical solution of the application, multiple reserved fixing grooves are offered on the sole plate, it is described reserved It is equipped in fixing groove multiple for fixing the first spud pile of the sole plate.
As a kind of technical solution of the application, multiple reserved fixing grooves are arranged in rows on the sole plate.
As a kind of technical solution of the application, multiple reserved locating slots are offered on the sole plate, it is multiple described The prefabricated panel is installed in reserved locating slot.
As a kind of technical solution of the application, cover board is installed on multiple prefabricated panels, is installed on the cover board There are multiple solar panels and multiple support rods, one end of the support rod is mounted on the cover board, and the other end is movably pacified On the solar panels, the other end of the support rod can be moved along the length direction of the solar panels, described Solar panels are arranged on the cover board.
As a kind of technical solution of the application, compartment of terrain offers multiple for storing the solar energy on the cover board The accommodating groove of plate, one end of the support rod are movably mounted in the accommodating groove, and the other end is movably attached to institute State solar panels.
As a kind of technical solution of the application, the bottom of the cover board is equipped with multiple fans, multiple dry walls The air inlet and air outlet being equipped with the fan are offered on plate respectively.
A kind of assembled architecture room construction method, above-described assembled architecture room, the assembled architecture are used Room construction method the following steps are included:
The occupied area in assembled architecture room is carried out data acquisition on the spot by S1, and size carries out institute according to area The precast concrete design in assembled architecture room is stated, while carrying out electrical and water-feeding drainaging line pre-buried design;
S2 carries out compacting processing according to the floor area dimensions smooth location in the assembled architecture room, will design With room land occupation position every room for building carry out unwrapping wire, to the connecting portion of the sole plate and the overturn-preventing ground beam It is marked;
S3 installs the sole plate: it is good that the prefabricated sole plate component is placed to setting-out using crane The installation flatness of position, the sole plate controls within the scope of ± 2mm, to ensure the installation of subsequent members;
The fixed sole plate: S4 opens up the multiple first reserved fixing grooves, by described first on the sole plate Spud pile is put into the described first reserved fixing groove reserved, and the vertical of first spud pile is measured by level guiding ruler It spends, after the verticality for adjusting first spud pile, first spud pile is hammered in insertion soil layer;It is pre- described first The gap position of fixing groove is stayed to fill waterproof cementitious material;
S5 installs the overturn-preventing ground beam: the link position of the overturn-preventing ground beam and the sole plate is kept tight Contiguity touching and vertical, opens up the multiple second reserved fixing grooves in the overturn-preventing ground beam, will second spud pile fixed installation In the second reserved fixing groove, the verticality of second spud pile is measured by level guiding ruler, and it is solid to adjust described second After the verticality for determining stake, second spud pile is hammered in insertion soil layer;At the gap position of the described second reserved fixing groove Fill waterproof cementitious material;
S6 installs the prefabricated panel and cover board: multiple reserved locating slots are opened up on the sole plate, it will be described pre- Wallboard processed is put into the reserved locating slot, and by the installation site of prefabricated panel described in axis trimming, deviation is controlled in 3mm model In enclosing;The cover plate lid is located on multiple prefabricated panels;
S7 installs fan and solar panels: multiple solar panels is installed on the cover board, at the bottom of the cover board Portion is installed by multiple fans.
As a kind of technical solution of the application, first spud pile and second spud pile are all made of high-intensitive aluminium Alloy material, a length of 2 meters of the stake of first spud pile and second spud pile, pile body is provided with multiple for reperfusion serosity Injected hole.
The application's the utility model has the advantages that
The assembled architecture of the application realizes energy-saving and environment-friendly assembled architecture using natural energy resources in room construction method With room, solar energy power store device is arranged by roof (i.e. cover board) and solves the future normal electrical problem, reduces outer power-on box, the energy is only It is vertical to use;Meanwhile air inlet and air outlet are set on roof, the natural wind of air inlet drives attic fan to make air-flow to interior And flowed, to increase air flowing, electric fan and air conditioning utilization rate are reduced, saves the energy.Meanwhile utilizing dry wall Recirculated water is set in plate, so that taking away indoor heat solves the problems, such as Temperature fall;It is combined using overturn-preventing ground beam and wirerope It solves the problems, such as to prevent from being toppled with room when extreme weather;When assembled architecture is installed with room, using prefabricated base plate, use is high-strength (i.e. the first spud pile and the second spud pile) is fixed in degree aluminium alloy stake, solves piling bar in the prior art in underground and is easy corruption It loses and influences the firm problem of foundation structure, also enhance the operability of site operation;Fastening bolt is used when wallboard is installed Form carries out wallboard and reinforces fixing measure, solves the problems, such as that prefabricated panel mounting and dismounting are inconvenient, fastening form also improves existing The flexible installation of field operation, is arranged circulation pipe by partition and some perforations reaches noise reduction soundproof effect.By utilizing natural energy Energy-saving and environment-friendly assembled architecture room is realized in source, changes conventional construction method, and this method installing and dismounting safety is convenient to assemble and disassemble, Reduce environmental pollution;Meanwhile the structure reusable rate is high, at low cost, structural stability is good, does not need to put into other big Type equipment preferably resolves the problem of the interim movable building room constructional difficulties in construction site.
Detailed description of the invention
It, below will be to use required in embodiment in order to illustrate more clearly of the technical solution of the application embodiment Attached drawing be briefly described, it should be understood that the following drawings illustrates only some embodiments of the application, therefore is not to be seen as It is the restriction to range, it for those of ordinary skill in the art, without creative efforts, can be with root Other relevant attached drawings are obtained according to these attached drawings.
Fig. 1 is the floor map in assembled architecture room provided by the embodiments of the present application;
Fig. 2 is that first spud pile in assembled architecture room provided by the embodiments of the present application installs diagrammatic cross-section;
Fig. 3 is the prefabricated panel diagrammatic cross-section in assembled architecture room provided by the embodiments of the present application;
Fig. 4 is the diagrammatic cross-section of assembled architecture room provided by the embodiments of the present application sole plate.
Icon: 1- assembled architecture room;2- sole plate;The first spud pile of 3-;4- prefabricated panel;5- overturn-preventing Beam;The second spud pile of 6-;7- first reserves fixing groove;8- reserves locating slot;9- cover board;10- solar panels;11- support rod; 12- accommodating groove;13- fan;14- air inlet;15- air outlet.
Specific embodiment
To keep the purposes, technical schemes and advantages of the embodiment of the present application clearer, below in conjunction with the embodiment of the present application In attached drawing, the technical scheme in the embodiment of the application is clearly and completely described, it is clear that described embodiment is Some embodiments of the present application, instead of all the embodiments.The application for usually describing and showing in attached drawing here is real The component for applying example can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiments herein provided in the accompanying drawings is not intended to limit below claimed Scope of the present application, but be merely representative of the selected embodiment of the application.Based on the embodiment in the application, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model of the application protection It encloses.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.
In the description of the present application, it should be noted that the orientation or positional relationship of the instructions such as term " on ", "lower" is base In orientation or positional relationship shown in the drawings or the invention product using when the orientation or positional relationship usually put, only It is the application and simplified description for ease of description, rather than the device or element of indication or suggestion meaning must have specifically Orientation is constructed and operated in a specific orientation, therefore should not be understood as the limitation to the application.
In addition, in this application unless specifically defined or limited otherwise, fisrt feature is on or below second feature It may include that the first and second features directly contact, also may include that the first and second features are not direct contacts but pass through it Between other characterisation contact.Moreover, fisrt feature is on second feature, top and above include fisrt feature the Right above two features and oblique upper, or first feature horizontal height is merely representative of higher than second feature.Fisrt feature is in the second spy Under sign, lower section and fisrt feature included below be directly below and diagonally below the second feature, or be merely representative of fisrt feature level Height is less than second feature.
In addition, the terms such as term "horizontal", "vertical" are not offered as requiring component abswolute level or pendency, but can be slightly Low dip.It is not to indicate that the structure has been had to if "horizontal" only refers to that its direction is more horizontal with respect to for "vertical" It is complete horizontal, but can be slightly tilted.
In the description of the present application, it is also necessary to which explanation is unless specifically defined or limited otherwise, term " setting ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally connect It connects;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, can also indirectly connected through an intermediary, it can To be the connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood with concrete condition Concrete meaning in this application.
Embodiment:
Fig. 1 is please referred to, referring to Figure 2 to Figure 4, the application provides a kind of assembled architecture room 1 for cooperation, and main includes basis Bottom plate 2, multiple the first spud piles 3, multiple prefabricated panels 4 and multiple overturn-preventing ground beams 5 for immobilizing foundation bottom plate 2;Base The multiple first reserved fixing grooves 7 are offered on plinth bottom plate 2, the first spud pile 3 is installed in first reserved fixing groove 7, and first is solid Determine to pour the waterproof cementitious material stake for the two to be fixedly connected, Duo Ge in stake 3 and the gap of the first reserved fixing groove 7 The extension of one spud pile 3 is fixed in soil layer;Meanwhile multiple reserved locating slots 8 are offered on sole plate 2, multiple reserved positioning Prefabricated panel 4 is installed in slot 8;Multiple overturn-preventing ground beams 5 are mounted on the side of sole plate 2, are opened up on overturn-preventing ground beam 5 There is the second reserved fixing groove, the second spud pile 6, the second spud pile 6 and the second reserved fixation are installed in the second reserved fixing groove Waterproof cementitious material has been poured in the gap of slot, achievees the effect that waterproof is firm;It is multiple to be used to fix the second of overturn-preventing ground beam 5 The extension of spud pile 6 is fixed in soil layer.
It should be noted that in the present embodiment, using fixed spiral shell at overturn-preventing ground beam 5 and 2 link position of sole plate Bolt is reinforced again, it is ensured that it is whole that overturn-preventing ground beam 5 connect formation with sole plate 2, to improve integrally-built firm Property.
It should be noted that in the present embodiment, multiple first reserved fixing grooves 7 are arranged in rows on sole plate 2, and On center in sole plate 2;Multiple reserved locating slots 8 are in the outside of the multiple first reserved fixing grooves 7, and it is opened Opening diameter of the mouth diameter less than the first reserved fixing groove 7.
Referring to figure 3., clamp device, clamp device and prefabricated panel 4 are installed in the reserved locating slot 8 of sole plate 2 Bottom be fixedly connected so that is connected between prefabricated panel 4 and sole plate 2 is stronger;It is opened on the bottom of prefabricated panel 4 Equipped with mounting hole, the position of clamp device can be adjusted by the mounting hole, so that prefabricated panel 4 and sole plate 2 It is tightly fastened to form effective entirety, reach using function;Prefabricated panel 4 is provided with reserved opening during the installation process, at top, The reserved opening is used to carry out tube body connection, to form circulation pipe between the built-in pipe in prefabricated panel 4, and is linked to be entirety, Recirculated water can be connected in the circulation pipe, so that taking away indoor heat solves the problems, such as Temperature fall.
Further, the lid of cover board 9 is located on multiple prefabricated panels 4, and compartment of terrain offers multiple for storing too on cover board 9 The accommodating groove 12 of positive energy plate 10, one end of support rod 11 are movably mounted in accommodating groove 12, and the other end is movably coupled to In solar panels 10;The other end of support rod 11 can be moved along the length direction of solar panels 10, and solar panels 10 are arranged On cover board 9.
It should be noted that in the present embodiment, solar panels 10 are arranged in accommodating groove 12, solar energy integral inclinedly Be provided on direction axially along on the bottom of plate 10 with the mutually matched sliding slot in one end of support rod 11, the support rod 11 One end is slidably mounted in the sliding slot, realizes solar panels 10 by the mobile position of the support rod 11 in sliding slot Lifting.
It should be noted that in the present embodiment, the bottom of cover board 9 is equipped with multiple fans 13, multiple prefabricated panels 4 Offer the air inlet 14 and air outlet 15 being equipped with fan 13 on top respectively, fan 13 by from air inlet 14 into The natural wind that enters drives own rotation, horizontal gas flow is introduced indoor, so that indoor air flow is effectively circulated, realizes really environmental protection Energy saving building assembled room.
It should be noted that in the present embodiment, a kind of 1 construction method of assembled architecture room is additionally provided, it is main The following steps are included:
The occupied area in room for building is carried out data on the spot first and acquired, according to area size by S1 according to purpose is used The PC component for carrying out room for building is designed, and when design will carry out electrical and water-feeding drainaging line pre-buried design simultaneously, is accomplished The decoration room of stabilized structure and beauty;Meanwhile micronization processes are carried out to each component connecting portion, guarantee the strong of connecting portion Degree and stability reach requirement, especially the stiffness and strength of extreme weather overturn-preventing ground beam 5 and wirerope it is practical and The angle etc. of wirerope;
S2 carries out compacting processing according to floor area dimensions smooth location, is built designed with room land occupation position every It builds and carries out unwrapping wire with room, it is ensured that the precision of installation reaches requirement, at least ensures that within 3mm, is difficult to handle seam to prevent the later period Problem.Meanwhile it to be also marked when the connecting portion setting-out of sole plate 2 and overturn-preventing ground beam 5, appearance when preventing connection Inconsistent phenomenon;
S3 first has to installation foundation bottom plate 2 when installing room for building: utilizing crane by base prefabricated sole plate 2 2 component of plinth bottom plate is placed to the good position of setting-out, and sole plate 2 keeps installation flatness control within the scope of ± 2mm, to ensure Subsequent members installation;
Immobilizing foundation bottom plate 2: S4 installs the first spud pile 3 using spud pile mounting device, the first spud pile 3 is put into In reserved 7 position of fixing groove of first reserved, the verticality of the first spud pile 3 is measured by level guiding ruler, by After the verticality of one spud pile 3 is adjusted, the first spud pile 3 is carried out in hammering insertion soil layer using weight, weight passes through Refitting, which is set, carries out promotion and free-falling, guarantees that weight is not subjected to displacement off center position by retaining wall in dropping process, and Guarantee is dropped hammer on the first spud pile 3;It should be noted that the first spud pile 3 is made using high-strength aluminum alloy material, Stake is about 2 meters, and the every section of subsection setup is about 1 meter, and connection is internal to use Bolted Flanged Connection, and multiple notes with interval are arranged in pile body Hole is starched, slip casting form is taken at geological conditions poor position, it is ensured that sole plate 2 consolidates, between the arrangement of the first spud pile 3 Away from about 1.5m or so one, it is ensured that ground forms an entirety;Waterproof gelling is filled at the gap position of the first reserved fixing groove 7 Material reaches waterproof effect;
S5 installs overturn-preventing ground beam 5: being first kept in contact overturn-preventing ground beam 5 with 2 link position of sole plate and closely hang down Directly, then the second spud pile 6 on overturn-preventing ground beam 5 is installed, it is reserved solid to offer multiple second for compartment of terrain on overturn-preventing ground beam 5 Determine slot;The second spud pile 6 is installed using spud pile mounting device, spud pile mounting device can carry out position shifting by movable pulley Dynamic and fixed position, position in the hammering to the soil layer of the second reserved fixing groove of the second spud pile 6, will guarantee that second is fixed after determining Stake 6 and ground are contacted, and are filled waterproof cementitious material at the gap position of the second reserved fixing groove, are reached waterproof effect;Together When, overturn-preventing ground beam 5 at 2 link position of sole plate use fixing bolt reinforced again, it is ensured that overturn-preventing ground beam 5 with The connection of sole plate 2 forms whole;
After S6, sole plate 2 and overturn-preventing ground beam 5 are installed, start that prefabricated panel 4 and roof plate 9 are installed;It is prefabricated When wallboard 4 is installed, prefabricated panel 4 is put into the reserved locating slot 8 of sole plate 2, the peace of axis trimming prefabricated panel 4 is passed through Holding position, deviation control within the scope of 3mm;Position is mounted on after adjusting by the mounting hole that prefabricated board bottom opens up to adjust Clamp device inside reserved locating slot 8, so that prefabricated panel 4 is tightly fastened with sole plate 2, so that effectively entirety is formed, Reach and uses function;In 4 installation process of prefabricated panel, internal built-in pipe offers reserved opening at top, so as to To carry out tube body connection, forms circulating line and be linked to be entirety;
S7, the installation of roofing fan 13 and solar panels 10: total carries out equipment installation after being installed again, more The top surface upper cover of a prefabricated board sets a roof plate 9, and multiple accommodating grooves 12, Mei Geshou are positioned apart from roof plate 9 It receives and is respectively mounted a solar panels 10 in slot 12, the bottom of solar panels 10 is supported by a support rod 11, the branch One end of strut 11 is slidably disposed on the bottom of solar panels 10, can along solar panels 10 axis direction into Row movement, the other end are movably disposed in accommodating groove 12;Through mobile support rod 11 on the bottom of solar panels 10 Solar panels 10 can be collected in strong wind weather and extreme weather, be put into accommodating groove 12 and protected by position, and And solar panels 10 according to using angle to be adjusted, can also ensure that the safety of solar panels 10 and reduce bring resistance Power;Meanwhile multiple fans 13 being installed in the bottom of cover board 9, air inlet is offered at the position that prefabricated board is connect with cover board 9 14 and air outlet 15, by driving fan 13 itself to be rotated by the natural wind entered in air inlet 14, by horizontal gas flow Interior is introduced, so that indoor air flow is effectively circulated, realizes real environmental protection and energy-saving building assembled room.
In summary, the assembled architecture of the application is realized energy-saving and environment-friendly in 1 construction method of room using natural energy resources Assembled architecture room 1 is arranged solar energy power store device by roof (i.e. cover board 9) and solves the future normal electrical problem, reduces outer Power-on box, the energy independently use;Meanwhile air inlet 14 and air outlet 15 are set on roof, the natural wind of air inlet 14 drives Attic fan 13 makes air-flow to interior and is flowed, to increase air flowing, reduces electric fan 13 and air conditioning utilization rate, Save the energy.Meanwhile using recirculated water is arranged in prefabricated panel 4, so that taking away indoor heat solves the problems, such as Temperature fall;It utilizes Overturn-preventing ground beam 5 and wirerope, which combine, to be prevented from being toppled with room when solving the problems, such as extreme weather;Assembled architecture is installed with room 1 When, it using prefabricated base plate 2, is fixed (i.e. the first spud pile 3 and the second spud pile 6), is solved with high-strength aluminum alloy stake Piling bar certainly in the prior art easily corrodes in underground and influences the firm problem of foundation structure, and also enhance site operation can Operability;Wallboard is carried out using fastening bolt form when wallboard is installed and reinforces fixing measure, solves 4 mounting and dismounting of prefabricated panel not Just the problem of, fastening form also improve the flexible installation of execute-in-place, and circulation pipe is arranged by partition and some perforations reach To noise reduction soundproof effect.By realizing energy-saving and environment-friendly assembled architecture room 1 using natural energy resources, change conventional construction side Method, this method installing and dismounting safety is convenient to assemble and disassemble, reduces environmental pollution;Meanwhile the structure reusable rate is high, cost It is low, structural stability is good, does not need to put into other large scale equipments, preferably resolve the interim movable building in construction site and applied with room The problem of work difficulty.
The foregoing is merely preferred embodiment of the present application, are not intended to limit this application, for the skill of this field For art personnel, various changes and changes are possible in this application.Within the spirit and principles of this application, made any to repair Change, equivalent replacement, improvement etc., it should be comprising within the scope of protection of this application.

Claims (9)

1. a kind of assembled architecture room characterized by comprising
Sole plate;
Multiple the first spud piles for being used to fix the sole plate, multiple first spud piles are mounted on institute with being respectively separated It states on sole plate, and extends and be fixed in soil layer;
Multiple prefabricated panels, multiple prefabricated panel compartment of terrain are fixed on the sole plate;
Multiple overturn-preventing ground beams, multiple overturn-preventing ground beams are mounted on the side of the sole plate;
Multiple the second spud piles for being used to fix the overturn-preventing ground beam, multiple second spud piles are mounted on being respectively separated On the overturn-preventing ground beam, and extends and be fixed in soil layer.
2. assembled architecture room according to claim 1, which is characterized in that offered on the sole plate multiple pre- Fixing groove is stayed, is equipped in the reserved fixing groove multiple for fixing the first spud pile of the sole plate.
3. assembled architecture room according to claim 2, which is characterized in that multiple reserved fixing grooves are in the base It is arranged in rows on plinth bottom plate.
4. assembled architecture room according to claim 1, which is characterized in that offered on the sole plate multiple pre- Locating slot is stayed, the prefabricated panel is installed in multiple reserved locating slots.
5. assembled architecture room according to claim 1, which is characterized in that be equipped with lid on multiple prefabricated panels Plate is equipped with multiple solar panels and multiple support rods on the cover board, and one end of the support rod is mounted on the cover board, The other end is movably mounted on the solar panels, and the other end of the support rod can be along the length of the solar panels It is mobile to spend direction, the solar panels are arranged on the cover board.
6. assembled architecture room according to claim 5, which is characterized in that compartment of terrain offers multiple on the cover board For storing the accommodating groove of the solar panels, one end of the support rod is movably mounted in the accommodating groove, another End is movably attached to the solar panels.
7. assembled architecture room according to claim 5, which is characterized in that the bottom of the cover board is equipped with multiple wind It fans, offers the air inlet and air outlet being equipped with the fan respectively on multiple prefabricated panels.
8. a kind of assembled architecture room construction method, including the described in any item assembled architecture rooms claim 1-7, Be characterized in that, assembled architecture room construction method the following steps are included:
The occupied area in assembled architecture room is carried out data acquisition on the spot by S1, and size carries out the dress according to area Precast concrete design with formula room for building, while carrying out electrical and water-feeding drainaging line pre-buried design;
S2 carries out compacting processing according to the floor area dimensions smooth location in the assembled architecture room, by designed use Every room for building that room takes up an area position carries out unwrapping wire, carries out to the connecting portion of the sole plate and the overturn-preventing ground beam Label;
S3 installs the sole plate: the prefabricated sole plate component is placed to the good position of setting-out using crane, The installation flatness of the sole plate controls within the scope of ± 2mm, to ensure the installation of subsequent members;
S4, the fixed sole plate: opening up the multiple first reserved fixing grooves on the sole plate, fixed by described first Stake is put into the described first reserved fixing groove reserved, and the verticality of first spud pile is measured by level guiding ruler, After the verticality for adjusting first spud pile, first spud pile is hammered in insertion soil layer;It is reserved described first Fill waterproof cementitious material in the gap position of fixing groove;
S5 installs the overturn-preventing ground beam: the link position holding of the overturn-preventing ground beam and the sole plate is closely connect Touching and vertical, opens up the multiple second reserved fixing grooves in the overturn-preventing ground beam, and second spud pile is fixedly mounted on the In two reserved fixing grooves, the verticality of second spud pile is measured by level guiding ruler, adjusts second spud pile Verticality after, by second spud pile hammer insertion soil layer in;It is filled at the gap position of the described second reserved fixing groove Waterproof cementitious material;
S6 installs the prefabricated panel and cover board: multiple reserved locating slots is opened up on the sole plate, by the dry wall Plate is put into the reserved locating slot, and by the installation site of prefabricated panel described in axis trimming, deviation is controlled in 3mm range It is interior;The cover plate lid is located on multiple prefabricated panels;
S7 installs fan and solar panels: installing multiple solar panels on the cover board, pacifies in the bottom of the cover board Fill multiple fans.
9. assembled architecture according to claim 8 room construction method, which is characterized in that first spud pile and institute It states the second spud pile and is all made of high-strength aluminum alloy material, a length of 2 meters of the stake of first spud pile and second spud pile, Pile body is provided with multiple injected holes for reperfusion serosity.
CN201910528576.8A 2019-06-18 2019-06-18 Construction method of prefabricated building house Active CN110295667B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910528576.8A CN110295667B (en) 2019-06-18 2019-06-18 Construction method of prefabricated building house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910528576.8A CN110295667B (en) 2019-06-18 2019-06-18 Construction method of prefabricated building house

Publications (2)

Publication Number Publication Date
CN110295667A true CN110295667A (en) 2019-10-01
CN110295667B CN110295667B (en) 2020-11-27

Family

ID=68028165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910528576.8A Active CN110295667B (en) 2019-06-18 2019-06-18 Construction method of prefabricated building house

Country Status (1)

Country Link
CN (1) CN110295667B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112240053A (en) * 2020-10-26 2021-01-19 温州展业建设工程有限公司 Prefabricated building room and construction method thereof
CN113047441A (en) * 2021-03-02 2021-06-29 广东华正建设工程有限公司 Mounting structure of prefabricated building and construction method thereof
CN113503046A (en) * 2021-09-09 2021-10-15 南通汉腾建筑科技有限公司 Supporting and locking device for mounting assembly type wall
CN114837215A (en) * 2022-03-31 2022-08-02 宁波阳明工业技术研究院有限公司 Foundation peripheral building structure and adjusting method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3629674B2 (en) * 1998-04-23 2005-03-16 清水建設株式会社 Building vibration control structure
CN101881028B (en) * 2010-07-03 2011-07-20 朱奎 Construction method of raft foundation
CN202989945U (en) * 2012-12-28 2013-06-12 杨众 Steel and concrete mixed assembly type tower footing
CN203961016U (en) * 2013-11-07 2014-11-26 江苏九鼎环球建设科技集团有限公司 Quick-assembling precast concrete prefabricated house
CN104471158A (en) * 2012-05-14 2015-03-25 Nev-X系统有限公司 Building foundation
CN107642161A (en) * 2016-07-20 2018-01-30 任丘市永基建筑安装工程有限公司 A kind of lightweight house
CN208235557U (en) * 2018-05-09 2018-12-14 广州杰赛科技股份有限公司 A kind of assembling type base

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3629674B2 (en) * 1998-04-23 2005-03-16 清水建設株式会社 Building vibration control structure
CN101881028B (en) * 2010-07-03 2011-07-20 朱奎 Construction method of raft foundation
CN104471158A (en) * 2012-05-14 2015-03-25 Nev-X系统有限公司 Building foundation
CN202989945U (en) * 2012-12-28 2013-06-12 杨众 Steel and concrete mixed assembly type tower footing
CN203961016U (en) * 2013-11-07 2014-11-26 江苏九鼎环球建设科技集团有限公司 Quick-assembling precast concrete prefabricated house
CN107642161A (en) * 2016-07-20 2018-01-30 任丘市永基建筑安装工程有限公司 A kind of lightweight house
CN208235557U (en) * 2018-05-09 2018-12-14 广州杰赛科技股份有限公司 A kind of assembling type base

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112240053A (en) * 2020-10-26 2021-01-19 温州展业建设工程有限公司 Prefabricated building room and construction method thereof
CN112240053B (en) * 2020-10-26 2021-11-23 温州展业建设工程有限公司 Prefabricated building room and construction method thereof
CN113047441A (en) * 2021-03-02 2021-06-29 广东华正建设工程有限公司 Mounting structure of prefabricated building and construction method thereof
CN113047441B (en) * 2021-03-02 2022-07-26 广东华正建设工程有限公司 Mounting structure of prefabricated building and construction method thereof
CN113503046A (en) * 2021-09-09 2021-10-15 南通汉腾建筑科技有限公司 Supporting and locking device for mounting assembly type wall
CN114837215A (en) * 2022-03-31 2022-08-02 宁波阳明工业技术研究院有限公司 Foundation peripheral building structure and adjusting method thereof

Also Published As

Publication number Publication date
CN110295667B (en) 2020-11-27

Similar Documents

Publication Publication Date Title
CN110295667A (en) A kind of assembled architecture room and assembled architecture room construction method
CN206971270U (en) Exterior wall formwork system in underground pipe gallery cast-in-place construction
US8584404B2 (en) Modular building
CN101766103A (en) Sunlight greenhouse structure
CN113089678B (en) Deep foundation pit unearthed ramp under complex surrounding environment and construction method
CN106437048B (en) A kind of folded truss formula Full-automatic telescopic awning and its operating method
JP5079919B2 (en) Planar body support frame and solar power generation device
TW201217726A (en) Sheet body supporting frame
CN109826443B (en) Method for building house by using prefabricated building modules
JPS5848698B2 (en) Kenchikuyouhonegumishikikouzo
CN206157971U (en) Prefabricated roof boarding of steel bar truss prefabricated unit and steel bar truss
CN215802536U (en) Novel hyperboloid curtain skeleton
CN113530236B (en) Construction method for mudflat photovoltaic power station
CN212358796U (en) Combined roof for emergency engineering
RU56905U1 (en) SMALL FOUNDATION
CN208633670U (en) One kind can have enough to meet the need multi-functional enclosing structure
CN206053427U (en) A kind of container house roof and container house
WO2020198579A2 (en) Roll-formed solar canopy structures and foundation structures and methods
RU2426841C2 (en) Collapsible building
JP2020176437A (en) Plant factory building
RU64235U1 (en) EXTERIOR GUARDING OF THE ATTIC
CN215053156U (en) Counter weight basis suitable for archaeology is visited square and is separated roof beam
CN215715328U (en) Combined type unearthed ramp of narrow and small deep basal pit
JP5974138B1 (en) building
RU2107137C1 (en) Architectural-construction system of cellular-thermostructural spatial modules for erection of dwelling buildings polygonal in plan

Legal Events

Date Code Title Description