CN110287511A - 基于bim技术的桩基选型及施工质量控制方法 - Google Patents
基于bim技术的桩基选型及施工质量控制方法 Download PDFInfo
- Publication number
- CN110287511A CN110287511A CN201910358965.0A CN201910358965A CN110287511A CN 110287511 A CN110287511 A CN 110287511A CN 201910358965 A CN201910358965 A CN 201910358965A CN 110287511 A CN110287511 A CN 110287511A
- Authority
- CN
- China
- Prior art keywords
- pile foundation
- data
- model
- pile
- surveyed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
- G06T17/05—Geographic models
Abstract
本发明具体是一种基于BIM技术的桩基选型及施工质量控制方法;其特征是:包括生成三维地质模型;通过三维模型可视化,信息数据,确定桩基类型:包括但不局限于灌注桩、摩擦桩、PHC桩、加筋桩;创建桩基模型;建立统一标高位置体系;将岩层与桩基模型进行合并;通过参数确定桩基长度;通过桩基类型及桩基长度进行数据筛选,选择合理、满足要求、经济实惠的桩基型号;通过地勘报告与模型数据对比,检查复核地勘报告,优化数据,控制桩基施工质量,提高精度,节约材料。本方法通过可视化、参数化的形式来进行桩基选型,可直观的进行比对、修改,提高了多方交流的效率,同时为后期桩基检测提供数据依据,控制桩基施工精度,准确精度高。
Description
技术领域
本发明涉及建筑工程施工领域,具体是一种基于BIM技术的桩基选型及施工质量控制方法。
背景技术
随着工程复杂性的日益增加,越来越多的工程需要对复杂地质的桩基类型方案进行选择,以满足建筑物的要求。目前桩基选型,是依据地质勘探报告分析,以地质勘探报告提供的不同岩层测点或等高线数据来结合规范进行计算,计算工作量大而且繁琐,容易导致数据出现偏差,基于繁琐数据、揣测、想象、也容易遗漏,同时桩基类型繁多,不同桩型所对应不同地质,不利于在桩基选型过程中交流。且在施工中因夹层或孤石造成桩施工问题难以规避。
发明内容
本发明的目的在于克服上述缺陷,提供通过BIM技术建立精准三维地质模型,模拟土层与岩层分布,以可视化、参数化的形式来进行不同地质条件下桩基类型选择从而实现控制桩基施工质量的目的。
为了达到上述目的,本发明是这样实现的:
一种基于BIM技术的桩基选型及施工质量控制方法;包括
步骤1、整理收集地勘报告;
步骤2、对地勘报告数据进行处理;
步骤2.1、将地勘报告数据归纳为:
一、纯点数据:分好点类、坐标、标高,以.txt格式导入到Civil 3D中,生成高程点、基于点高程生成曲面;纯点数据只包括X,Y,Z的大地坐标,以最直接的钻探数据得到;
二、平面等高线加标高数据:用曲面工具提取对象将文字移动到高程,基于等高线生成曲面;
三、等高线多段线数据,基于钻探点数据生成的曲面多段线dwg格式文件,等高多段线成空间布置,具有三维特性;生成岩层面、基于岩层面之间生成对应岩层;
步骤3:将岩层以dwg格式导入Revit中,生成三维地质模型;
步骤4:通过三维模型可视化,信息数据,确定桩基类型:包括但不局限于灌注桩、摩擦桩、PHC桩、加筋桩;
步骤5:创建桩基模型;建立统一标高位置体系:
一、绝对标高系:用Revit软件建立绝对标高体系是因为前期施工挖土以及其它位置点的复核参考都是依据绝对标高进行校核,绝对标高体系拥有对接地勘数据的优势,同时可以在三维状态下直接提取任意位置的高程;
二、水平方位定位:以绝对标高±0建筑物红线边角作为水平方位定位点,方便不同软件模型的位置链接;基于标高体系建立桩基模型:在Revit平台中基于已有的坐标系,做好底板模型;基于底板模型设立参照面、基于参照面和设计底图内建拉伸,给予桩名称和标签,生成桩基模型,
步骤6:将岩层与桩基模型进行合并;
步骤7:通过参数确定桩基长度;
步骤8:通过桩基类型及桩基长度进行数据筛选,选择合理、满足要求、经济实惠的桩基型号;
步骤9:通过地勘报告与模型数据对比,检查复核地勘报告,优化数据,控制桩基施工质量,提高精度,节约材料。
本方法通过可视化、参数化的形式来进行桩基选型,可直观的进行比对、修改,提高了多方交流的效率,同时为后期桩基检测提供数据依据,控制桩基施工精度,准确精度高、经济效益大。
附图说明
图1为本施工方法的工艺流程图。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1所示,一种基于BIM技术的桩基选型及施工质量控制方法;包括
步骤1、整理收集地勘报告;
步骤2、对地勘报告数据进行处理;
步骤2.1、将地勘报告数据归纳为:
一、纯点数据:分好点类、坐标、标高,以.txt格式导入到Civil 3D中,生成高程点、基于点高程生成曲面;纯点数据只包括X,Y,Z的大地坐标,以最直接的钻探数据得到;
二、平面等高线加标高数据:用曲面工具提取对象将文字移动到高程,基于等高线生成曲面;
三、等高线多段线数据,基于钻探点数据生成的曲面多段线dwg格式文件,等高多段线成空间布置,具有三维特性;生成岩层面、基于岩层面之间生成对应岩层;
步骤3:将岩层以dwg格式导入Revit中,生成三维地质模型;
步骤4:通过三维模型可视化,信息数据,确定桩基类型:包括但不局限于灌注桩、摩擦桩、PHC桩、加筋桩;
步骤5:创建桩基模型;建立统一标高位置体系:
一、绝对标高系:用Revit软件建立绝对标高体系是因为前期施工挖土以及其它位置点的复核参考都是依据绝对标高进行校核,绝对标高体系拥有对接地勘数据的优势,同时可以在三维状态下直接提取任意位置的高程;
二、水平方位定位:以绝对标高±0建筑物红线边角作为水平方位定位点,方便不同软件模型的位置链接;基于标高体系建立桩基模型:在Revit平台中基于已有的坐标系,做好底板模型;基于底板模型设立参照面、基于参照面和设计底图内建拉伸,给予桩名称和标签,生成桩基模型,
步骤6:将岩层与桩基模型进行合并;
步骤7:通过参数确定桩基长度;
步骤8:通过桩基类型及桩基长度进行数据筛选,选择合理、满足要求、经济实惠的桩基型号;
步骤9:通过地勘报告与模型数据对比,检查复核地勘报告,优化数据,控制桩基施工质量,提高精度,节约材料。
本方法通过可视化、参数化的形式来进行桩基选型,可直观的进行比对、修改,提高了多方交流的效率,同时为后期桩基检测提供数据依据,控制桩基施工精度,准确精度高、经济效益大。
Claims (1)
1.一种基于BIM技术的桩基选型及施工质量控制方法;其特征是:包括
步骤1、整理收集地勘报告;
步骤2、对地勘报告数据进行处理;
步骤2.1、将地勘报告数据归纳为:
一、纯点数据:分好点类、坐标、标高,以.txt格式导入到Civil 3D中,生成高程点、基于点高程生成曲面;纯点数据只包括X,Y,Z的大地坐标,以最直接的钻探数据得到;
二、平面等高线加标高数据:用曲面工具提取对象将文字移动到高程,基于等高线生成曲面;
三、等高线多段线数据,基于钻探点数据生成的曲面多段线dwg格式文件,等高多段线成空间布置,具有三维特性;生成岩层面、基于岩层面之间生成对应岩层;
步骤3:将岩层以dwg格式导入Revit中,生成三维地质模型;
步骤4:通过三维模型可视化,信息数据,确定桩基类型:包括但不局限于灌注桩、摩擦桩、PHC桩、加筋桩;
步骤5:创建桩基模型;建立统一标高位置体系:
一、绝对标高系:用Revit软件建立绝对标高体系是因为前期施工挖土以及其它位置点的复核参考都是依据绝对标高进行校核,绝对标高体系拥有对接地勘数据的优势,同时可以在三维状态下直接提取任意位置的高程;
二、水平方位定位:以绝对标高±0建筑物红线边角作为水平方位定位点,方便不同软件模型的位置链接;基于标高体系建立桩基模型:在Revit平台中基于已有的坐标系,做好底板模型;基于底板模型设立参照面、基于参照面和设计底图内建拉伸,给予桩名称和标签,生成桩基模型,
步骤6:将岩层与桩基模型进行合并;
步骤7:通过参数确定桩基长度;
步骤8:通过桩基类型及桩基长度进行数据筛选,选择合理、满足要求、经济实惠的桩基型号;
步骤9:通过地勘报告与模型数据对比,检查复核地勘报告,优化数据,控制桩基施工质量,提高精度,节约材料。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910358965.0A CN110287511B (zh) | 2019-04-30 | 2019-04-30 | 基于bim技术的桩基选型及施工质量控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910358965.0A CN110287511B (zh) | 2019-04-30 | 2019-04-30 | 基于bim技术的桩基选型及施工质量控制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110287511A true CN110287511A (zh) | 2019-09-27 |
CN110287511B CN110287511B (zh) | 2023-01-31 |
Family
ID=68001591
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910358965.0A Active CN110287511B (zh) | 2019-04-30 | 2019-04-30 | 基于bim技术的桩基选型及施工质量控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110287511B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111125821A (zh) * | 2019-12-16 | 2020-05-08 | 福建建工集团有限责任公司 | 基于bim+gis地基与基础分部工程分析及选型方法 |
CN113010953A (zh) * | 2021-03-30 | 2021-06-22 | 中交水运规划设计院有限公司 | 导航墙模型的生成方法及装置 |
CN113360963A (zh) * | 2021-06-03 | 2021-09-07 | 中国建筑第八工程局有限公司 | 基于bim技术的工程桩桩长批量预判方法 |
CN113515654A (zh) * | 2021-04-30 | 2021-10-19 | 中冶建工集团有限公司 | 基于建筑信息建模的桩基施工参数可视化处理方法及装置 |
CN113742813A (zh) * | 2021-07-23 | 2021-12-03 | 上海宝冶冶金工程有限公司 | 一种基于bim的三类桩施工方法及系统 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106815415A (zh) * | 2016-12-30 | 2017-06-09 | 中建三局第建设工程有限责任公司 | 基于bim的工程桩施工方法 |
CN109636906A (zh) * | 2018-12-11 | 2019-04-16 | 浙江华东建设工程有限公司 | 基于bim技术的混凝土灌注桩施工方法及系统 |
-
2019
- 2019-04-30 CN CN201910358965.0A patent/CN110287511B/zh active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106815415A (zh) * | 2016-12-30 | 2017-06-09 | 中建三局第建设工程有限责任公司 | 基于bim的工程桩施工方法 |
CN109636906A (zh) * | 2018-12-11 | 2019-04-16 | 浙江华东建设工程有限公司 | 基于bim技术的混凝土灌注桩施工方法及系统 |
Non-Patent Citations (2)
Title |
---|
侯振国等: "BIM在地勘与桩长选择方面应用的探索", 《价值工程》 * |
饶嘉谊等: "基于BIM的三维地质模型与桩长校核应用", 《土木建筑工程信息技术》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111125821A (zh) * | 2019-12-16 | 2020-05-08 | 福建建工集团有限责任公司 | 基于bim+gis地基与基础分部工程分析及选型方法 |
CN111125821B (zh) * | 2019-12-16 | 2023-09-01 | 福建建工集团有限责任公司 | 基于bim+gis地基与基础分部工程分析及选型方法 |
CN113010953A (zh) * | 2021-03-30 | 2021-06-22 | 中交水运规划设计院有限公司 | 导航墙模型的生成方法及装置 |
CN113515654A (zh) * | 2021-04-30 | 2021-10-19 | 中冶建工集团有限公司 | 基于建筑信息建模的桩基施工参数可视化处理方法及装置 |
CN113360963A (zh) * | 2021-06-03 | 2021-09-07 | 中国建筑第八工程局有限公司 | 基于bim技术的工程桩桩长批量预判方法 |
CN113360963B (zh) * | 2021-06-03 | 2023-11-21 | 中国建筑第八工程局有限公司 | 基于bim技术的工程桩桩长批量预判方法 |
CN113742813A (zh) * | 2021-07-23 | 2021-12-03 | 上海宝冶冶金工程有限公司 | 一种基于bim的三类桩施工方法及系统 |
CN113742813B (zh) * | 2021-07-23 | 2024-02-23 | 上海宝冶冶金工程有限公司 | 一种基于bim的三类桩施工方法及系统 |
Also Published As
Publication number | Publication date |
---|---|
CN110287511B (zh) | 2023-01-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110287511A (zh) | 基于bim技术的桩基选型及施工质量控制方法 | |
CN103279986B (zh) | 三维水平地质剖面图制作方法及其用途 | |
CN101509382B (zh) | 一种隧道勘察方法 | |
US20150331971A1 (en) | Interactive well pad plan | |
CN110245427A (zh) | 基于bim的煤矿工作面煤层gim数字模型创建方法 | |
CN109472866B (zh) | 一种大地质建筑信息模型的建模方法 | |
CN109933867A (zh) | 一种岩土工程勘察方案动态优化方法 | |
CN102622526A (zh) | 数字矿山中的巷道开掘搜索预测方法 | |
CN112052495B (zh) | 一种基于bim技术的滑坡治理工程三维设计方法 | |
CN110221340A (zh) | 一种隧道掘进施工超前地质预报方法 | |
CN103218850B (zh) | 一种真三维采矿爆破单元体模型建立方法 | |
CN104809266A (zh) | 一种基于样条曲线的工作面煤层赋存情况精确预测方法 | |
CN112465972B (zh) | 基于bim模型及桩基建模进行地质研判方法 | |
CN111191307A (zh) | 一种基于bim+gis技术的土方工程虚拟施工方法 | |
CN111539052B (zh) | 地铁盾构区间近距离下穿顶管隧道沉降控制标准制定方法 | |
CN107564101B (zh) | 一种基于AutoCAD建立可视化三维地质模型的方法 | |
CN109635367A (zh) | 一种掘进机三维模拟方法、装置及系统 | |
CN114549774A (zh) | 一种基于钻孔数据的三维地层建模方法 | |
CN108256130B (zh) | 一种地质钻孔空间轨迹还原方法 | |
CN113235655B (zh) | 海底沉管隧道基槽分土质工程土方量计算方法 | |
CN106920275A (zh) | 一种复杂属性边界三维矢量迭代方法及应用系统 | |
CN114279398B (zh) | 一种基于无人机航测技术的金属矿开采地表沉降监测方法 | |
CN112648974B (zh) | 一种基于航摄三维影像数据的工程量测算方法 | |
CN114741749A (zh) | 一种基于bim技术计算复杂地质地形土石比的方法 | |
CN110838177B (zh) | 一种基于Revit平台的地质勘测图和桩基图融合方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |