CN110260039A - 一种基于bim技术的纵向曲线顶管施工方法 - Google Patents
一种基于bim技术的纵向曲线顶管施工方法 Download PDFInfo
- Publication number
- CN110260039A CN110260039A CN201910635461.9A CN201910635461A CN110260039A CN 110260039 A CN110260039 A CN 110260039A CN 201910635461 A CN201910635461 A CN 201910635461A CN 110260039 A CN110260039 A CN 110260039A
- Authority
- CN
- China
- Prior art keywords
- jacking
- push pipe
- construction
- pipe jacking
- parameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明公开了一种基于BIM技术的纵向曲线顶管施工方法,属于市政工程顶管施工技术领域。本发明包括以下步骤:步骤一、确定顶管基础施工参数;步骤二、创建基于分层结构的顶管开挖三维有限元模型,分析不同埋深与管径下的土体沉降情况;步骤三、基于三维有限元分析的顶管顶进过程仿真模拟中,分析顶管顶进过程中土体受到的综合作用力;步骤四、依据土体综合作用力对顶管顶进参数进行优化,得出最优工况条件下的顶管系统参数;步骤五、基于BIM软件建立顶管施工的三维可视化模型,进行施工模拟;步骤六、现场施工及监测。本发明可以有效提高施工准确性,更好的控制土体沉降和纵向曲线顶管顶进姿态。
Description
技术领域
本发明属于市政工程顶管施工技术领域,更具体地说,涉及一种基于BIM技术的纵向曲线顶管施工方法。
背景技术
随着我国城市基础设施的快速发展,开发与利用城市地下空间成为当前城市发展的必然。顶管法施工在城市地下空间开发建设中经常使用,顶管施工技术是一种非开挖技术,主要特点就是将管道敷设明挖改为暗挖,其具体是在工作坑内借助于顶进设备产生的顶力,克服管道与周围土壤的摩擦力,将管道按设计的坡度顶入土中,并将土方运走。一节管子完成顶入土层之后,再下第二节管子继续顶进,其原理是借助于主顶油缸及管道间、中继间等推力,把工具管或掘进机从工作坑内穿过土层一直推进到接收坑内吊起,管道紧随工具管或掘进机后,埋设在两坑之间。
相比其它施工技术,顶管施工具有施工不需开挖、节约用地、对周围环境影响小、施工周期短、经济效益好等优点。面对现代加快开发地下空间的进程中,顶管技术显得尤为重要,得到了长足和快速的发展并广泛地应用于城市地下综合管线的建设和改造。但是作为一种地下开挖方法,顶管施工也不可避免地会对管道周围的土体产生扰动,扰动的结果是使周围的土体出现卸载或加载等复杂的力学行为,土体的应力状态不断发生变化,引起管道周围土体产生变形,使土体产生移动。当土体变形超过一定范围时,会严重危及邻近建筑物基础、邻近建筑物、路面和地下管线的安全,引起一系列环境岩土问题。因此,顶管施工工艺参数的精确控制对于保证施工的正确率,更好的控制顶管顶进姿态具有重要的意义。
但是,随着地层条件越来越复杂,施工条件越来越复杂,顶管施工技术中需要解决更多的实际技术问题以满足实际应用。而采用现有曲线顶管施工技术施工过程中,纵向曲线顶管顶进姿态不易控制、易出现偏差,且土体沉降控制不稳,从而无法有效保证施工的准确性。
如,中国专利申请号为201811645746.2的申请案公开了一种顶管施工方法,该申请案中利用激光测试仪检测顶管机的机头的顶进位置以及角度,根据检测到的结果与预期的效果进行比对,并通过控制器控制顶管机的机头的前进方向以及位置;在顶进工作结束后进行泥浆置换,在钢管的外壁的土体上开设注装孔,在注装孔上安装第三注浆管路,第三注浆管路用于通入水泥砂浆或粉煤灰水泥砂浆以置换钢管外壁处的触变泥浆,以提高钢管处土体的结构强度以防止地面沉降;泥浆置换结束后,拆除第三注浆管路,并将注装孔进行注装封堵,并在注装孔的外侧设置密封板以进行密封。但是,采用该申请案的方法对顶管顶进姿态进行监测和调整时,不能直观地对比出参数调整后的顶管顶进姿态与计划顶进姿态之间的一致性。
发明内容
1.要解决的问题
本发明的目的在于克服采用现有曲线顶管施工技术进行施工时,易存在较大施工偏差,顶管顶进姿态及土体沉降不易控制的不足,提供了一种基于BIM技术的纵向曲线顶管施工方法。采用本发明的技术方案能够有效降低纵向曲线顶管施工偏差,提升施工效率和正确率,从而更好地控制土体沉降与纵向曲线顶管顶进姿态。
2.技术方案
为了解决上述问题,本发明所采用的技术方案如下:
本发明的一种基于BIM技术的纵向曲线顶管施工方法,包括以下步骤:
步骤一、确定顶管基础施工参数
根据待施工地质情况和环境条件对顶管顶进参数的初始值进行预测;
步骤二、创建基于分层结构的顶管开挖三维有限元模型,分析不同埋深与管径下的土体沉降情况,以重新确定不同埋深与管径下的顶进参数;
步骤三、基于三维有限元分析的顶管顶进过程仿真模拟中,分析顶管顶进过程中土体受到的综合作用力;
步骤四、依据土体综合作用力对顶管顶进参数进行优化,直至土体综合作用力达到预定要求,得出最优工况条件下的顶管系统参数;
步骤五、基于BIM软件建立顶管施工的三维可视化模型,进行施工模拟,以提前预测施工中可能出现的问题;
步骤六、现场施工及监测
根据步骤四中得到的最优工况条件下的顶管系统参数及步骤五的模拟情况确定最佳施工工艺并进行现场施工。
更进一步的,所述步骤二中管径分别取500mm、800mm、1500mm、2000mm和2500mm,埋深分别取1.0m、1.2m、1.4m、1.6m、1.8m、2.0m、2.2m、2.4m、2.6m、2.8m、3.0m、3.2m。
更进一步的,所述步骤一中的顶管顶进参数主要包括顶进速度、排土量、纠偏角度和刀头转速;顶管顶进过程中土体受力包括注浆压力、顶进力、切削力和管道摩阻力。
更进一步的,所述步骤四中土体综合作用力为其所受各力的加权数值,其优化范围为0.9-1.1。
更进一步的,所述步骤五中基于BIM的顶管施工三维可视化模型包含工作井,千斤顶,操作室,支护舱,掘进机,刀盘,监视器,纠偏千斤顶,泥浆输送系统,注浆系统和管节等。
更进一步的,所述步骤六中现场施工时构建RFID系统,采用RFID电子标签在施工过程进行顶管无线定位追踪,实时追踪顶管顶进姿态,并反馈到主机绘制实际顶进姿态,若与计划顶进姿态相比有变,则随时采取措施进行纠偏控制。
3.有益效果
相比于现有技术,本发明的有益效果为:
(1)本发明的一种基于BIM技术的纵向曲线顶管施工方法,利用三维有限元模型分析顶管顶进过程中的土体受力情况,从而可以对顶管顶进参数进行合理优化,然后基于BIM三维可视化进行顶管施工模拟,以提前预测施工中可能出现的问题,以便提前解决问题及优化施工方案或者重新调整顶管施工技术参数。结合有限元模拟优化结果和BIM三维可视化模拟情况可以预先确定得到最佳施工工艺,避免直接进行盲目施工造成的施工偏差,有效提高了施工准确率和施工效率,能够更好地控制土体沉降与纵向曲线顶管顶进姿态,进而可以有效避免安全事故,避免返工,降低了工程成本。
(2)本发明的一种基于BIM技术的纵向曲线顶管施工方法,在施工过程中还构建RFID系统,采用RFID电子标签在施工过程进行顶管无线定位追踪,实时追踪顶管顶进姿态,与计划顶进姿态进行比较,从而能够及时采取措施进行纠偏控制,进一步保证了施工准确性。
(3)本发明的一种基于BIM技术的纵向曲线顶管施工方法,通过RFID系统与BIM技术的结合,能够更加直观的展示顶管计划顶进姿态与实时顶进姿态;同时检测设备(RFID电子标签)与主机及显示器进行联动,能够进行实时顶进姿态与计划顶进姿态的对比,对于调整实时参数具有直观的对比效果,从而有利于进一步保证实际施工的准确性。
附图说明
图1为本发明的基于BIM技术的纵向曲线顶管施工方法的工艺流程图。
具体实施方式
如图1所示,本发明的一种基于BIM技术的纵向曲线顶管施工方法,按以下步骤实现:
步骤一、确定顶管基础施工参数
根据待施工地质情况和环境条件对顶管顶进参数的初始值进行预测(根据以往施工经验);顶进参数主要包括顶进速度、排土量、纠偏角度、刀头转速等。
步骤二、创建基于分层结构的顶管开挖三维有限元模型,分别计算不同埋深与管径下的土体沉降情况,并根据土体沉降情况重新确定不同埋深与管径下的顶进参数;其中管径分别取500mm、800mm、1500mm、2000mm和2500mm,埋深分别取1.0m、1.2m、1.4m、1.6m、1.8m、2.0m、2.2m、2.4m、2.6m、2.8m、3.0m、3.2m。
步骤三、基于三维有限元分析的顶管顶进过程仿真模拟中,分析顶管顶进过程中土体受到的综合作用力,土体所受力包含注浆压力、顶进力、切削力和管道摩阻力等。
步骤四、依据土体综合作用力对顶管顶进参数进行优化,直至土体综合作用力达到预定要求,得出最优工况条件下的顶管系统参数;土体综合作用力为步骤三所述土体受力的加权数值,该数值优化范围为0.9-1.1,即对顶管顶进参数进行优化,直至土体综合作用力达到上述数值范围。
步骤五、基于BIM软件建立顶管施工的三维可视化模型,包含工作井,千斤顶,操作室,支护舱,掘进机,刀盘,监视器,纠偏千斤顶,泥浆输送系统,注浆系统,管节等,按照确定的施工方案进行施工模拟,提前预测施工中可能出现的问题,以便提前解决问题及优化施工方案或者重新调整顶管施工技术参数。因此通过BIM技术在顶管施工中的应用,可以预先确定施工方案,避免返工,减少浪费,节省成本。
步骤六、现场施工及监测
根据步骤四中得到的最优工况条件下的顶管系统参数及步骤五的模拟情况确定最佳施工工艺并进行现场施工。施工过程中构建RFID系统(包含电子标签、手持终端、条码生成软件、条码打印软件、无线追踪器、追踪系统与BIM系统耦合接口;其中电子标签具有非接触可识别及可无线定位源),采用RFID电子标签在施工过程进行顶管无线定位追踪,实时追踪顶管顶进姿态,反馈到主机绘制实际顶进姿态,并与计划顶进姿态进行比较,若存在偏差则及时采取措施进行纠偏控制。本发明具有三维可视化效果,能够直观地展示顶管计划顶进姿态与实时顶进姿态;同时检测设备(RFID电子标签)与主机及显示器进行联动,能够进行实时顶进姿态与计划顶进姿态的对比,对于调整实时参数具有直观的对比效果,从而有利于进一步保证实际施工的准确性。
针对现有曲线顶管施工工艺存在的易存在较大施工偏差,顶管顶进姿态及土体沉降情况不易控制,从而导致施工准确性和施工效率较低,需要经常返工,且易引起安全事故发生的问题,本发明将三维有限元模拟与BIM技术进行结合,从而可以预先对曲线顶管的具体施工工艺,尤其是对顶管顶进参数进行优化,并根据BIM模拟情况提前预测施工中可能出现的问题,以便指导实际施工时提前采取措施,从而可以有效提高曲线顶管施工的准确性和施工效率,能够更好地控制土体沉降与纵向曲线顶管顶进姿态,避免返工现象和安全事故的发生,符合“四节一环保”的绿色施工理念,有效提升了工程建设附加值。同时,本发明在真实施工过程中还采用RFID系统对顶管顶进姿态进行实时监测,从而有利于进一步保证顶管顶进姿态的准确性。
Claims (6)
1.一种基于BIM技术的纵向曲线顶管施工方法,其特征在于,包括以下步骤:
步骤一、确定顶管基础施工参数
根据待施工地质情况和环境条件对顶管顶进参数的初始值进行预测;
步骤二、创建基于分层结构的顶管开挖三维有限元模型,分析不同埋深与管径下的土体沉降情况,以重新确定不同埋深与管径下的顶进参数;
步骤三、基于三维有限元分析的顶管顶进过程仿真模拟中,分析顶管顶进过程中土体受到的综合作用力;
步骤四、依据土体综合作用力对顶管顶进参数进行优化,直至土体综合作用力达到预定要求,得出最优工况条件下的顶管系统参数;
步骤五、基于BIM软件建立顶管施工的三维可视化模型,进行施工模拟,以提前预测施工中可能出现的问题;
步骤六、现场施工
根据步骤四中得到的最优工况条件下的顶管系统参数及步骤五的模拟情况确定最佳施工工艺并进行现场施工。
2.根据权利要求1所述的一种基于BIM技术的纵向曲线顶管施工方法,其特征在于:所述步骤二中管径分别取500mm、800mm、1500mm、2000mm和2500mm,埋深分别取1.0m、1.2m、1.4m、1.6m、1.8m、2.0m、2.2m、2.4m、2.6m、2.8m、3.0m、3.2m。
3.根据权利要求1所述的一种基于BIM技术的纵向曲线顶管施工方法,其特征在于:所述步骤一中的顶管顶进参数主要包括顶进速度、排土量、纠偏角度和刀头转速;顶管顶进过程中土体受力主要包括注浆压力、顶进力、切削力和管道摩阻力。
4.根据权利要求1所述的一种基于BIM技术的纵向曲线顶管施工方法,其特征在于:所述步骤四中土体综合作用力为其所受各力的加权数值,其优化范围为0.9-1.1。
5.根据权利要求1-4中任一项所述的一种基于BIM技术的纵向曲线顶管施工方法,其特征在于:所述步骤五中基于BIM的顶管施工三维可视化模型包含工作井,千斤顶,操作室,支护舱,掘进机,刀盘,监视器,纠偏千斤顶,泥浆输送系统,注浆系统和管节等。
6.根据权利要求1-4中任一项所述的一种基于BIM技术的纵向曲线顶管施工方法,其特征在于:所述步骤六中现场施工时构建RFID系统,采用RFID电子标签在施工过程进行顶管无线定位追踪,实时追踪顶管顶进姿态,并反馈到主机绘制实际顶进姿态,若与计划顶进姿态相比有变,则随时采取措施进行纠偏控制。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910635461.9A CN110260039B (zh) | 2019-07-15 | 2019-07-15 | 一种基于bim技术的纵向曲线顶管施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910635461.9A CN110260039B (zh) | 2019-07-15 | 2019-07-15 | 一种基于bim技术的纵向曲线顶管施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110260039A true CN110260039A (zh) | 2019-09-20 |
CN110260039B CN110260039B (zh) | 2021-01-26 |
Family
ID=67926071
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910635461.9A Active CN110260039B (zh) | 2019-07-15 | 2019-07-15 | 一种基于bim技术的纵向曲线顶管施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110260039B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119901A (zh) * | 2019-12-12 | 2020-05-08 | 中电建生态环境集团有限公司 | 穿过既有构筑物沉降控制方法 |
CN111236957A (zh) * | 2020-01-14 | 2020-06-05 | 广州坚磊建设有限公司 | 机械顶管施工工艺 |
CN111563287A (zh) * | 2020-03-24 | 2020-08-21 | 中铁隧道集团二处有限公司 | 一种基于分段位移控制法的竖向曲线顶管顶进力估算方法 |
CN113653150A (zh) * | 2021-09-17 | 2021-11-16 | 北京城乡建设集团有限责任公司 | 一种回转钻机钻穿污水管线的施工方法 |
CN115046055A (zh) * | 2022-06-21 | 2022-09-13 | 北京住总集团有限责任公司 | 一种顶管沉降控制系统及方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102733478A (zh) * | 2012-04-04 | 2012-10-17 | 中国航空规划建设发展有限公司 | 一种基于承载全过程研究的索穹顶结构设计指标确定方法 |
CN103727310A (zh) * | 2014-01-03 | 2014-04-16 | 上海市基础工程集团有限公司 | 长距离顶管中继环联动施工方法 |
CN105825027A (zh) * | 2016-03-30 | 2016-08-03 | 广东工业大学 | 顶管顶进过程的多体系统动力学数值模拟方法 |
CN107330282A (zh) * | 2017-07-05 | 2017-11-07 | 中铁四局集团第五工程有限公司 | 一种适用于长距离顶管顶进偏移对顶力函数的计算方法 |
CN109299575A (zh) * | 2018-11-09 | 2019-02-01 | 上海市基础工程集团有限公司 | 基于bim技术的顶管施工过程的监测方法 |
-
2019
- 2019-07-15 CN CN201910635461.9A patent/CN110260039B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102733478A (zh) * | 2012-04-04 | 2012-10-17 | 中国航空规划建设发展有限公司 | 一种基于承载全过程研究的索穹顶结构设计指标确定方法 |
CN103727310A (zh) * | 2014-01-03 | 2014-04-16 | 上海市基础工程集团有限公司 | 长距离顶管中继环联动施工方法 |
CN105825027A (zh) * | 2016-03-30 | 2016-08-03 | 广东工业大学 | 顶管顶进过程的多体系统动力学数值模拟方法 |
CN107330282A (zh) * | 2017-07-05 | 2017-11-07 | 中铁四局集团第五工程有限公司 | 一种适用于长距离顶管顶进偏移对顶力函数的计算方法 |
CN109299575A (zh) * | 2018-11-09 | 2019-02-01 | 上海市基础工程集团有限公司 | 基于bim技术的顶管施工过程的监测方法 |
Non-Patent Citations (2)
Title |
---|
李建阳: "浅谈BIM技术在市政综合管廊施工阶段的应用 ", 《低碳世界》 * |
百度文库: "《https://wenku.baidu.com/view/3bd7b7b20408763231126edb6f1aff00bed5708d.html》", 9 March 2019 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119901A (zh) * | 2019-12-12 | 2020-05-08 | 中电建生态环境集团有限公司 | 穿过既有构筑物沉降控制方法 |
CN111236957A (zh) * | 2020-01-14 | 2020-06-05 | 广州坚磊建设有限公司 | 机械顶管施工工艺 |
CN111563287A (zh) * | 2020-03-24 | 2020-08-21 | 中铁隧道集团二处有限公司 | 一种基于分段位移控制法的竖向曲线顶管顶进力估算方法 |
CN113653150A (zh) * | 2021-09-17 | 2021-11-16 | 北京城乡建设集团有限责任公司 | 一种回转钻机钻穿污水管线的施工方法 |
CN113653150B (zh) * | 2021-09-17 | 2023-01-24 | 北京城乡建设集团有限责任公司 | 一种回转钻机钻穿污水管线的施工方法 |
CN115046055A (zh) * | 2022-06-21 | 2022-09-13 | 北京住总集团有限责任公司 | 一种顶管沉降控制系统及方法 |
CN115046055B (zh) * | 2022-06-21 | 2024-05-28 | 北京住总集团有限责任公司 | 一种顶管沉降控制系统及方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110260039B (zh) | 2021-01-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110260039A (zh) | 一种基于bim技术的纵向曲线顶管施工方法 | |
CN112945139B (zh) | 一种三维扫描结合bim技术的盾构工程辅助系统 | |
CN114894154B (zh) | 一种盾构施工段稳定性判断方法及设备 | |
AU2019259069C1 (en) | Underground space intelligent construction system and method | |
Xie et al. | A real-time interaction platform for settlement control during shield tunnelling construction | |
Zhang et al. | Ground settlement induced by tunneling crossing interface of water-bearing mixed ground: A lesson from Changsha, China | |
CN103791159A (zh) | 小直径管道的顶管施工方法 | |
CN113153335A (zh) | 用于盾构下穿的安全管理系统 | |
Yang et al. | Performance of overlapped shield tunneling through an integrated physical model tests, numerical simulations and real-time field monitoring | |
CN203422091U (zh) | 一种动态实时测量顶管机位置和姿态的测量装置 | |
Zheng et al. | Multistage regulation strategy as a tool to control the vertical displacement of railway tracks placed over the building site of two overlapped shield tunnels | |
CN106949877A (zh) | 一种多维度盾构隧道上方地表沉降的监测方法 | |
CN102733812B (zh) | 城市江底分岔段小净距隧道侧壁扩挖的隧道施工方法 | |
CN113090274B (zh) | 基于大数据的自动巡航盾构超前地质预报系统及工作方法 | |
CN105986570A (zh) | 用作地连墙接口外加固封口止水的高压旋喷桩施工方法 | |
Li et al. | Development of the safety control framework for shield tunneling in close proximity to the operational subway tunnels: case studies in mainland China | |
Huang et al. | Numerical Study on the Disturbance Effect of Short‐Distance Parallel Shield Tunnelling Undercrossing Existing Tunnels | |
CN103742163A (zh) | 一种确定地面出入式盾构施工盾构机土仓控制压力的方法 | |
Ledyaev et al. | An assessment of the sewer tunnel stress-strain behavior during the reconstruction of an object of cultural heritage | |
Zheng et al. | Environmental impact of ground deformation caused by underground construction in China | |
CN209413903U (zh) | 长距离曲线顶管自动导向系统 | |
Mamaqani et al. | Settlement analysis of box jacking projects | |
Nangulama et al. | Deformation control monitoring of basement excavation at field construction site: a case of hydraulic servo steel enhancement geotechnology | |
Huo et al. | RETRACTED ARTICLE: Numerical simulation and analysis of the three-step excavation of an extra-large cross section and a low flat-ratio railway tunnel | |
CN111749243B (zh) | 一种半自动挖掘机数字化土方场地标高控制施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |