CN110258442B - Method and device for determining engineering construction process scheme of high-pile wharf - Google Patents

Method and device for determining engineering construction process scheme of high-pile wharf Download PDF

Info

Publication number
CN110258442B
CN110258442B CN201910473267.5A CN201910473267A CN110258442B CN 110258442 B CN110258442 B CN 110258442B CN 201910473267 A CN201910473267 A CN 201910473267A CN 110258442 B CN110258442 B CN 110258442B
Authority
CN
China
Prior art keywords
construction
construction process
information
project
resource
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910473267.5A
Other languages
Chinese (zh)
Other versions
CN110258442A (en
Inventor
杨国平
商剑平
邰世文
毕磊
郑天立
郭享
刘春泽
唐颖
柳海宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Water Transport Planning And Design Institute Co ltd
Original Assignee
Cccc Water Transport Planning And Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Water Transport Planning And Design Institute Co ltd filed Critical Cccc Water Transport Planning And Design Institute Co ltd
Priority to CN201910473267.5A priority Critical patent/CN110258442B/en
Publication of CN110258442A publication Critical patent/CN110258442A/en
Application granted granted Critical
Publication of CN110258442B publication Critical patent/CN110258442B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/068Landing stages for vessels

Abstract

The invention discloses a method and a device for determining a construction process scheme of a high-pile wharf project. Wherein, the method comprises the following steps: acquiring engineering information of a high-pile wharf engineering; simulating the construction process of the high-pile wharf engineering based on the engineering information to obtain initial construction process scheme information of each subsection construction engineering in the construction process; and optimizing the construction process based on the initial construction process scheme information to obtain a target construction process scheme of each subsection project construction project. The invention solves the technical problem that the existing method for predicting and analyzing the construction process of the high-pile wharf engineering according to construction experience causes inaccurate technical scheme of the high-pile wharf engineering construction.

Description

Method and device for determining engineering construction process scheme of high-pile wharf
Technical Field
The invention relates to the technical field of port engineering, in particular to a method and a device for determining a high-pile wharf engineering construction process scheme.
Background
The high-pile wharf engineering is a key control engineering in port construction projects, and has the characteristics of large investment, long period, complex construction management and the like, so that the information and intelligent decision management of the high-pile wharf construction process is needed to be carried out for improving the management efficiency and quality of the engineering projects.
However, planning and arrangement of the high-pile wharf engineering are easily affected by random factors, and analysis and research of the high-pile wharf engineering are difficult to perform by adopting an analytical method. At present, computer simulation technology for port engineering construction management is less in application research, and research in high-pile wharf construction engineering is less.
At present, the construction method and the construction organization plan of the high-pile wharf engineering are mainly established on the basis of construction experience. However, planning and controlling construction by means of construction experience has certain limitations, especially for construction under a brand new structure or complex condition, analysis and prediction in various aspects of planning, feasibility, control optimization, accident prediction, production scheduling optimization and the like of engineering construction by means of experience may ignore important results due to thinking inertia or only analyze partial and few results due to carelessness, and even fail to perform quantitative analysis, for example, when analyzing a high-pile wharf project in the prior art, the contents of special topography, geology and tide in a construction system, modification of a construction scheme in a construction process, safety risk assessment, scheme evaluation and the like are not considered, so that the problems of inaccurate analysis result and low analysis efficiency are caused.
In view of the above problems, no effective solution has been proposed.
Disclosure of Invention
The embodiment of the invention provides a method and a device for determining a high-pile wharf engineering construction process scheme, which at least solve the technical problem that the high-pile wharf engineering construction process scheme is inaccurate due to the fact that the existing method for predicting and analyzing the high-pile wharf engineering construction process according to construction experience.
According to an aspect of the embodiment of the present invention, a method for determining a high-pile wharf engineering construction process scheme is provided, including: acquiring engineering information of a high-pile wharf engineering; simulating the construction process of the high-pile wharf engineering based on the engineering information to obtain initial construction process scheme information of each subsection construction engineering in the construction process; and optimizing the construction process based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction project.
Further, the method for determining the construction process scheme of the high-pile wharf engineering further comprises the following steps: configuring the construction process flow of the high-pile wharf engineering according to the engineering information to obtain a configuration result; dividing the construction implementation mode of the high-pile wharf engineering on the spatial arrangement according to the engineering information to obtain a division result; determining the construction sequence of each construction process according to the configuration result and the division result; acquiring resource information corresponding to each construction process, wherein the resource information comprises at least one of the following: device information and manual information; and simulating the construction process according to the construction sequence and the resource information to obtain the initial process information of each construction process.
Further, the method for determining the construction process scheme of the high-pile wharf engineering further comprises the following steps: acquiring initial process information of a construction process corresponding to each preset time period; determining a resource intensity value in each preset time period according to the initial process information; determining a maximum value of the resource intensity from the resource intensity values in a plurality of preset time periods; and optimizing the construction process according to the maximum value of the resource intensity and the maximum value of the target intensity and preset rules.
Further, the method for determining the construction process scheme of the high-pile wharf engineering further comprises the following steps: under the condition that the maximum value of the resource intensity in the current preset time period is larger than the maximum value of the target intensity, determining a first construction process in which the resource intensity value in the current preset time period is minimum; when the number of the first construction processes is one, postponing the construction starting time corresponding to the first construction process to the next preset time period; and under the condition that the number of the first construction procedures is multiple, acquiring adjustable time differences corresponding to the multiple first construction procedures, and optimizing the construction process according to the adjustable time differences.
Further, the method for determining the construction process scheme of the high-pile wharf engineering further comprises the following steps: acquiring adjustable time differences corresponding to a plurality of first construction processes, and determining a second construction process with the maximum adjustable time difference; when the number of the second construction processes is one, postponing the starting time corresponding to the second construction process to the next preset time period; and under the condition that the number of the second construction processes is multiple, acquiring the maximum value of the first resource intensity, and postponing the starting time of the corresponding second construction process when the maximum value of the first resource intensity is smaller than the maximum value of the target intensity until the next preset time period.
Further, the first resource strength maximum value is obtained by any one or more of the following ways: acquiring the starting time corresponding to each second construction procedure, and postponing the starting time to the maximum value of the corresponding resource strength in the next preset time period to obtain the maximum value of the first resource strength; and adjusting the resource allocation corresponding to each second construction process to obtain an adjusted second construction process, wherein the maximum value of the resource intensity corresponding to the adjusted second construction process is the maximum value of the first resource intensity.
Further, the method for determining the construction process scheme of the high-pile wharf engineering further comprises the following steps: determining the maximum value of the target intensity by any one of the following modes: determining a target intensity maximum value according to the product of the resource intensity maximum value and a preset weight, wherein the preset weight is a positive number smaller than 1; or determining the maximum value of the target intensity according to the difference value between the maximum value of the resource intensity and a preset value, wherein the preset value is a positive number.
Further, the engineering information includes at least one of: the method comprises the following steps of (1) dividing project information, construction process information and construction resource information of high-pile wharf projects; the initial construction process scheme information comprises at least one of the following: the starting time, the ending time, the resource intensity, the total construction period and the key route of the construction process.
According to another aspect of the embodiments of the present invention, there is also provided a device for determining a high-pile wharf engineering construction process scheme, including: the acquisition module is used for acquiring the engineering information of the high-pile wharf engineering; the simulation module is used for simulating the construction process of the high-pile wharf engineering based on the engineering information to obtain the initial construction process scheme information of each subsection project construction engineering in the construction process; and the optimization module is used for optimizing the construction process based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction project.
According to another aspect of the embodiment of the present invention, there is also provided a storage medium, where the storage medium includes a stored program, and when the program runs, the apparatus on which the storage medium is located is controlled to execute the method for determining the engineering technical scheme of the high-pile wharf engineering.
According to another aspect of the embodiment of the present invention, a processor is further provided, where the processor is configured to execute a program, where the program executes the method for determining the engineering technical scheme of the high-piled wharf engineering.
In the embodiment of the invention, a method of analyzing and optimizing the construction process scheme information of each subsection project construction project of the high-pile wharf project is adopted, after the project information of the high-pile wharf project is obtained, the construction process of the high-pile wharf project is simulated based on the project information to obtain the initial construction process scheme information of each subsection project construction project in the construction process, and then the construction process is optimized based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction project. It is easy to notice that, in the application, the relevant information in the construction process of the high-pile wharf engineering is comprehensively considered, and the construction process scheme information of each subsection construction engineering is obtained according to the relevant information, so that the accurate analysis of the high-pile wharf engineering is realized. In addition, in order to further improve the accuracy of analysis, after the construction process scheme information of each subsection construction project is obtained, each subsection construction project is further optimized, and then an optimal construction scheme is obtained.
Therefore, the scheme provided by the application achieves the purpose of predicting and analyzing the high-pile wharf engineering, the technical effect of improving the accuracy of prediction and analysis of the high-pile wharf engineering is achieved, and the technical problem that the existing method for predicting and analyzing the construction process of the high-pile wharf engineering according to construction experience causes inaccuracy of the construction process scheme of the high-pile wharf engineering is solved.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the invention without limiting the invention. In the drawings:
FIG. 1 is a flow chart of a method for determining a high-pile wharf engineering construction process scheme according to an embodiment of the invention;
FIG. 2(a) is a schematic diagram of an alternative construction process according to an embodiment of the present invention;
FIG. 2(b) is a flow chart of an alternative construction process according to an embodiment of the present invention;
FIG. 2(c) is a schematic illustration of an alternative base construction process according to an embodiment of the present invention;
fig. 2(d) is a schematic view of an alternative pile foundation and soil retaining structure construction process according to an embodiment of the present invention;
FIG. 2(e) is a schematic diagram of an alternative cast-in-place process according to an embodiment of the invention;
FIG. 3 is a flow chart of an alternative method for determining a high pile wharf project construction process scheme according to an embodiment of the invention; and
fig. 4 is a schematic diagram of a device for determining a high-pile wharf engineering construction process scheme according to an embodiment of the invention.
Detailed Description
In order to make the technical solutions of the present invention better understood, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that the terms "first," "second," and the like in the description and claims of the present invention and in the drawings described above are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It is to be understood that the data so used is interchangeable under appropriate circumstances such that the embodiments of the invention described herein are capable of operation in sequences other than those illustrated or described herein. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
Example 1
In accordance with an embodiment of the present invention, there is provided an embodiment of a method for determining a project engineering process plan for a high pile wharf, it should be noted that the steps illustrated in the flowchart of the drawings may be executed in a computer system such as a set of computer executable instructions, and that although a logical order is illustrated in the flowchart, in some cases, the steps illustrated or described may be executed in an order different from the order illustrated.
Fig. 1 is a flowchart of a method for determining a high-pile wharf engineering construction process scheme according to an embodiment of the invention, and as shown in fig. 1, the method includes the following steps:
and S102, acquiring engineering information of the high-pile wharf engineering.
In step S102, the project information of the high pile wharf project includes at least one of: and the subsection of the high-pile wharf engineering is divided into project information, construction process information and construction resource information. Optionally, the construction process information includes, but is not limited to, a high pile wharf type, wherein the high pile wharf type includes, but is not limited to, a beam slab type and other types; the construction resource information includes, but is not limited to, information about the type of equipment used during construction, work efficiency, work type, and construction team.
In an optional embodiment, the simulation model may obtain engineering information of the high-pile wharf engineering, where the simulation model is a model of a typical high-pile wharf construction process established by using a discrete system simulation technique, and the model may simulate each subsection construction engineering of a detailed construction process of the high-pile wharf under a given construction scheme and resource constraints, reflect characteristics of the subsection construction engineering, and may output information of a construction period, construction cost, and the like of the construction scheme for quantitative analysis. Meanwhile, the simulation model can comprehensively and definitely reflect the interrelation, the mutual restriction and the interdependence among all the construction processes, and reflect a key route in a plan with various processes and complex relations, so that managers can concentrate on catching the main contradiction to ensure the construction period. By utilizing the starting time of each construction process reflected by the simulation model, resources can be better equipped and utilized, so that the aim of reducing the cost is fulfilled. In the process of executing the high-pile wharf project, the influence degree of delay of a certain subsection construction project on the completion time of other subsection construction projects or the total construction period can be predicted, and measures can be taken to adjust as soon as possible. The application of the simulation model provides powerful support for engineering construction planning and intelligent decision making of the high-pile wharf. In addition, the simulation model of the high-pile wharf project can be established by programming in a JAVA programming language.
Optionally, the manager establishes the simulation model through the computer, and inputs the engineering information of the high-pile wharf project through the input device of the computer, for example, the manager inputs the wharf type used in the construction process of the high-pile wharf project, the type of the adopted equipment, the work efficiency, the work type and the like to the simulation model through the keyboard.
And S104, simulating the construction process of the high-pile wharf project based on the project information to obtain the initial construction process scheme information of each subsection project construction project in the construction process.
In step S104, the initial construction process recipe information includes at least one of: the starting time, the ending time, the resource intensity, the total construction period and the key route of the construction process.
Optionally, after obtaining the engineering information of the high-pile wharf engineering, the simulation model simulates the construction process of the high-pile wharf engineering, and the discrete system simulation technology and the cyclic network technology are adopted to simulate the construction process, so as to obtain the start time, the end time and the resource strength of each construction process in the construction process, and the total construction period and the key route determined in the construction process. The method can regard resources involved in the construction process as flow units, divide the flow units into working and queuing waiting states according to the queuing theory, simultaneously regard the whole construction process as a dynamic flow process of the flow units, establish a circulating network model for the construction process of an engineering object, perform simulation calculation on a computer, and simulate a construction period progress index under different resource configurations and construction plans. And then, comprehensively considering the construction progress of the high-pile wharf engineering, and performing initial assignment on the engineering information in the simulation model by using an expert experience method and an engineering comparison method to form initial information of each construction process.
In addition, it should be noted that the simulation technique can be divided into a continuous system simulation technique and a discrete system simulation technique according to the relationship between the system state change and the time. In the high-pile wharf engineering construction system, the state changes of the ship equipment, the pile caps, the beam lattices and other entities all occur at discrete time points and are discontinuous in time, so that a discrete system simulation technology is adopted in the application.
The simulation of the construction process of the high-pile wharf engineering is realized through the step S104, the relevant information in the construction process of the high-pile wharf engineering is comprehensively considered in the simulation process of the construction process, and the construction process scheme information of each subsection construction engineering is obtained according to the relevant information, so that the accurate analysis of the high-pile wharf engineering is realized.
And S106, optimizing the construction process based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction project.
In the process of the process information of each construction process obtained through the simulation model, the start time of the construction process on the non-critical route is the earliest start time of the construction process, so that the construction is concentrated in some time intervals, which causes excessive resource intensity or large difference of the demand of the resources in each time interval. If the resources are not optimized in a balanced manner, a phenomenon of labor rescue or work loss can be caused in the construction process, and the material supply can be disconnected or excessive, so that the smooth construction is influenced, and unnecessary waste of manpower and material resources is caused. Therefore, after the initial process information of each construction process is obtained by the simulation model, it is necessary to perform intensity statistics on the initial process information and perform resource balance optimization. Optionally, the starting time of the construction process of the non-critical route may be adjusted by the maneuvering time difference of each construction process to achieve balanced allocation of resources. The resource balance optimization in the high-pile wharf project aims to solve the problem of resource balance consumption under the condition of a certain construction period, namely the problem of 'construction period limitation and resource balance'.
Optionally, in the present application, a "peak clipping and valley filling method" is used to perform resource intensity equalization optimization, and the method achieves the purpose of gradually reducing the maximum resource intensity and reducing the fluctuation of the dynamic curve by adjusting the start time of a part of the construction process within the maximum resource intensity period based on the maximum intensity value of the dynamic curve of the resource.
Based on the schemes defined in the above steps S102 to S106, it can be known that, by analyzing and optimizing the construction process scheme information of each subsection of the high-pile wharf project, after the project information of the high-pile wharf project is obtained, the construction process of the high-pile wharf project is simulated based on the project information to obtain the initial construction process scheme information of each subsection of the construction project in the construction process, and then the construction process is optimized based on the initial construction process scheme information to obtain the construction process scheme of each subsection of the construction project.
It is easy to notice that, in the application, the relevant information in the construction process of the high-pile wharf engineering is comprehensively considered, and the construction process scheme information of each subsection construction engineering is obtained according to the relevant information, so that the accurate analysis of the high-pile wharf engineering is realized. In addition, in order to further improve the accuracy of analysis, after the construction process scheme information of each subsection construction project is obtained, each subsection construction project is further optimized, and then an optimal construction scheme is obtained.
Therefore, the scheme provided by the application achieves the purpose of predicting and analyzing the high-pile wharf engineering, the technical effect of improving the accuracy of prediction and analysis of the high-pile wharf engineering is achieved, and the technical problem that the existing method for predicting and analyzing the construction process of the high-pile wharf engineering according to construction experience causes inaccuracy of the construction process scheme of the high-pile wharf engineering is solved.
In an optional embodiment, after obtaining the engineering information of the high-pile wharf engineering, the simulation model simulates the construction process of the high-pile wharf engineering based on the engineering information to obtain the initial construction process scheme information of each subsection construction engineering in the construction process. Specifically, the simulation model configures the construction process flow of the high-pile wharf project according to the project information to obtain a configuration result, divides the construction implementation mode of the high-pile wharf project on the spatial arrangement according to the project information to obtain a division result, determines the construction sequence of each subsection construction project according to the configuration result and the division result, obtains resource information corresponding to each subsection construction project, and finally simulates the construction process according to the construction sequence and the resource information to obtain initial construction process scheme information of each subsection construction project.
In the above process, the resource information includes at least one of: device information, and manual information. The device information includes, but is not limited to, a device type, a maximum number of devices, and a minimum number of devices; the manual information includes, but is not limited to, work category maximum number, and work category minimum number.
In addition, the high-pile wharf engineering is divided, which mainly means that the high-pile wharf engineering is divided in spatial arrangement when the construction engineering is organized in flowing water construction, wherein the high-pile wharf engineering can be divided into a structure section, a construction section and a surface layer strip.
Optionally, the structure section is in the work progress, and high stake pier major structure divides into a plurality of structure sections that the structure is similar, and wherein, the construction of pile foundation uses the structure section to construct as unit order. The construction section is a division concept of horizontal construction of upper structural parts (e.g., pile caps, beam lattices, cast-in-place nodes, panels, and slab joints) within a structural section, and one structural section may be divided into a plurality of construction sections for construction, which are advanced in a horizontal direction. The construction process of pile caps, beam grids (including longitudinal beams, cross beams, track beams and ship leaning components), cast-in-place nodes, panels and plate joints is promoted by a typical construction section. The construction of the surface layer strip is not included in the category of a typical construction section, but the construction process of the surface layer strip is similar to the concept of the typical construction section, the surface layer is divided into a plurality of strips, and each part is constructed by the flow of the construction project.
Optionally, fig. 2(a) to 2(e) show a flow chart of an optional construction process, where fig. 2(c) is a schematic diagram of a basic construction process, fig. 2(d) is a schematic diagram of a pile foundation and soil retaining structure construction process, and fig. 2(e) is a schematic diagram of a cast-in-place process. As can be seen from fig. 2(a) to 2(e), in the horizontal plane, the construction direction is sequentially constructed in units of structural sections from the wharf end until completion. The construction sequence of the single structural section on the vertical surface is as follows: pile foundation → pile cap, beam lattice, node, panel, plate joint construction with construction section → surface layer construction → installation of wharf appurtenances and others. The superstructure in the structure section can divide into sea and land both sides by oneself, and every side is under construction alone, can start to promote the construction to the other end from the one end of structure section, also can start to promote the construction to the pier centre from the both ends of structure section. The resources involved in the construction process comprise ship equipment, human resources and template resources. Generally, the more resources are allocated, the shorter the construction period; the less the resource is allocated, the longer the construction period.
Further, after the initial construction process scheme information of each subsection project construction is obtained, in order to improve the accuracy of analysis and save resources, the simulation model optimizes the construction process based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction. Specifically, the simulation model firstly obtains initial process information of a construction process corresponding to each preset time period, then determines a resource intensity value in each preset time period according to the initial process information, determines a maximum resource intensity value from the resource intensity values in the preset time periods, and finally optimizes the construction process according to the maximum resource intensity value and the maximum target intensity value and preset rules.
Optionally, the optimizing the construction process according to the maximum resource intensity value and the maximum target intensity value and according to a preset rule includes: under the condition that the maximum value of the resource intensity in the current preset time period is larger than the maximum value of the target intensity, determining a first construction process in which the resource intensity value in the current preset time period is minimum; when the number of the first construction processes is one, postponing the construction starting time corresponding to the first construction process to the next preset time period; and under the condition that the number of the first construction procedures is multiple, acquiring adjustable time differences corresponding to the multiple first construction procedures, and optimizing the construction process according to the adjustable time differences.
Wherein, the step of optimizing the work progress according to the adjustable time difference comprises: acquiring adjustable time differences corresponding to a plurality of first construction processes, and determining a second construction process with the maximum adjustable time difference; when the number of the second construction processes is one, postponing the starting time corresponding to the second construction process to the next preset time period; and under the condition that the number of the second construction processes is multiple, acquiring the maximum value of the first resource intensity, and postponing the starting time of the corresponding second construction process when the maximum value of the first resource intensity is smaller than the maximum value of the target intensity until the next preset time period.
Specifically, the simulation model detects the construction process being constructed and detects the construction strength of the construction process being constructed each time Δ T (namely, a preset time period) is advanced in the simulation time, then counts the engineering quantity in the preset time period and the resource strength value in each preset time period, draws an initial resource strength dynamic curve graph, and determines the maximum resource strength value Rmax1 according to the resource strength dynamic curve graph.
Further, the simulation model compares the resource intensity maximum value Rmax1 with the target intensity maximum value Rmax 2. Specifically, the simulation model selects a non-critical process which is positioned in the preset time period and can be postponed to start after the preset time period according to a priority postponing rule from back to front for resource intensity peaks of all preset time periods which are larger than the maximum value Rmax2 of the target intensity, and postpones the non-critical process to start after the preset time period, so that the resource intensity peaks are cut down once, and the resource intensity valleys are filled up once correspondingly. The simulation model then modifies the time parameters (e.g., start time, end time) in the corresponding construction process, and repeats the above process until the maximum resource strength value cannot be reduced.
In addition, the "priority deferral" rule may include: preferentially postponing the construction process with low resource strength; under the condition of the same resource strength, the construction process with large adjustable time difference is delayed preferentially; the adjusted peak intensity of the resource is lower than the peak value of the target resource.
It should be noted that the first maximum resource strength value may be obtained by any one or more of the following manners:
acquiring the starting time corresponding to each second construction procedure, and postponing the starting time to the maximum value of the corresponding resource strength in the next preset time period to obtain the maximum value of the first resource strength; and/or adjusting the resource allocation corresponding to each second construction process to obtain an adjusted second construction process, wherein the maximum value of the resource intensity corresponding to the adjusted second construction process is the maximum value of the first resource intensity.
In addition, before the construction process is optimized according to the maximum resource intensity value and the maximum target intensity value and according to a preset rule, the maximum target intensity value can be determined in any one of the following manners: determining a maximum value of the target intensity according to a product of the maximum value of the resource intensity and a preset weight, wherein the preset weight is a positive number less than 1, for example, 97% of the maximum value of the resource intensity may be the maximum value of the target intensity, and 97% is the preset weight; or determining the maximum value of the target intensity according to the difference value between the maximum value of the resource intensity and a preset value, wherein the preset value is a positive number.
In addition, it should be noted that the decision of the high-pile wharf construction project is a multi-objective optimization problem. The multi-objective optimization problem is that under the condition that the resource allocation of the process is not fixed (for example, the resource allocation quantity is not unique or within a range, and the work in the project has a combination form of various working hours and resource demand for selection), the preset targets of cost and construction period are finally achieved by adjusting the resource allocation of the construction process and the work starting time of the construction process. In the method, the optimization model is solved by adopting a genetic algorithm, so that the intelligent decision of the construction process is realized.
Optionally, fig. 3 shows a flow chart of a method for determining an optional construction procedure of a high-pile wharf project, and as can be seen from fig. 3, the method mainly includes four stages, namely, a project and resource information entry stage, a construction planning stage, a construction network generation stage, and a simulation and optimization stage. In the engineering and resource information input stage, a user selects a high-pile wharf type through a computer and then inputs branch project information, ship equipment and manual information of the wharf. In the construction planning stage, the simulation model divides the construction project into a structure section, a construction section and a surface layer strip, and selects a subsection project process flow to further determine the construction equipment and the manual information of each construction process. In the stage of generating the construction network, the simulation model generates a network diagram of the construction processes according to the process flows of the sub-engineering, wherein the network diagram of the construction processes is a directed network relation diagram among the construction processes. In the simulation and optimization stage, the simulation model optimizes the construction process to obtain an optimization result. Specifically, under the condition that the process resource allocation is fixed, the minimum value of the total resource input amount is calculated, so that the construction cost is minimum; under the condition that the process resource allocation and the total resource input amount are fixed, reasonably arranging the construction sequence to ensure that the total construction period is shortest; and under the conditions that the resource allocation of the process is variable, the total resource investment is fixed or the total resource investment is not limited, performing multi-objective optimization. And finally, generating a construction plan according to the optimization result, wherein the construction plan comprises but is not limited to a construction period, a key route, a resource allocation plan, a process construction schedule, a resource input plan and the like.
Therefore, according to the scheme provided by the application, the computer simulation technology is applied to the construction planning process of the high-pile wharf, the special characteristics of the high-pile wharf engineering can be met, the method has strong pertinence, and the actual problem in the construction process planning of the high-pile wharf can be better solved.
Example 2
According to an embodiment of the present invention, there is further provided an embodiment of a device for determining a high-pile wharf engineering technical scheme, where fig. 4 is a schematic diagram of the device for determining a high-pile wharf engineering technical scheme according to an embodiment of the present invention, and as shown in fig. 4, the device includes: an acquisition module 401, a simulation module 403, and an optimization module 405.
The acquiring module 401 is configured to acquire engineering information of a high-pile wharf project; the simulation module 403 is configured to simulate a construction process of a high-pile wharf project based on the project information to obtain initial construction process scheme information of each subsection project construction project in the construction process; and the optimization module 405 is configured to optimize the construction process based on the initial construction process scheme information to obtain the construction process schemes of the respective sub-project construction projects.
It should be noted here that the obtaining module 401, the simulating module 403 and the optimizing module 405 correspond to steps S102 to S106 of the above embodiment, and the three modules are the same as the corresponding steps in the implementation example and application scenario, but are not limited to the disclosure of the above embodiment.
In an alternative embodiment, the simulation module comprises: the device comprises a configuration module, a dividing module, a first determining module, a first obtaining module and a first obtaining module. The configuration module is used for configuring the construction process flow of the high-pile wharf project according to the project information to obtain a configuration result; the dividing module is used for dividing the construction implementation mode of the high-pile wharf engineering on the spatial arrangement according to the engineering information to obtain a dividing result; the first determining module is used for determining the construction sequence of each construction procedure according to the configuration result and the division result; the first acquisition module is used for acquiring resource information corresponding to each construction process, wherein the resource information comprises at least one of the following: device information and manual information; and the first processing module is used for simulating the construction process according to the construction sequence and the resource information to obtain the initial construction process scheme information of each subsection project construction project.
In an alternative embodiment, the optimization module comprises: the device comprises a second obtaining module, a second determining module, a third determining module and a first optimizing module. The second acquisition module is used for acquiring initial process information of the construction process corresponding to each preset time period; the second determining module is used for determining the resource intensity value in each preset time period according to the initial process information; the third determining module is used for determining the maximum value of the resource intensity from the resource intensity values in a plurality of preset time periods; and the first optimization module is used for optimizing the construction process according to the maximum value of the resource intensity and the maximum value of the target intensity and preset rules.
In an alternative embodiment, the first optimization module comprises: the device comprises a fourth determination module, a second processing module and a second optimization module. The fourth determining module is used for determining the first construction process with the minimum resource intensity value in the current preset time period under the condition that the maximum resource intensity value in the current preset time period is greater than the maximum target intensity value; the second processing module is used for postponing the construction starting time corresponding to the first construction procedure to the next preset time period under the condition that the number of the first construction procedures is one; and the second optimization module is used for acquiring the adjustable time difference corresponding to the first construction procedures under the condition that the number of the first construction procedures is multiple, and optimizing the construction process according to the adjustable time difference.
In an alternative embodiment, the second optimization module comprises: the device comprises a third acquisition module, a third processing module and a fourth processing module. The third acquisition module is used for acquiring adjustable time differences corresponding to the plurality of first construction processes and determining a second construction process with the largest adjustable time difference; the third processing module is used for postponing the starting time corresponding to the second construction procedure to the next preset time period under the condition that the number of the second construction procedures is one; and the fourth processing module is used for acquiring the maximum value of the first resource strength under the condition that the number of the second construction processes is multiple, and postponing the starting time of the corresponding second construction process when the maximum value of the first resource strength is smaller than the maximum value of the target strength to the next preset time period.
In an alternative embodiment, the fourth processing module comprises: a fifth processing module, wherein the fifth processing module is configured to obtain the first resource strength maximum value by any one or more of the following manners: acquiring the starting time corresponding to each second construction procedure, and postponing the starting time to the maximum value of the corresponding resource strength in the next preset time period to obtain the maximum value of the first resource strength; and adjusting the resource allocation corresponding to each second construction process to obtain an adjusted second construction process, wherein the maximum value of the resource intensity corresponding to the adjusted second construction process is the maximum value of the first resource intensity.
In an optional embodiment, the apparatus for determining a project construction process scheme for a high-pile wharf further includes: and a fifth determining module. The fifth determining module is configured to determine the maximum value of the target intensity by any one of the following methods: determining a target intensity maximum value according to the product of the resource intensity maximum value and a preset weight, wherein the preset weight is a positive number smaller than 1; or determining the maximum value of the target intensity according to the difference value between the maximum value of the resource intensity and a preset value, wherein the preset value is a positive number.
Optionally, the engineering information includes at least one of: the method comprises the following steps of (1) dividing project information, construction process information and construction resource information of high-pile wharf projects; the initial construction process scheme information comprises at least one of the following: the starting time, the ending time, the resource intensity, the total construction period and the key route of the construction process.
Example 3
According to another aspect of the embodiment of the present invention, a storage medium is further provided, where the storage medium includes a stored program, and when the program runs, the device on which the storage medium is located is controlled to execute the determination method of the high-pile wharf engineering construction process scheme in embodiment 1.
Example 4
According to another aspect of the embodiment of the present invention, a processor is further provided, where the processor is configured to execute the program, where the program executes the method for determining the engineering technical scheme of the high-piled wharf engineering in embodiment 1 when running.
The above-mentioned serial numbers of the embodiments of the present invention are merely for description and do not represent the merits of the embodiments.
In the above embodiments of the present invention, the descriptions of the respective embodiments have respective emphasis, and for parts that are not described in detail in a certain embodiment, reference may be made to related descriptions of other embodiments.
In the embodiments provided in the present application, it should be understood that the disclosed technology can be implemented in other ways. The above-described embodiments of the apparatus are merely illustrative, and for example, the division of the units may be a logical division, and in actual implementation, there may be another division, for example, multiple units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, units or modules, and may be in an electrical or other form.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present invention may be embodied in the form of a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, or a network device) to execute all or part of the steps of the method according to the embodiments of the present invention. And the aforementioned storage medium includes: a U-disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a removable hard disk, a magnetic or optical disk, and other various media capable of storing program codes.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, various modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.

Claims (10)

1. A method for determining a high-pile wharf engineering construction process scheme is characterized by comprising the following steps:
acquiring engineering information of a high-pile wharf engineering;
simulating the construction process of the high-pile wharf project based on the project information to obtain initial construction process scheme information of each subsection project construction project in the construction process;
optimizing the construction process based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction project;
simulating the construction process of the high-pile wharf project based on the engineering information to obtain the initial construction process scheme information of each subsection project construction project in the construction process, wherein the initial construction process scheme information comprises the following steps:
configuring the construction process flow of the high-pile wharf engineering according to the engineering information to obtain a configuration result;
dividing the construction implementation mode of the high-pile wharf project on the spatial arrangement according to the project information to obtain a division result;
determining the construction sequence of each construction procedure according to the configuration result and the division result;
acquiring resource information corresponding to each construction process, wherein the resource information comprises at least one of the following: device information and manual information;
and simulating the construction process according to the construction sequence and the resource information to obtain the initial construction process scheme information of each subsection project construction project.
2. The method of claim 1, wherein optimizing the construction process based on the initial construction process scenario information to obtain a construction process scenario for each of the sub-division construction projects comprises:
acquiring initial process information of a construction process corresponding to each preset time period;
determining a resource intensity value in each preset time period according to the initial process information;
determining a maximum value of the resource intensity from the resource intensity values in a plurality of preset time periods;
and optimizing the construction process according to the maximum resource intensity value and the maximum target intensity value and preset rules.
3. The method of claim 2, wherein optimizing the construction process according to the maximum resource intensity value and the maximum target intensity value according to a preset rule comprises:
determining a first construction process with the minimum resource intensity value in the current preset time period under the condition that the maximum resource intensity value in the current preset time period is greater than the maximum target intensity value;
when the number of the first construction processes is one, postponing the construction starting time corresponding to the first construction process to a next preset time period;
and under the condition that the number of the first construction procedures is multiple, acquiring a plurality of adjustable time differences corresponding to the first construction procedures, and optimizing the construction process according to the adjustable time differences.
4. The method of claim 3, wherein optimizing the construction process based on the adjustable time difference comprises:
acquiring adjustable time differences corresponding to a plurality of first construction processes, and determining a second construction process with the maximum adjustable time difference;
when the number of the second construction processes is one, postponing the starting time corresponding to the second construction process to the next preset time period;
and under the condition that the number of the second construction processes is multiple, acquiring a first resource intensity maximum value, and postponing the starting time of the corresponding second construction process when the first resource intensity maximum value is smaller than the target intensity maximum value to the next preset time period.
5. The method of claim 4, wherein the first resource strength maximum is obtained by any one or more of:
acquiring a starting time corresponding to each second construction procedure, and postponing the starting time to a maximum value of the corresponding resource strength within a next preset time period to obtain a maximum value of the first resource strength;
and adjusting the resource allocation corresponding to each second construction process to obtain an adjusted second construction process, wherein the maximum value of the resource intensity corresponding to the adjusted second construction process is the maximum value of the first resource intensity.
6. The method of claim 2, wherein before optimizing the construction process according to the resource intensity maximum and the target intensity maximum according to a preset rule, the method further comprises:
determining the target intensity maximum by any one of:
determining the maximum value of the target intensity according to the product of the maximum value of the resource intensity and a preset weight, wherein the preset weight is a positive number smaller than 1; alternatively, the first and second electrodes may be,
and determining the maximum value of the target intensity according to the difference value between the maximum value of the resource intensity and a preset value, wherein the preset value is a positive number.
7. The method of claim 1, wherein the engineering information comprises at least one of: the method comprises the following steps of (1) dividing project information, construction process information and construction resource information of high-pile wharf projects; the initial construction process scheme information comprises at least one of the following: the starting time, the ending time, the resource intensity, the total construction period and the key route of the construction process.
8. A device for determining a high-pile wharf engineering construction process scheme is characterized by comprising the following steps:
the acquisition module is used for acquiring the engineering information of the high-pile wharf engineering;
the simulation module is used for simulating the construction process of the high-pile wharf project based on the project information to obtain the initial construction process scheme information of each subsection project construction project in the construction process;
the optimization module is used for optimizing the construction process based on the initial construction process scheme information to obtain the construction process scheme of each subsection project construction project;
the simulation module comprises a configuration module, a dividing module, a first determining module, a first acquiring module and a first processing module,
the configuration module is used for configuring the construction process flow of the high-pile wharf project according to the project information to obtain a configuration result;
the dividing module is used for dividing the construction implementation mode of the high-pile wharf project on the spatial arrangement according to the project information to obtain a dividing result;
the first determining module is used for determining the construction sequence of each construction procedure according to the configuration result and the division result;
the first obtaining module is configured to obtain resource information corresponding to each construction process, where the resource information includes at least one of: device information and manual information;
and the first processing module is used for simulating the construction process according to the construction sequence and the resource information to obtain the initial construction process scheme information of each subsection project construction project.
9. A storage medium, characterized in that the storage medium comprises a stored program, wherein when the program runs, the device on which the storage medium is located is controlled to execute the method for determining the engineering technical scheme of the high pile wharf engineering according to any one of claims 1 to 7.
10. A processor, characterized in that the processor is configured to run a program, wherein the program is configured to execute the method for determining a high pile wharf engineering construction process scheme according to any one of claims 1 to 7 when running.
CN201910473267.5A 2019-05-31 2019-05-31 Method and device for determining engineering construction process scheme of high-pile wharf Active CN110258442B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910473267.5A CN110258442B (en) 2019-05-31 2019-05-31 Method and device for determining engineering construction process scheme of high-pile wharf

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910473267.5A CN110258442B (en) 2019-05-31 2019-05-31 Method and device for determining engineering construction process scheme of high-pile wharf

Publications (2)

Publication Number Publication Date
CN110258442A CN110258442A (en) 2019-09-20
CN110258442B true CN110258442B (en) 2021-03-30

Family

ID=67916372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910473267.5A Active CN110258442B (en) 2019-05-31 2019-05-31 Method and device for determining engineering construction process scheme of high-pile wharf

Country Status (1)

Country Link
CN (1) CN110258442B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114922132B (en) * 2022-05-19 2023-07-14 中交第二航务工程局有限公司 Construction method for upper structure of high pile wharf based on combined inclined piles
CN117473840B (en) * 2023-12-26 2024-04-26 中交第四航务工程勘察设计院有限公司 Simulation and optimization method and system based on construction process for sheet pile wharf

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101303569A (en) * 2008-06-20 2008-11-12 上海振华港口机械(集团)股份有限公司 Full analogue simulation system and method of automatization dock equipment
CN103321237A (en) * 2013-06-04 2013-09-25 中交第二航务工程勘察设计院有限公司 Tubular pile combined structure and construction method for wharf engineering
CN105975722A (en) * 2016-05-26 2016-09-28 河海大学 Unloading effect evaluation method for pile bearing platform in separation unloading type sheet pile wharf

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101303569A (en) * 2008-06-20 2008-11-12 上海振华港口机械(集团)股份有限公司 Full analogue simulation system and method of automatization dock equipment
CN103321237A (en) * 2013-06-04 2013-09-25 中交第二航务工程勘察设计院有限公司 Tubular pile combined structure and construction method for wharf engineering
CN105975722A (en) * 2016-05-26 2016-09-28 河海大学 Unloading effect evaluation method for pile bearing platform in separation unloading type sheet pile wharf

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
BIM技术在高桩码头设计施工一体化建设中的应用;李薇等;《中国水运》;20181031;第1-5小节 *

Also Published As

Publication number Publication date
CN110258442A (en) 2019-09-20

Similar Documents

Publication Publication Date Title
Tavana et al. A new multi-objective multi-mode model for solving preemptive time–cost–quality trade-off project scheduling problems
Wang et al. Time–cost–quality trade-off analysis for planning construction projects
Reca et al. Optimisation model for water allocation in deficit irrigation systems: I. Description of the model
Arditi et al. Effect of learning on line-of-balance scheduling
Cheng et al. Two-phase differential evolution for the multiobjective optimization of time–cost tradeoffs in resource-constrained construction projects
CN110258442B (en) Method and device for determining engineering construction process scheme of high-pile wharf
Fallah‐Fini et al. Optimizing highway maintenance operations: dynamic considerations
CN104700662A (en) Coordinated path time slot allocation method based on fuzzy comprehensive evaluation
Ke et al. Modeling stochastic project time–cost trade-offs with time-dependent activity durations
CN111754336A (en) Network scheduling method and device
CN104407688A (en) Virtualized cloud platform energy consumption measurement method and system based on tree regression
Leong et al. Application of water evaluation and planning model for integrated water resources management: case study of langat river basin, Malaysia
Lu et al. A resource investment problem based on project splitting with time windows for aircraft moving assembly line
CN113378486A (en) Regional traffic signal optimization method and device, computing equipment and storage medium
Scherz et al. Challenges in the achievement of a Net Zero Carbon Built Environment–A systemic approach to support the decision-aiding process in the design stage of buildings
CN102142192B (en) Method and system for forewarning pedestrian traffic congestion based on combined multi-step prediction
Eisenblätter et al. Multistage stochastic programming in strategic telecommunication network planning
Marzouk et al. Quantifying weather impact on formwork shuttering and removal operation using system dynamics
CN111861397A (en) Intelligent scheduling platform for client visit
Majid et al. Distributed model predictive control of freeway traffic networks: A serial partially cooperative approach
Rastogi et al. Planning for a changing climate without accurate predictions
KR101482004B1 (en) Construction Lifting Simulation Method and System using an Optimal B&B Algorithm
Rustom et al. Estimating productivity using simulation: A case study of Gaza beach embankment protection project
CN116822877B (en) Knowledge graph-based water resource distribution method, device and medium
Wu et al. Optimization for multi-resource allocation and leveling based on a self-adaptive ant colony algorithm

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant