CN110245918A - Project supervision monitoring and managing method and system based on BIM - Google Patents

Project supervision monitoring and managing method and system based on BIM Download PDF

Info

Publication number
CN110245918A
CN110245918A CN201910518658.4A CN201910518658A CN110245918A CN 110245918 A CN110245918 A CN 110245918A CN 201910518658 A CN201910518658 A CN 201910518658A CN 110245918 A CN110245918 A CN 110245918A
Authority
CN
China
Prior art keywords
construction
subelement
accounting
project
bim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910518658.4A
Other languages
Chinese (zh)
Inventor
张誉颢
袁红武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Bolian Engineering Supervision Co Ltd
Original Assignee
Shanghai Bolian Engineering Supervision Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Bolian Engineering Supervision Co Ltd filed Critical Shanghai Bolian Engineering Supervision Co Ltd
Priority to CN201910518658.4A priority Critical patent/CN110245918A/en
Publication of CN110245918A publication Critical patent/CN110245918A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)

Abstract

The present invention relates to management regulation technique fields, disclose a kind of project supervision monitoring and managing method and system based on BIM, and wherein to include: design side establish project BIM model according to state architectural design standard to method, and project has subelement;Threedimensional model is constructed according to the arrangement and method for construction of Construction Party, multiple submodels are generated for threedimensional model, submodel compares one by one with subelement, submodel and subelement are compared, set up multiple threads, corresponding submodel and subelement are compared, it is whether reasonable according to the time-consuming of comparing result and accounting assessment Construction Party's arrangement and method for construction of threedimensional model size;It submits design side to appraise and decide in the place that accounting is greater than setting accounting value, and is optimized accordingly, modified, be finally completed the adjustment of arrangement and method for construction;The design document of Construction Party is examined using the accounting of the time-consuming and threedimensional model size of comparing result, quickly remind submodel and subelement, information verification is high-efficient, is truly realized detail ground management control.

Description

Project supervision monitoring and managing method and system based on BIM
Technical field
The present invention relates to management regulation technique fields, more specifically, it relates to a kind of project supervision supervision based on BIM Method and system.
Background technique
Project Supervision unit is entrusted by construction unit, according to laws and regulations, engineering construction standard, prospective design file And contract, project delivery method, cost, progress are controlled in the construction stage, contract, information are managed, to engineering The relationship of construction related side is coordinated, and fulfils the service activity of construction project production safety management statutory obligation.
With the popularization of BIM at home, BIM is gradually used in management.If notification number is CN105844380A Chinese patent disclose the management method and system of a kind of BIM engineering project element based on BIM, by that will include BIM number According to library, progress management subsystem, cost management subsystem, contract management subsystem, System of Quality Control and mobile terminal collection It is realized in set of system, the management of engineering project top 5 factor can be completed using set of system, reduce management cost.
But the unit and department being related to due to project supervision are numerous, traditional method such as has a meeting, mode of sending the documents, letter The efficiency for ceasing verification is very low, and grasping dynamic information verification in time more seems very difficult.
Summary of the invention
Problem in view of the prior art, the purpose of the present invention one are to provide a kind of project supervision monitoring party based on BIM Method has the advantages that information verification is high-efficient.The purpose of the present invention two is to provide a kind of project supervision supervision based on BIM System has the advantages that information verification is high-efficient.
To achieve the above object one, the present invention provides the following technical scheme that
A kind of project supervision monitoring and managing method based on BIM, includes the following steps:
Step S1: establishing project BIM model according to state architectural design standard, and project has subelement, is that each subelement is standby Part data;
Step S2: constructing threedimensional model according to the arrangement and method for construction of Construction Party, generates multiple submodels for threedimensional model, submodel with Subelement compares one by one, and the submodel in threedimensional model is compared with the subelement in project BIM model, sets up multiple lines Journey, while the corresponding submodel of multiple groups and subelement are compared, it is commented according to the accounting of the time-consuming and threedimensional model size of comparing result Whether reasonable estimate Construction Party's arrangement and method for construction;
Step S3: it submits design side to appraise and decide in the place that accounting is greater than setting accounting value, and is optimized accordingly, modified, most The adjustment of arrangement and method for construction is completed eventually.
Through the above technical solutions, utilizing the time-consuming and threedimensional model of comparing result using BIM ancillary technique coordinated management The accounting of size examines the design document of Construction Party, quickly reminds the son that " Wrong, missing is touched, lacked " is likely to occur in drawing Model and subelement, information verification is high-efficient, is truly realized detail ground management control.
Further, in step s 2, the occupied arithmetic core of multiple threads is different.
Through the above technical solutions, the difference of arithmetic core can reduce the queuing rate between contrast operation, it is conducive to shorten fortune Evaluation time.
Further, in step s 2, amplification accounting to accounting is greater than 1.
It through the above technical solutions, being greater than 1 accounting, can be compared with 1, and sentencing for later period multiple accountings can be conducive to It is disconnected.
Further, in step s 2, using project BIM model, management side assembles complex node in order and says Solution.
Through the above technical solutions, assembling is said in order when management side provides technical support to technical work personnel Solution will be more easy.
Further, in step s 2, management side is pre-installed by a plurality of crosspoint of the BIM technology to pipe network, and Corresponding technical advice suggestion is proposed to Construction Party.
Through the above technical solutions, management side pre-installs a plurality of crosspoint by BIM technology, in strict accordance with design Drawing requirement arranges every pipe network, is demonstrated, and pre-control before doing good avoids the generation of quality accident.
A kind of project supervision supervisory systems based on BIM, comprising:
Background data base, it is each subelement Backup Data that for the data of save project BIM model, project, which has subelement,;
Cloud Server is connect with the background data base, for updating, managing data in the background data base;
Mobile terminal is connect with the Cloud Server, and the project BIM in the background data base is read by the Cloud Server Model data, and the threedimensional model constructed to Cloud Server transmission arrangement and method for construction, generate multiple submodels for threedimensional model;
The mobile terminal includes wireless transport module, recording module and contrast module, and the wireless transport module is used for and institute State Cloud Server exchange information, the recording module is used to input the arrangement and method for construction of Construction Party, the contrast module respectively with institute Recording module is stated to connect with the wireless transport module;
Submodel compares one by one with subelement, and the subelement in the submodel and project BIM model in threedimensional model is carried out pair Than multiple threads being set up, while comparing the corresponding submodel of multiple groups and subelement, according to the time-consuming and threedimensional model of comparing result Whether accounting assessment Construction Party's arrangement and method for construction of size is reasonable, and the place that accounting is greater than setting accounting value is passed through wireless transmission mould Block is sent to Cloud Server.
Further, the occupied arithmetic core of multiple threads is different.
Further, amplification accounting to accounting is greater than 1.
Further, the mobile terminal is equipped with project supervision APP, and the project supervision APP includes: design APP, supplies Project BIM model is stored into the background data base by design side;APP is contracted, three will constructed by arrangement and method for construction for Construction Party Dimension module is transferred to the Cloud Server;The comparing result of threedimensional model and project BIM model is presented to management by management APP Side.
Further, the background data base also stores construction progress information, the Cloud Server further include: construct into Journey reminding module reminds the complex node of engineering according to the construction progress information in the background data base to the mobile terminal Or a plurality of crosspoint of pipe network.
Compared with prior art, the beneficial effects of the present invention are: management side is read using mobile terminal by Cloud Server Project BIM model data and threedimensional model in background data base compare submodule and subelement, find out accounting after the two verification The arrangement and method for construction of Construction Party is uploaded to Cloud Server using mobile terminal by the difference of numerical value, management side;Design can pass through shifting Dynamic terminal access background data base, appraises and decides the arrangement and method for construction of building side, and optimized accordingly, modified, by designing Arrangement and method for construction adjusted is uploaded to Cloud Server by side, is supervised simple and convenient.
Detailed description of the invention
Fig. 1 is the method flow schematic diagram of the embodiment of the present invention one.
Fig. 2 is the system block diagram of the embodiment of the present invention two.
Specific embodiment
With reference to the accompanying drawings and examples, the present invention will be described in detail.
Embodiment one
A kind of project supervision supervision based on BIM, as shown in Figure 1, including the following steps:
Step S1: project BIM model is established according to state architectural design standard.
Step S2: constructing threedimensional model according to the arrangement and method for construction of Construction Party, generates multiple submodels, submodule for threedimensional model Type compares one by one with subelement, and the submodel in threedimensional model is compared with the subelement in project BIM model, is set up more A thread, multiple occupied arithmetic cores of thread are different, the queuing rate between contrast operation reduced, when being conducive to shorten operation Between.The corresponding submodel of multiple groups and subelement are compared simultaneously, is commented according to the accounting of the time-consuming and threedimensional model size of comparing result Whether reasonable estimate Construction Party's arrangement and method for construction.Wherein, amplification accounting to accounting is greater than 1, and the accounting greater than 1 can be compared with 1, And the judgement of later period multiple accountings can be conducive to.
Step S3: it submits design side to appraise and decide in the place that accounting is greater than setting accounting value, and is optimized accordingly, repaired Change, is finally completed the adjustment of arrangement and method for construction.
Using BIM ancillary technique coordinated management, the design document of Construction Party can be examined, in reduction drawing " wrong, Leak, touch, lack " probability, realize by management side by accounting value check Construction Party's arrangement and method for construction feasibility, reasonability.It can also Quality control is carried out by accounting value to the corresponding submodel of single group and subelement, reinforces construction quality management, solves in construction Emphasis, difficulties.The generation of common quality defect can be effectively controlled from multiple accounting values simultaneously, promote engineering entity matter Amount is truly realized detail management control to simplify the work of Construction Party and management side, promote working efficiency and quality.Its In, under normal circumstances, accounting numerical value between operation time and threedimensional model size and ratio between accounting value is set as 1 left side The right side is longer than normal condition if accounting is greater than 1 for time-consuming, illustrates that BIM detects abnormal conditions and carries out operation to abnormal conditions, It can be submitted at this time to place is changed, abnormal prompt, information verification can be provided by calculating specific Exception Type without waiting for BIM It is high-efficient.
In step S2, using project BIM model, complex node and key technology are simulated by management side, to work order Position carries out technical support and process inspection.Previous plane institution movement is formed 3D three-dimensional real object by the visualization thinking provided using BIM Figure is shown in face of technical work personnel, is carried out quality control to special joint, is reinforced construction quality management, solves in construction Emphasis, difficulties, to greatly improve work effect.
In step s 2, using project BIM model, management side assembles complex node in order and explains;Management side When providing technical support to technical work personnel, assembling, which will carry out explanation, in order to be more easy.In step s 2, management side It is pre-installed by a plurality of crosspoint of the BIM technology to pipe network, and proposes corresponding technical advice suggestion to Construction Party;Management Side pre-installs a plurality of crosspoint by BIM technology, requires to arrange every pipe network in strict accordance with design drawing, drill Show, pre-control before doing good avoids the generation of quality accident.
Embodiment two
A kind of project supervision supervision based on BIM, as shown in Fig. 2, being with the difference of embodiment one, system includes back-end data Library, the data for save project BIM model.
Cloud Server is connect with background data base, for updating, data in management backstage database.
Mobile terminal is connect with the Cloud Server, reads the item in the background data base by the Cloud Server Mesh BIM model data, and the threedimensional model constructed to Cloud Server transmission arrangement and method for construction, generate multiple sons for threedimensional model Model.Mobile terminal includes wireless transport module, recording module and contrast module, and the wireless transport module is used for and the cloud Server exchange information, the recording module are used to input the arrangement and method for construction of Construction Party, the contrast module respectively with the record Enter module to connect with the wireless transport module.Submodel compares one by one with subelement, by the submodel and item in threedimensional model Subelement in mesh BIM model compares, and sets up multiple threads, and multiple occupied arithmetic cores of thread are different.It is right simultaneously Submodel more corresponding than multiple groups and subelement are applied according to the time-consuming of comparing result and the accounting assessment Construction Party of threedimensional model size Whether work scheme is reasonable, and amplification accounting to accounting is greater than 1.The place that accounting is greater than setting accounting value is passed through into wireless transport module It is sent to Cloud Server.
Project BIM model data and three-dimensional in background data base are read by Cloud Server using mobile terminal in management side Model, finds out difference between the two, and the arrangement and method for construction of Construction Party is uploaded to Cloud Server using mobile terminal by management side.If Meter can appraise and decide the arrangement and method for construction of building side by mobile terminal accessing background data base, and optimized accordingly, Arrangement and method for construction adjusted is uploaded to Cloud Server by design side, supervised simple and convenient by modification.
Background data base also stores construction progress information, Cloud Server further include: construction progress reminding module, according to rear Construction progress information in platform database reminds the complex node of engineering or a plurality of crosspoint of pipe network to mobile terminal.Management It can be confirmed whether to send engineer to construction ground according to the complex node or a plurality of crosspoint that construction progress reminding module is reminded Point carries out management, improves working efficiency.
Project supervision APP is installed, project supervision APP includes: design APP, for design side by project BIM on mobile terminal Model is stored into background data base;APP is contracted, for Construction Party by the three-dimensional model transmitting constructed by arrangement and method for construction to cloud service Device.The comparing result of threedimensional model and project BIM model is presented to management side by management APP.Design side, contractor and management It is mounted on corresponding APP on the mobile phone or tablet computer of side, different operations can be performed in different APP, efficient and convenient.It moves Dynamic terminal is that perhaps tablet computer mobile phone or tablet computer are light small and exquisite for smart phone, facilitates and is carried.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (10)

1. a kind of project supervision monitoring and managing method based on BIM, which comprises the steps of:
Step S1: establishing project BIM model according to state architectural design standard, and project has subelement, is that each subelement is standby Part data;
Step S2: constructing threedimensional model according to the arrangement and method for construction of Construction Party, generates multiple submodels for threedimensional model, submodel with Subelement compares one by one, and the submodel in threedimensional model is compared with the subelement in project BIM model, sets up multiple lines Journey, while the corresponding submodel of multiple groups and subelement are compared, it is commented according to the accounting of the time-consuming and threedimensional model size of comparing result Whether reasonable estimate Construction Party's arrangement and method for construction;
Step S3: it submits design side to appraise and decide in the place that accounting is greater than setting accounting value, and is optimized accordingly, modified, most The adjustment of arrangement and method for construction is completed eventually.
2. the method according to claim 1, wherein in step s 2, multiple occupied arithmetic cores of thread It is different.
3. according to the method described in claim 2, it is characterized in that, in step s 2, amplification accounting to accounting is greater than 1.
4. according to the method described in claim 3, it is characterized in that, in step s 2, utilizing project BIM model, management side pair Complex node assembles explained in order.
5. according to the method described in claim 4, it is characterized in that, in step s 2, management side is by BIM technology to pipe network A plurality of crosspoint is pre-installed, and proposes corresponding technical advice suggestion to Construction Party.
6. a kind of project supervision supervisory systems based on BIM characterized by comprising
Background data base, it is each subelement Backup Data that for the data of save project BIM model, project, which has subelement,;
Cloud Server is connect with the background data base, for updating, managing data in the background data base;
Mobile terminal is connect with the Cloud Server, and the project BIM in the background data base is read by the Cloud Server Model data, and the threedimensional model constructed to Cloud Server transmission arrangement and method for construction, generate multiple submodels for threedimensional model;
The mobile terminal includes wireless transport module, recording module and contrast module, and the wireless transport module is used for and institute State Cloud Server exchange information, the recording module is used to input the arrangement and method for construction of Construction Party, the contrast module respectively with institute Recording module is stated to connect with the wireless transport module;
Submodel compares one by one with subelement, and the subelement in the submodel and project BIM model in threedimensional model is carried out pair Than multiple threads being set up, while comparing the corresponding submodel of multiple groups and subelement, according to the time-consuming and threedimensional model of comparing result Whether accounting assessment Construction Party's arrangement and method for construction of size is reasonable, and the place that accounting is greater than setting accounting value is passed through wireless transmission mould Block is sent to Cloud Server.
7. system according to claim 6, which is characterized in that multiple occupied arithmetic cores of thread are different.
8. system according to claim 7, which is characterized in that amplification accounting to accounting is greater than 1.
9. system according to claim 8, which is characterized in that the mobile terminal is equipped with project supervision APP, the work Journey management APP includes: design APP, and project BIM model is stored into the background data base for design side;APP is contracted, for building If square by the three-dimensional model transmitting constructed by arrangement and method for construction to the Cloud Server;Management APP, by threedimensional model and project BIM The comparing result of model is presented to management side.
10. system according to claim 9, which is characterized in that the background data base also stores construction progress information, The Cloud Server further include: construction progress reminding module, according to the construction progress information in the background data base to described Mobile terminal reminds the complex node of engineering or a plurality of crosspoint of pipe network.
CN201910518658.4A 2019-06-15 2019-06-15 Project supervision monitoring and managing method and system based on BIM Withdrawn CN110245918A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910518658.4A CN110245918A (en) 2019-06-15 2019-06-15 Project supervision monitoring and managing method and system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910518658.4A CN110245918A (en) 2019-06-15 2019-06-15 Project supervision monitoring and managing method and system based on BIM

Publications (1)

Publication Number Publication Date
CN110245918A true CN110245918A (en) 2019-09-17

Family

ID=67887424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910518658.4A Withdrawn CN110245918A (en) 2019-06-15 2019-06-15 Project supervision monitoring and managing method and system based on BIM

Country Status (1)

Country Link
CN (1) CN110245918A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111062084A (en) * 2019-12-30 2020-04-24 广东海外建设咨询有限公司 Municipal bridge engineering construction supervision system
CN111709081A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Construction cost control system based on BIM technology
CN111833016A (en) * 2020-07-08 2020-10-27 惠州市筑成工程管理有限公司 Infrastructure building supervision method based on BIM
CN112101893A (en) * 2020-08-11 2020-12-18 江苏纬信工程咨询有限公司 Digital process and method for supervision and civil engineering experiment detection
CN112100722A (en) * 2020-09-11 2020-12-18 浙江勤业建工集团有限公司 Same-model multi-person cooperative operation method for BIM (building information modeling) pipe comprehensive design
CN112613850A (en) * 2020-12-30 2021-04-06 广东建瀚工程管理有限公司 Project supervision method based on BIM system
CN112734370A (en) * 2020-12-31 2021-04-30 鲁焱工程技术咨询有限公司 BIM-based project supervision information management method and system
CN112990844A (en) * 2020-12-26 2021-06-18 上海建科工程咨询有限公司 Construction method and management system based on BIM
CN114136293A (en) * 2021-11-05 2022-03-04 中铁十九局集团有限公司 BIM-based visual monitoring and early warning method and device

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111062084A (en) * 2019-12-30 2020-04-24 广东海外建设咨询有限公司 Municipal bridge engineering construction supervision system
CN111709081A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Construction cost control system based on BIM technology
CN111833016A (en) * 2020-07-08 2020-10-27 惠州市筑成工程管理有限公司 Infrastructure building supervision method based on BIM
CN112101893A (en) * 2020-08-11 2020-12-18 江苏纬信工程咨询有限公司 Digital process and method for supervision and civil engineering experiment detection
CN112100722A (en) * 2020-09-11 2020-12-18 浙江勤业建工集团有限公司 Same-model multi-person cooperative operation method for BIM (building information modeling) pipe comprehensive design
WO2022052250A1 (en) * 2020-09-11 2022-03-17 浙江勤业建工集团有限公司 Same-model multi-person cooperative operation method for bim pipe integration deepening design
CN112100722B (en) * 2020-09-11 2023-08-25 浙江勤业建工集团有限公司 Same-model multi-person collaborative operation method for BIM (building information modeling) pipe comprehensive deep design
CN112990844A (en) * 2020-12-26 2021-06-18 上海建科工程咨询有限公司 Construction method and management system based on BIM
CN112613850A (en) * 2020-12-30 2021-04-06 广东建瀚工程管理有限公司 Project supervision method based on BIM system
CN112734370A (en) * 2020-12-31 2021-04-30 鲁焱工程技术咨询有限公司 BIM-based project supervision information management method and system
CN114136293A (en) * 2021-11-05 2022-03-04 中铁十九局集团有限公司 BIM-based visual monitoring and early warning method and device
CN114136293B (en) * 2021-11-05 2024-04-02 中铁十九局集团有限公司 BIM-based visual monitoring and early warning method and device

Similar Documents

Publication Publication Date Title
CN110245918A (en) Project supervision monitoring and managing method and system based on BIM
CN109345195A (en) A kind of project supervision monitoring and managing method and system based on BIM
WO2018019176A1 (en) Xbrl-based intelligent financial cloud platform system, construction method, and service implementation method
CN112395325A (en) Data management method, system, terminal equipment and storage medium
CN109213754A (en) A kind of data processing system and data processing method
CN104636868A (en) Application management system for nuclear power station equipment maintenance information and application method thereof
CN102254234A (en) Realization method of business process and workflow engine
CN102750350B (en) Monitoring system and method
CN103050931A (en) Power system hierarchical data matching and relay protection setting merging method
CN102983999B (en) Method for parameter configuration, the system of a kind of monitor supervision platform system and device cluster
CN109523424A (en) A kind of assembled architecture Information Management System and method based on BIM
CN103020360A (en) Integration design method of intelligent substation based on three-dimensional design platform and professional software
CN111934274A (en) Intelligent substation protection constant value intelligent downloading method
CN110148066A (en) A kind of intellectual water meter management system and method
CN112348345A (en) Intelligent automatic order dispatching method and system
CN110032154B (en) Production control method and system for small-batch products
CN104102195A (en) Communication delay-existing discrete event system distributed supervision and control method
CN104793570A (en) Portable motor train unit fault processing support equipment and portable motor train unit fault processing support system
CN102201082A (en) Device and method for realizing correspondence between type of business object and subject
CN108876577A (en) The system that multilingual mobile visualization collects processing information
CN104504491A (en) Meter reading control method and system
CN103106555B (en) Maintaining-managing system based on the integration of online off-line and method
CN116012031A (en) Intelligent inspection digital platform and system for electric power marketing
CN116149849A (en) Edge computing method for intelligent water affair complex time scale data fusion
CN114943109A (en) Engineering project digital delivery method and system based on BIM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20190917

WW01 Invention patent application withdrawn after publication