CN110230253A - A kind of bridge floor built-in fitting basis and its manufacturing method - Google Patents

A kind of bridge floor built-in fitting basis and its manufacturing method Download PDF

Info

Publication number
CN110230253A
CN110230253A CN201910301557.1A CN201910301557A CN110230253A CN 110230253 A CN110230253 A CN 110230253A CN 201910301557 A CN201910301557 A CN 201910301557A CN 110230253 A CN110230253 A CN 110230253A
Authority
CN
China
Prior art keywords
ring flange
buried ring
buried
flange
bridge floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910301557.1A
Other languages
Chinese (zh)
Inventor
上官甦
刘闯
吴敬武
孙平宽
曾怡然
王成斌
潘德雄
吕晓宇
李邦武
符策源
阳振中
李远明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd
Original Assignee
CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd filed Critical CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd
Priority to CN201910301557.1A priority Critical patent/CN110230253A/en
Publication of CN110230253A publication Critical patent/CN110230253A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2253Mounting poles or posts to the holder
    • E04H12/2261Mounting poles or posts to the holder on a flat base

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Present disclose provides a kind of bridge floor built-in fitting bases, comprising: the pre-buried ring flange in lower part, inner edges are embedded in box beam flange end top surface;The pre-buried ring flange in top is fixed with the relative position of the pre-buried ring flange in the lower part;At least one foundation bolt passes through the pre-buried ring flange in the top and the pre-buried ring flange in lower part, and extends to the pre-buried ring flange top in top, wherein safeguard structure is arranged in the exposed part in the pre-buried ring flange top in top in the foundation bolt.For the disclosure by having carried out anti-corrosion protection using the lower safeguard structure of intensity to built-in fitting exposed portion, it is convenient to remove, and on the basis of facilitating subsequent High-Pole Lamp to install, ensure that installation quality.

Description

A kind of bridge floor built-in fitting basis and its manufacturing method
Technical field
This disclosure relates to bridge technology field more particularly to a kind of bridge floor built-in fitting basis and its manufacturing method.
Background technique
During carrying out bridge construction, bridge floor is generally reserved with the built-in fitting for installing guard rail lamp.The guard rail lamp High-Pole Lamp is generallyd use, High-Pole Lamp refers generally to the lighting device that 15 meters of combination of the above formula lamp brackets and steel tapered lamp post are constituted, it By internal lamps and lanterns, the foundations such as electrical, lamp bracket, lamp panel and the body of rod are formed.Lamp disc of high-pole lamp moulding can according to ambient enviroment, Depending on the concrete condition for illuminating needs;The internal more Projecting Lamp compositions of lamps and lanterns, high-pressure sodium lamp illuminate radius far up to 50 as lamp source Rice.Body of rod roll of steel plate system multi-purpose greatly forms, and is pyramid independent body structure, height is generally 15-40 meters.Due to the height of High-Pole Lamp Limitation, installation and maintenance are an important problems;And since certain bridge spanning the sea construction conditions are extremely complex, such as certain Bridge spanning the sea before spreading, project are located at macroseism, high wind, deep-etching area and cross over the previous Qinglan active fault of paving, earthquake intensity VIII Grade, design basic wind speed are domestic highest.Bridge spanning the sea concrete box beam section and steel box-girder section bridge deck are all made of 13 meters before spreading High high pole street lamp, since the bridge spanning the sea completion time of project is longer, High-Pole Lamp is usually just installed before completion, therefore bridge floor On for installing the built-in fitting of High-Pole Lamp face more serious etching problem, High-Pole Lamp installation quality is had some impact on.
Summary of the invention
(1) technical problems to be solved
It is set forth above at least partly to solve present disclose provides a kind of bridge floor built-in fitting basis and its manufacturing method Technical problem.
(2) technical solution
According to one aspect of the disclosure, a kind of bridge floor built-in fitting basis is provided, comprising:
The pre-buried ring flange in lower part, inner edges are embedded in box beam flange end top surface;
The pre-buried ring flange in top is fixed with the relative position of the pre-buried ring flange in the lower part;
At least one foundation bolt passes through the pre-buried ring flange in the top and the pre-buried ring flange in lower part and connect with the two, And extend to the pre-buried ring flange lower part box beam flange end in the pre-buried ring flange top in top and lower part, wherein the foundation bolt exists Safeguard structure is arranged in the exposed part in the pre-buried ring flange top in top.
In some embodiments, the bridge floor built-in fitting basis, further includes:
Protective block is set to the top of the pre-buried ring flange in the top, and fits closely with the pre-buried ring flange in the top, The protective block is fully wrapped around by the exposed part of foundation bolt.
In some embodiments, the protective block uses M10 mortar.
In some embodiments, the bridge floor built-in fitting basis, further includes:
Plastic sleeve is set between the protective block and foundation bolt, for wrapping foundation bolt exposed parts It wraps up in, then protective block is set.
In some embodiments, it is condensed between the pre-buried ring flange of the pre-buried ring flange in top and lower part with concreting.
In some embodiments, inward flange is embedded in box beam flange end top surface 10mm when the pre-buried ring flange in lower part is pre-buried.
In some embodiments, the pre-buried ring flange in the top and the pre-buried ring flange in lower part are rectangular or round, describedly Foot bolt is 8, and the aperture with 8 foundation bolts is uniformly distributed in the pre-buried flange in the top need to be with the pre-buried flange in lower part Disk.
In some embodiments, the pre-buried ring flange in the top and the pre-buried ring flange in lower part use Q235C steel, describedly Foot bolt uses the high-strength structural carbon steel of 45#.
A kind of method of construction on bridge floor built-in fitting basis another aspect of the present disclosure provides, comprising:
S1, the top of guardrail base is set to using the pre-buried ring flange in lower part, and the pre-buried ring flange in top is placed in safeguard structure Lower section, and pass through the pre-buried ring flange in the top and the pre-buried ring flange in lower part using more foundation bolts;
S2 fixes the pre-buried ring flange in the top and the pre-buried ring flange in lower part and the relative position of more foundation bolts, More foundation bolts are welded;
S3, by bridge floor built-in fitting basis integral built-in after relative position is fixed, inward flange when lower flange disk is pre-buried The depth of insertion box beam flange end top surface is calculated according to the numerical values recited of deck transverse slope;
S4 pours concrete box girder and guardrail base, and exposes section with protective block package foundation bolt and prevented Shield.
In some embodiments, it is further comprised the steps of: after the step S4
S5 destroys the protective block when carrying out guard rail lamp installation, and guardrail lamp base is carried out reinforcing peace using high-strength nut Dress.
(3) beneficial effect
It can be seen from the above technical proposal that disclosure bridge floor built-in fitting basis and its manufacturing method at least have and following have One of beneficial effect:
(1) anti-corrosion protection has been carried out using M10 mortar to concrete box beam section access bridge built-in fitting exposed portion, due to M10 Mortar bulk strength is not high, and it is convenient to remove, and on the basis of facilitating subsequent High-Pole Lamp to install, ensure that installation quality;
(2) since built-in fitting topmost is prefabricated ring flange, facilitate the disassembly of the subsequent High-Pole Lamp for damage more It changes.
Detailed description of the invention
Fig. 1 is the structural schematic diagram on embodiment of the present disclosure bridge floor built-in fitting basis.
Fig. 2 is the structural schematic diagram on bridge floor built-in fitting basis of the embodiment of the present disclosure with protective block.
Fig. 3 is the flow chart of the method for construction on embodiment of the present disclosure face built-in fitting basis.
[embodiment of the present disclosure main element symbol description in attached drawing]
1, the pre-buried ring flange in lower part;2, the pre-buried ring flange in lower part
3, foundation bolt;4, concrete
5, protective block
Specific embodiment
For the purposes, technical schemes and advantages of the disclosure are more clearly understood, below in conjunction with specific embodiment, and reference The disclosure is further described in attached drawing.
Disclosure some embodiments will be done referring to appended attached drawing in rear and more comprehensively describe to property, some of but not complete The embodiment in portion will be shown.In fact, the various embodiments of the disclosure can be realized by many different forms, without that should be solved It is interpreted as being limited to embodiments set forth herein;Relatively, these embodiments are provided so that the disclosure meets applicable legal requirement.
In an exemplary embodiment of the disclosure, a kind of bridge floor built-in fitting basis is provided.Fig. 1 is disclosure implementation The structural schematic diagram on example bridge floor built-in fitting basis.As shown in Figure 1, disclosure bridge floor built-in fitting basis includes: the pre-buried flange in lower part Disk 1, the pre-buried ring flange 2 in top, foundation bolt 3 etc..
The bridge spanning the sea access bridge concrete box beam section before paving, in the mobile formwork assembling reinforcement stage, with 2 pre-buried ring flanges 8 foundation bolts are welded, the pre-buried ring flange be it is rectangular or round, using Q235C steel, foundation bolt is used The high-strength structural carbon steel of 45#.Condensation, this reality are poured with concrete 4 between the pre-buried ring flange 1 of the pre-buried ring flange 2 in top and lower part It applies concrete 4 described in example and uses C50 concrete, 8 foundation bolts 3 pass through the pre-buried ring flange 2 in top and lower part is pre-buried Ring flange 1, and extend to pre-buried 2 top of ring flange in top, pre-buried 1 lower part of ring flange in lower part.Preferably, with 8 lower margins The aperture of bolt 3 is uniformly distributed in the pre-buried ring flange 2 in the top and the pre-buried ring flange 1 in lower part.
Integral built-in after the pre-buried ring flange 2 in top is fixed with pre-buried 1 relative position of ring flange in lower part, the pre-buried method in lower part Inward flange should be embedded in box beam flange end top surface 10mm when blue disk 1 is pre-buried, so that guard rail lamp built-in fitting overall structure rigidity is enhanced, Guarantee that the rated wind velocity when high hurdle street lamp installation after the completion of pouring reaches that design is specified to be required simultaneously so that built-in fitting basis by Power is clear, structure is safe.
Fig. 2 is the structural schematic diagram on bridge floor built-in fitting basis of the embodiment of the present disclosure with protective block.Carrying out High-Pole Lamp road Lamp install when, High-Pole Lamp base jack is coupled with the foundation bolt on corresponding built-in fitting basis, and use high-strength nut into Row reinforces installation, dismounting when conveniently being replaced when built-in fitting basis is damaged.It is poured in concrete box girder and guardrail base After the completion of building, exerted bolt is wrapped up using plastic sleeve, then section is exposed to built-in fitting with protective block 5 and carries out anti-corrosion, institute The top that protective block 5 is set to the pre-buried ring flange 2 in the top is stated, and is fitted closely with the pre-buried ring flange 2 in the top.It is described Protective block 5 is fully wrapped around by foundation bolt 3, solves etching problem of the foundation bolt in longer construction duration.Meanwhile in order to Convenient for removing when High-Pole Lamp is installed to protective block 5, the protective block 5 uses the lower material of intensity, it is preferred that described Protective block 5 uses M10 mortar.
Fig. 3 is the flow chart of the method for construction on embodiment of the present disclosure face built-in fitting basis.As shown in figure 3, the present embodiment bridge The method of construction on face built-in fitting basis includes:
S1, the top of guardrail base is set to using the pre-buried ring flange in lower part, and the pre-buried ring flange in top is placed in safeguard structure Lower section, and pass through the pre-buried ring flange in the top and the pre-buried ring flange in lower part using more foundation bolts;
S2 fixes the pre-buried ring flange in the top and the pre-buried ring flange in lower part and the relative position of more foundation bolts, More foundation bolts are welded;
S3, by bridge floor built-in fitting basis integral built-in after relative position is fixed, according to the numerical values recited of deck transverse slope Calculate lower flange disk it is pre-buried when inward flange should be embedded in box beam flange end top surface 10mm;
S4 pours concrete box girder and guardrail base, and exposes section with protective block package foundation bolt and prevented Shield.
After completing the procedure, it can be convenient the installation of subsequent High-Pole Lamp, and guarantee installation quality.
Wherein, the fire blocks use M10 mortar protective block.
It is further comprised the steps of: after step S4 described in the method for construction on the built-in fitting basis
S5 destroys the protective block when carrying out guard rail lamp installation, and guardrail lamp base is carried out reinforcing peace using high-strength nut Dress.
In order to achieve the purpose that brief description, any technical characteristic for making same application is described all in above-described embodiment 1 And in this, without repeating identical narration.
So far, attached drawing is had been combined the embodiment of the present disclosure is described in detail.It should be noted that in attached drawing or saying In bright book text, the implementation for not being painted or describing is form known to a person of ordinary skill in the art in technical field, and It is not described in detail.In addition, the above-mentioned definition to each element and method be not limited in mentioning in embodiment it is various specific Structure, shape or mode, those of ordinary skill in the art simply can be changed or be replaced to it.
It should also be noted that, the direction term mentioned in embodiment, for example, "upper", "lower", "front", "rear", " left side ", " right side " etc. is only the direction with reference to attached drawing, not is used to limit the protection scope of the disclosure.Through attached drawing, identical element by Same or similar appended drawing reference indicates.When may cause understanding of this disclosure and cause to obscure, conventional structure will be omitted Or construction.
And the shape and size of each component do not reflect actual size and ratio in figure, and only illustrate the embodiment of the present disclosure Content.In addition, in the claims, any reference symbol between parentheses should not be configured to the limit to claim System.
It unless there are known entitled phase otherwise anticipates, the numerical parameter in this specification and appended claims is approximation, energy Enough bases pass through the resulting required characteristic changing of content of this disclosure.Specifically, all be used in specification and claim The middle content for indicating composition, the number of reaction condition etc., it is thus understood that repaired by the term of " about " in all situations Decorations.Under normal circumstances, the meaning expressed refers to include by specific quantity ± 10% variation in some embodiments, some ± 5% variation in embodiment, ± 1% variation in some embodiments, in some embodiments ± 0.5% variation.
Furthermore word "comprising" does not exclude the presence of element or step not listed in the claims.It is located in front of the element Word "a" or "an" does not exclude the presence of multiple such elements.
In addition, unless specifically described or the step of must sequentially occur, there is no restriction in the above institute for the sequence of above-mentioned steps Column, and can change or rearrange according to required design.And above-described embodiment can be based on the considerations of design and reliability, that This mix and match is used using or with other embodiments mix and match, i.e., the technical characteristic in different embodiments can be freely combined Form more embodiments.
Those skilled in the art will understand that can be carried out adaptively to the module in the equipment in embodiment Change and they are arranged in one or more devices different from this embodiment.It can be the module or list in embodiment Member or component are combined into a module or unit or component, and furthermore they can be divided into multiple submodule or subelement or Sub-component.Other than such feature and/or at least some of process or unit exclude each other, it can use any Combination is to all features disclosed in this specification (including adjoint claim, abstract and attached drawing) and so disclosed All process or units of what method or apparatus are combined.Unless expressly stated otherwise, this specification is (including adjoint power Benefit require, abstract and attached drawing) disclosed in each feature can carry out generation with an alternative feature that provides the same, equivalent, or similar purpose It replaces.Also, in the unit claims listing several devices, several in these devices can be by same hard Part item embodies.
Similarly, it should be understood that in order to simplify the disclosure and help to understand one or more of each open aspect, Above in the description of the exemplary embodiment of the disclosure, each feature of the disclosure is grouped together into single implementation sometimes In example, figure or descriptions thereof.However, the disclosed method should not be interpreted as reflecting the following intention: i.e. required to protect The disclosure of shield requires features more more than feature expressly recited in each claim.More precisely, as following Claims reflect as, open aspect is all features less than single embodiment disclosed above.Therefore, Thus the claims for following specific embodiment are expressly incorporated in the specific embodiment, wherein each claim itself All as the separate embodiments of the disclosure.
Particular embodiments described above has carried out further in detail the purpose of the disclosure, technical scheme and beneficial effects Describe in detail it is bright, it is all it should be understood that be not limited to the disclosure the foregoing is merely the specific embodiment of the disclosure Within the spirit and principle of the disclosure, any modification, equivalent substitution, improvement and etc. done should be included in the guarantor of the disclosure Within the scope of shield.

Claims (10)

1. a kind of bridge floor built-in fitting basis, comprising:
The pre-buried ring flange in lower part, inner edges are embedded in box beam flange end top surface;
The pre-buried ring flange in top is fixed with the relative position of the pre-buried ring flange in the lower part;
At least one foundation bolt passes through the pre-buried ring flange in the top and the pre-buried ring flange in lower part and connect with the two, and to The pre-buried ring flange top in top extends, wherein the foundation bolt part setting exposed on the pre-buried ring flange top in top is anti- Protection structure.
2. bridge floor built-in fitting basis according to claim 1, further includes:
Protective block is set to the top of the pre-buried ring flange in the top, and fits closely with the pre-buried ring flange in the top, described Protective block is fully wrapped around by the exposed part of foundation bolt.
3. bridge floor built-in fitting basis according to claim 2, wherein the protective block uses M10 mortar.
4. bridge floor built-in fitting basis according to claim 2, further includes:
Plastic sleeve is set between the protective block and foundation bolt, for foundation bolt exposed parts to be wrapped up, then Protective block is set.
5. bridge floor built-in fitting according to claim 2 basis, wherein the pre-buried ring flange in top and the pre-buried ring flange in lower part it Between condensed with concreting.
6. bridge floor built-in fitting basis according to claim 2, inward flange is embedded in the box beam wing when the pre-buried ring flange in lower part is pre-buried Acies top surface 10mm.
7. bridge floor built-in fitting basis according to claim 2, wherein the pre-buried ring flange in top and the pre-buried flange in lower part Disk be it is rectangular or round, the foundation bolt be 8, it is pre- that the aperture with 8 foundation bolts is uniformly distributed in the top Bury ring flange and the pre-buried ring flange in lower part.
8. bridge floor built-in fitting basis according to claim 2, wherein the pre-buried ring flange in top and the pre-buried flange in lower part Disk uses Q235C steel, and the foundation bolt uses the high-strength structural carbon steel of 45#.
9. a kind of method of construction on bridge floor built-in fitting basis, comprising:
S1, the top of guardrail base is set to using the pre-buried ring flange in lower part, and the pre-buried ring flange in top is placed under safeguard structure Side, and the pre-buried ring flange in the top and the pre-buried ring flange in lower part are passed through using more foundation bolts;
S2 fixes the pre-buried ring flange in the top and the pre-buried ring flange in lower part and the relative position of more foundation bolts, to more Root foundation bolt is welded;
S3, by bridge floor built-in fitting basis integral built-in after relative position is fixed, inward flange is embedded in when lower flange disk is pre-buried The depth of box beam flange end top surface is calculated according to the numerical values recited of deck transverse slope;
S4 pours concrete box girder and guardrail base, and exposes section with protective block package foundation bolt and protected.
10. method of construction according to claim 9, wherein further comprised the steps of: after the step S4
S5 destroys the protective block when carrying out guard rail lamp installation, and guardrail lamp base is carried out reinforcing installation using high-strength nut.
CN201910301557.1A 2019-04-15 2019-04-15 A kind of bridge floor built-in fitting basis and its manufacturing method Pending CN110230253A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910301557.1A CN110230253A (en) 2019-04-15 2019-04-15 A kind of bridge floor built-in fitting basis and its manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910301557.1A CN110230253A (en) 2019-04-15 2019-04-15 A kind of bridge floor built-in fitting basis and its manufacturing method

Publications (1)

Publication Number Publication Date
CN110230253A true CN110230253A (en) 2019-09-13

Family

ID=67860919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910301557.1A Pending CN110230253A (en) 2019-04-15 2019-04-15 A kind of bridge floor built-in fitting basis and its manufacturing method

Country Status (1)

Country Link
CN (1) CN110230253A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528407A (en) * 2019-09-27 2019-12-03 招商局重庆交通科研设计院有限公司 The device and method of kerb under a kind of anticollision barrier for reinforcement bridge
CN114164756A (en) * 2021-12-22 2022-03-11 武汉理工大学 Light high-strength assembly type bridge anti-collision guardrail

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29914077U1 (en) * 1999-08-17 2001-01-18 BETOMAX Kunststoff- und Metallwarenfabrik GmbH & Co KG, 41460 Neuss Railing anchors for subsequent provision with railing posts
CN202208884U (en) * 2011-06-03 2012-05-02 北京中路安交通科技有限公司 Lightweight rollover prevention guardrail of bridge
CN203891052U (en) * 2013-12-15 2014-10-22 河南省电力勘测设计院 Novel electric transmission line pole and tower anchor bolt protective cover
CN105040576A (en) * 2015-08-20 2015-11-11 苏州同尚工程设计咨询有限公司 Anti-capsizing street lamp base used for bridge
CN205678615U (en) * 2016-06-02 2016-11-09 上海华城工程建设管理有限公司 The pre-buried pedestal of viaduct bridge guardrail lamp stand
CN106702907A (en) * 2016-12-19 2017-05-24 中交路桥建设有限公司 Bridge guardrail base adjustable flange plate construction method
CN207062766U (en) * 2017-08-23 2018-03-02 吉林铁道勘察设计院有限公司 A kind of combination protection system on the outside of across railway structure pavement
CN207862764U (en) * 2018-01-15 2018-09-14 湖南省交通规划勘察设计院有限公司 A kind of steel anticollision barrier connecting structure being easy to construction suitable for STC bridge decks
CN109469392A (en) * 2018-09-17 2019-03-15 深圳市建艺装饰集团股份有限公司 Intelligent light current upright bar and construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29914077U1 (en) * 1999-08-17 2001-01-18 BETOMAX Kunststoff- und Metallwarenfabrik GmbH & Co KG, 41460 Neuss Railing anchors for subsequent provision with railing posts
CN202208884U (en) * 2011-06-03 2012-05-02 北京中路安交通科技有限公司 Lightweight rollover prevention guardrail of bridge
CN203891052U (en) * 2013-12-15 2014-10-22 河南省电力勘测设计院 Novel electric transmission line pole and tower anchor bolt protective cover
CN105040576A (en) * 2015-08-20 2015-11-11 苏州同尚工程设计咨询有限公司 Anti-capsizing street lamp base used for bridge
CN205678615U (en) * 2016-06-02 2016-11-09 上海华城工程建设管理有限公司 The pre-buried pedestal of viaduct bridge guardrail lamp stand
CN106702907A (en) * 2016-12-19 2017-05-24 中交路桥建设有限公司 Bridge guardrail base adjustable flange plate construction method
CN207062766U (en) * 2017-08-23 2018-03-02 吉林铁道勘察设计院有限公司 A kind of combination protection system on the outside of across railway structure pavement
CN207862764U (en) * 2018-01-15 2018-09-14 湖南省交通规划勘察设计院有限公司 A kind of steel anticollision barrier connecting structure being easy to construction suitable for STC bridge decks
CN109469392A (en) * 2018-09-17 2019-03-15 深圳市建艺装饰集团股份有限公司 Intelligent light current upright bar and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528407A (en) * 2019-09-27 2019-12-03 招商局重庆交通科研设计院有限公司 The device and method of kerb under a kind of anticollision barrier for reinforcement bridge
CN114164756A (en) * 2021-12-22 2022-03-11 武汉理工大学 Light high-strength assembly type bridge anti-collision guardrail

Similar Documents

Publication Publication Date Title
CN109972517B (en) Construction method of main beam of cable-stayed bridge with steel-concrete composite beam
Frosch et al. Retrofit of non-ductile moment-resisting frames using precast infill wall panels
CN110230253A (en) A kind of bridge floor built-in fitting basis and its manufacturing method
KR100837608B1 (en) J.K Bracket Method
Morgenthal et al. Engineering the tower and main span construction of stonecutters bridge
CN101135138A (en) Continuous rigid frame bridge vertical rotation construction method
CN103046476A (en) Railway long-span rotator T-shaped bridge construction method
CN208685437U (en) A kind of wet seam construction of prefabricated assembled concrete floorings
KR20120133867A (en) Segmental concrete-filled-steel tube column construction method
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
JP3916083B2 (en) Simple foundation and aggregate of simple foundations
CN202174638U (en) Steel strand paying off device for prestress of railway box-girder
JP2014517170A (en) Frame support
JP2008297886A (en) Steel balustrade and balustrade replacing method
CN209619853U (en) Box girder supporting system utilizing existing structural columns
JP2004183433A (en) Box girder bridge structure and its construction method
JP2005350904A (en) Cofferdam structure and cofferdam construction method
JP2011174372A (en) Steel balustrade
CN104652292B (en) The bridge deck structure strengthening reconstruction method of prestressed concrete trussed combination arch bridge
CN211872617U (en) Permanent isolation guardrail for urban bridge
Colford et al. Forth Road Bridge main cables: replacement/augmentation study
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
JP2005090108A (en) Erection method of bridge
CN106400715A (en) Multifunctional barrier for municipal engineering
CN112095780A (en) Upper cover structure system applied to track operation line and implementation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190913

RJ01 Rejection of invention patent application after publication