CN110219256B - Construction method for complex support of channel passing through box culvert - Google Patents

Construction method for complex support of channel passing through box culvert Download PDF

Info

Publication number
CN110219256B
CN110219256B CN201910520262.3A CN201910520262A CN110219256B CN 110219256 B CN110219256 B CN 110219256B CN 201910520262 A CN201910520262 A CN 201910520262A CN 110219256 B CN110219256 B CN 110219256B
Authority
CN
China
Prior art keywords
channel
manual hole
box culvert
place pile
digging cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910520262.3A
Other languages
Chinese (zh)
Other versions
CN110219256A (en
Inventor
王丽梅
户潇博
王保华
张振禹
郭建东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Civil Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201910520262.3A priority Critical patent/CN110219256B/en
Publication of CN110219256A publication Critical patent/CN110219256A/en
Application granted granted Critical
Publication of CN110219256B publication Critical patent/CN110219256B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Abstract

The invention discloses a construction method for a complex channel support penetrating through a box culvert, which comprises the following steps of excavating the upper part, the left outer side wall and the right outer side wall of the box culvert, and covering soil to the bottom wall of the box culvert to form a foundation pit; the right side wall and the left side wall of the box culvert are respectively and sequentially provided with three right side manual hole digging cast-in-place piles and a left side manual hole digging cast-in-place pile; grouting in soil between the right and left manual hole digging cast-in-place piles; continuously penetrating and excavating from the right side of the bottom wall of the foundation pit to the left side of the bottom wall of the foundation pit downwards, and erecting a scaffold while excavating in the excavation process; sequentially erecting three steel pipe supporting columns in the middle of the bottom wall of the box culvert; and building sidewalk channel side walls on two sides of the construction channel respectively, pouring a sidewalk channel top plate on the top of the sidewalk channel, and plugging holes at the sidewalk channel top plate corresponding to the steel pipe support columns. The method ensures the safety of the construction structure of the main body of the excavation and the channel thereof.

Description

Construction method for complex support of channel passing through box culvert
Technical Field
The invention relates to a support construction method, in particular to a complex support construction method for a channel passing through a box culvert.
Background
As urban land is becoming more and more tense, underpasses and underground structures are often provided to alleviate this problem. Under the complex environment, the channel is required to pass through the flood control box culvert, rubble and silt are arranged under the box culvert, a sand layer is arranged, and the danger is high.
The chinese patent with the application number of CN201710366196 discloses "a bicycle expressway box culvert structure", and this box culvert structure includes hollow box, be provided with the bicycle lane in the box, the wing wall is installed to the both sides of box, the headwall is installed in the entry and the exit at box both ends, the pitch waterproof layer has been laid to the box periphery wall, the bicycle lane with be provided with the escape canal between the box. The hollow box body is arranged in barriers such as mountains in a penetrating manner, the bicycle lane is arranged in the box body and is connected with an external bicycle high-speed lane, so that the mileage is shortened, and a rider can ride the bicycle conveniently; lay the pitch waterproof layer at the periphery wall of box, make the box have good water-proof effects, set up the escape canal between bicycle lane and box, guaranteed good drainage effect, at the entry and the exit installation headwall at the both sides installation wing wall of box and box both ends, play and keep off soil and flow backwards the effect. This patent is passageway box culvert structure, sets up bicycle lane in the box, and the passageway that passes through the box culvert with this application supports the construction and is the construction field of two kinds of differences.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a complex support construction method for a channel passing through a box culvert, which has the advantages of low construction safety cost, short construction period and reliable support structure quality.
A construction method for complex channel support crossing a box culvert comprises the following steps:
(1) according to a set channel position penetrating through the box culvert, excavating earth above the road underground box culvert at the channel position and earth at the left and right outer side walls of the box culvert to the bottom wall of the box culvert to form a foundation pit, wherein the width of the foundation pit is greater than the width of the channel penetrating through the box culvert;
(2) the bottom of a foundation pit at the right side wall of the box culvert is sequentially provided with a right first manual hole-digging cast-in-place pile, a right second manual hole-digging cast-in-place pile and a right third manual hole-digging cast-in-place pile at intervals from front to back along the width direction of a channel to be constructed, wherein the excavation and the pouring of the right first manual hole-digging cast-in-place pile and the right second manual hole-digging cast-in-place pile are firstly carried out, and the excavation and the pouring of the right third manual hole-digging cast-in-place pile are carried out after the concrete strength of the right first manual hole-digging cast-in-place pile and the right second manual hole-digging cast; finally, constructing crown beams on the pile tops of the first manual hole-digging cast-in-place pile on the right side, the second manual hole-digging cast-in-place pile on the right side and the third manual hole-digging cast-in-place pile on the right side;
one part of the top wall of the first right-side manual hole-digging cast-in-place pile, the second right-side manual hole-digging cast-in-place pile and the third right-side manual hole-digging cast-in-place pile is supported on the bottom wall of the box culvert, and the other part of the top wall is arranged on the outer side of the bottom wall of the box culvert;
(3) repeating the step (2) and according to the method in the step (2), respectively arranging a left first manual hole-digging cast-in-place pile, a left second manual hole-digging cast-in-place pile and a left third manual hole-digging cast-in-place pile at the bottom of the foundation pit at the left side wall of the box culvert at intervals from front to back along the width direction of the channel to be constructed;
(4) grouting in soil between the three right-side manual hole-digging cast-in-place piles and the three left-side manual hole-digging cast-in-place piles;
(5) continuously excavating from the right side of the bottom wall of the foundation pit downwards to the bottom elevation position of the bottom plate of the construction channel and continuously excavating to the left side of the bottom wall of the foundation pit along the length direction of the construction channel in a penetrating manner, and erecting a scaffold while excavating in the excavating process so that the scaffold is supported on the bottom wall of the box culvert exposed by excavation;
(6) carrying out net hanging and guniting on soil bodies in the length directions of the front side and the rear side of the excavated construction channel, and sequentially laying a construction channel bottom plate cushion layer and a channel bottom plate at the bottom of the construction channel;
(7) sequentially erecting a first steel pipe supporting column, a second steel pipe supporting column and a third steel pipe supporting column at intervals from front to back in the width direction of the construction channel in the middle of the bottom wall of the box culvert; the bottoms of the first steel pipe support column, the second steel pipe support column and the third steel pipe support column are all fixed on the bottom plate of the construction channel, and the tops of the first steel pipe support column, the second steel pipe support column and the third steel pipe support column are fixed on the bottom wall of the box culvert;
(8) building pedestrian channel side walls on the front side and the rear side of the construction channel respectively according to the set width of the pedestrian channel along the length direction of the construction channel, wherein an inlet and an outlet of the pedestrian channel are respectively communicated with the existing basements arranged on the left side and the right side of the box culvert, and a pedestrian channel top plate is poured at the top of the pedestrian channel between the front and rear pedestrian channel side walls, wherein a second manual hole digging cast-in-place pile on the right side and a second manual hole digging cast-in-place pile on the left side are positioned between the front and rear pedestrian channel side walls, the pedestrian channel top plate is of a convex structure, and the box culvert bottom wall is supported on a boss of the pedestrian channel top plate;
(9) after the concrete strength of the top plate of the pedestrian passageway reaches 100%, building retaining walls at left and right convex shoulders of the top plate of the pedestrian passageway;
(10) removing the first steel pipe support column and the third steel pipe support column, backfilling earthwork outside the left side wall and the right side wall of the box culvert, and removing the second steel pipe support column;
(11) welding double layers of reinforcing mesh sheets on the inner walls of the holes on the top plate of the pedestrian passageway corresponding to the steel pipe support columns, then plugging the holes with micro-expansion fine stone anti-permeability concrete, laying a waterproof layer, and then laying a waterproof additional layer on the outer wall of the waterproof layer;
(12) removing the second manual hole-digging cast-in-place pile on the right side and the second manual hole-digging cast-in-place pile on the left side;
(13) filling gaps between the top plates of the pedestrian passageways and the box culverts with micro-expansive concrete;
(14) and backfilling earthwork at the top of the box culvert.
In the method, when the channel is constructed, the construction is carried out step by adopting a mode of excavating the earth and replacing the support with other structures, so that the force transmission is reasonable, economic and safe. And (4) setting reinforcing points at key positions, and transmitting the upper load to the channel bottom plate layer by using the steel pipe supporting columns. Meanwhile, the main channel structure construction is considered, so that the supporting structures at all stages are different, the manual excavation of the supporting piles, the soil body grouting, the scaffold, the steel pipe supporting columns and the layer-by-layer progressive progression ensure the safety of the excavation and the main channel structure construction.
Drawings
FIG. 1 is a schematic view of a construction node in a top view of the construction method for a complex channel support crossing a box culvert, according to the present invention;
FIG. 2 is a schematic view of a vertical construction node of the complex channel supporting construction method for box culvert penetration
Detailed Description
The invention is described in detail below with reference to the figures and specific embodiments.
As shown in the attached drawings, the complex supporting construction method for the channel penetrating through the box culvert, disclosed by the invention, comprises the following steps of:
(1) according to a set channel position penetrating through the box culvert, excavating earth above a road underground box culvert 1 at the channel position and earth at the left and right outer side walls of the box culvert 1 to the bottom wall 2 of the box culvert to form a foundation pit, wherein the width of the foundation pit is greater than that of a construction channel penetrating through the box culvert;
(2) the bottom of a foundation pit at the right side wall of the box culvert is sequentially provided with a right first manual hole-digging cast-in-place pile 4-1, a right second manual hole-digging cast-in-place pile 4-2 and a right third manual hole-digging cast-in-place pile 4-3 along the width direction of a channel to be constructed at intervals in the front-back direction, wherein the excavation and the pouring of the right first manual hole-digging cast-in-place pile 4-1 and the right second manual hole-digging cast-in-place pile 4-2 are firstly carried out, and the excavation and the pouring of the right third manual hole-digging cast-in-place pile 4-3 are carried out after the concrete strength of the right first manual hole-digging cast-in-place pile and the right second manual hole-. And finally constructing crown beams on the pile tops of the first manual hole-digging cast-in-place pile 4-1 on the right side, the second manual hole-digging cast-in-place pile 4-2 on the right side and the third manual hole-digging cast-in-place pile 4-3 on the right side.
The first manual hole bored concrete pile, the manual hole bored concrete pile and the manual partial setting in 2 outsides of box culvert diapire of roof of digging hole bored concrete pile and right side third in the right side first manual hole bored concrete pile, the manual hole bored concrete pile and the manual hole bored concrete pile that dig in the right side are supported on the box culvert diapire and the roof another part sets up in the box culvert diapire, the manual hole bored concrete pile radially the box culvert outside enlarge 500mm usually can, it is more convenient to go out the soil during the manual hole digging, the steel reinforcement cage is transferred to the disposable of being convenient for, construction quality can be guaranteed.
(3) And (3) repeating the step (2) and according to the method in the step (2), respectively arranging a left first manual hole-digging cast-in-place pile 3-1, a left second manual hole-digging cast-in-place pile 3-2 and a left third manual hole-digging cast-in-place pile 3-3 at the bottom of the foundation pit at the left side wall of the box culvert at intervals from front to back along the width direction of the channel to be constructed.
Namely: the method comprises the steps of firstly excavating and pouring a first left-side first manual hole-excavating cast-in-place pile 3-1 and a second left-side second manual hole-excavating cast-in-place pile 3-2, and excavating and pouring a third left-side third manual hole-excavating cast-in-place pile 3-3 after the concrete strength of the first left-side first manual hole-excavating cast-in-place pile and the second left-side second manual hole-excavating cast-in-place pile reaches the design strength. And finally constructing crown beams on the pile tops of the first left-side manual hole-digging cast-in-place pile 3-1, the second left-side manual hole-digging cast-in-place pile 3-2 and the third left-side manual hole-digging cast-in-place pile 3-3.
The first manual hole bored concrete pile, the manual hole bored concrete pile of digging of left side second and the manual hole bored concrete pile of digging of left side third partly support on the box culvert diapire and the another part setting of roof is in the 2 outsides of box culvert diapire, the manual pile radial box culvert outside of digging the hole bored concrete pile expand 500mm usually can, it is more convenient to go out the soil during manual hole digging, is convenient for once only transfer the steel reinforcement cage, can guarantee construction quality by the at utmost.
(4) And grouting in soil bodies between the three right-side manual hole-digging cast-in-place piles and the three left-side manual hole-digging cast-in-place piles.
(5) Continuously excavating from the right side of the bottom wall of the foundation pit downwards to the bottom elevation position of a bottom plate 6 of the construction channel 5 and continuously excavating to the left side of the bottom wall of the foundation pit in a penetrating manner along the length direction of the construction channel, and erecting a scaffold while excavating in the excavation process so that the scaffold is supported on the bottom wall of the box culvert exposed by excavation;
(6) carrying out net hanging and guniting on soil bodies in the length directions of the front side and the rear side of the excavated construction channel 5, and sequentially laying a channel bottom plate cushion layer and a channel bottom plate 6 at the bottom of the construction channel 5;
(7) a first steel pipe supporting column 7-1, a second steel pipe supporting column 7-2 and a third steel pipe supporting column 7-3 are sequentially erected in the middle of the bottom wall of the box culvert 1 and at intervals in the front and back direction of the width direction of the construction channel 5. The bottoms of the first steel pipe support column, the second steel pipe support column and the third steel pipe support column are all fixed on a bottom plate 6 of the construction channel, and the tops of the first steel pipe support column, the second steel pipe support column and the third steel pipe support column are fixed on the bottom wall of the box culvert 1;
(8) building pedestrian passageway side walls 8 on the front side and the rear side of the construction passageway 5 along the length direction of the construction passageway according to the set width of the pedestrian passageway, wherein the inlet and the outlet of the pedestrian passageway are respectively communicated with the existing basements arranged on the left side and the right side of the box culvert, and a pedestrian passageway top plate 9 is poured at the top of the pedestrian passageway between the front and rear pedestrian passageway side walls 8, wherein a right second manual hole-digging cast-in-place pile 4-2 and a left second manual hole-digging cast-in-place pile 3-2 are positioned between the front and rear pedestrian passageway side walls 8, the pedestrian passageway top plate 9 is of a convex structure, and the box culvert bottom wall 2 is supported on a boss of the pedestrian passageway top plate 9;
(9) after the concrete strength of the top plate 9 of the pedestrian passageway reaches 100%, building retaining walls 10 at left and right convex shoulders of the top plate of the pedestrian passageway;
(10) dismantling the first steel pipe support column 7-1 and the third steel pipe support column 7-3, backfilling earthwork outside the left side wall 1-2 and the right side wall 1-2 of the box culvert, and dismantling the second steel pipe support column 7-2;
(11) welding double-layer reinforcing mesh sheets on the inner walls of the holes on the top plate of the pedestrian passageway corresponding to the steel pipe support columns, then plugging the holes with micro-expansion fine stone anti-permeability concrete, paving a waterproof layer, and then paving a waterproof additional layer on the outer wall of the waterproof layer.
(12) The second manual hole-digging cast-in-place pile 4-2 on the right side and the second manual hole-digging cast-in-place pile 3-2 on the left side are dismantled;
(13) filling gaps between the top plate 9 of the pedestrian passageway and the box culvert 1 with micro-expansion concrete;
(14) and backfilling earthwork at the top of the box culvert 1.

Claims (1)

1. A construction method for complex channel support crossing a box culvert is characterized by comprising the following steps:
(1) according to a set channel position penetrating through the box culvert, excavating earth above the road underground box culvert at the channel position and earth at the left and right outer side walls of the box culvert to the bottom wall of the box culvert to form a foundation pit, wherein the width of the foundation pit is larger than the width of a construction channel penetrating through the box culvert;
(2) the bottom of a foundation pit at the right side wall of the box culvert is sequentially provided with a right first manual hole-digging cast-in-place pile, a right second manual hole-digging cast-in-place pile and a right third manual hole-digging cast-in-place pile at intervals from front to back along the width direction of a channel to be constructed, wherein the excavation and the pouring of the right first manual hole-digging cast-in-place pile and the right second manual hole-digging cast-in-place pile are firstly carried out, and the excavation and the pouring of the right third manual hole-digging cast-in-place pile are carried out after the concrete strength of the right first manual hole-digging cast-in-place pile and the right second manual hole-digging cast; finally, constructing crown beams on the pile tops of the first manual hole-digging cast-in-place pile on the right side, the second manual hole-digging cast-in-place pile on the right side and the third manual hole-digging cast-in-place pile on the right side;
one part of the top wall of the first right-side manual hole-digging cast-in-place pile, the second right-side manual hole-digging cast-in-place pile and the third right-side manual hole-digging cast-in-place pile is supported on the bottom wall of the box culvert, and the other part of the top wall is arranged on the outer side of the bottom wall of the box culvert;
(3) according to the method in the step (2), respectively arranging a left first manual hole-digging cast-in-place pile, a left second manual hole-digging cast-in-place pile and a left third manual hole-digging cast-in-place pile at the bottom of the foundation pit at the left side wall of the box culvert at intervals from front to back along the width direction of the channel to be constructed; finally, constructing crown beams on the pile tops of the first manual hole-digging cast-in-place pile on the left side, the second manual hole-digging cast-in-place pile on the left side and the third manual hole-digging cast-in-place pile on the left side;
(4) grouting in soil between the three right-side manual hole-digging cast-in-place piles and the three left-side manual hole-digging cast-in-place piles;
(5) continuously excavating from the right side of the bottom wall of the foundation pit downwards to the bottom elevation position of the bottom plate of the construction channel and continuously excavating to the left side of the bottom wall of the foundation pit along the length direction of the construction channel in a penetrating manner, and erecting a scaffold while excavating in the excavating process so that the scaffold is supported on the bottom wall of the box culvert exposed by excavation;
(6) carrying out net hanging and guniting on soil bodies in the length directions of the front side and the rear side of the excavated construction channel, and sequentially laying a construction channel bottom plate cushion layer and a channel bottom plate at the bottom of the construction channel;
(7) sequentially erecting a first steel pipe supporting column, a second steel pipe supporting column and a third steel pipe supporting column at intervals from front to back in the width direction of the construction channel in the middle of the bottom wall of the box culvert; the bottoms of the first steel pipe support column, the second steel pipe support column and the third steel pipe support column are all fixed on the bottom plate of the construction channel, and the tops of the first steel pipe support column, the second steel pipe support column and the third steel pipe support column are fixed on the bottom wall of the box culvert;
(8) building pedestrian channel side walls on the front side and the rear side of the construction channel respectively according to the set width of the pedestrian channel along the length direction of the construction channel, wherein an inlet and an outlet of the pedestrian channel are respectively communicated with the existing basements arranged on the left side and the right side of the box culvert, and a pedestrian channel top plate is poured at the top of the pedestrian channel between the front and rear pedestrian channel side walls, wherein a second manual hole digging cast-in-place pile on the right side and a second manual hole digging cast-in-place pile on the left side are positioned between the front and rear pedestrian channel side walls, the pedestrian channel top plate is of a convex structure, and the box culvert bottom wall is supported on a boss of the pedestrian channel top plate;
(9) after the concrete strength of the top plate of the pedestrian passageway reaches 100%, building retaining walls at left and right convex shoulders of the top plate of the pedestrian passageway;
(10) removing the first steel pipe support column and the third steel pipe support column, backfilling earthwork outside the left side wall and the right side wall of the box culvert, and removing the second steel pipe support column;
(11) welding double layers of reinforcing mesh sheets on the inner walls of the holes on the top plate of the pedestrian passageway corresponding to the steel pipe support columns, then plugging the holes with micro-expansion fine stone anti-permeability concrete, laying a waterproof layer, and then laying a waterproof additional layer on the outer wall of the waterproof layer;
(12) removing the second manual hole-digging cast-in-place pile on the right side and the second manual hole-digging cast-in-place pile on the left side;
(13) filling gaps between the top plates of the pedestrian passageways and the box culverts with micro-expansive concrete;
(14) and backfilling earthwork at the top of the box culvert.
CN201910520262.3A 2019-06-17 2019-06-17 Construction method for complex support of channel passing through box culvert Active CN110219256B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910520262.3A CN110219256B (en) 2019-06-17 2019-06-17 Construction method for complex support of channel passing through box culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910520262.3A CN110219256B (en) 2019-06-17 2019-06-17 Construction method for complex support of channel passing through box culvert

Publications (2)

Publication Number Publication Date
CN110219256A CN110219256A (en) 2019-09-10
CN110219256B true CN110219256B (en) 2021-02-19

Family

ID=67817327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910520262.3A Active CN110219256B (en) 2019-06-17 2019-06-17 Construction method for complex support of channel passing through box culvert

Country Status (1)

Country Link
CN (1) CN110219256B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851328B (en) * 2020-07-06 2021-08-27 海门市帕源路桥建设有限公司 Modular, standardized prefabricating and assembling construction process for box culvert concrete structural steel bars
CN113026811B (en) * 2021-03-17 2022-05-27 中电建生态环境集团有限公司 Channel support construction method for crossing box culvert

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725357B (en) * 2008-10-23 2011-11-02 上海天演建筑物移位工程有限公司 Construction method for lower section of underground tunnel
CN106351134B (en) * 2016-11-02 2018-06-15 湖南联智桥隧技术有限公司 Existing line box culvert is worn under one kind and synchronizes jacking system and jacking method
CN106640121B (en) * 2017-01-11 2023-06-27 中铁第六勘察设计院集团有限公司 Supporting structure for six-pilot tunnel large-section subway station to pass through existing line
CN106761779B (en) * 2017-01-24 2019-02-15 中铁二十局集团第六工程有限公司 A kind of shallow-depth-excavation tunnel passes through the construction method of box culvert
CN109235221A (en) * 2018-11-16 2019-01-18 上海市地下空间设计研究总院有限公司 A kind of subterranean tunnel through bridge structure

Also Published As

Publication number Publication date
CN110219256A (en) 2019-09-10

Similar Documents

Publication Publication Date Title
CN108868778B (en) Non-excavation construction method for large underground structure
CN110439571B (en) Transverse channel construction method for leading flat pilot tunnel to main tunnel and transverse channel
CN108612128B (en) Open-cut single-layer double or multi-hole tunnel framing reverse support-changing construction method
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN103174074B (en) Sedimentation control structure of passable road highway roadbed and construction method
CN111594232A (en) Large-scale filling type karst cave geological tunnel foundation reinforcing structure and construction method thereof
CN107386317A (en) Foam concrete lightweight barricade and construction method are excavated after a kind of first precompressed of deep ultra-soft soil
CN111778793B (en) Cavity collapse prevention and control structure and construction method
KR20160131410A (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
CN104727302A (en) Cast-in-place construction process for inter-pile board wall between slide-resistant piles
CN110219256B (en) Construction method for complex support of channel passing through box culvert
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN110778334A (en) Construction method of bias tunnel portal excavation protection structure
CN111945743A (en) Multi-layer unbalanced foundation pit supporting method suitable for staged excavation
WO2023213117A1 (en) Widening structure and construction method for existing subgrade embankment wall section near river
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN112681374A (en) Shallow-buried underground-excavated channel cover excavation top-down construction method under complex conditions
CN111188355B (en) Super-gravity type anchorage shallow-buried foundation and construction method
CN210507181U (en) Multi-support construction structure for complex environment
CN110117959B (en) Construction method for foundation pit support near river
CN105986830B (en) The tunneling method of construction of roadside strip underground garage
CN216765941U (en) Tunnel decompression load shedding structure under bias voltage state
CN115450221A (en) Construction method for subway crossing river channel
CN115653000A (en) Gravity pipe gallery in-situ protection structure system in foundation pit range and construction method
CN110792440B (en) Construction method of water-rich loess tunnel penetrating through loess towards valley

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20210415

Granted publication date: 20210219

PP01 Preservation of patent right
PD01 Discharge of preservation of patent

Date of cancellation: 20240109

Granted publication date: 20210219

PD01 Discharge of preservation of patent