CN110210789A - Resource distribution dispatching method, the device, equipment of power grid test business - Google Patents
Resource distribution dispatching method, the device, equipment of power grid test business Download PDFInfo
- Publication number
- CN110210789A CN110210789A CN201910522366.8A CN201910522366A CN110210789A CN 110210789 A CN110210789 A CN 110210789A CN 201910522366 A CN201910522366 A CN 201910522366A CN 110210789 A CN110210789 A CN 110210789A
- Authority
- CN
- China
- Prior art keywords
- business
- measured
- resource
- test
- power grid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012360 testing method Methods 0.000 title claims abstract description 203
- 238000009826 distribution Methods 0.000 title claims abstract description 41
- 238000000034 method Methods 0.000 title claims abstract description 41
- 238000012913 prioritisation Methods 0.000 claims abstract description 64
- 230000000694 effects Effects 0.000 claims abstract description 30
- 238000005457 optimization Methods 0.000 claims abstract description 18
- 238000004422 calculation algorithm Methods 0.000 claims abstract description 15
- 238000003860 storage Methods 0.000 claims abstract description 14
- 238000004590 computer program Methods 0.000 claims description 11
- 238000013468 resource allocation Methods 0.000 claims description 5
- 238000004364 calculation method Methods 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 3
- 230000008520 organization Effects 0.000 description 3
- 230000002159 abnormal effect Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000013439 planning Methods 0.000 description 2
- 230000003044 adaptive effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 238000010998 test method Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Health & Medical Sciences (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Public Health (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The invention discloses a kind of resource distribution dispatching methods of power grid test business, method includes the following steps: obtaining the idling-resource of power grid test macro;The corresponding test prioritization of each business to be measured is calculated, and by each delineation of activities to be measured into corresponding test prioritization queue;Using the sequence of colony intelligence optimization algorithm according to priority from high to low, idling-resource is distributed to each business to be measured in each test prioritization queue.Using technical solution provided by the embodiment of the present invention, testing efficiency is significantly improved, improves resource utilization, reduces test operating cost.The invention also discloses resource distribution dispatching device, equipment and the storage mediums of a kind of power grid test business, have relevant art effect.
Description
Technical field
The present invention relates to the configuration of power network resources intelligence and dispatching technique fields, more particularly to a kind of power grid test business
Resource distribution dispatching method, device, equipment and computer readable storage medium.
Background technique
Modern age scientific and technological progress promotes the automation and intelligence of production process again, proposes to the power quality of power grid higher
The requirement of update needs to test power grid.
In the prior art, power grid test organization carries out the demand money of artificial layout test plan and human configuration test business
Source generally requires repeatedly to confirm that can system idling-resource meet the test plan of institute's layout, while more systems being needed to provide
Source ensures that test business smoothly executes.If there are abnormal conditions in test process of service execution, tester can not the
One time adjusted test plan, and testing efficiency is low, and the resource utilization for testing the test macro of business department is low, tests business
It is at high cost.
In conclusion how to efficiently solve, existing power grid test method testing efficiency is low, and resource utilization is low, test
The problems such as operating cost is high is current those skilled in the art's urgent problem.
Summary of the invention
The object of the present invention is to provide a kind of resource distribution scheduling of power grid test business, this method significantly improves survey
Efficiency is tried, resource utilization is improved, reduces test operating cost;It is a further object of the present invention to provide a kind of tests of power grid
Resource distribution dispatching method, device, equipment and the computer readable storage medium of business.
In order to solve the above technical problems, the invention provides the following technical scheme:
A kind of resource distribution dispatching method of power grid test business, comprising:
Obtain the idling-resource of power grid test macro;
Calculate the corresponding test prioritization of each business to be measured, and by each delineation of activities to be measured to corresponding test
In priority query;
Using the sequence of colony intelligence optimization algorithm according to priority from high to low, the idling-resource is distributed into each survey
Try each business to be measured in priority query.
In a kind of specific embodiment of the invention, the idling-resource is being distributed into each test prioritization team
After each business to be measured in column, further includes:
When receiving business addition request to be measured, the step of the idling-resource for obtaining power grid test macro is repeated
Suddenly, to be redistributed to the idling-resource.
In a kind of specific embodiment of the invention, the corresponding test prioritization of each business to be measured is calculated, comprising:
To the corresponding resource requirement configuration information of each business to be measured, length of testing speech information and urgency level information
It is weighted, obtains the corresponding test prioritization of each business to be measured;
By each delineation of activities to be measured into corresponding test prioritization queue, comprising:
By service priority range belonging to each business to be measured, by each delineation of activities to be measured to corresponding test
In priority query.
In a kind of specific embodiment of the invention, further includes:
According to the busy degree of the total resources demand configuration information of current each business to be measured, phase is carried out to system resource
The investment and release adjustment answered.
A kind of resource distribution dispatching device of power grid test business, comprising:
Source obtaining module, for obtaining the idling-resource of power grid test macro;
Delineation of activities module, for calculating the corresponding test prioritization of each business to be measured, and by each industry to be measured
Business is divided into corresponding test prioritization queue;
Resource distribution module, for the sequence using colony intelligence optimization algorithm according to priority from high to low, by the free time
Resource allocation is to each business to be measured in each test prioritization queue.
In a kind of specific embodiment of the invention, the source obtaining module is also used to by the idling-resource
After distributing to each business to be measured in each test prioritization queue, when receiving business addition request to be measured,
The step of repeating the idling-resource for obtaining power grid test macro, to be redistributed to the idling-resource.
In a kind of specific embodiment of the invention, the delineation of activities module includes priority computational submodule and industry
Business divides submodule,
The priority computational submodule be specially to the corresponding resource requirement configuration information of each business to be measured,
Length of testing speech information and urgency level information are weighted, and obtain the corresponding test prioritization of each business to be measured
Module;
The delineation of activities submodule is specially to press service priority range belonging to each business to be measured, will be each described
Delineation of activities to be measured is to the module in corresponding test prioritization queue.
In a kind of specific embodiment of the invention, further includes:
System resource adjusts module, for the busy according to the currently total resources demand configuration information of each business to be measured
Degree is put into accordingly to system resource and is discharged adjustment.
A kind of resource distribution controlling equipment of power grid test business, comprising:
Memory, for storing computer program;
Processor realizes the resource distribution scheduling of power grid test business as previously described when for executing the computer program
The step of method.
A kind of computer readable storage medium is stored with computer program on the computer readable storage medium, described
The step of resource distribution dispatching method of power grid test business as previously described is realized when computer program is executed by processor.
Using method provided by the embodiment of the present invention, by the way that when executing power grid test business, the automatic power grid that obtains is surveyed
The idling-resource of test system, calculates the corresponding test prioritization of each business to be measured, and will each delineation of activities to be measured to correspondence
Test prioritization queue in, using the sequence of colony intelligence optimization algorithm according to priority from high to low, idling-resource is distributed to
Each business to be measured in each test prioritization queue.It is tested compared to existing by artificial layout test plan and human configuration
The mode of business demand resource, the application is by automatically calculating the idling-resource of power grid test macro using colony intelligence optimization
Idling-resource is distributed to each business to be measured in each test prioritization queue by the sequence of method according to priority from high to low, larger
Ground improves testing efficiency, improves resource utilization, reduces test operating cost.
Correspondingly, the embodiment of the invention also provides corresponding with the above-mentioned power grid test resource distribution dispatching method of business
Power grid test business resource distribution dispatching device, equipment and computer readable storage medium, have above-mentioned technique effect,
This is repeated no more.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is a kind of implementation flow chart for the resource distribution dispatching method that power grid tests business in the embodiment of the present invention;
Fig. 2 is another implementation flow chart for the resource distribution dispatching method that power grid tests business in the embodiment of the present invention;
Fig. 3 is a kind of structural block diagram of the resource distribution dispatching device of power grid test business in the embodiment of the present invention;
Fig. 4 is a kind of structural block diagram of the resource distribution controlling equipment of power grid test business in the embodiment of the present invention.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, with reference to the accompanying drawings and detailed description
The present invention is described in further detail.Obviously, described embodiments are only a part of the embodiments of the present invention, rather than
Whole embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creative work premise
Under every other embodiment obtained, shall fall within the protection scope of the present invention.
Embodiment one:
Referring to Fig. 1, Fig. 1 is a kind of implementation stream for the resource distribution dispatching method that power grid tests business in the embodiment of the present invention
Cheng Tu, this method may comprise steps of:
S101: the idling-resource of power grid test macro is obtained.
Director server can be established in advance with the power grid test macro in power grid test organization and is connected to the network, and can such as be passed through
GPRS or WIFI network connection such as can be start by set date test business, can obtain when needing to test business to be measured
The idling-resource of power grid test macro is taken, so as to know the current resource distribution situation of power grid test macro.
S102: calculating the corresponding test prioritization of each business to be measured, and by each delineation of activities to be measured to corresponding survey
It tries in priority query.
For existing business to be measured, the corresponding test prioritization of each business to be measured can be calculated, it such as can be according to
The urgency level of each business to be measured is each corresponding test prioritization of traffic assignments to be measured.And test prioritization can be preset
Queue, and each delineation of activities to be measured can such as be preset into the to be measured of which rank into corresponding test prioritization queue
Business corresponds to the test prioritization queue of which appropriate level, in order to it is subsequent according to the test arranging service table to the sky of system
Not busy resource is allocated and dispatches.
S103: using the sequence of colony intelligence optimization algorithm according to priority from high to low, idling-resource is distributed into each test
Each business to be measured in priority query.
The idling-resource of power grid test macro is being got, and it is preferential that the corresponding test of each business to be measured is calculated
Grade and by each business to be measured and after being divided into corresponding test prioritization queue, can use colony intelligence optimization algorithm with maximum
Changing cloud computing resources utilization rate is guiding, finds out the optimal solution of all service dynamic planning to be measured in each test prioritization queue,
And according to the principle of priority from high in the end, the sky of the business to be measured in the high test prioritization queue of preferential layout priority
The idling-resource distribution of business to be tested in not busy resource allocation, then the low test prioritization queue of layout priority, thus raw
At optimal test arranging service table, so as to carry out test operation to each business to be measured according to each test prioritization, realize
Automation layout to power grid business to be measured avoids and fights for test business caused by resource mutually between each business to be measured and execute
Have some setbacks problem, can real-time and accurately grasp the idling-resource of current service resources conditions of demand and power grid test macro to be measured
Situation.It does not need artificial cumbersome ground and repeatedly confirms whether system idling-resource can satisfy the test plan of institute's layout, do not need
For each business to be measured it is special it is vacant go out excessive resource ensure the smooth execution of each business to be measured, reduce unit business to be measured
Resource consumption, cloud computing intelligent resource distribution and scheduling system can effectively be combined with test business, fill power grid
The blank that layout test assignment is automated in Process of Information, improves resource utilization, significantly improves to business to be measured
Testing efficiency, reduce test operating cost.
Using method provided by the embodiment of the present invention, by the way that when executing power grid test business, the automatic power grid that obtains is surveyed
The idling-resource of test system, calculates the corresponding test prioritization of each business to be measured, and will each delineation of activities to be measured to correspondence
Test prioritization queue in, using the sequence of colony intelligence optimization algorithm according to priority from high to low, idling-resource is distributed to
Each business to be measured in each test prioritization queue.It is tested compared to existing by artificial layout test plan and human configuration
The mode of business demand resource, the application is by automatically calculating the idling-resource of power grid test macro using colony intelligence optimization
Idling-resource is distributed to each business to be measured in each test prioritization queue by the sequence of method according to priority from high to low, larger
Ground improves testing efficiency, improves resource utilization, reduces test operating cost.
It should be noted that based on the above embodiment one, the embodiment of the invention also provides be correspondingly improved scheme.Rear
Involved in continuous embodiment with can mutually be referred between same steps or corresponding steps in above-described embodiment one, corresponding beneficial effect
Can also be cross-referenced, it is no longer repeated one by one in improvement embodiment below.
Embodiment two:
Referring to fig. 2, Fig. 2 is that the another of the resource distribution dispatching method that power grid tests business in the embodiment of the present invention is implemented
Flow chart, this method may comprise steps of:
S201: the idling-resource of power grid test macro is obtained.
S202: the corresponding resource requirement configuration information of each business to be measured, length of testing speech information and urgency level are believed
Breath is weighted, and obtains the corresponding test prioritization of each business to be measured.
In view of the resource requirement configuration information of each business to be measured, length of testing speech information and urgency level information survey calculating
The importance of priority is tried, it can be to the corresponding resource requirement configuration information of each business to be measured, length of testing speech information and tight
Anxious degree information is weighted, and obtains the corresponding weight of each business to be measured, so as to according to weight size obtain respectively to
The corresponding test prioritization of survey business.For example, being essentially that the corresponding test of the relatively high business to be measured of urgency level is excellent
First grade is relatively high.
S203: by service priority range belonging to each business to be measured, each delineation of activities to be measured is excellent to corresponding test
In first grade queue.
Multiple service priority ranges can be preset, the corresponding test of each business to be measured is preferential being calculated
It, can be preferential to corresponding test by each delineation of activities to be measured by service priority range belonging to each business to be measured after grade
In grade queue.
S204: using the sequence of colony intelligence optimization algorithm according to priority from high to low, idling-resource is distributed into each test
Each business to be measured in priority query.
S205: judging whether to receive business addition request to be measured, if so, the step of repeating S201 to S204,
If it is not, thening follow the steps S206.
Director server can obtain in real time the test business executive condition of test macro, the operating status of test macro with
And whether receive business addition request to be measured.When determine receive business to be measured addition request when, then illustrate there is currently
The priority of each business to be measured is there may be variation, the step of needing to repeat S201 to S204, to update current electric grid
The idling-resource of test macro and the priority that each business to be measured after new business to be measured is added, to carry out weight to idling-resource
New distribution, realizes the automation layout to power grid business to be measured.Generally guarantee test macro normal operation, when receive to
After the addition request of survey business, director server can recalculate the priority of all business to be measured, and be divided into corresponding test
In priority query, priority level is first calculated to maximize cloud computing resources utilization rate as guiding using colony intelligence optimization algorithm
The resource allocation proposal of business to be measured in high test prioritization queue, then calculate in the low test prioritization queue of priority to
The service resources allocation plan to be measured of survey business.It is eventually calculated in 2min~3min and generates newest arranging service to be measured
Planning chart and corresponding resource distribution and scheduling scheme, thus realize that power grid test organization directly effectively increases and decreases test business,
And efficiently carry out operational trials work.And works as test macro operating status to deposit when abnormal, step can also be repeated
Test arranging service work of the S201 into step S204, can adjust in time test plan.If not receiving to be measured
Business addition request, then illustrate that not new business to be measured is added, can continue to hold according to original test arranging service scheme
Each test business of row, and step S206 can be continued to execute.
S206: according to the busy degree of the total resources demand configuration information of current each business to be measured, system resource is carried out
Corresponding investment and release adjustment.
It, can be according to current each to be measured under the premise of guaranteeing that the resource allocation of each business to be measured meets test resource demand
The busy degree of the total resources demand configuration information of business, is put into accordingly to system resource and is discharged adjustment." not busy
When ", i.e., it, can be to the system of not running when being much smaller than the total resources of power grid test macro to resource needed for operational trials to be measured
Resource is discharged.In " busy ", i.e., when larger to resource needed for operational trials to be measured, the resource previously discharged can be thrown
Enter test to use, to improve system resource utilization rate, and realizes the smallest optimal solution adaptive resource scheduling strategy of energy consumption.
System resource can be virtual machine system resource.
Corresponding to above method embodiment, the embodiment of the invention also provides a kind of resource distributions of power grid test business
Dispatching device, the resource distribution dispatching device of power grid test business described below and the money of above-described power grid test business
Source configuration schedules method can correspond to each other reference.
Referring to Fig. 3, Fig. 3 is a kind of structural frames of the resource distribution dispatching device of power grid test business in the embodiment of the present invention
Figure, the apparatus may include:
Source obtaining module 31, for obtaining the idling-resource of power grid test macro;
Delineation of activities module 32, for calculating the corresponding test prioritization of each business to be measured, and by each business to be measured
It is divided into corresponding test prioritization queue;
Resource distribution module 33 provides the free time for the sequence using colony intelligence optimization algorithm according to priority from high to low
Distribute to each business to be measured in each test prioritization queue in source.
Using device provided by the embodiment of the present invention, by the way that when executing power grid test business, the automatic power grid that obtains is surveyed
The idling-resource of test system, calculates the corresponding test prioritization of each business to be measured, and will each delineation of activities to be measured to correspondence
Test prioritization queue in, using the sequence of colony intelligence optimization algorithm according to priority from high to low, idling-resource is distributed to
Each business to be measured in each test prioritization queue.It is tested compared to existing by artificial layout test plan and human configuration
The mode of business demand resource, the application is by automatically calculating the idling-resource of power grid test macro using colony intelligence optimization
Idling-resource is distributed to each business to be measured in each test prioritization queue by the sequence of method according to priority from high to low, larger
Ground improves testing efficiency, improves resource utilization, reduces test operating cost.
In a kind of specific embodiment of the invention, source obtaining module 31 is also used to distribute to by idling-resource
After each business to be measured in each test prioritization queue, when receiving business addition request to be measured, acquisition electricity is repeated
The step of idling-resource of net test macro, to be redistributed to idling-resource.
In a kind of specific embodiment of the invention, delineation of activities module 32 includes priority computational submodule and business
Submodule is divided,
Priority computational submodule is specially to the corresponding resource requirement configuration information of each business to be measured, length of testing speech
Information and urgency level information are weighted, and obtain the module of the corresponding test prioritization of each business to be measured;
Delineation of activities submodule is specially to press service priority range belonging to each business to be measured, by each delineation of activities to be measured
To the module in corresponding test prioritization queue.
In a kind of specific embodiment of the invention, further includes:
System resource adjusts module, for the busy journey according to the currently total resources demand configuration information of each business to be measured
Degree, is put into accordingly to system resource and is discharged adjustment.
Corresponding to above method embodiment, referring to fig. 4, Fig. 4 is the resource that power grid provided by the present invention tests business
The schematic diagram of configuration schedules equipment, the equipment may include:
Memory 41, for storing computer program;
Processor 42 can realize following steps when for executing the computer program of the above-mentioned storage of memory 41:
Obtain the idling-resource of power grid test macro;The corresponding test prioritization of each business to be measured is calculated, and will be each
Delineation of activities to be measured is into corresponding test prioritization queue;Utilize colony intelligence optimization algorithm according to priority from high to low suitable
Idling-resource is distributed to each business to be measured in each test prioritization queue by sequence.
Above method embodiment is please referred to for the introduction of equipment provided by the invention, this will not be repeated here by the present invention.
It is computer-readable the present invention also provides a kind of computer readable storage medium corresponding to above method embodiment
It is stored with computer program on storage medium, can realize following steps when computer program is executed by processor:
Obtain the idling-resource of power grid test macro;The corresponding test prioritization of each business to be measured is calculated, and will be each
Delineation of activities to be measured is into corresponding test prioritization queue;Utilize colony intelligence optimization algorithm according to priority from high to low suitable
Idling-resource is distributed to each business to be measured in each test prioritization queue by sequence.
The computer readable storage medium may include: USB flash disk, mobile hard disk, read-only memory (Read-Only
Memory, ROM), random access memory (Random Access Memory, RAM), magnetic or disk etc. is various to deposit
Store up the medium of program code.
Above method embodiment is please referred to for the introduction of computer readable storage medium provided by the invention, the present invention exists
This is not repeated them here.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with it is other
The difference of embodiment, same or similar part may refer to each other between each embodiment.For being filled disclosed in embodiment
It sets, for equipment and computer readable storage medium, since it is corresponded to the methods disclosed in the examples, so the comparison of description
Simply, reference may be made to the description of the method.
Used herein a specific example illustrates the principle and implementation of the invention, and above embodiments are said
It is bright to be merely used to help understand technical solution of the present invention and its core concept.It should be pointed out that for the common of the art
, without departing from the principle of the present invention, can be with several improvements and modifications are made to the present invention for technical staff, these
Improvement and modification are also fallen within the protection scope of the claims of the present invention.
Claims (10)
1. a kind of resource distribution dispatching method of power grid test business characterized by comprising
Obtain the idling-resource of power grid test macro;
It calculates the corresponding test prioritization of each business to be measured and tests each delineation of activities to be measured preferentially to corresponding
In grade queue;
Using the sequence of colony intelligence optimization algorithm according to priority from high to low, it is excellent that the idling-resource is distributed into each test
Each business to be measured in first grade queue.
2. the resource distribution dispatching method of power grid according to claim 1 test business, which is characterized in that by the sky
After not busy resource allocation is to each business to be measured in each test prioritization queue, further includes:
When receiving business to be measured addition request, the step of repeating the idling-resource for obtaining power grid test macro,
To be redistributed to the idling-resource.
3. the resource distribution dispatching method of power grid test business according to claim 1 or 2, which is characterized in that calculate each
The corresponding test prioritization of business to be measured, comprising:
The corresponding resource requirement configuration information of each business to be measured, length of testing speech information and urgency level information are carried out
Weighted calculation obtains the corresponding test prioritization of each business to be measured;
By each delineation of activities to be measured into corresponding test prioritization queue, comprising:
It is by service priority range belonging to each business to be measured, each delineation of activities to be measured is preferential to corresponding test
In grade queue.
4. the resource distribution dispatching method of power grid test business according to claim 3, which is characterized in that further include:
According to the busy degree of the total resources demand configuration information of current each business to be measured, system resource is carried out corresponding
Investment and release adjustment.
5. a kind of resource distribution dispatching device of power grid test business characterized by comprising
Source obtaining module, for obtaining the idling-resource of power grid test macro;
Delineation of activities module is drawn for calculating the corresponding test prioritization of each business to be measured, and by each business to be measured
It assigns in corresponding test prioritization queue;
Resource distribution module, for the sequence using colony intelligence optimization algorithm according to priority from high to low, by the idling-resource
Distribute to each business to be measured in each test prioritization queue.
6. the resource distribution dispatching device of power grid test business according to claim 5, which is characterized in that the resource obtains
Modulus block, be also used to the idling-resource is distributed to each business to be measured in each test prioritization queue it
Afterwards, when receiving business to be measured addition request, the step of repeating the idling-resource for obtaining power grid test macro, with
The idling-resource is redistributed.
7. the resource distribution dispatching device of power grid test business according to claim 5 or 6, which is characterized in that the industry
Business division module includes priority computational submodule and delineation of activities submodule,
The priority computational submodule is specially to the corresponding resource requirement configuration information of each business to be measured, test
Duration information and urgency level information are weighted, and obtain the mould of the corresponding test prioritization of each business to be measured
Block;
The delineation of activities submodule is specially to press service priority range belonging to each business to be measured, will be each described to be measured
Delineation of activities is to the module in corresponding test prioritization queue.
8. the resource distribution dispatching device of power grid test business according to claim 7, which is characterized in that further include:
System resource adjusts module, for the busy journey according to the currently total resources demand configuration information of each business to be measured
Degree, is put into accordingly to system resource and is discharged adjustment.
9. a kind of resource distribution controlling equipment of power grid test business characterized by comprising
Memory, for storing computer program;
Processor, the power grid test business as described in any one of Claims 1-4 is realized when for executing the computer program
The step of resource distribution dispatching method.
10. a kind of computer readable storage medium, which is characterized in that be stored with computer on the computer readable storage medium
Program realizes the money of the power grid test business as described in any one of Claims 1-4 when the computer program is executed by processor
The step of source configuration schedules method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910522366.8A CN110210789A (en) | 2019-06-17 | 2019-06-17 | Resource distribution dispatching method, the device, equipment of power grid test business |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910522366.8A CN110210789A (en) | 2019-06-17 | 2019-06-17 | Resource distribution dispatching method, the device, equipment of power grid test business |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110210789A true CN110210789A (en) | 2019-09-06 |
Family
ID=67793155
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910522366.8A Pending CN110210789A (en) | 2019-06-17 | 2019-06-17 | Resource distribution dispatching method, the device, equipment of power grid test business |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110210789A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111506898A (en) * | 2020-04-07 | 2020-08-07 | 中国信息通信研究院 | Information service security evaluation method and device |
CN111709723A (en) * | 2020-07-20 | 2020-09-25 | 港胜技术服务(深圳)有限公司 | RPA business process intelligent processing method, device, computer equipment and storage medium |
CN111800310A (en) * | 2020-06-17 | 2020-10-20 | 北京智网信测科技有限公司 | Scheduling algorithm for task management module of Internet of things testing cloud platform |
CN112650687A (en) * | 2020-12-30 | 2021-04-13 | 绿盟科技集团股份有限公司 | Method, device, equipment and medium for testing execution priority of engine scheduling action |
CN113282402A (en) * | 2021-07-22 | 2021-08-20 | 航天中认软件测评科技(北京)有限责任公司 | Test task scheduling method oriented to complex resource constraint |
CN114285780A (en) * | 2021-12-23 | 2022-04-05 | 中国电子科技集团公司第十四研究所 | Radar network testing system and method based on priority queue |
CN115794591A (en) * | 2023-02-06 | 2023-03-14 | 南方电网数字电网研究院有限公司 | Scheduling method of power grid IT (information technology) resources |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102915254A (en) * | 2011-08-02 | 2013-02-06 | 中兴通讯股份有限公司 | Task management method and device |
CN103699445A (en) * | 2013-12-19 | 2014-04-02 | 北京奇艺世纪科技有限公司 | Task scheduling method, device and system |
CN106506670A (en) * | 2016-11-21 | 2017-03-15 | 北京永信至诚科技股份有限公司 | A kind of cloud platform virtual resource high speed dispatching method and system |
CN108345501A (en) * | 2017-01-24 | 2018-07-31 | 全球能源互联网研究院 | A kind of distributed resource scheduling method and system |
-
2019
- 2019-06-17 CN CN201910522366.8A patent/CN110210789A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102915254A (en) * | 2011-08-02 | 2013-02-06 | 中兴通讯股份有限公司 | Task management method and device |
CN103699445A (en) * | 2013-12-19 | 2014-04-02 | 北京奇艺世纪科技有限公司 | Task scheduling method, device and system |
CN106506670A (en) * | 2016-11-21 | 2017-03-15 | 北京永信至诚科技股份有限公司 | A kind of cloud platform virtual resource high speed dispatching method and system |
CN108345501A (en) * | 2017-01-24 | 2018-07-31 | 全球能源互联网研究院 | A kind of distributed resource scheduling method and system |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111506898A (en) * | 2020-04-07 | 2020-08-07 | 中国信息通信研究院 | Information service security evaluation method and device |
CN111800310B (en) * | 2020-06-17 | 2021-11-26 | 北京智网信测科技有限公司 | Scheduling method for task management module of Internet of things test cloud platform |
CN111800310A (en) * | 2020-06-17 | 2020-10-20 | 北京智网信测科技有限公司 | Scheduling algorithm for task management module of Internet of things testing cloud platform |
CN111709723A (en) * | 2020-07-20 | 2020-09-25 | 港胜技术服务(深圳)有限公司 | RPA business process intelligent processing method, device, computer equipment and storage medium |
CN111709723B (en) * | 2020-07-20 | 2023-11-28 | 港胜技术服务(深圳)有限公司 | RPA business process intelligent processing method, device, computer equipment and storage medium |
CN112650687A (en) * | 2020-12-30 | 2021-04-13 | 绿盟科技集团股份有限公司 | Method, device, equipment and medium for testing execution priority of engine scheduling action |
CN112650687B (en) * | 2020-12-30 | 2024-03-19 | 绿盟科技集团股份有限公司 | Method, device, equipment and medium for testing execution priority of engine scheduling action |
CN113282402B (en) * | 2021-07-22 | 2021-11-05 | 航天中认软件测评科技(北京)有限责任公司 | Test task scheduling method oriented to complex resource constraint |
CN113282402A (en) * | 2021-07-22 | 2021-08-20 | 航天中认软件测评科技(北京)有限责任公司 | Test task scheduling method oriented to complex resource constraint |
CN114285780A (en) * | 2021-12-23 | 2022-04-05 | 中国电子科技集团公司第十四研究所 | Radar network testing system and method based on priority queue |
CN114285780B (en) * | 2021-12-23 | 2023-12-15 | 中国电子科技集团公司第十四研究所 | Radar network testing system and testing method based on priority queue |
CN115794591A (en) * | 2023-02-06 | 2023-03-14 | 南方电网数字电网研究院有限公司 | Scheduling method of power grid IT (information technology) resources |
CN115794591B (en) * | 2023-02-06 | 2023-05-23 | 南方电网数字电网研究院有限公司 | Scheduling method for IT (information technology) resources of power grid |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110210789A (en) | Resource distribution dispatching method, the device, equipment of power grid test business | |
CN105740051B (en) | Cloud computing resources based on Revised genetic algorithum dispatch implementation method | |
CN109606180B (en) | Intelligent dynamic power allocation charging method | |
CN109861850B (en) | SLA-based stateless cloud workflow load balancing scheduling method | |
CN110515704A (en) | Resource regulating method and device based on Kubernetes system | |
CN105468435A (en) | NFV dynamic resource distribution method | |
CN106293950A (en) | A kind of resource optimization management method towards group system | |
CN102665282B (en) | Distribution method of multi-user parallel transmission resource in wireless heterogeneous network | |
CN104951372A (en) | Method for dynamic allocation of Map/Reduce data processing platform memory resources based on prediction | |
CN113132945B (en) | Energy-saving scheduling method and system for railway private network base station cell | |
CN101374077A (en) | Method and system for forwarding network management alarm | |
WO2020134133A1 (en) | Resource allocation method, substation, and computer-readable storage medium | |
CN110289631A (en) | A kind of calculation method and system of wind farm energy storage device capacity | |
CN109451056A (en) | Server dynamic allocation method and system between more clusters | |
CN103703830B (en) | A kind of physical resource adjustment, device and controller | |
CN115543624A (en) | Heterogeneous computing power arrangement scheduling method, system, equipment and storage medium | |
CN103458520A (en) | Allocation method and device of uplink frequency domain resources | |
CN112092670B (en) | Charging pile queuing and charging management method | |
CN116231632B (en) | Power regulation and control method and system for photovoltaic power station, electronic equipment and storage medium | |
CN116131304A (en) | Power distribution energy storage management system for novel power system | |
CN105955816A (en) | Event scheduling method and device | |
CN112968962B (en) | Cloud platform storage resource scheduling method based on distributed computer cluster architecture | |
CN110955522B (en) | Resource management method and system for coordination performance isolation and data recovery optimization | |
CN104572304A (en) | Method for intelligently maintaining and managing cluster rendering tasks in balance manner | |
CN109475006A (en) | M2M service resource allocation method and distribution system based on Dynamic Packet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190906 |