CN110170125A - The interim fire-fighting system of super high-rise building in a kind of work progress - Google Patents

The interim fire-fighting system of super high-rise building in a kind of work progress Download PDF

Info

Publication number
CN110170125A
CN110170125A CN201910551587.8A CN201910551587A CN110170125A CN 110170125 A CN110170125 A CN 110170125A CN 201910551587 A CN201910551587 A CN 201910551587A CN 110170125 A CN110170125 A CN 110170125A
Authority
CN
China
Prior art keywords
fire
interim
water tank
building
fighting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910551587.8A
Other languages
Chinese (zh)
Inventor
王芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910551587.8A priority Critical patent/CN110170125A/en
Publication of CN110170125A publication Critical patent/CN110170125A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A62LIFE-SAVING; FIRE-FIGHTING
    • A62CFIRE-FIGHTING
    • A62C3/00Fire prevention, containment or extinguishing specially adapted for particular objects or places
    • A62C3/02Fire prevention, containment or extinguishing specially adapted for particular objects or places for area conflagrations, e.g. forest fires, subterranean fires
    • AHUMAN NECESSITIES
    • A62LIFE-SAVING; FIRE-FIGHTING
    • A62CFIRE-FIGHTING
    • A62C35/00Permanently-installed equipment
    • A62C35/58Pipe-line systems
    • A62C35/60Pipe-line systems wet, i.e. containing extinguishing material even when not in use
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B11/00Arrangements or adaptations of tanks for water supply
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/02Public or like main pipe systems
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B17/00Fire alarms; Alarms responsive to explosion

Landscapes

  • Public Health (AREA)
  • Health & Medical Sciences (AREA)
  • Emergency Management (AREA)
  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Water Supply & Treatment (AREA)
  • Structural Engineering (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Ecology (AREA)
  • Forests & Forestry (AREA)
  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The invention discloses a kind of interim fire-fighting systems of super high-rise building in work progress, belong to structural fire protection technical field.The defect which solve the super high-rise buildings in work progress in the prior art to lack effectively interim fire-fighting system, cannot play the role of fire-fighting and water tank installation inconvenience to interim exterior wall.It mainly includes lateral loops pipe unit, control device and at least one fire prevention zone, the fire prevention zone includes low layer fire fighting unit and high building fire-proof unit, and the low layer fire fighting unit is responsible in the building in work progress A layers to B layers of fire-fighting and including low layer fire standpipe;The high building fire-proof unit is responsible in the building in work progress B+1 layers to the fire-fighting of n-th layer and including high building fire-proof vertical tube, water tank and interim water tank;The lateral loops pipe unit includes at least one lateral endless tube, and lateral endless tube is connect along interim exterior wall horizontal extension and with interim exterior wall.The present invention is for the high-rise interim fire-fighting in work progress.

Description

The interim fire-fighting system of super high-rise building in a kind of work progress
Technical field
The invention belongs to structural fire protection technical fields, specifically, more particularly to a kind of super high-rise building in work progress Interim fire-fighting system.
Background technique
The interim fire-fighting system of super high-rise building is primarily referred to as during construction of super highrise building, to ensure the fire-fighting built Safe and foundation a set of Building Fire Fighting System.With economic development, the construction of super high-rise building is more and more frequent, and due to super The construction of skyscraper has the characteristics that the period is long, cross-operation is more, combustibles are more, occurs that super high-rise building in work progress The number of fire constantly increases, and fire is occurring for the super high-rise building in work progress often due to without fire prevention zone and maturation Interim fire-fighting system and be difficult to control the intensity of a fire, fire spreading speed is fast, it is difficult to save, and blocks due to lacking, and flue gas is from 300 The construction bottom of rice or so only needs, and due to highly higher, fire attack is made to lack effective tool, need It wants fireman the consumption plenty of time to enter fire floor, and more since construction environment is severe, becomes the evacuation of construction personnel It is difficult, so the early warning and early stage when fire occurs for super high-rise building in work progress save it is extremely important;By outer Occupy certain ratio, exterior-wall heat insulation in the super high-rise building of fire caused by wall insulating layer in the construction process fire occurred Layer in the case of fire, since insulating layer be in vertical plane and has the characteristics that flammable, makes difficulty of saving, and insulating layer of external wall When losing often very huge, current interim fire-fighting system caused by caused fire and often not having exterior wall fire occurs Fighting ability;In a kind of work progress in the interim fire-fighting system of super high-rise building, require to use interim water tank, due to facing When water tank volume it is larger, so the mode that interim water tank generally takes steel plate to weld at present, that is, needing to place interim water tank Plurality of steel plates is temporarily welded into water tank by worker by floor, and the interim water tank welded in this way tends not to multiple benefit With, and it is time-consuming and laborious, there is also the risks for causing fire in the welding process.
Summary of the invention
It is an object of the present invention to provide a kind of interim fire-fighting systems of super high-rise building in work progress, to overcome the prior art Super high-rise building in middle work progress lacks effectively interim fire-fighting system, cannot play the role of fire-fighting and water tank to interim exterior wall Inconvenient defect is installed.
The present invention adopts the following technical solutions realizes: the interim fire-fighting system of super high-rise building in a kind of work progress System, including lateral loops pipe unit, control device and at least one fire prevention zone, the fire prevention zone include low layer fire fighting unit and High building fire-proof unit, the low layer fire fighting unit be responsible for A layers to B layers of fire-fighting in the building in work progress and including Low layer fire standpipe, low layer fire standpipe one end connection city planting ductwork are simultaneously upwardly extended along interim exterior wall, and the low layer disappears Anti- vertical tube connects first level pipe in each corresponding floor position, and the first level pipe connects fire hydrant;The high building fire-proof Unit is responsible in the building in work progress B+1 layers to the fire-fighting of n-th layer and including high building fire-proof vertical tube, water tank and is faced When water tank, the water tank is arranged in ground or basement and connect respectively with city planting ductwork and high building fire-proof vertical tube, described Water tank is connect by high building fire-proof vertical tube with adjacent interim water tank, and installation is faced between water tank and high building fire-proof vertical tube When high-pressure pump, connect with water tank temporary high-pressure pump the water in water tank is transported in adjacent interim water tank, phase It is connected between adjacent two interim water tanks by high building fire-proof vertical tube, interim water tank connection temporary high-pressure pump, the interim water tank of downside The interim cistern water supply to adjacent upside is pumped by temporary high-pressure, high building fire-proof vertical tube connects the second water in corresponding floor position Flat pipe, the second horizontal tube connect fire hydrant, and the fire hydrant is installed in floor;The lateral loops pipe unit includes at least one A transverse direction endless tube, lateral endless tube are connect along interim exterior wall horizontal extension and with interim exterior wall, lateral endless tube and high building fire-proof vertical tube It connects and passes through high building fire-proof vertical tube and supply water, lateral endless tube and high building fire-proof vertical tube have collectively constituted the closing of a horizontal direction Annular installs multiple high pressure fire fighting spray heads on the transverse direction endless tube, the control device connection temporary high-pressure pump and high pressure fire fighting Spray head and can control temporary high-pressure pump and high pressure fire fighting spray head open or close.
It further, is fire disaster refuge layer by the storey setting for being equipped with the interim water tank.
Further, the lateral endless tube is connect by multiple U-shaped bars with exterior wall, and described U-shaped bar one end is embedded in exterior wall In, lateral endless tube passes through U-shaped bar and provides support force by U-shaped bar.
It further, further include intelligent monitoring and controlling device, the intelligent monitoring and controlling device includes interim fire detector and fire Alarm controller, multiple positions of each floor of the building of the interim fire detector installation in the construction process and with fire The connection of calamity alarm controller, each floor are respectively mounted fire alarm control unit, and fire alarm control unit includes GPRS communication apparatus And warning device, fire alarm control unit connect mobile receiver by GPRS communication apparatus.
Further, between the low layer fire standpipe and first level pipe and high building fire-proof vertical tube and the second horizontal tube it Between pass through three-way ball valve connect.
Further, the interim water tank includes liquid-level switch, and the liquid-level switch connects control device, and control device connects Temporary high-pressure pump is connect, control device can control temporary high-pressure pump according to the feedback information of liquid-level switch and open or close, make interim Water tank is full of water always.
Further, the interim water tank includes at least four sub- water tanks, and the sub- water tank includes tank body, the water The cross section of case ontology be it is rectangular, connecting tube, connecting tube one end Method for Installation are installed in two neighboring side respectively on the downside of tank body It is blue.
Further, dustproof cover is installed on the tank body top surface.
Further, seal groove is opened up on the end face of the flange, mounting O-shaped sealing ring in seal groove.
Compared with prior art, the beneficial effects of the present invention are:
1, the present invention can play the role of extraordinary interim fire-fighting, Er Qiejie for the super high-rise building in work progress Structure is simple, stability is high, is responsible in work progress by setting low layer fire fighting unit and high building fire-proof unit, low layer fire fighting unit Building in A layers to B layers of fire-fighting, described A layers are the bottoms in the building in work progress, can be -3 layers Or -2 layers or -1 layer, described B layers is that the water pressure of local city planting ductwork is easier to reach top, the high building fire-proof unit It is responsible for the B+1 layers of fire-fighting to n-th layer in the building in work progress, N is top in the building in work progress, such as B is set 6 buildings, i.e., 6 buildings by we and 6 buildings floors below are responsible for by low layer fire fighting unit, i.e., 6 buildings and 6 buildings floors below Fire fighting supply directly transported by city planting ductwork, 6 buildings or more floors are responsible for by high building fire-proof unit, in the construction process, when We build the quantity of floor at B+1 layers or more but also not to the floor of first interim water tank of installation when, be when B layers B layers with Calamity of lighting a fire is issued, is to provide fire demand water by low layer fire standpipe by city planting ductwork cylinder, when B layers or more generation fire, because For B layers or more interim water tank is not installed also, so being provided by temporary high-pressure pump by high building fire-proof vertical tube by water tank Fire demand water installs first interim water tank when we, which build floor quantity, reaches the floor that first interim water tank is built, And water is added to first interim water tank by water tank, and after first interim water tank topped up with water, B+1 layers to installation first The fire fighting supply of floor between the floor of interim water tank is provided by first interim water tank by gravity water supply, and gravity water supply is Water in interim water tank is supplied water by gravity from high building fire-proof vertical tube to fire hydrant, is faced when we build number of floor levels and reach first When water tank and second interim water tank between floor when, first interim water tank to the floor between second interim water tank Fire fighting supply is pumped by temporary high-pressure by first interim water tank and is provided, the adjacent first interim water of described second interim water tank Case and on the upside of first interim water tank, when second interim water tank is built up, first interim water tank to second interim water tank Between floor fire fighting supply by second interim water tank by gravity water supply provide, and so on, until n-th layer has been built At roof installs interim water tank.
2, the present invention can accomplish that early warning and early stage are saved, and be respectively mounted by every layer in the building in work progress more A interim fire detector, interim fire detector connect fire alarm control unit, and fire alarm control unit includes GPRS communication Equipment and warning device can transmit a signal to fire alarming and controlling when fire detector detects, and fire occurs at work Device, fire alarm control unit issue alarm and send the information that fire occurs to mobile reception by GPRS communication module Device, the mobile receiver are the terminals such as mobile phone or computer, and people at the scene or not at the scene is made to know that fire is believed at the first time Breath.
3, the present invention has fighting ability when fire occurs for External Wall, by installing lateral endless tube, make lateral endless tube and High building fire-proof vertical tube has collectively constituted the closed ring of a horizontal direction, and multiple high pressure fire fighting spray heads are installed on lateral endless tube, Four-way pipe is arranged in the junction of the transverse direction endless tube and high building fire-proof vertical tube, and at work, we can be spaced certain number of floor levels peace A lateral endless tube is filled, such as we can install a lateral endless tube at interval of 8 layers, keep the temperature when starting installation on interim exterior wall Layer, and when case of fire occurs for insulating layer, lateral loops that staff can be nearest by control device command range ignition point High pressure fire fighting spray head work in high pressure fire fighting spray head work on pipe, or the multiple lateral endless tubes of control.
4, water tank of the present invention facilitates transhipment, installation and repeatedly utilizes, and water tank needs human weld's before avoiding Disadvantage, by the way that four sub- water tanks are arranged, when we need sub- water tank being transported to mounting layer by temporary elevator, due to sub- water Case size is smaller avoid very well before large water tank the case where can not being transported by elevator, two neighboring sub- water tank during installation, It is aligned the flange on two water tanks, and two flange fastenings are made by nut bolt.
Detailed description of the invention
Fig. 1 is schematic diagram of the invention;
Fig. 2 is the structural schematic diagram of sub- water tank of the present invention;
Fig. 3 is the structural schematic diagram of interim water tank of the present invention;
Fig. 4 is the structural schematic diagram of U-shaped bar of the present invention.
In figure: 1, low layer fire standpipe;2, city planting ductwork;3, interim exterior wall;4, first level pipe;5, fire hydrant;6, high Layer fire standpipe;7, water tank;8, interim water tank;9, temporary high-pressure pumps;10, lateral endless tube;11, U-shaped bar;12, water tank sheet Body;13, connecting tube;14, flange;15, through-hole;16, dustproof cover;17, O-ring seal;18, the second horizontal tube.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings.
The interim fire-fighting system of super high-rise building in a kind of work progress, including lateral loops pipe unit, control device and extremely A few fire prevention zone, the fire prevention zone include low layer fire fighting unit and high building fire-proof unit, and the low layer fire fighting unit is negative Blame work progress in building in A layers to B layers fire-fighting and including low layer fire standpipe 1, the low layer fire standpipe 1 one End connection city planting ductwork 2 is simultaneously upwardly extended along interim exterior wall 3, and the low layer fire standpipe 1 is connected in each corresponding floor position First level pipe 4, the first level pipe 4 connect fire hydrant 5;The high building fire-proof unit is responsible in the building in work progress B+1 layers to n-th layer fire-fighting and set including high building fire-proof vertical tube 6, water tank 7 and interim water tank 8, the water tank 7 It sets in ground or basement and is connect respectively with city planting ductwork 2 and high building fire-proof vertical tube 6, the water tank 7 is disappeared by high level Anti- vertical tube 6 is connect with adjacent interim water tank 8, temporary high-pressure pump 9 is installed between water tank 7 and high building fire-proof vertical tube 6, with confession Water in water tank 7 is transported in adjacent interim water tank 8 by the temporary high-pressure pump 9 that water tank 7 connects, two neighboring interim It is connected between water tank 8 by high building fire-proof vertical tube 6, interim water tank 8 connects temporary high-pressure pump 9, and the interim water tank 8 of downside is by facing When high-pressure pump 9 supply water to the interim water tank 8 of adjacent upside, high building fire-proof vertical tube 6 is horizontal in corresponding floor position connection second Pipe 18, the second horizontal tube 18 connect fire hydrant 5, and the fire hydrant 5 is installed in floor;The lateral loops pipe unit includes extremely Few one lateral endless tube 10, lateral endless tube 10 connects along interim 3 horizontal extension of exterior wall and with interim exterior wall 3, lateral endless tube 10 and High building fire-proof vertical tube 6 is connected and is supplied water by high building fire-proof vertical tube 6, and lateral endless tube 10 and high building fire-proof vertical tube 6 collectively constitute The closed ring of one horizontal direction installs multiple high pressure fire fighting spray heads on the transverse direction endless tube 10, the control device connection Temporary high-pressure pump 9 and high pressure fire fighting spray head and can control temporary high-pressure pump 9 and high pressure fire fighting spray head open or close.
The present invention is responsible in work progress by setting low layer fire fighting unit and high building fire-proof unit, low layer fire fighting unit A layers to B layers of fire-fighting in building, the bottom in building in the A layers of work progress, can be -3 layers or -2 layers Or -1 layer, described B layers is that the water pressure of local city planting ductwork 2 is easier to reach top, and the high building fire-proof unit is responsible for The B+1 layers of fire-fighting to n-th layer in building in work progress, N are top in the building in work progress, such as we It can set B to 6 buildings, i.e., 6 buildings and 6 buildings floors below are responsible for by low layer fire fighting unit, i.e. 6 buildings and 6 buildings floors below Fire fighting supply is directly transported by city planting ductwork 2, and 6 buildings or more floors are responsible for by high building fire-proof unit, in the construction process, when me Build the quantity of floor at B+1 layers or more but also not to the floor of first interim water tank 8 of installation when, be B layers or less when B layers Fire occurs, is to provide fire demand water by low layer fire standpipe 1 by city planting ductwork 2, when B layers or more generation fire, because For B layers or more interim water tank 8 is not installed also, so be to provide fire demand water by high building fire-proof vertical tube 6 by water tank 7, when When we build floor quantity and reach the floor that first interim water tank 8 is built, first interim water tank 8 is installed, and pass through confession Water tank 7 is to first interim water tank 8 plus water, and after first interim 8 topped up with water of water tank, B+1 layers to installation first interim The fire fighting supply of floor between the floor of water tank 8 is provided by first interim water tank 8 by gravity water supply, and gravity water supply faces When water tank 8 in water supplied water from high building fire-proof vertical tube 6 to fire hydrant 5 by gravity, reach first when we build floor quantity When floor between a interim water tank 8 and second interim water tank 8, between first interim water tank 8 of 8 to the second, interim water tank The fire fighting supply of floor provided by first interim water tank 8 by temporary high-pressure pump 9, described second interim water tank 8 be adjacent First interim water tank 8 and first 8 upside of interim water tank, when second interim water tank 8 is built up, first interim water tank 8 Fire fighting supply to the floor between second interim water tank 8 is provided by second interim water tank 8 by gravity water supply, with such It pushes away, builds and complete until n-th layer, n-th layer or roof install interim water tank 8.The present invention can install one temporarily at interval of 15 layers Water tank 8.The present invention makes lateral endless tube 10 and high building fire-proof vertical tube 6 collectively constitute a level by installing lateral endless tube 10 The closed ring in direction installs multiple high pressure fire fighting spray heads, the transverse direction endless tube 10 and high building fire-proof vertical tube 6 on lateral endless tube 10 Junction four-way pipe is set, at work, we can be spaced certain number of floor levels and install a lateral endless tube 10, such as we can A lateral endless tubes 10 are installed at interval of 8 layers, when starting to install insulating layer on interim exterior wall 3, and fire behavior occurs for insulating layer When condition, staff can pass through the high pressure fire fighting spray head work on the nearest lateral endless tube 10 of control device command range ignition point Make, or the high pressure fire fighting spray head work on the multiple lateral endless tubes 10 of control.
It is fire disaster refuge layer by the storey setting for being equipped with the interim water tank 8.
The present invention is fire disaster refuge layer by the storey setting that will be equipped with the interim water tank 8, is sending out construction worker When calamity of lighting a fire is escaped without enough time, refuge story can be entered nearby, the refuge story is semi-open-type refuge story.
The transverse direction endless tube 10 is connect by multiple U-shaped bars 11 with exterior wall, and described U-shaped 11 one end of bar is embedded in exterior wall, Lateral endless tube 10 passes through U-shaped bar 11 and provides support force by U-shaped bar 11.
It further include intelligent monitoring and controlling device, the intelligent monitoring and controlling device includes interim fire detector and fire alarming and controlling Device, multiple positions of each floor of the building of the interim fire detector installation in the construction process and with fire alarm control Device connection processed, each floor are respectively mounted fire alarm control unit, and fire alarm control unit includes that GPRS communication apparatus and alarm are set Standby, fire alarm control unit connects mobile receiver by GPRS communication apparatus.
The present invention is respectively mounted multiple interim fire detectors, interim fire detection by every layer in the building in work progress Device connects fire alarm control unit, and fire alarm control unit includes that GPRS communication apparatus and warning device work as fire at work Detector, which detects, occurs to transmit a signal to fire alarm control unit when fire, and fire alarm control unit issues alarm and leads to It crosses GPRS communication module and sends the information that fire occurs to mobile receiver, the mobile receiver is that mobile phone or computer etc. are whole End makes people at the scene or not at the scene know fire information at the first time.
Between the low layer fire standpipe 1 and first level pipe 4 between high building fire-proof vertical tube 6 and the second horizontal tube 18 It is connected by three-way ball valve.
The interim water tank 8 includes liquid-level switch, and the liquid-level switch connects control device, and control device connection is interim high Press pump 9, control device can control temporary high-pressure pump 9 according to the feedback information of liquid-level switch and open or close, and interim water tank 8 is made to begin It is full of water eventually.
The present invention in application process, when the liquid-level switch in the interim water tank 8 of upside detects the water of interim water tank 8 not When sufficient, control device can be transmitted a signal to, control device controls the pump of the temporary high-pressure on the interim water tank 8 of downside adjacent thereto 9 work.
The interim water tank 8 includes at least four sub- water tanks, and the sub- water tank includes tank body 12, the tank body 12 cross section be it is rectangular, connecting tube 13, the installation of 13 one end of connecting tube are installed in the two neighboring side in the downside of tank body 12 respectively Flange 14 opens up through-hole 15 on flange 14.
The present invention is by four sub- water tanks of setting, when we need sub- water tank being transported to mounting layer by temporary elevator When, due to sub- tank size it is smaller very well avoid before large water tank can not be transported by elevator the case where, two neighboring sub- water Case during installation, is aligned the flange 14 on two water tanks, and fastens two flanges 14 by nut bolt.
Dustproof cover 16 is installed on 12 top surface of tank body.
Seal groove is opened up on the end face of the flange 14, mounting O-shaped sealing ring 17 in seal groove.
O-ring seal 17 of the present invention can prevent 14 junction leak of flange.

Claims (9)

1. the interim fire-fighting system of super high-rise building in a kind of work progress, it is characterised in that: including lateral loops pipe unit, control Device and at least one fire prevention zone, the fire prevention zone includes low layer fire fighting unit and high building fire-proof unit, and the low layer disappears Anti- unit is responsible for A layers to B layers of fire-fighting in the building in work progress and including low layer fire standpipe (1), described low Layer fire standpipe (1) one end connection city planting ductwork (2) is simultaneously upwardly extended along interim exterior wall (3), and the low layer fire standpipe (1) exists Each corresponding floor position connection first level pipe (4), the first level pipe (4) connect fire hydrant (5);The high building fire-proof Unit is responsible for B+1 layers in the building in work progress to the fire-fighting of n-th layer and including high building fire-proof vertical tube (6), water supply water Case (7) and interim water tank (8), the water tank (7) be arranged in ground or basement and respectively with city planting ductwork (2) and high level Fire standpipe (6) connection, the water tank (7) are connect by high building fire-proof vertical tube (6) with adjacent interim water tank (8), are supplied Temporary high-pressure pump (9) is installed, the temporary high-pressure pump connecting with water tank (7) between water tank (7) and high building fire-proof vertical tube (6) (9) water in water tank (7) is transported in adjacent interim water tank (8), passes through height between two neighboring interim water tank (8) Layer fire standpipe (6) connects, and interim water tank (8) connection temporary high-pressure pump (9), the interim water tank (8) of downside passes through temporary high-pressure The interim water tank (8) for pumping the upside of (9) Xiang Xianglin supplies water, and high building fire-proof vertical tube (6) is horizontal in corresponding floor position connection second It manages (18), the second horizontal tube (18) connects fire hydrant (5), and the fire hydrant (5) is installed in floor;The transverse direction endless tube list Member includes at least one lateral endless tube (10), and lateral endless tube (10) connects along interim exterior wall (3) horizontal extension and with interim exterior wall (3) Connect, lateral endless tube (10) connect with high building fire-proof vertical tube (6) and is supplied water by high building fire-proof vertical tube (6), lateral endless tube (10) and High building fire-proof vertical tube (6) has collectively constituted the closed ring of a horizontal direction, installs on the transverse direction endless tube (10) multiple high It presses applicator, the control device connection temporary high-pressure pump (9) and high pressure fire fighting spray head and can control temporary high-pressure pump (9) It is opened or closed with high pressure fire fighting spray head.
2. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 1, it is characterised in that: will The storey setting for being equipped with the interim water tank (8) is fire disaster refuge layer.
3. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 1, it is characterised in that: institute It states lateral endless tube (10) to connect by multiple U-shaped bars (11) with exterior wall, described U-shaped bar (11) one end is embedded in exterior wall, laterally Endless tube (10) passes through U-shaped bar (11) and provides support force by U-shaped bar (11).
4. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 1, it is characterised in that: also Including intelligent monitoring and controlling device, the intelligent monitoring and controlling device includes interim fire detector and fire alarm control unit, described interim Multiple positions of each floor of the building of fire detector installation in the construction process are simultaneously connect with fire alarm control unit, often A floor is respectively mounted fire alarm control unit, and fire alarm control unit includes GPRS communication apparatus and warning device, fire alarm Controller connects mobile receiver by GPRS communication apparatus.
5. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 1, it is characterised in that: institute It states logical between high building fire-proof vertical tube (6) and the second horizontal tube (18) between low layer fire standpipe (1) and first level pipe (4) Cross three-way ball valve connection.
6. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 1, it is characterised in that: institute Stating interim water tank (8) includes liquid-level switch, and the liquid-level switch connects control device, and control device connects temporary high-pressure pump (9), Control device can control temporary high-pressure pump (9) according to the feedback information of liquid-level switch and open or close, and make interim water tank (8) always Full of water.
7. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 1, it is characterised in that: institute Stating interim water tank (8) includes at least four sub- water tanks, and the sub- water tank includes tank body (12), the tank body (12) Cross section be it is rectangular, two neighboring side is installed connecting tube (13) respectively on the downside of tank body (12), connecting tube (13) one end peace It fills flange (14), opens up through-hole (15) on flange (14).
8. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 7, it is characterised in that: institute State installation dustproof cover (16) on tank body (12) top surface.
9. the interim fire-fighting system of super high-rise building in a kind of work progress according to claim 7, it is characterised in that: institute It states and opens up seal groove on the end face of flange (14), mounting O-shaped sealing ring (17) in seal groove.
CN201910551587.8A 2019-06-24 2019-06-24 The interim fire-fighting system of super high-rise building in a kind of work progress Pending CN110170125A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910551587.8A CN110170125A (en) 2019-06-24 2019-06-24 The interim fire-fighting system of super high-rise building in a kind of work progress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910551587.8A CN110170125A (en) 2019-06-24 2019-06-24 The interim fire-fighting system of super high-rise building in a kind of work progress

Publications (1)

Publication Number Publication Date
CN110170125A true CN110170125A (en) 2019-08-27

Family

ID=67698774

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910551587.8A Pending CN110170125A (en) 2019-06-24 2019-06-24 The interim fire-fighting system of super high-rise building in a kind of work progress

Country Status (1)

Country Link
CN (1) CN110170125A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111150955A (en) * 2020-01-19 2020-05-15 中国科学技术大学 Fixing and moving combined compressed air foam fire extinguishing system suitable for super high-rise building and design method thereof
CN111388927A (en) * 2020-04-07 2020-07-10 中国建筑西北设计研究院有限公司 Ultrahigh-rise indoor fire hydrant series water supply method and system
KR102216096B1 (en) * 2020-06-16 2021-02-16 신기남 Fire extinguishing control system during and after construction
CN112814081A (en) * 2021-02-03 2021-05-18 江苏省华建建设股份有限公司 Construction site permanent-temporary combined near-water supply system with pressure stabilizing function
CN113318368A (en) * 2021-05-17 2021-08-31 上海景文同安机电消防工程有限公司 Energy-saving consumption-reducing fire-fighting water supply system
CN115591154A (en) * 2022-10-10 2023-01-13 杨卫才(Cn) High-rise building fire extinguishing system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120318372A1 (en) * 2011-06-17 2012-12-20 James Robert Wendling Standpipe Emergency Bypass Method and Kit for Firefighters
KR101386335B1 (en) * 2013-11-13 2014-04-17 고현수 System for water supply and fire extinguishing installations of high-rise apartment building
CN104127981A (en) * 2014-08-08 2014-11-05 北京建工四建工程建设有限公司 Fire fighting system for super high-rise cyclic relay type construction
CN205839878U (en) * 2016-07-18 2016-12-28 张龙 Fire water source station
CN107261367A (en) * 2017-08-17 2017-10-20 镇江市丹徒区硕源材料科技有限公司 A kind of fire-fighting system and fire-fighting mode
CN109432662A (en) * 2018-11-26 2019-03-08 中建三局集团有限公司 Fire fighting water system and its construction method for the construction of super highrise building stage
CN210542968U (en) * 2019-06-24 2020-05-19 王芳 Temporary fire fighting system of super high-rise building in construction process

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120318372A1 (en) * 2011-06-17 2012-12-20 James Robert Wendling Standpipe Emergency Bypass Method and Kit for Firefighters
KR101386335B1 (en) * 2013-11-13 2014-04-17 고현수 System for water supply and fire extinguishing installations of high-rise apartment building
CN104127981A (en) * 2014-08-08 2014-11-05 北京建工四建工程建设有限公司 Fire fighting system for super high-rise cyclic relay type construction
CN205839878U (en) * 2016-07-18 2016-12-28 张龙 Fire water source station
CN107261367A (en) * 2017-08-17 2017-10-20 镇江市丹徒区硕源材料科技有限公司 A kind of fire-fighting system and fire-fighting mode
CN109432662A (en) * 2018-11-26 2019-03-08 中建三局集团有限公司 Fire fighting water system and its construction method for the construction of super highrise building stage
CN210542968U (en) * 2019-06-24 2020-05-19 王芳 Temporary fire fighting system of super high-rise building in construction process

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111150955A (en) * 2020-01-19 2020-05-15 中国科学技术大学 Fixing and moving combined compressed air foam fire extinguishing system suitable for super high-rise building and design method thereof
CN111150955B (en) * 2020-01-19 2024-01-09 中国科学技术大学 Solid-moving combined compressed air foam fire extinguishing system suitable for super high-rise building and design method thereof
CN111388927A (en) * 2020-04-07 2020-07-10 中国建筑西北设计研究院有限公司 Ultrahigh-rise indoor fire hydrant series water supply method and system
CN111388927B (en) * 2020-04-07 2021-05-04 中国建筑西北设计研究院有限公司 Ultrahigh-rise indoor fire hydrant series water supply method and system
KR102216096B1 (en) * 2020-06-16 2021-02-16 신기남 Fire extinguishing control system during and after construction
CN112814081A (en) * 2021-02-03 2021-05-18 江苏省华建建设股份有限公司 Construction site permanent-temporary combined near-water supply system with pressure stabilizing function
CN113318368A (en) * 2021-05-17 2021-08-31 上海景文同安机电消防工程有限公司 Energy-saving consumption-reducing fire-fighting water supply system
CN115591154A (en) * 2022-10-10 2023-01-13 杨卫才(Cn) High-rise building fire extinguishing system

Similar Documents

Publication Publication Date Title
CN110170125A (en) The interim fire-fighting system of super high-rise building in a kind of work progress
CN214006002U (en) Building shock isolation device
CN104027924A (en) Fire extinguishing system suitable for high-rise residential building
KR101937330B1 (en) apparatus controlling and preventing fastening of pump
CN202136713U (en) Normal, stable and high pressure water mist fire extinguishing system
CN201543150U (en) High-rise industrial building fire-fighting water supply system configuration structure
CN208694102U (en) Construction site high altitude firefighting water tank
CN210542968U (en) Temporary fire fighting system of super high-rise building in construction process
CN207998893U (en) Core Walls Structure climbing formwork for construction pipe band fire-fighting water storage system
CN114432631A (en) Automatic water spraying fire extinguishing system and fire extinguishing method for cooling tower
CN209437933U (en) A kind of fire hydrant pipeline structure
CN204352419U (en) A kind of construction exterior rack Multi-functional spray system
CN216925208U (en) Automatic water spraying fire extinguishing system of cooling tower
CN107784800A (en) Antidetonation suspension and support intelligence managing and control system
TWI623338B (en) Multi-purpose multi-pressure variable frequency variable speed fire pump
CN211705704U (en) Automatic water spraying fire extinguishing system using indoor fire hydrant ring pipe network for water supply
CN104324471A (en) Multifunctional spraying system of building outer frame and mounting method of multifunctional spraying system
CN210263469U (en) Profiled steel structure with fire prevention function
CN205698984U (en) Plane domain guide tracked fire of high-rise building rescue aid
CN111330201A (en) Temporary fire-fighting water system for construction site
CN111053997A (en) Automatic water-spraying fire-extinguishing system using indoor fire hydrant annular pipe network for water supply and construction method thereof
CN207749578U (en) Underground hydrant outside a kind of hydraulically extensible room
CN221663796U (en) Disassembly-free temporary water supply device for construction
CN214550751U (en) Novel fast assembly type efficient fire-fighting spraying device
CN206090705U (en) Novel fire control pump house is moved in two frequency conversions

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190827