CN110158464A - A kind of novel shear key combination beam and its construction method - Google Patents

A kind of novel shear key combination beam and its construction method Download PDF

Info

Publication number
CN110158464A
CN110158464A CN201910474941.1A CN201910474941A CN110158464A CN 110158464 A CN110158464 A CN 110158464A CN 201910474941 A CN201910474941 A CN 201910474941A CN 110158464 A CN110158464 A CN 110158464A
Authority
CN
China
Prior art keywords
steel plate
hole
stirrup
shear key
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910474941.1A
Other languages
Chinese (zh)
Inventor
胡所亭
李旺旺
苏永华
班新林
葛凯
陶晓燕
韩冰
荣峤
赵体波
朱希同
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
China State Railway Group Co Ltd
Original Assignee
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
China Railway Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Railway Sciences Corp Ltd CARS, Railway Engineering Research Institute of CARS, China Railway Corp filed Critical China Academy of Railway Sciences Corp Ltd CARS
Priority to CN201910474941.1A priority Critical patent/CN110158464A/en
Publication of CN110158464A publication Critical patent/CN110158464A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The present invention provides a kind of novel shear key combination beams, including concrete slab (1), stirrup (2), shear key (3) and girder steel (4), the girder steel (4) is set to the concrete slab (1) lower surface, the concrete slab (1) is internal to be provided with shear key (3) at bottom surface, the stirrup (2) is vertically installed in the concrete slab (1) inside, and the shear key (3) and the stirrup (2) contact position weld.A kind of novel shear key combination beam of the present invention realizes the reserved hole location of concrete slab and accurately docks with girder steel connector, ensure overall performance of the concrete slab after reserved hole location, steel construction and concrete structure are connected to become whole co-operation by the effect for giving full play to shear connector.

Description

A kind of novel shear key combination beam and its construction method
Technical field
The present invention relates to field of bridge construction, and in particular to a kind of combination beam.
Background technique
Steel-concrete combined structure is that one kind is formed steel construction and concrete structure integrally altogether by shear connector With the structure type of work, shear connector is the key that steel-concrete combined structure stress performance.This kind of structure type can The mechanical property of steel and concrete material is given full play to, has the small stability of the big self weight of the high rigidity of good bearing capacity good And the advantages that easy for construction, in engineering fields extensive applications such as bridge building structure piping lanes.
With the development of engineering technology, requirement of the people to construction technology and construction quality is higher and higher, fabricated construction The application of technology is further extensive.The construction of Standard formula can be achieved component and all complete in factory, can be improved component quality, Construction material dosage is reduced, for building energy conservation important in inhibiting.Fabricated construction can greatly reduce site operation workload And the time, stringent and site operation bad environments engineering important roles are required for the construction period.
The problem of how shear connector is set is faced in the fabricated construction of the mixed composite structure of steel-.At present using the most Extensive Welded-Stud Conectors need multi-point to coordinate, and reserving point in precast slab can be since concrete be in hardening process In contraction and change in location occurs, be unable to complete in installation process multi-point matching.Perforated steel plate connector is due to along beam It is longitudinally continuous and runs through, longitudinal direction can not be reserved in precast slab through seam, and cannot achieve perforated steel plate connector and mix Effective connection of solidifying soil prefabricated board.Concrete prefabricated board reserves large hole in separate type peg group's connection method existing at present Hole, longitudinal reinforcement and transverse steel between reserving hole are all truncated, and seriously affect the globality of concrete slab, and peg group with Power transmission is only carried out by rear pouring concrete between precast slab, Welded-Stud Conectors be unable to give full play effect by steel construction and Concrete structure is connected to become entirety.
The prefabricated construction of steel-concrete combined structure needs to solve the problems, such as three aspects of connector.First, prefabricated mixed How reserved hole location in concrete board is accurately docked with the Welded-Stud Conectors on steel construction.Second, how to reduce prefabricated mixed Concrete board reserving hole reduces its influence to precast slab globality.How third gives full play to shear connector Effect, is connected to become entirety for steel construction and concrete structure.
Patent CN201120487335 disclose it is a kind of in bridge construction fasten concrete shear key, if including by The shear key ontology that shear key unit interconnected is constituted is done, the shear key unit includes support plate, the support plate Both ends are provided with mounting plate, and several groups through-hole is provided on the mounting plate, is provided with support column between every group of through-hole.
Though the patent is using the entirety being interconnected to constitute using shear key unit, since its supporting plate structure is more multiple It is miscellaneous, cause manufacturing process equally complex;Though being caused between its each shear key using its shear key unit set-up mode simultaneously Entirety is so formed, but is affected to concrete globality.
Now need a kind of reserved hole location in precast slab that can carry out with the Welded-Stud Conectors on steel construction accurate Docking;Concrete slab preformed hole is smaller;Steel construction and concrete structure are connected to become to whole combination beam.
Summary of the invention
The present invention is docked precisely to solve the reserved hole location of concrete slab in the prior art with Welded-Stud Conectors on steel construction The problem of degree reduces the influence to precast slab globality, gives full play to the effect of shear connector provides a kind of new Type shear key combination beam, concrete slab globality is high, and preformed hole is smaller, is easy to accurately dock, solves the above problem.
The present invention provides a kind of novel shear key combination beam, including concrete slab, stirrup, shear key and girder steel, girder steels It is set to concrete slab lower surface, is provided with shear key at bottom surface inside concrete slab, stirrup is vertically installed in coagulation Native intralamellar part, shear key and stirrup contact position weld.
A kind of novel shear key combination beam of the present invention, it is preferred that, shear key includes pin rod iron, with holes Steel plate, pre-buried perforated steel plate, perforated steel plate are provided with mounting hole, and perforated steel plate is vertically arranged at girder steel upper surface, pin steel plate It is set in mounting hole, pre-buried perforated steel plate plate face is provided with through-hole, and perforated steel plate is set in through-hole, pre-buried perforated steel plate edge Embedded in concrete structure basal surface position.Pre-buried perforated steel plate both ends should be neat with template top, prevents in concreting process It buries steel plate position and changes and cannot carry out Matching installation with the connector being pre-designed.
A kind of novel shear key combination beam of the present invention, it is preferred that, stirrup is including disconnection stirrup and commonly Stirrup disconnects stirrup and is uniformly arranged on the perpendicular where pre-buried perforated steel plate through-hole, and disconnection stirrup both ends are set to pre-buried Perforated steel plate through-hole two sides bottom surface, common stirrup are uniformly arranged on the perpendicular of pre-buried perforated steel plate through-hole two sides.
By burying pin rod iron mounting plate in concrete structure, the hole location merging precision of shear connector is improved;Pass through Pin rod iron and pin rod iron mounting plate realize simplicity, quickly, are reliably connected.Perforated steel plate is arranged reserved at design position Perforated steel plate is installed in hole, and both ends and template top are neat, guarantees that position does not change in concreting process, is realized anti- Connector hole location is cut accurately to dock.Perforated steel plate after the installation is completed, is laid with common stirrup and disconnects stirrup in concrete structure, And weld it with pre-buried perforated steel plate, the longitudinal reinforcement at the alternative position of perforated steel plate avoids at the position Longitudinal reinforcement is disconnected due to reserving hole, improves structural integrity.
Connector connection method is to dock after the completion of concrete slab and prefabricated steel construction according to perforated steel plate through-hole hole location After the completion, pin rod iron is inserted into pin rod iron mounting plate, that completes shear connector is reliably fixed connection.
Two kinds of preformed holes on pin rod iron mounting plate and perforated steel plate consider suitably to amplify, to consider concrete shrinkage It is influenced with various errors.
A kind of novel shear key combination beam of the present invention, it is preferred that, pre-buried perforated steel plate and stirrup weld.
A kind of novel shear key combination beam of the present invention, it is preferred that, perforated steel plate is longitudinal or horizontal along girder steel To arrangement.Pin steel column connecting plate can also improve lateral shear behavior along the lateral arrangement of beam.Pin steel column connecting plate can be along beam It is longitudinally arranged, longitudinal shear resistance performance can be improved.
A kind of novel shear key combination beam of the present invention, it is preferred that, pin rod iron includes the first rotary table, the Two rotary tables, cylinder interconnecting piece, first the second rotary table of rotary table and cylinder interconnecting piece are coaxial, the first rotary table and the second rotary table bottom surface It is set to two bottom surface of cylinder interconnecting piece, the first rotary table and the second rotary table bottom surface area≤cylinder interconnecting piece base area.
Splicing efficiency is improved convenient for positioning when splicing using the pin rod iron of class shuttle shape.
A kind of novel shear key combination beam of the present invention, it is preferred that, pin rod iron and mounting hole are interference Cooperation.
The amplification of 1~2mm is considered as when aperture, to consider that various errors influence.
A kind of novel shear key combination beam of the present invention, it is preferred that, concrete slab includes concrete slab sheet Body and high-performance fiber concrete, concrete body be it is board-like, concrete body is provided with preformed hole, and preformed hole is counterbore, in advance It boxes out and is set to the reversed one end of pre-buried perforated steel plate, preformed hole bottom end is provided with that be overlapped size with mounting hole vertical position identical Through-hole is provided with through-hole assembly shear key, high-performance fiber Concrete Filled preformed hole in preformed hole.
Consider the convenience of site operation, therefore selects the very-high performance fiber concrete of the non-evaporating feeding microdilatancy of self-compaction.
Stirrup includes the disconnection stirrup connecting with shear connector and the common stirrup not connecting with shear connector, positive throwing It is provided with the setting of perforated steel plate position on shadow face and disconnects stirrup, common stirrup is set without perforated steel plate position on frontal plane of projection.
The present invention provides a kind of novel shear key to combine beam construction method, comprising the following steps:
S1. pin rod iron is made;
S2. it makes girder steel and perforated steel plate, perforated steel plate is welded in girder steel top surface;
S3. the pre-buried perforated steel plate of concrete slab is made;
S4. on-site consolidation is carried out, steel construction perforated steel plate is reserved into hole location with concrete slab and carries out docking assembly;By pin Rod iron is by concrete slab preformed hole and is arranged in the reversed one end insertion girder steel perforated steel plate of pre-buried perforated steel plate;
S5. the very-high performance fiber concrete of the non-evaporating feeding microdilatancy of self-compaction is poured at reserved hole location.
A kind of novel shear key of the present invention combines beam construction method, it is preferred that, step S3 is specifically included:
S31. prefabricated reinforced concrete structure template support is carried out, perforated steel plate is laid with, is laid with laterally common stirrup and pre- It boxes out and disconnects stirrup at position, laterally common stirrup and disconnection stirrup are welded with pre-buried perforated steel plate;
S32. it is laid with longitudinal regular reinforcement;
S33., preformed hole at concrete slab connector position is set;
S34. casting concrete, demoulding after the completion of concrete curing.
The present invention has the beneficial effect that:
(1) by perforated steel plate pre-buried in reinforced concrete structure, the influence of concrete shrinkage is substantially reduced, is realized The accurate positioning of assembled steel-concrete structure shear connector hole location;
(2) pre-buried perforated steel plate is welded with common stirrup and the section place of opening stirrup in reinforced concrete structure, is avoided Stirrup is disconnected and being influenced at reserved hole location, improves the globality of structure;
(3) longitudinal reinforcement in reinforced concrete structure at the alternative position of pre-buried perforated steel plate, avoids the position Place's longitudinal reinforcement is disconnected due to reserved hole location, improves the globality of structure;
(4) after steel construction and concrete structure are installed according to reserved hole location, by installing pin rod iron in perforated steel plate The two is formed into entirety, not only considered the convenience of construction but also can guarantee effective connection of connector, the rigidity of pin rod iron compared with Greatly, the shearing between steel construction and concrete structure can be effectively transmitted, while being effective against between concrete structure and steel construction Start;
(5) perforated steel plate can be according to the vertical and horizontal flexible arrangement of beam, spacing between steel plate, the length of perforated steel plate Degree, wherein the size of aperture and pin rod iron can be with higher to be applicable according to practical set formula requirement of engineering flexible arrangement Property;
(6) steel construction and concrete structure after the installation is completed, pour the non-evaporating feeding microdilatancy of self-compaction in reserved hole location Very-high performance fiber concrete, it is contemplated that the operability of site operation.Very-high performance fiber concrete and normal concrete are same For cement-based material, reliable bond can be carried out, and very-high performance fiber concrete has fine and close material structure and good resistance to Long property more effectively protects the knot at Shear connection position while the power effectively between transmitting steel construction and concrete structure Structure.
Detailed description of the invention
Fig. 1 is combination beam concrete slab vertical section schematic diagram;
Fig. 2 is combination beam shear key schematic diagram;
Fig. 3 is combination beam shear key pin rod iron schematic diagram;
Fig. 4 is combination beam concrete slab perspective diagram;
Fig. 5 is combination beam construction method flow chart.
Appended drawing reference:
1, concrete slab;11, concrete slab ontology;12, high-performance fiber concrete;2, stirrup;21, common stirrup;22, Disconnect stirrup;3, shear key;31, pin rod iron;311, the first rotary table;312, the second rotary table;31, cylinder interconnecting piece;32, with holes Steel plate;33, pre-buried perforated steel plate;4, girder steel.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out understanding that is complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Embodiment 1
As shown in Figure 1, a kind of novel shear key combination beam, including concrete slab 1, stirrup 2, shear key 3 and girder steel 4, steel Beam 4 is set to 1 lower surface of concrete slab, and 1 inside of concrete slab is provided with shear key 3 at bottom surface, and stirrup 2 is vertically arranged Inside concrete slab 1, shear key 3 and 2 contact position of stirrup are welded.
As shown in Fig. 2, shear key 3 includes pin rod iron 31, perforated steel plate 32, pre-buried perforated steel plate 33, perforated steel plate 32 It is provided with mounting hole, perforated steel plate 32 is vertically arranged at 4 upper surface of girder steel, and pin rod iron 31 is set in mounting hole, pre- buried strap Steel plate 33 plate face in hole is provided with through-hole, and perforated steel plate 32 is set in through-hole, and pre-buried perforated steel plate 33 is embedded in 1 bottom of concrete slab Face position.Pin rod iron 31 and mounting hole are interference fit.The amplification of 1~2mm is considered as when aperture, to consider various error shadows It rings.The steel plate both ends should be neat with template top, prevent in concreting process in bury steel plate position change cannot with it is pre- The connector first designed carries out Matching installation.
As shown in figure 3, pin rod iron 31 includes the first rotary table 311, the second rotary table 312, cylinder interconnecting piece 313, the first circle 311. second rotary table 312 of platform and cylinder interconnecting piece 313 are coaxial, and the first rotary table 311 and 312 bottom surface of the second rotary table are set to cylinder 313 liang of bottom surfaces of interconnecting piece, the first rotary table 311 and the second rotary table 312 bottom surface area≤313 base area of cylinder interconnecting piece.Pin Bolt rod iron mounting plate 2 is made of steel plate, and Circularhole diameter matches with pin rod iron cylinder interconnecting piece base circle diameter (BCD), root weldering It is connected at the top of steel construction.
As shown in figure 4, stirrup 2 includes disconnecting stirrup 22 and common stirrup 21, disconnects stirrup 22 and be uniformly arranged on pre- buried strap Perpendicular where 33 through-hole of hole steel plate disconnects 22 both ends of stirrup and is set to pre-buried 33 through-hole two sides bottom surface of perforated steel plate, general Logical stirrup 21 is uniformly arranged on the perpendicular of pre-buried 33 through-hole two sides of perforated steel plate.Pre-buried perforated steel plate 33 is welded with stirrup 2. Perforated steel plate 32 is longitudinally-or laterally-disposed along girder steel 4.Concrete slab 1 includes concrete slab ontology 11 and high-performance fiber concrete 12, concrete body 11 be it is board-like, concrete body 11 is provided with preformed hole, and preformed hole is counterbore, and preformed hole is set to pre-buried The reversed one end of perforated steel plate 33, preformed hole bottom end, which is provided with, is overlapped the identical through-hole of size, preformed hole with mounting hole vertical position It is inside provided with through-hole assembly shear key 3, high-performance fiber concrete 12 fills preformed hole.Preformed hole size is relative to reserved The setting of hole site lack of balance, a preformed hole are middle line, a length of pin rod iron overall length in side, and counterbore a length of half in side is heavy Hole, counterbore depth are slightly larger than 32 width of perforated steel plate slightly larger than 32 height of perforated steel plate, width.Between 31 length perforated steel plates 2 Away from its own length of, arrangement form can be designed according to actual requirement of engineering and be determined.
As shown in figure 5, novel shear key combines beam construction method, comprising the following steps:
S1. pin rod iron 31 is made;
S2. it makes girder steel 4 and perforated steel plate 32, perforated steel plate 32 is welded in 4 top surface of girder steel;
S3. the pre-buried perforated steel plate 33 of concrete slab 1 is made;
S4. on-site consolidation is carried out, steel construction perforated steel plate 32 is reserved into hole location with concrete slab 1 and carries out docking assembly;It will Pin rod iron 31 is inserted into 4 perforated steel plate 32 of girder steel by 1 preformed hole of concrete slab and setting reversed one end of pre-buried perforated steel plate 33 It is interior;
S5. the very-high performance fiber concrete 12 of the non-evaporating feeding microdilatancy of self-compaction is poured at reserved hole location.
Step S3 is specifically included:
S31. prefabricated reinforced concrete structure template support is carried out, perforated steel plate 32 is laid with, is laid with laterally common stirrup 21 With disconnection stirrup 22 at reserved hole location, laterally common stirrup 21 and disconnection stirrup 22 are welded with pre-buried perforated steel plate 33 It connects;
S32. it is laid with longitudinal regular reinforcement;
S33., preformed hole at concrete slab connector position is set;
S34. casting concrete, demoulding after the completion of concrete curing.
The preformed hole to match with perforated steel plate 2 on steel construction, while reserved energy are reserved in concrete structure prefabrication process Enough preformed holes that pin rod iron 1 is fit into reserved steel plate.Two kinds of preformed holes consider suitably to amplify, to consider that concrete is received Contracting and various errors influence.
Preformed hole is arranged in pre-buried perforated steel plate 33 at design position, installs pre-buried perforated steel plate 33, both ends and template Top is neat, guarantees that position does not change in concreting process, realizes that shear connector hole location is accurately docked.It is pre-buried with holes Steel plate 33 after the installation is completed, is laid with common stirrup and disconnects stirrup, and by itself and pre-buried perforated steel plate 33 in concrete structure It is welded.
After the completion of concrete structure and prefabricated steel construction, after the completion of the docking of reserved hole location, pin rod iron 1 is inserted into In perforated steel plate 2, that completes shear connector is reliably fixed connection.
After the completion of concrete structure and steel structure assembling, the non-evaporating feeding microdilatancy superelevation of self-compaction is poured in reserved hole location Energy fiber concrete, considers property easy for construction and connection reliability.
Shear connector and construction method proposed by the present invention for assembled steel-concrete combined structure, by It pre-buried perforated steel plate 33 and is welded with stirrup in concrete structure, welds perforated steel plate 2 in girder steel top surface;It is prefabricated in the factory After the completion, it after being installed by reserved hole location, is fixed by pin rod iron 1;After the installation is completed, it is poured in preformed hole The very-high performance fiber concrete of the non-evaporating feeding microdilatancy of self-compaction.This kind of connection type substantially increases assembled steel-concrete The globality of composite structure, effectively enhance assembled steel-mix composite structure shearing strength and rigidity, ensured steel construction with The collaborative work of concrete structure.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (10)

1. a kind of novel shear key combination beam, it is characterised in that: including concrete slab (1), stirrup (2), shear key (3) and girder steel (4), the girder steel (4) is set to the concrete slab (1) lower surface, and the concrete slab (1) is internal to be set at bottom surface It is equipped with shear key (3), the stirrup (2) is vertically installed in the concrete slab (1) inside, the shear key (3) and the hoop The welding of muscle (2) contact position.
2. a kind of novel shear key combination beam according to claim 1, it is characterised in that: the shear key (3) includes pin Bolt rod iron (31), perforated steel plate (32), pre-buried perforated steel plate (33), the perforated steel plate (32) are provided with mounting hole, the band Hole steel plate (32) is vertically arranged at the girder steel (4) upper surface, and the pin rod iron (31) is set in the mounting hole, described Pre-buried perforated steel plate (33) plate face is provided with through-hole, and the perforated steel plate (32) is set in the through-hole, described pre-buried with holes Steel plate (33) is embedded in the concrete slab (1) basal surface position.
3. a kind of novel shear key combination beam according to claim 2, it is characterised in that: the stirrup (2) includes disconnecting Stirrup (22) and common stirrup (21), the disconnection stirrup (22) are uniformly arranged on where pre-buried perforated steel plate (33) through-hole Perpendicular, disconnection stirrup (22) both ends are set to pre-buried perforated steel plate (33) the through-hole two sides bottom surface, described general Logical stirrup (21) are uniformly arranged on the perpendicular of pre-buried perforated steel plate (33) the through-hole two sides.
4. a kind of novel shear key combination beam described in any one of its according to claim 1~3, it is characterised in that: described Pre-buried perforated steel plate (33) and the stirrup (2) are welded.
5. a kind of novel shear key combination beam according to claim 4, it is characterised in that: the perforated steel plate (32) is along institute It is longitudinally-or laterally-disposed to state girder steel (4).
6. according to claim 4~5 its any one of described in a kind of novel shear key combination beam, it is characterised in that: it is described Pin rod iron (31) includes the first rotary table (311), the second rotary table (312), cylinder interconnecting piece (313), first rotary table (311) Second rotary table (312) and the cylinder interconnecting piece (313) coaxially, first rotary table (311) and second rotary table (312) bottom surface is set to (313) two bottom surface of cylinder interconnecting piece, first rotary table (311) and second rotary table (312) bottom surface area≤cylinder interconnecting piece (313) base area.
7. a kind of novel shear key combination beam according to claim 5, it is characterised in that: the pin rod iron (31) and institute Mounting hole is stated as interference fit.
8. a kind of novel shear key combination beam according to claim 5, it is characterised in that: the concrete slab (1) includes Concrete slab ontology (11) and high-performance fiber concrete (12), the concrete body (11) are board-like, the concrete sheet Body (11) is provided with preformed hole, and the preformed hole is counterbore, and it is reversed that the preformed hole is set to the pre-buried perforated steel plate (33) One end, the preformed hole bottom end are provided with and are overlapped the identical through-hole of size with the mounting hole vertical position, in the preformed hole It is provided with the through-hole and assembles the shear key (3), the high-performance fiber concrete (12) fills the preformed hole.
9. a kind of novel shear key combines beam construction method, it is characterised in that: the following steps are included:
S1. pin rod iron (31) are made;
S2. girder steel (4) are made and perforated steel plate (32), perforated steel plate (32) is welded in girder steel (4) top surface;
S3. concrete slab (1) is made, pre-buried perforated steel plate (33);
S4. on-site consolidation is carried out, steel construction perforated steel plate (32) is reserved into hole location with concrete slab (1) and carries out docking assembly;It will Pin rod iron (31) is by concrete slab (1) preformed hole and the reversed one end insertion girder steel of the pre-buried perforated steel plate (33) is arranged (4) in perforated steel plate (32);
S5. the very-high performance fiber concrete (12) of the non-evaporating feeding microdilatancy of self-compaction is poured at reserved hole location.
10. a kind of novel shear key according to claim 9 combines beam construction method, it is characterised in that: step S3 is specific Include:
S31. prefabricated reinforced concrete structure template support is carried out, is laid with perforated steel plate (32), laterally common stirrup (21) is laid with Disconnect stirrup (22) at preformed hole, by the common stirrup of the transverse direction (21) and the disconnection stirrup (22) with pre-buried steel with holes Plate (33) is welded;
S32. it is laid with longitudinal regular reinforcement;
S33., preformed hole at concrete slab connector position is set;
S34. casting concrete, demoulding after the completion of concrete curing.
CN201910474941.1A 2019-06-03 2019-06-03 A kind of novel shear key combination beam and its construction method Pending CN110158464A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910474941.1A CN110158464A (en) 2019-06-03 2019-06-03 A kind of novel shear key combination beam and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910474941.1A CN110158464A (en) 2019-06-03 2019-06-03 A kind of novel shear key combination beam and its construction method

Publications (1)

Publication Number Publication Date
CN110158464A true CN110158464A (en) 2019-08-23

Family

ID=67627050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910474941.1A Pending CN110158464A (en) 2019-06-03 2019-06-03 A kind of novel shear key combination beam and its construction method

Country Status (1)

Country Link
CN (1) CN110158464A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080083181A1 (en) * 2003-07-18 2008-04-10 Pedro Ospina Integral composite-structure construction system
CN103741877A (en) * 2013-12-30 2014-04-23 北京工业大学 Lattice anti-shearing device-steel-profiled steel plate-renewable concrete combination beam and production method
CN205421722U (en) * 2016-02-19 2016-08-03 中南大学 Steel - concrete structure's compound shear force connecting piece
CN106677049A (en) * 2017-01-20 2017-05-17 福州大学 Assembled steel-concrete combination structure bridge and construction method
CN211368387U (en) * 2019-06-03 2020-08-28 中国铁道科学研究院集团有限公司铁道建筑研究所 Novel shear force component combination beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080083181A1 (en) * 2003-07-18 2008-04-10 Pedro Ospina Integral composite-structure construction system
CN103741877A (en) * 2013-12-30 2014-04-23 北京工业大学 Lattice anti-shearing device-steel-profiled steel plate-renewable concrete combination beam and production method
CN205421722U (en) * 2016-02-19 2016-08-03 中南大学 Steel - concrete structure's compound shear force connecting piece
CN106677049A (en) * 2017-01-20 2017-05-17 福州大学 Assembled steel-concrete combination structure bridge and construction method
CN211368387U (en) * 2019-06-03 2020-08-28 中国铁道科学研究院集团有限公司铁道建筑研究所 Novel shear force component combination beam

Similar Documents

Publication Publication Date Title
CN108149825A (en) A kind of connection mode and construction method for the prefabricated board of assembled architecture, prefabricated board and beam
CN109457801A (en) A kind of connecting node and its construction method of prefabricated prestressed concrete beam
CN108571063A (en) A kind of shear wall structure building assembly System Design
CN108166619A (en) A kind of novel fabricated concrete structure bean column node
CN105040822A (en) Steel coupling beam and concrete shear wall assembly type connecting structure reserving construction allowance
CN105803939A (en) Open steel tube and reinforced-concrete combined girder bridge structure
CN110512765A (en) A kind of fabricated shear wall and construction method with steel plate peg combined type diagonal brace
CN103061357B (en) Connection joint between basement base plate and underground diaphragm wall
CN203440993U (en) Connection joint of prefabricated reinforced concrete beam
KR101625995B1 (en) Precast deck and slab having the same
CN209941467U (en) Assembled stride ultra high performance concrete box girder combination formula node greatly
CN209637027U (en) A kind of fabricated shear wall
CN110158464A (en) A kind of novel shear key combination beam and its construction method
CN207314537U (en) A kind of assembled Outsourcing-type steel chain type combining structure
CN106121055B (en) A kind of steel box column and beams of concrete connecting node and its construction method
CN105040855A (en) Assembled prefabricated shear wall welding end plate and horizontal steel combination connecting device
CN210975497U (en) Shear connector
CN211368387U (en) Novel shear force component combination beam
CN212053436U (en) Strenghthened type precast concrete wallboard and connection structure with from structure of taking one's place
CN209228135U (en) A kind of reinforced concrete precast assembling movie theatre stand structure
CN110158448A (en) A kind of shear connector
CN109555232B (en) Precast beam mortise and tenon joint connects
CN207761108U (en) A kind of level splices and combines wall
KR20220123926A (en) Precast slab with interrocking shear member and construction method using the same
JP3162264U (en) Support pile structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination