CN110139384A - The transmission method and terminal device of uplink information - Google Patents

The transmission method and terminal device of uplink information Download PDF

Info

Publication number
CN110139384A
CN110139384A CN201810136516.7A CN201810136516A CN110139384A CN 110139384 A CN110139384 A CN 110139384A CN 201810136516 A CN201810136516 A CN 201810136516A CN 110139384 A CN110139384 A CN 110139384A
Authority
CN
China
Prior art keywords
transmission
priority
uci
information
uplink information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810136516.7A
Other languages
Chinese (zh)
Other versions
CN110139384B (en
Inventor
鲁智
沈晓冬
潘学明
李娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Vivo Mobile Communication Co Ltd
Original Assignee
Vivo Mobile Communication Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Vivo Mobile Communication Co Ltd filed Critical Vivo Mobile Communication Co Ltd
Priority to CN201810136516.7A priority Critical patent/CN110139384B/en
Priority to PCT/CN2019/073165 priority patent/WO2019154127A1/en
Publication of CN110139384A publication Critical patent/CN110139384A/en
Application granted granted Critical
Publication of CN110139384B publication Critical patent/CN110139384B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W72/00Local resource management
    • H04W72/04Wireless resource allocation
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W72/00Local resource management
    • H04W72/12Wireless traffic scheduling
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W72/00Local resource management
    • H04W72/20Control channels or signalling for resource management
    • H04W72/21Control channels or signalling for resource management in the uplink direction of a wireless link, i.e. towards the network
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W72/00Local resource management
    • H04W72/50Allocation or scheduling criteria for wireless resources
    • H04W72/56Allocation or scheduling criteria for wireless resources based on priority criteria
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W72/00Local resource management
    • H04W72/50Allocation or scheduling criteria for wireless resources
    • H04W72/56Allocation or scheduling criteria for wireless resources based on priority criteria
    • H04W72/566Allocation or scheduling criteria for wireless resources based on priority criteria of the information or information source or recipient
    • H04W72/569Allocation or scheduling criteria for wireless resources based on priority criteria of the information or information source or recipient of the traffic information
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W74/00Wireless channel access, e.g. scheduled or random access
    • H04W74/08Non-scheduled or contention based access, e.g. random access, ALOHA, CSMA [Carrier Sense Multiple Access]
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W74/00Wireless channel access, e.g. scheduled or random access
    • H04W74/08Non-scheduled or contention based access, e.g. random access, ALOHA, CSMA [Carrier Sense Multiple Access]
    • H04W74/0808Non-scheduled or contention based access, e.g. random access, ALOHA, CSMA [Carrier Sense Multiple Access] using carrier sensing, e.g. as in CSMA
    • H04W74/0816Non-scheduled or contention based access, e.g. random access, ALOHA, CSMA [Carrier Sense Multiple Access] using carrier sensing, e.g. as in CSMA carrier sensing with collision avoidance

Abstract

The embodiment of the invention discloses the transmission method of uplink information and terminal devices, and for solving the problems, such as the UE of support multiple business, when transmitting uplink information, there may be the conflicts of transfer resource.This method comprises: at least one of type, transmission cycle, the duration of transmission based on uplink information determine the precedence information of at least two uplink information when the transfer resource of at least two uplink informations has conflict;And it is based on the precedence information, transmit the uplink information of highest priority at least two uplink information.The embodiment of the present invention, when transmitting uplink information, provides a kind of contention-resolution schemes of transfer resource in the multiple services UE of support.

Description

The transmission method and terminal device of uplink information
Technical field
The present invention relates to the communications field more particularly to the transmission methods and terminal device of a kind of uplink information.
Background technique
With the fast development of mobile Internet and Internet technology and continuing to bring out for various new business, with Past mobile communication system is compared, and the 5th third-generation mobile communication technology (5th-Generation, 5G) needs to adapt to more diversified Scene and business demand.Currently, the big typical application scenarios of the three of the 5G that 3GPP is defined include enhancing mobile broadband (Enhance Mobile Broadband, eMBB), low time delay, high reliable communication (Ultra-Reliable and Low-Latency Communications, URLLC) and magnanimity machine type communication (massive machine type of Communication, mMTC).These application scenarios propose highly reliable, low time delay, big bandwidth to 5G system, and wide covering etc. is wanted It asks.
In 5G system, certain user's terminal (User Equipment, UE) may support different numerical value to configure (numerology) business, such as UE can both support URLLC business, while can also support eMBB business.
In above-mentioned scene, for supporting the UE of multiple business, the UE is when transmitting uplink information, it is understood that there may be transmission money The conflict in source, the prior art provide the solution of conflict not yet.
Summary of the invention
The purpose of the embodiment of the present invention is that the transmission method and terminal device of a kind of uplink information are provided, it is more to solve to support The UE of kind of business the problem of there may be the conflicts of transfer resource when transmitting uplink information.
In order to solve the above technical problems, the embodiments of the present invention are implemented as follows:
In a first aspect, a kind of transmission method of uplink information is proposed, this method comprises:
When there is conflict in the transfer resource of at least two uplink informations, type, transmission cycle, biography based on uplink information At least one of defeated duration determines the precedence information of at least two uplink information;
Based on the precedence information, the uplink information of highest priority at least two uplink information is transmitted.
Second aspect proposes a kind of terminal device, comprising:
Determination unit, when there is conflict for the transfer resource when at least two uplink informations, the class based on uplink information At least one of type, transmission cycle, the duration of transmission determine the precedence information of at least two uplink information;
Transmission unit transmits highest priority at least two uplink information for being based on the precedence information Uplink information.
The third aspect proposes a kind of terminal device, comprising:
Processor;And
It is configured as the memory of storage computer executable instructions, the executable instruction makes the place when executed Manage the method for device execution as described in relation to the first aspect.
Fourth aspect proposes a kind of computer readable storage medium, the computer-readable recording medium storage one Or multiple programs, one or more of programs are when the electronic equipment for being included multiple application programs executes, so that the electricity Sub- equipment executes method as described in relation to the first aspect.
By the above technical solution provided in an embodiment of the present invention as it can be seen that the embodiment of the present invention at least has following one kind Technical effect:
In the embodiment of the present invention, when the transfer resource of at least two uplink informations has conflict, it can be believed based on uplink At least one of the type of breath, transmission cycle, the duration of transmission determine the priority letter of at least two uplink informations Breath, and it can be based on the precedence information, transmit the uplink information of highest priority at least two uplink informations.Further Ground provides a kind of contention-resolution schemes of transfer resource, for example work as branch to support multiple services UE when transmitting uplink information Multiple services UE is held when transmitting uplink information, the UCI that the SR/ of URLLC exempts from authorization business and the PUCCH of eMBB appears in identical It, can be based on the precedence information of uplink information, transmission priority highest when the period, that is, there are when transfer resource conflict Uplink information, and other uplink informations can be given up.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The some embodiments recorded in invention, for those of ordinary skill in the art, in the premise of not making the creative labor property Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is in communication system, the end UE exempts from authorization business there are SR/ and there is the signal to conflict with the transfer resource of UCI Figure;
Fig. 2 is the implementation process diagram of the transmission method of uplink information according to embodiments of the present invention;
Fig. 3 is that according to embodiments of the present invention, when at least two uplink informations include SR and UCI, transfer resource has conflict Schematic diagram;
Fig. 4 is that according to embodiments of the present invention, when at least two uplink informations include SR and UCI, transfer resource has conflict Another schematic diagram;
Fig. 5 is the transfer resource when at least two uplink informations include exempting from authorization business and UCI according to embodiments of the present invention There are the schematic diagrames of conflict;
Fig. 6 is the transfer resource when at least two uplink informations include exempting from authorization business and UCI according to embodiments of the present invention There are another schematic diagrames of conflict;
Fig. 7 is the transfer resource when at least two uplink informations include SR and exempt from authorization business according to embodiments of the present invention There are the schematic diagrames of conflict;
Fig. 8 is the transmission when at least two uplink informations include SR, exempt from authorization business and UCI according to embodiments of the present invention There is the schematic diagram of conflict in resource;
Fig. 9 is the transmission when at least two uplink informations include SR, exempt from authorization business and UCI according to embodiments of the present invention There is another schematic diagram of conflict in resource;
Figure 10 is a kind of structural schematic diagram of terminal device according to embodiments of the present invention;
Figure 11 is the structural schematic diagram of another terminal device according to embodiments of the present invention.
Specific embodiment
Technical solution in order to enable those skilled in the art to better understand the present invention, below in conjunction with of the invention real The attached drawing in example is applied, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without creative efforts, all should belong to protection of the present invention Range."and/or" used in specification and claim indicate connecting object at least one.
Technical solution of the present invention can be applied to various communication systems, such as: global system for mobile communications (GSM, Global System of Mobile communication), CDMA (CDMA, Code Division Multiple Access) system, wideband code division multiple access (WCDMA, Wideband Code Division Multiple Access), general point Group wireless traffic (GPRS, General Packet Radio Service), long term evolution (LTE, Long Term Evolution)/enhancing long term evolution (LTE-A, Long Term Evolutionadvanced), NR (New Radio) etc..
User terminal (UE, User Equipment), also referred to as mobile terminal (Mobile Terminal), mobile use Family equipment etc., can through wireless access network (for example, RAN, Radio Access Network) and one or more core nets into Row communication, user equipment can be mobile terminal, such as mobile phone (or being " honeycomb " phone) and the meter with mobile terminal Calculation machine, for example, it may be portable, pocket, hand-held, built-in computer or vehicle-mounted mobile device, they and nothing Line access exchanges language and/or data.
Base station can be the base station (BTS, Base Transceiver Station) in GSM or CDMA, be also possible to Base station (NodeB) in WCDMA can also be evolved base station (eNB or e-NodeB, evolutional Node in LTE B) and the base station 5G (gNB), the present invention does not limit, but for convenience of description, and following embodiments are illustrated by taking gNB as an example.
As described in the background art, in 5G system, certain ends UE may support multiple business, when the letter of two kinds of business Road frequency division when occurring simultaneously, then will lead to the end UE papr (Peak to Average Power Ratio, PAPR) higher, and since cost is relatively low for the power amplifier at the end UE, and limited battery capacity, therefore high PAPR can reduce the end UE Power utilization.Therefore it is badly in need of a solution to cope with above-mentioned these problems.
And due in the following 5G system, mainly having this three big typical application scenarios of eMBB, URLLC and mMTC, this three grand ceremony The priority for the business for including in type application scenarios is divided into height, therefore when two or more industry occurs simultaneously in the end UE When business, it may be considered that the priority based on these business selects the higher business of priority to be transmitted, and how to guarantee preferential The higher business of grade causes transfer resource to rush by priority processing, such as when the end UE two or more business occurs simultaneously When prominent, how to guarantee that the high business of the end UE prioritised transmission priority, the prior art provide corresponding solution not yet.It is above-mentioned Illustrate by taking 5G system as an example, right one of ordinary skill in the art are appreciated that the application of the embodiment of the present invention is not limited to 5G system.
As shown in Figure 1, for the end UE, there are SR/ to exempt from authorization business and uplink control information (uplink control Imformation, UCI) transfer resource exist conflict schematic diagram, Fig. 1 include 4 kinds of conflict situations, wherein the first conflict The duration for the transmission that SR/ exempts from authorization business in situation and second of conflict situations is respectively less than the duration of the transmission of UCI, The duration for the transmission that SR/ exempts from authorization business in the third conflict situations and the 4th kind of conflict situations is all larger than the transmission of UCI Duration.The first conflict situations is at the t1 moment, and the end UE SR/ occurs and exempts from authorization business and UCI transmission resource contention Situation;Second of conflict situations is to start to transmit UCI at the moment UE end t2, but at the t3 moment, SR/ occur and exempt from authorization business need It is to be transmitted and the case where cause transfer resource to conflict;The third conflict situations is at the t1 moment, and the end UE SR/ occurs and exempts to authorize industry The case where business and UCI transmission resource contention;4th kind of conflict situations are to start transmission SR/ at the moment UE end t2 to exempt from authorization business, But at the t3 moment, occur UCI need it is to be transmitted and the case where cause transfer resource to conflict.
In the first conflict situations and the third conflict situations, the end UE be prioritised transmission SR/ exempt from authorization business or UCI, and in second of conflict situations and the 4th kind of conflict situations, the end UE is to continue with transmission in transmission at the t3 moment Uplink information still abandons the uplink information uplink information that simultaneously the prioritised transmission t3 moment occurs, and will be the present invention one or more A embodiment will solve the problems, such as.
Fig. 2 is the embodiment flow diagram for the transmission method that one embodiment of the present of invention determines uplink information.Fig. 1's Method is executed by terminal device.This method comprises:
Step 101, when the transfer resource of at least two uplink informations has conflict, type, biography based on uplink information At least one of defeated period, the duration of transmission, determine the precedence information of at least two uplink informations;
Uplink information includes uplink scheduling request (Scheduling Request, SR), exempts from authorization business and uplink It controls information (Uplink Control Infromation, UCI), wherein uplink SR can be carried on physical uplink link control It is transmitted on channel (Physical Uplink Control CHannel, PUCCH) processed, physics can be carried on by exempting from authorization business Transmitted on Uplink Shared Channel (Physical Uplink Shared Channel, PUSCH), UCI can be carried on PUCCH and Any one transmission in the two channels of PUSCH.
Under normal conditions, in uplink information corresponding to the duration of transmission cycle or transmission shorter uplink information The priority of business is higher, and since UCI includes confirm/not confirming (Acknowledgement, ACK/Negative Acknowledgement, NACK), aperiodic channel state information (Aperiodic Channel State Information, A-CSI), semi-continuous channel state information (Semi-Persistent Channel State Information, SP-CSI) and the period channel state information (Periodic Channel Status Information, P-CSI) these four types, and the priority orders of these four types are as follows: ACK/NACK > A-CSI > SP-CSI > P-CSI.This The higher uplink information of priority in UCI of the inventive embodiments in order to determine these four types, and according to definitive result The higher uplink information of prioritised transmission priority divides UCI for the first kind and Second Type, the first kind and Second Type Respectively at least one of ACK/NACK, A-CSI, SP-CSI and P-CSI, and the priority of the first kind is greater than the second class The priority of type.
Due to the determination of the priority of uplink information be related to the transmission cycle of uplink information, transmission duration and The type of uplink information, the embodiment of the present invention are based on this point, when there is conflict in the transfer resource of at least two uplink informations, Can at least one of type, transmission cycle and the duration of transmission based on uplink information, come determine this at least two The precedence information of a uplink information.And since this at least two uplink information may include SR, exempt from authorization business and UCI At least two, therefore at least one of the type based on uplink information, transmission cycle and duration of transmission determine The precedence information of this at least two uplink information can include following several situations:
The first situation, when at least two uplink informations include scheduling request (Scheduling Request, SR) and upper When downlink control information (Uplink Control Infromation, UCI), type, transmission cycle based on uplink information, At least one of duration of transmission determines the priority of at least two uplink informations, can specifically include: if it is determined that When the type of UCI is the first kind, then it can determine that the priority of UCI is higher than the priority of SR;And if it is determined that the type of UCI is When Second Type, then can the transmission cycle based on SR or transmission duration, determine the upper of at least two specified types The precedence information of row information.
It is ACK/NACK, Second Type P-CSI with the first kind when at least two uplink informations include SR and UCI For, however, it is determined that the type of UCI is ACK/NACK, then can determine that the priority of UCI is higher than the priority of SR, in such case Under, as shown in Figure 3, at the t1 moment, if the end UE exist simultaneously SR and UCI need it is to be transmitted and when transfer resource being caused to conflict, Since it is determined the type of UCI is ACK/NACK, then it can determine that the priority of UCI is higher than the priority of SR, therefore, in t1 It carves, the precedence information, prioritised transmission UCI can be based on, and SR can be given up.If the end UE starts transmission should at the t1 moment UCI, and the t2 moment occur SR need it is to be transmitted, and at this time UCI also in transmission state, then based on the preferential of UCI and SR Grade information, continues to transmit the UCI, and can give up SR.
(1) based on the transmission cycle of SR, the precedence information of at least two uplink informations is determined: in the type for determining UCI When for Second Type (for example being P-CSI), the duration of transmission cycle or transmission based on SR, at least two uplinks are determined The precedence information of information, specifically, if the transmission cycle of SR can determine the priority of SR less than the first preset threshold Priority higher than UCI;And if the transmission cycle of SR is greater than the first preset threshold, and the priority of SR can be determined lower than UCI Priority.
As shown in Figure 3 and Figure 4, it is assumed that the transmission cycle T1 of SR is less than the first preset threshold, and transmission cycle T2 is greater than the One preset threshold, in Fig. 3, since the transmission cycle T1 of SR is less than the first preset threshold, the priority of SR is higher than UCI Priority, then, at the t3 moment, the end UE starts to transmit UCI, and SR occur at the t4 moment needs to be transmitted, and UCI is also at this time State in transmission then can give up UCI, and transmit SR based on the precedence information of UCI and SR.In Fig. 4, in t1 Carve, the end UE exist simultaneously SR and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined the transmission cycle T1 of SR Less than the first preset threshold, then it can determine that the priority of SR is higher than the priority of UCI, then can then be based at the t1 moment The precedence information transmits SR and can give up UCI.
In Fig. 4, at the t3 moment, the end UE starts to transmit UCI, and the t4 moment SR occurs and needs to be transmitted, and UCI is also at this time State in transmission can then determine that the priority of SR is lower than since the transmission cycle T2 of SR is greater than the first preset threshold UCI, then at the t4 moment, although occur SR need it is to be transmitted, then can be based on the precedence information of UCI and SR, after resuming Defeated UCI, and SR can be given up.If the end UE exists simultaneously SR and UCI and needs to be transmitted and lead to transfer resource conflict at the t3 moment When, it can transmit UCI based on UCI and SR precedence information and SR can be given up.
(2) duration of the transmission based on SR determines the precedence information of at least two uplink informations: the biography based on SR Defeated period or the duration of transmission, the precedence information of at least two uplink informations is determined, specifically, if the transmission of SR Duration less than the second preset threshold, then can determine SR priority be higher than UCI priority;And if the transmission of SR Duration is greater than the second preset threshold, then can determine that the priority of SR is lower than the priority of UCI.
In fig. 4, it is assumed that the duration a1 of the transmission of SR is less than the second preset threshold, and the duration a2 of its transmission Greater than the second preset threshold, then the end UE exists simultaneously SR and UCI and needs to be transmitted and lead to transfer resource conflict at the t1 moment When, since it is determined the duration a1 of the transmission of SR less than the second preset threshold, then can determine that the priority of SR is higher than UCI Priority can then be based on the precedence information then at the t1 moment, transmission SR simultaneously can give up UCI.
As shown in figure 4, at the t3 moment, the end UE starts to transmit UCI, and SR occurs in the t4 moment needs to be transmitted, and UCI at this time It can then determine that SR's is preferential since the duration a2 of the transmission of SR is greater than the second preset threshold also in the state of transmission Grade is lower than UCI, then at the t4 moment, although occur SR need it is to be transmitted, then can based on the precedence information of UCI and SR, Continue to transmit UCI, and SR can be given up.If the end UE exists simultaneously SR and UCI and needs to be transmitted and transmission is caused to provide at the t3 moment When source conflicts, it can transmit UCI based on UCI and SR precedence information and SR can be given up.
Second situation is based on uplink when the uplink information of at least two specified types includes exempting from authorization business and UCI At least one of the type of information, transmission cycle, the duration of transmission, determine the uplink information of at least two specified types Precedence information, specifically, if the type of UCI be the first kind, can determine UCI priority be higher than exempt from authorize industry The priority of business;And if the type of UCI be Second Type, can holding based on the transmission cycle or transmission for exempting from authorization business The continuous time, determine the precedence information of the uplink information of at least two specified types.
It is ACK/NACK, Second Type with the first kind when at least two uplink informations include exempting from authorization business and UCI For P-CSI, however, it is determined that the type of UCI is ACK/NACK, then can determine that the priority of UCI is higher than and exempt from the excellent of authorization business First grade, in this case, as shown in Figure 5, at the t1 moment, if the end UE exists simultaneously and exempts from authorization business and UCI needs are passed It is defeated and when transfer resource being caused to conflict, since it is determined the type of UCI is ACK/NACK, then can determine that the priority of UCI is high In the priority for exempting from authorization business, therefore, at the t1 moment, it can be based on the precedence information, prioritised transmission UCI, and can give up Authorization business is exempted from abandoning.If the end UE starts to transmit the UCI at the t1 moment, and the t2 moment occur exempting from authorization business need it is to be transmitted, And UCI continues to transmit the UCI also in the state of transmission then based on UCI and the precedence information for exempting from authorization business at this time, and It can give up and exempt from authorization business.
(1) based on the transmission cycle for exempting from authorization business, the precedence information of at least two uplink informations is determined: when UCI's When type is Second Type (for example being P-CSI), based on the duration for the transmission cycle or transmission for exempting from authorization business, determine The precedence information of the uplink information of at least two specified types, specifically, if exempting from the transmission cycle of authorization business less than Three preset thresholds, it is determined that the priority for exempting from authorization business is higher than the priority of UCI;And if the transmission cycle for exempting from authorization business is big In third predetermined threshold value, then it can determine that the priority for exempting from authorization business is lower than the priority of UCI.
As shown in Figure 5 and Figure 6, it is assumed that the transmission cycle T3 for exempting from authorization business is less than third predetermined threshold value, and transmission cycle T4 is greater than third predetermined threshold value, and in Fig. 5, the transmission cycle T3 due to exempting from authorization business is less than third predetermined threshold value, exempt from The priority of authorization business is higher than the priority of UCI, then, at the t3 moment, the end UE starts to transmit UCI, and occurs at the t4 moment Exempting from authorization business need to be to be transmitted, and UCI then based on UCI and can exempt from the excellent of authorization business also in the state of transmission at this time First grade information gives up UCI, and transmits and exempt from authorization business.In Fig. 6, at the t1 moment, the end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined to be less than third pre- by the transmission cycle T3 for exempting from authorization business If threshold value, then it can determine that the priority for exempting from authorization business is higher than the priority of UCI, then can then be based on should at the t1 moment Precedence information, transmission exempt from authorization business and can give up UCI.
In Fig. 6, at the t3 moment, the end UE starts to transmit UCI, and the t4 moment occur exempting from authorization business need it is to be transmitted, and At this time UCI also in transmission state, due to exempt from authorization business transmission cycle T4 be greater than third predetermined threshold value, then can determine Exempt from the priority of authorization business lower than UCI, then at the t4 moment, although occur exempting from authorization business need it is to be transmitted, then can be with Based on UCI and the precedence information for exempting from authorization business, continue to transmit UCI, and can give up and exempt from authorization business.If at the t3 moment, The end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, based on UCI and can exempt to authorize The precedence information of business transmits UCI and can give up and exempts from authorization business.
(2) duration based on the transmission for exempting from authorization business, the precedence information of at least two uplink informations is determined: when When the type of UCI is Second Type, based on the duration for the transmission cycle or transmission for exempting from authorization business, at least two are determined The precedence information of the uplink information of specified type, specifically, if exempting from the duration of the transmission of authorization business less than the 4th Preset threshold, it is determined that the priority for exempting from authorization business is higher than the priority of UCI;If exempting from the duration of the transmission of authorization business Greater than the 4th preset threshold, it is determined that the priority for exempting from authorization business is lower than the priority of UCI.
In fig. 6, it is supposed that exempt from the duration a3 of the transmission of authorization business less than the 4th preset threshold, and its transmission is held Continuous time a4 is greater than the 4th preset threshold, then at the t1 moment, the end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted and When transfer resource being caused to conflict, since it is determined exempting from the duration a3 of the transmission of authorization business less than the 4th preset threshold, then It can determine that the priority for exempting from authorization business is higher than the priority of UCI, then can then believe based on the priority at the t1 moment Breath, transmission exempt from authorization business and can give up UCI.
As shown in fig. 6, at the t3 moment, the end UE starts to transmit UCI, and the t4 moment occur exempting from authorization business need it is to be transmitted, And UCI is greater than the 4th preset threshold due to exempting from the duration a4 of transmission of authorization business, then also in the state of transmission at this time It can determine and exempt from the priority of authorization business lower than UCI, then at the t4 moment, although occurring exempting from authorization business needs is passed It is defeated, then it can continue to transmit UCI, and can give up and exempt from authorization business based on UCI and the precedence information for exempting from authorization business.If At the t3 moment, the end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, can be based on UCI and the precedence information for exempting from authorization business transmit UCI and can give up and exempt from authorization business.
The third situation is based on uplink when the uplink information of at least two specified types includes SR and exempts from authorization business At least one of the type of information, transmission cycle, the duration of transmission, determine the uplink information of at least two specified types Precedence information may include specifically following two specific implementation:
(1) based on SR and the transmission cycle for exempting from authorization business, the precedence information of at least two uplink informations is determined: if SR Transmission cycle be less than and exempt from the transmission cycle of authorization business, it is determined that the priority of SR is higher than the priority for exempting from authorization business;And If the transmission cycle of SR is greater than the transmission cycle for exempting from authorization business, it is determined that the priority of SR, which is lower than, exempts from the preferential of authorization business Grade.
As shown in Figure 7, it is assumed that the transmission cycle T1 of SR is less than the transmission cycle T2 for exempting from the transmission cycle T3, SR of authorization business Greater than the transmission cycle T4 for exempting from authorization business, then the end UE exists simultaneously SR and exempts from authorization business need to be to be transmitted at the t1 moment And when transfer resource being caused to conflict, since it is determined the transmission cycle T1 of SR is less than the transmission cycle T3 for exempting from authorization business, then may be used Exempt from the priority of authorization business to determine that the priority of SR is higher than, then can then be based on the precedence information at the t1 moment, pass Defeated SR simultaneously can give up and exempt from authorization business.If the end UE starts transmission and exempts from authorization business, and SR occurs at the t2 moment at the t1 moment Need to be to be transmitted, and exempt from authorization business also in transmission, then it can be given up based on SR and the precedence information for exempting from authorization business What is transmitted exempts from authorization business, and transmits SR.
And at the t3 moment, the end UE starts to transmit SR business, and it is to be transmitted to occur exempting from authorization business need at the t4 moment, and SR business since the transmission cycle T2 of SR is greater than the transmission cycle T4 for exempting from authorization business, then can determine SR also in transmission Priority be lower than and exempt from the priority of authorization business, therefore the precedence information can be based on, give up the SR transmitted, and pass It is defeated to exempt from authorization business.
(2) duration based on SR He the transmission for exempting from authorization business determines the priority letter of at least two uplink informations Breath: if the duration of the transmission of SR is less than the duration for exempting from the transmission of authorization business, it is determined that the priority of SR, which is higher than, to be exempted from The priority of authorization business;If the duration of the transmission of SR is greater than the duration for exempting from the transmission of authorization business, it is determined that SR Priority be lower than and exempt from the priority of authorization business.
As shown in Figure 7, it is assumed that the duration a1 of the transmission of SR is less than the duration a3, SR for exempting from the transmission of authorization business Transmission duration a2 be greater than exempt from authorization business transmission duration a4, then the end UE exists simultaneously at the t1 moment SR and exempt from authorization business need it is to be transmitted and when transfer resource being caused to conflict, exempt to award since it is determined the duration a1 of SR is less than The duration a3 of the transmission of power business can then determine that the priority of SR is higher than the priority for exempting from authorization business, then in t1 Moment can then be based on the precedence information, transmit SR and can give up and exempt from authorization business.If the end UE starts to pass at the t1 moment It is defeated to exempt from authorization business, and SR occur at the t2 moment need to be to be transmitted, and exempts from authorization business also in transmission, then can be based on SR and the precedence information for exempting from authorization business, give up transmitting exempt from authorization business, and transmit SR.
And at the t3 moment, the end UE starts to transmit SR business, and it is to be transmitted to occur exempting from authorization business need at the t4 moment, and SR business exempts from the duration a4 of the transmission of authorization business also in transmission, since the duration a2 of the transmission of SR is greater than, It can then determine that the priority of SR is lower than the priority for exempting from authorization business, therefore the precedence information can be based on, give up The SR of transmission, and transmit and exempt from authorization business.
4th kind of situation is based on when the uplink information of at least two specified types includes SR, exempts from authorization business and UCI At least one of the type of uplink information, transmission cycle, the duration of transmission, determine the uplink of at least two specified types The precedence information of information, specifically, if the type of UCI is the first kind, it is determined that the priority of UCI is higher than SR and exempts from The priority of authorization business;And if the type of UCI be Second Type when, transmission cycle or transmission based on uplink information Duration determines the precedence information of the uplink information of at least two specified types.
As shown in figure 8, being ACK/ with the first kind when at least two uplink informations include SR, exempt from authorization business and UCI NACK, for Second Type is P-CSI, however, it is determined that the type of UCI is ACK/NACK, then can determine that the priority of UCI is higher than SR and the priority for exempting from authorization business, in this case, as shown in Figure 8, at the t1 moment, if the end UE exists simultaneously SR, exempts from Authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined the type of UCI is ACK/NACK, then It can determine that the priority of UCI is higher than SR and therefore at the t1 moment, can be based on the priority with the priority for exempting from authorization business Information, prioritised transmission UCI, and SR can be given up and exempt from authorization business.If the end UE starts to transmit the UCI at the t1 moment, and in t2 Moment occur SR and exempt from authorization business need it is to be transmitted, and at this time UCI also in transmission state, then based on the excellent of UCI and SR First grade information continues to transmit the UCI, and can give up SR.
If the type of UCI is Second Type, the duration of transmission cycle or transmission based on uplink information, really The precedence information of the uplink information of fixed at least two specified types may include specifically following two specific implementation side Formula:
(1) based on SR, exempt from authorization business and the transmission cycle of UCI, determine the precedence information of at least two uplink informations: Firstly, the transmission cycle based on uplink information, determines the shortest uplink information of transmission cycle from uplink information;Then, it will pass Defeated period shortest uplink information, is determined as the uplink information of highest priority.
As shown in Figure 8, it is assumed that the transmission cycle T4 for exempting from authorization business is less than the transmission cycle T2 of SR, and exempts from the transmission week of SR Phase T2 is less than the transmission cycle T5 of UCI, if at the t3 moment, the end UE exists simultaneously SR, exempt from authorization business and UCI need it is to be transmitted and When transfer resource being caused to conflict, since it is determined the transmission cycle T4 for exempting from authorization business is most short, then it can determine and exempt from authorization business Priority be higher than the priority of SR and UCI and therefore at the t3 moment, the precedence information can be based on, transmission exempts to authorize industry Business, and SR and UCI can be given up.And if at the t3 moment, the end UE have begun transmission SR and UCI, occur exempting to authorize at the t4 moment Business needs to be transmitted, and SR and UCI is also in the state transmitted, therefore can be based on precedence information, give up and pass Defeated SR and UCI, and transmit and exempt from authorization business.
(2) based on SR, exempt from duration of authorization business and the transmission of UCI, to determine the preferential of at least two uplink informations Grade information: firstly, the duration of the transmission based on uplink information, determines that the duration of transmission is shortest from uplink information Uplink information;Then, by the duration of transmission shortest uplink information, it is determined as the uplink information of highest priority.
As shown in Figure 8, it is assumed that exempt from the duration a2 of transmission of the duration a4 less than SR of the transmission of authorization business, and The duration a5 for exempting from transmission of the duration a2 less than UCI of the transmission of SR, if the end UE exists simultaneously SR, exempts from the t3 moment Authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined exempting from continuing for the transmission of authorization business Time, a4 was most short, then can determine that the priority for exempting from authorization business is higher than the priority of SR and UCI, therefore, can be at the t3 moment Based on the precedence information, authorization business is exempted from transmission, and can give up SR and UCI.If the end UE has begun biography and at the t3 moment Defeated SR and UCI, occurring exempting from authorization business at the t4 moment needs to be transmitted, and SR and UCI is also in the state transmitted, therefore can To be based on precedence information, give up the SR and UCI transmitted, and transmit and exempt from authorization business.
5th kind of situation, when at least two uplink informations include scheduling request SR and UCI, the class based on uplink information At least one of type, transmission cycle, the duration of transmission, determine the precedence information of at least two uplink informations, specifically For, can the transmission cycle based on SR or transmission duration, determine the precedence information of at least two uplink informations, Including following two specific implementation:
(1) based on the transmission cycle of SR, the precedence information of at least two uplink informations is determined: if the transmission cycle of SR is small In the first preset threshold, it is determined that the priority of SR is higher than the priority of UCI;And if the transmission cycle of SR is greater than the first default threshold Value, it is determined that the priority of SR is lower than the priority of UCI.It can be found in Fig. 4, it is assumed that the transmission cycle T1 of SR is less than the first default threshold Value, and transmission cycle T2 is greater than the first preset threshold, at the t1 moment, the end UE exists simultaneously SR and UCI and needs to be transmitted and cause When transfer resource conflicts, since it is determined the transmission cycle T1 of SR can then determine the priority of SR less than the first preset threshold Priority higher than UCI transmits SR and can give up UCI then can then be based on the precedence information at the t1 moment.
In Fig. 4, at the t3 moment, the end UE starts to transmit UCI, and the t4 moment SR occurs and needs to be transmitted, and UCI is also at this time State in transmission can then determine that the priority of SR is lower than since the transmission cycle T2 of SR is greater than the first preset threshold UCI, then at the t4 moment, although occur SR need it is to be transmitted, then can be based on the precedence information of UCI and SR, after resuming Defeated UCI, and SR can be given up.If the end UE exists simultaneously SR and UCI and needs to be transmitted and lead to transfer resource conflict at the t3 moment When, it can transmit UCI based on UCI and SR precedence information and SR can be given up.
(2) duration of the transmission based on SR determines the precedence information of at least two uplink informations: if the transmission of SR Duration less than the second preset threshold, it is determined that the priority of SR be higher than UCI priority;And if the transmission of SR continues Time is greater than the second preset threshold, it is determined that the priority of SR is lower than the priority of UCI.It can be found in Fig. 4, it is assumed that the transmission of SR Duration a1 is less than the second preset threshold, and the duration a2 of its transmission is greater than the second preset threshold, then at the t1 moment, The end UE exist simultaneously SR and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined the transmission of SR it is lasting when Between a1 less than the second preset threshold, then can determine that the priority of SR is higher than the priority of UCI, then can be with then at the t1 moment Based on the precedence information, transmits SR and UCI can be given up.
As shown in figure 4, at the t3 moment, the end UE starts to transmit UCI, and SR occurs in the t4 moment needs to be transmitted, and UCI at this time It can then determine that SR's is preferential since the duration a2 of the transmission of SR is greater than the second preset threshold also in the state of transmission Grade is lower than UCI, then at the t4 moment, although occur SR need it is to be transmitted, then can based on the precedence information of UCI and SR, Continue to transmit UCI, and SR can be given up.If the end UE exists simultaneously SR and UCI and needs to be transmitted and transmission is caused to provide at the t3 moment When source conflicts, it can transmit UCI based on UCI and SR precedence information and SR can be given up.
6th kind of situation, when at least two uplink informations include exempting from authorization business and UCI, the class based on uplink information At least one of type, transmission cycle, the duration of transmission, determine the precedence information of at least two uplink informations, specifically Based on the duration for the transmission cycle or transmission for exempting from authorization business, the priority letter of at least two uplink informations can be determined Breath mainly includes following two specific implementation:
(1) based on the transmission cycle for exempting from authorization business, the precedence information of at least two uplink informations is determined: if exempting to authorize The transmission cycle of business is less than third predetermined threshold value, it is determined that the priority for exempting from authorization business is higher than the priority of UCI;And if exempting from The transmission cycle of authorization business is greater than third predetermined threshold value, it is determined that the priority for exempting from authorization business is lower than the priority of UCI.
It can be found in Fig. 6, it is assumed that the transmission cycle T3 for exempting from authorization business is less than third predetermined threshold value, and transmission cycle T4 is greater than Third predetermined threshold value, the transmission cycle T3 due to exempting from authorization business are less than third predetermined threshold value, and at the t1 moment, the end UE is existed simultaneously Exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined exempting from the transmission cycle of authorization business T3 is less than third predetermined threshold value, then can determine that the priority for exempting from authorization business is higher than the priority of UCI, then at the t1 moment, It can be then based on the precedence information, transmission exempts from authorization business and can give up UCI.
In Fig. 6, at the t3 moment, the end UE starts to transmit UCI, and the t4 moment occur exempting from authorization business need it is to be transmitted, and At this time UCI also in transmission state, due to exempt from authorization business transmission cycle T4 be greater than third predetermined threshold value, then can determine Exempt from the priority of authorization business lower than UCI, then at the t4 moment, although occur exempting from authorization business need it is to be transmitted, then can be with Based on UCI and the precedence information for exempting from authorization business, continue to transmit UCI, and can give up and exempt from authorization business.If at the t3 moment, The end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, based on UCI and can exempt to authorize The precedence information of business transmits UCI and can give up and exempts from authorization business.
(2) duration based on the transmission for exempting from authorization business, the precedence information of at least two uplink informations is determined: if Exempt from the duration of the transmission of authorization business less than the 4th preset threshold, it is determined that exempt from the priority of authorization business higher than UCI's Priority;And if the duration for exempting from the transmission of authorization business is greater than the 4th preset threshold, it is determined that exempt from the preferential of authorization business Grade is lower than the priority of UCI.
Refer to Fig. 6, it is assumed that exempt from the duration a3 of the transmission of authorization business less than the 4th preset threshold, and its transmission Duration a4 is greater than the 4th preset threshold, then at the t1 moment, the end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted And when transfer resource being caused to conflict, since it is determined exempt from the duration a3 of the transmission of authorization business less than the 4th preset threshold, It can then determine that the priority for exempting from authorization business is higher than the priority of UCI, then can then believe based on the priority at the t1 moment Breath, transmission exempt from authorization business and can give up UCI.
As shown in fig. 6, at the t3 moment, the end UE starts to transmit UCI, and the t4 moment occur exempting from authorization business need it is to be transmitted, And UCI is greater than the 4th preset threshold due to exempting from the duration a4 of transmission of authorization business, then also in the state of transmission at this time It can determine and exempt from the priority of authorization business lower than UCI, then at the t4 moment, although occurring exempting from authorization business needs is passed It is defeated, then it can continue to transmit UCI, and can give up and exempt from authorization business based on UCI and the precedence information for exempting from authorization business.If At the t3 moment, the end UE exist simultaneously exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, can be based on UCI and the precedence information for exempting from authorization business transmit UCI and can give up and exempt from authorization business.
7th kind of situation, when at least two uplink informations include SR, exempt from authorization business and UCI, based on uplink information At least one of type, transmission cycle, the duration of transmission determine the precedence information of at least two uplink informations, tool Body can the transmission cycle based on uplink information or transmission duration, determine the priority letter of at least two uplink informations Breath mainly includes following two specific implementation:
(1) based on SR, exempt from authorization business and the transmission cycle of UCI, determine the uplink information of at least two specified types Precedence information: specifically, can be primarily based on the transmission cycle of uplink information, determine and pass from least two uplink informations Defeated period shortest uplink information;Then by the shortest uplink information of transmission cycle, it is determined as the uplink information of highest priority.
As shown in Figure 9, it is assumed that the transmission cycle T4 for exempting from authorization business is less than the transmission cycle T5 of UCI, and the transmission week of UCI Transmission cycle T2 of the phase T4 less than SR then exempts from authorization business thus may determine that the transmission cycle T4 for exempting from authorization business is most short Highest priority, if the end UE starts UCI and SR at the t1 moment, and the t2 moment occur exempting from authorization business need it is to be transmitted, and SR and UCI also in transmission, then can based on SR, exempt from authorization business and the precedence information of UCI, give up the SR transmitted And UCI, and transmit and exempt from authorization business.
And at the t1 moment, the end UE exists simultaneously SR, exempt from authorization business and UCI is needed to be transmitted and led to transfer resource conflict When, since it is determined the transmission cycle T4 for exempting from authorization business is most short, then it can determine the highest priority for exempting from authorization business, therefore It can be based on the precedence information, transmission exempts from authorization business, gives up SR and UCI.
(2) based on SR, exempt from duration of authorization business and the transmission of UCI, to determine the uplink of at least two specified types The precedence information of information: specifically, can be primarily based on the duration of the transmission of uplink information, from least two uplinks The duration shortest uplink information of transmission is determined in information;Then by the duration of transmission shortest uplink information, really It is set to the uplink information of highest priority.
As shown in Figure 9, it is assumed that exempt from the duration a2 of transmission of the duration a4 less than SR of the transmission of authorization business, and Exempt from the duration a5 of transmission of the duration a2 less than UCI of the transmission of SR, if the end UE has begun transmission SR at the t1 moment And UCI, occurring exempting from authorization business at the t2 moment needs to be transmitted, and SR and UCI is also in the state transmitted, therefore can be with base In precedence information, give up the SR and UCI transmitted, and transmit and exempt from authorization business.If the end UE exists simultaneously and at the t3 moment SR, exempt from authorization business and UCI need it is to be transmitted and when transfer resource being caused to conflict, since it is determined exempting from the transmission of authorization business Duration, a4 was most short, then can determine that the priority for exempting from authorization business is higher than the priority of SR and UCI, therefore, at the t3 moment, It can be based on the precedence information, authorization business is exempted from transmission, and can give up SR and UCI.
Step 102, it is based on precedence information, transmits the uplink information of highest priority at least two uplink informations.
In addition, being based on precedence information, transmit at least two uplink informations after the uplink information of highest priority, also Other uplink informations can be given up.
In the embodiment of the present invention, when the transfer resource of at least two uplink informations has conflict, it can be believed based on uplink At least one of the type of breath, transmission cycle, the duration of transmission determine the priority letter of at least two uplink informations Breath, and it can be based on the precedence information, transmit the uplink information of highest priority at least two uplink informations.Further Ground provides a kind of contention-resolution schemes of transfer resource, for example work as branch to support multiple services UE when transmitting uplink information Multiple services UE is held when transmitting uplink information, the UCI that the SR/ of URLLC exempts from authorization business and the PUCCH of eMBB appears in identical It, can be based on the precedence information of uplink information, transmission priority highest when the period, that is, there are when transfer resource conflict Uplink information, and other uplink informations can be given up.
Figure 10 is the structural schematic diagram of one embodiment of the present of invention terminal device 1000.As shown in Figure 10, terminal device 1000 can include: determination unit 1001 and transmission unit 1002.Wherein,
Determination unit, when there is conflict for the transfer resource when at least two uplink informations, the class based on uplink information At least one of type, transmission cycle, the duration of transmission determine the precedence information of at least two uplink information;
Transmission unit transmits highest priority at least two uplink information for being based on the precedence information Uplink information.
In the embodiment of the present invention, determination unit 1001 is when there is conflict in the transfer resource of at least two uplink informations, energy At least one of enough types based on uplink information, transmission cycle, the duration of transmission, determine at least two uplink informations Precedence information, transmission unit 1002 can be based on the precedence information, transmit at least two uplink informations in priority most High uplink information.Further, to support multiple services UE when transmitting uplink information, a kind of rushing for transfer resource is provided Prominent solution, for example when transmitting uplink information, the SR/ of URLLC exempts from authorization business and eMBB when supporting multiple services UE It, can be based on the preferential of uplink information when the UCI of PUCCH appears in same time period, that is, there are when transfer resource conflict Grade information, the highest uplink information of transmission priority, and other uplink informations can be given up.
Optionally, when at least two uplink information includes SR and UCI, the determination unit 1001 is used for:
If the type of the UCI is the first kind, it is determined that the priority of the UCI is higher than the priority of the SR;
If the type of the UCI be Second Type, the duration of transmission cycle or transmission based on the SR, really The precedence information of fixed at least two uplink information.
Optionally, the determination unit 1001, is used for:
If the transmission cycle of the SR is less than the first preset threshold, it is determined that the priority of the SR is higher than the UCI's Priority;
If the transmission cycle of the SR is greater than first preset threshold, it is determined that the priority of the SR is lower than described The priority of UCI.
Optionally, the determination unit 1001, is used for:
If the duration of the transmission of the SR is less than the second preset threshold, it is determined that the priority of the SR is higher than described The priority of UCI;
If the duration of the transmission of the SR is greater than second preset threshold, it is determined that the priority of the SR is lower than The priority of the UCI.
Optionally, when at least two uplink information includes exempting from authorization business and UCI, the determination unit 1001, For:
If the type of the UCI is the first kind, it is determined that the priority of the UCI exempts from the excellent of authorization business higher than described First grade;
If the type of the UCI is Second Type, holding based on the transmission cycle for exempting from authorization business or transmission The continuous time, determine the precedence information of at least two uplink information.
Optionally, the determination unit 1001, is used for:
If the transmission cycle for exempting from authorization business is less than third predetermined threshold value, it is determined that described to exempt from the preferential of authorization business Grade is higher than the priority of the UCI;
If the transmission cycle for exempting from authorization business is greater than the third predetermined threshold value, it is determined that the authorization business of exempting from Priority is lower than the priority of the UCI.
Optionally, the determination unit 1001, is used for:
If the duration of the transmission for exempting from authorization business is less than the 4th preset threshold, it is determined that described to exempt from authorization business Priority be higher than the UCI priority;
If the duration of the transmission for exempting from authorization business is greater than the 4th preset threshold, it is determined that described to exempt to authorize The priority of business is lower than the priority of the UCI.
Optionally, when at least two uplink information includes SR and exempts from authorization business, the determination unit 1001 is used In:
If the transmission cycle of the SR is less than the transmission cycle for exempting from authorization business, it is determined that the priority of the SR is high In the priority for exempting from authorization business;
If the transmission cycle of the SR is greater than the transmission cycle for exempting from authorization business, it is determined that the priority of the SR is low In the priority for exempting from authorization business.
Optionally, when at least two uplink information includes SR and exempts from authorization business, the determination unit 1001 is used In:
If the duration of the transmission of the SR is less than the duration of the transmission for exempting from authorization business, it is determined that described The priority of SR is higher than the priority for exempting from authorization business;
If the duration of the transmission of the SR is greater than the duration of the transmission for exempting from authorization business, it is determined that described The priority of SR is lower than the priority for exempting from authorization business.
Optionally, when at least two uplink information includes SR, exempts from authorization business and UCI, the determination unit 1001, it is used for:
If the type of the UCI is the first kind, it is determined that the priority of the UCI is higher than the SR and described exempts to award The priority of power business;
If the type of the UCI be Second Type, transmission cycle or transmission based on uplink information it is lasting when Between, determine the precedence information of at least two uplink information.
Optionally, the determination unit 1001, is used for:
Transmission cycle based on uplink information determines the shortest uplink of transmission cycle from least two uplink information Information;
By the shortest uplink information of the transmission cycle, it is determined as the uplink information of highest priority.
Optionally, the determination unit 1001, is used for:
The duration of transmission based on uplink information, from least two uplink information determine transmission it is lasting when Between shortest uplink information;
By the duration of the transmission shortest uplink information, it is determined as the uplink information of highest priority.
Optionally, the first kind and Second Type are respectively confirm/not confirm ACK/NACK, aperiodic channel shape At least one of state information A-CSI, semi-continuous channel state information SP-CSI and the channel state information P-CSI in period;
The priority of the ACK/NACK is greater than the priority of the A-CSI, and the priority of the A-CSI is greater than described The priority of SP-CSI, the priority of the SP-CSI are greater than the priority of the P-SCI;
The priority of the first kind is greater than the priority of the Second Type.
Optionally, when at least two uplink information includes SR and UCI, the determination unit 1001 is used for:
The duration of transmission cycle or transmission based on the SR, determine at least two uplink information Precedence information.
Optionally, the determination unit 1001, is used for:
If the transmission cycle of the SR is less than the first preset threshold, it is determined that the priority of the SR is higher than the UCI's Priority;
If the transmission cycle of the SR is greater than first preset threshold, it is determined that the priority of the SR is lower than described The priority of UCI.
Optionally, the determination unit 1001, is used for:
If the duration of the transmission of the SR is less than the second preset threshold, it is determined that the priority of the SR is higher than described The priority of UCI;
If the duration of the transmission of the SR is greater than second preset threshold, it is determined that the priority of the SR is lower than The priority of the UCI.
Optionally, when at least two uplink information includes exempting from authorization business and UCI, the determination unit 1001, For:
Duration based on the transmission cycle for exempting from authorization business or transmission determines at least two uplinks letter The precedence information of breath.
Optionally, the determination unit 1001, is used for:
If the transmission cycle for exempting from authorization business is less than third predetermined threshold value, it is determined that described to exempt from the preferential of authorization business Grade is higher than the priority of the UCI;
If the transmission cycle for exempting from authorization business is greater than the third predetermined threshold value, it is determined that the authorization business of exempting from Priority is lower than the priority of the UCI.
Optionally, the determination unit 1001, is used for:
If the duration of the transmission for exempting from authorization business is less than the 4th preset threshold, it is determined that described to exempt from authorization business Priority be higher than the UCI priority;
If the duration of the transmission for exempting from authorization business is greater than the 4th preset threshold, it is determined that described to exempt to authorize The priority of business is lower than the priority of the UCI.
Optionally, when at least two uplink information includes SR, exempts from authorization business and UCI, the determination unit 1001, it is used for:
The duration of transmission cycle or transmission based on uplink information determines the excellent of at least two uplink information First grade information.
Optionally, the determination unit 1001, is used for:
Transmission cycle based on uplink information determines the shortest uplink of transmission cycle from least two uplink information Information;
By the shortest uplink information of the transmission cycle, it is determined as the uplink information of highest priority.
Optionally, the determination unit 1001, is used for:
The duration of transmission based on uplink information, from least two uplink information determine transmission it is lasting when Between shortest uplink information;
By the duration of the transmission shortest uplink information, it is determined as the uplink information of highest priority.
The method that terminal device 1000 can also carry out Fig. 2~Fig. 9, specific implementation can refer to Fig. 2~embodiment illustrated in fig. 9.
Figure 11 shows the structural schematic diagram of terminal device according to another embodiment of the present invention, as shown in figure 11, terminal Equipment 1100 includes: at least one processor 1110, memory 1120, at least one network interface 1130 and user interface 1140.Various components in terminal device 1100 are coupled by bus system 1150.It is understood that bus system 1150 is used Connection communication between these components of realization.Bus system 1150 further includes power bus, control in addition to including data/address bus Bus and status signal bus in addition processed.But for the sake of clear explanation, various buses are all designated as bus system in Figure 11 1150。
Wherein, user interface 1140 may include display, keyboard or pointing device (for example, mouse, trace ball (trackball), touch-sensitive plate or touch screen etc..
It is appreciated that the memory 1120 in the embodiment of the present invention can be volatile memory or non-volatile memories Device, or may include both volatile and non-volatile memories.Wherein, nonvolatile memory can be read-only memory (Read-Only Memory, ROM), programmable read only memory (Programmable ROM, PROM), erasable programmable are only Read memory (Erasable PROM, EPROM), electrically erasable programmable read-only memory (Electrically EPROM, ) or flash memory EEPROM.Volatile memory can be random access memory (Random Access Memory, RAM), use Make External Cache.By exemplary but be not restricted explanation, the RAM of many forms is available, such as static random-access Memory (Static RAM, SRAM), dynamic random access memory (Dynamic RAM, DRAM), synchronous dynamic random-access Memory (Synchronous DRAM, SDRAM), double data speed synchronous dynamic RAM (Double Data Rate SDRAM, DDRSDRAM), it is enhanced Synchronous Dynamic Random Access Memory (Enhanced SDRAM, ESDRAM), synchronous Connect dynamic random access memory (Synclink DRAM, SLDRAM) and direct rambus random access memory (Direct Rambus RAM, DRRAM).The embodiment of the present invention description system and method memory 1120 be intended to include but It is not limited to the memory of these and any other suitable type.
In some embodiments, memory 1120 stores following element, executable modules or data structures, or Their subset of person or their superset: operating system 1121 and application program 1122.
Wherein, operating system 1121 include various system programs, such as ccf layer, core library layer, driving layer etc., are used for Realize various basic businesses and the hardware based task of processing.Application program 1122 includes various application programs, such as media Player (Media Player), browser (Browser) etc., for realizing various applied business.Realize the embodiment of the present invention The program of method may be embodied in application program 1122.
In embodiments of the present invention, terminal device 1100 further include: storage on a memory 1120 and can be in processor The computer program run on 1110, computer program realize the transmission method of above-mentioned uplink information when being executed by processor 1110 Each process, and identical technical effect can be reached, to avoid repeating, which is not described herein again.
The method that the embodiments of the present invention disclose can be applied in processor 1110, or real by processor 1110 It is existing.Processor 1110 may be a kind of IC chip, the processing capacity with signal.During realization, the above method Each step can be completed by the instruction of the integrated logic circuit of the hardware in processor 1110 or software form.Above-mentioned Processor 1110 can be general processor, digital signal processor (Digital Signal Processor, DSP), dedicated Integrated circuit (Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic, Discrete hardware components.It may be implemented or execute disclosed each method, step and the logic diagram in the embodiment of the present invention.It is general Processor can be microprocessor or the processor is also possible to any conventional processor etc..In conjunction with institute of the embodiment of the present invention The step of transmission method of disclosed uplink information, can be embodied directly in hardware decoding processor and execute completion, or with decoding Hardware and software module combination in processor execute completion.Software module can be located at random access memory, flash memory, read-only storage Computer-readable the depositing of this fields such as device, programmable read only memory or electrically erasable programmable memory, register maturation In storage media.The computer readable storage medium is located at memory 1120, and processor 1110 reads the information in memory 1120, The step of completing the transmission method of above-mentioned ascending resource in conjunction with its hardware.Specifically, it is stored on the computer readable storage medium There is computer program, the method in the transmission method such as above-mentioned ascending resource is realized when computer program is executed by processor 1110 Each step of embodiment.
It is understood that the embodiment of the present invention description these embodiments can with hardware, software, firmware, middleware, Microcode or combinations thereof is realized.For hardware realization, processing unit be may be implemented in one or more specific integrated circuits (Application Specific Integrated Circuits, ASIC), digital signal processor (Digital Signal Processing, DSP), digital signal processing appts (DSP Device, DSPD), programmable logic device (Programmable Logic Device, PLD), field programmable gate array (Field-Programmable Gate Array, FPGA), general place It manages in device, controller, microcontroller, microprocessor, other electronic units for executing function of the present invention or combinations thereof.
For software implementations, can by execute the embodiment of the present invention described in function module (such as process, function etc.) come Realize technology described in the embodiment of the present invention.Software code is storable in memory and is executed by processor.Memory can With portion realizes in the processor or outside the processor.
The embodiment of the present invention also provides a kind of computer readable storage medium, and meter is stored on computer readable storage medium Calculation machine program, the computer program realize each process of the transmission method of above-mentioned uplink information, and energy when being executed by processor Reach identical technical effect, to avoid repeating, which is not described herein again.Wherein, the computer readable storage medium, such as only Read memory (Read-Only Memory, ROM), random access memory (Random Access Memory, RAM), magnetic disk Or CD etc..
In short, the foregoing is merely illustrative of the preferred embodiments of the present invention, it is not intended to limit the scope of the present invention. All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in of the invention Within protection scope.
System, device, module or the unit that above-described embodiment illustrates can specifically realize by computer chip or entity, Or it is realized by the product with certain function.It is a kind of typically to realize that equipment is computer.Specifically, computer for example may be used Think personal computer, laptop computer, cellular phone, camera phone, smart phone, personal digital assistant, media play It is any in device, navigation equipment, electronic mail equipment, game console, tablet computer, wearable device or these equipment The combination of equipment.
Computer-readable medium includes permanent and non-permanent, removable and non-removable media can be by any method Or technology come realize information store.Information can be computer readable instructions, data structure, the module of program or other data. The example of the storage medium of computer includes, but are not limited to phase change memory (PRAM), static random access memory (SRAM), moves State random access memory (DRAM), other kinds of random access memory (RAM), read-only memory (ROM), electric erasable Programmable read only memory (EEPROM), flash memory or other memory techniques, read-only disc read only memory (CD-ROM) (CD-ROM), Digital versatile disc (DVD) or other optical storage, magnetic cassettes, tape magnetic disk storage or other magnetic storage devices Or any other non-transmission medium, can be used for storage can be accessed by a computing device information.As defined in this article, it calculates Machine readable medium does not include temporary computer readable media (transitory media), such as the data-signal and carrier wave of modulation.
It should also be noted that, the terms "include", "comprise" or its any other variant are intended to nonexcludability It include so that the process, method, commodity or the equipment that include a series of elements not only include those elements, but also to wrap Include other elements that are not explicitly listed, or further include for this process, method, commodity or equipment intrinsic want Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described want There is also other identical elements in the process, method of element, commodity or equipment.
All the embodiments in this specification are described in a progressive manner, same and similar portion between each embodiment Dividing may refer to each other, and each embodiment focuses on the differences from other embodiments.Especially for system reality For applying example, since it is substantially similar to the method embodiment, so being described relatively simple, related place is referring to embodiment of the method Part explanation.

Claims (25)

1. a kind of transmission method of uplink information characterized by comprising
When there is conflict in the transfer resource of at least two uplink informations, type, transmission cycle, transmission based on uplink information At least one of duration determines the precedence information of at least two uplink information;And
Based on the precedence information, the uplink information of highest priority at least two uplink information is transmitted.
2. the method as described in claim 1, which is characterized in that when at least two uplink information include scheduling request SR and When uplink control information UCI, at least one of type, transmission cycle, the duration of transmission based on uplink information, Determine the precedence information of at least two uplink information, comprising:
If the type of the UCI is the first kind, it is determined that the priority of the UCI is higher than the priority of the SR;
If the type of the UCI is Second Type, the duration of transmission cycle or transmission based on the SR, institute is determined State the precedence information of at least two uplink informations.
3. method according to claim 2, which is characterized in that transmission cycle or transmission based on the SR it is lasting when Between, determine the precedence information of at least two uplink information, comprising:
If the transmission cycle of the SR is less than the first preset threshold, it is determined that the priority of the SR is preferential higher than the UCI's Grade;
If the transmission cycle of the SR is greater than first preset threshold, it is determined that the priority of the SR is lower than the UCI's Priority.
4. method according to claim 2, which is characterized in that transmission cycle or transmission based on the SR it is lasting when Between, determine the precedence information of at least two uplink information, comprising:
If the duration of the transmission of the SR is less than the second preset threshold, it is determined that the priority of the SR is higher than the UCI Priority;
If the duration of the transmission of the SR is greater than second preset threshold, it is determined that the priority of the SR is lower than described The priority of UCI.
5. the method as described in claim 1, which is characterized in that when at least two uplink information include exempt from authorization business and When UCI, at least one of type, transmission cycle, the duration of transmission based on uplink information determine described at least two The precedence information of uplink information, comprising:
If the type of the UCI is the first kind, it is determined that the priority of the UCI exempts from the preferential of authorization business higher than described Grade;
If the type of the UCI is Second Type, when lasting based on the transmission cycle for exempting from authorization business or transmission Between, determine the precedence information of at least two uplink information.
6. method as claimed in claim 5, which is characterized in that based on the transmission cycle for exempting from authorization business or transmission Duration determines the precedence information of at least two uplink information, comprising:
If the transmission cycle for exempting from authorization business is less than third predetermined threshold value, it is determined that the priority for exempting from authorization business is high In the priority of the UCI;
If the transmission cycle for exempting from authorization business is greater than the third predetermined threshold value, it is determined that described to exempt from the preferential of authorization business Grade is lower than the priority of the UCI.
7. method as claimed in claim 5, which is characterized in that based on the transmission cycle for exempting from authorization business or transmission Duration determines the precedence information of at least two uplink information, comprising:
If the duration of the transmission for exempting from authorization business is less than the 4th preset threshold, it is determined that described to exempt from the excellent of authorization business First grade is higher than the priority of the UCI;
If the duration of the transmission for exempting from authorization business is greater than the 4th preset threshold, it is determined that described to exempt from authorization business Priority be lower than the UCI priority.
8. the method as described in claim 1, which is characterized in that when at least two uplink information includes SR and exempts to authorize industry When business, at least one of type, transmission cycle, the duration of transmission based on uplink information determine described at least two The precedence information of the uplink information of specified type, comprising:
If the transmission cycle of the SR is less than the transmission cycle for exempting from authorization business, it is determined that the priority of the SR is higher than institute State the priority for exempting from authorization business;
If the transmission cycle of the SR is greater than the transmission cycle for exempting from authorization business, it is determined that the priority of the SR is lower than institute State the priority for exempting from authorization business.
9. the method as described in claim 1, which is characterized in that when at least two uplink information includes SR and exempts to authorize industry When business, at least one of the duration of transmission cycle, transmission based on uplink information determines at least two uplinks letter The precedence information of breath, comprising:
If the duration of the transmission of the SR is less than the duration of the transmission for exempting from authorization business, it is determined that the SR's Priority is higher than the priority for exempting from authorization business;
If the duration of the transmission of the SR is greater than the duration of the transmission for exempting from authorization business, it is determined that the SR's Priority is lower than the priority for exempting from authorization business.
10. the method as described in claim 1, which is characterized in that when at least two uplink information includes SR, exempts to authorize industry Business and when UCI, at least one of type, transmission cycle, the duration of transmission based on uplink information, determine it is described at least The precedence information of two uplink informations, comprising:
If the type of the UCI be the first kind, it is determined that the priority of the UCI be higher than the SR and it is described exempt from authorize industry The priority of business;
If the type of the UCI is Second Type, the duration of transmission cycle or transmission based on uplink information, really The precedence information of fixed at least two uplink information.
11. method as claimed in claim 10, which is characterized in that if the type of the UCI is Second Type, based on upper The transmission cycle of row information or the duration of transmission determine the priority of the uplink information of at least two specified type Information, comprising:
Transmission cycle based on uplink information determines the shortest uplink letter of transmission cycle from least two uplink information Breath;
By the shortest uplink information of the transmission cycle, it is determined as the uplink information of highest priority.
12. method as claimed in claim 10, which is characterized in that if the type of the UCI is Second Type, based on upper The transmission cycle of row information or the duration of transmission determine the priority of the uplink information of at least two specified type Information, comprising:
The duration of transmission based on uplink information determines the duration of transmission most from least two uplink information Short uplink information;
By the duration of the transmission shortest uplink information, it is determined as the uplink information of highest priority.
13. the method as described in any in claim 2 or 5, which is characterized in that
The first kind and Second Type are respectively confirm/not confirm ACK/NACK, aperiodic channel state information A- At least one of CSI, semi-continuous channel state information SP-CSI and the channel state information P-CSI in period;
The priority of the ACK/NACK is greater than the priority of the A-CSI, and the priority of the A-CSI is greater than the SP-CSI Priority, the priority of the SP-CSI is greater than the priority of the P-SCI;
The priority of the first kind is greater than the priority of the Second Type.
14. the method as described in claim 1, which is characterized in that when at least two uplink information includes scheduling request SR When with UCI, at least one of type, transmission cycle, the duration of transmission based on uplink information determine described at least two The precedence information of a uplink information, comprising:
The duration of transmission cycle or transmission based on the SR, determine the preferential of at least two uplink information Grade information.
15. the method as described in right wants 14, which is characterized in that transmission cycle or transmission based on the SR continue Time determines the precedence information of at least two uplink information, comprising:
If the transmission cycle of the SR is less than the first preset threshold, it is determined that the priority of the SR is preferential higher than the UCI's Grade;
If the transmission cycle of the SR is greater than first preset threshold, it is determined that the priority of the SR is lower than the UCI's Priority.
16. method as claimed in claim 14, which is characterized in that transmission cycle or transmission based on the SR it is lasting when Between, determine the precedence information of at least two uplink information, comprising:
If the duration of the transmission of the SR is less than the second preset threshold, it is determined that the priority of the SR is higher than the UCI Priority;
If the duration of the transmission of the SR is greater than second preset threshold, it is determined that the priority of the SR is lower than described The priority of UCI.
17. the method as described in claim 1, which is characterized in that when at least two uplink information includes exempting from authorization business When with UCI, at least one of type, transmission cycle, the duration of transmission based on uplink information determine described at least two The precedence information of a uplink information, comprising:
Duration based on the transmission cycle for exempting from authorization business or transmission, determine at least two uplink information Precedence information.
18. method as claimed in claim 17, which is characterized in that based on the transmission cycle for exempting from authorization business or transmission Duration, determine the precedence information of at least two uplink information, comprising:
If the transmission cycle for exempting from authorization business is less than third predetermined threshold value, it is determined that the priority for exempting from authorization business is high In the priority of the UCI;
If the transmission cycle for exempting from authorization business is greater than the third predetermined threshold value, it is determined that described to exempt from the preferential of authorization business Grade is lower than the priority of the UCI.
19. method as claimed in claim 17, which is characterized in that based on the transmission cycle for exempting from authorization business or transmission Duration, determine the precedence information of at least two uplink information, comprising:
If the duration of the transmission for exempting from authorization business is less than the 4th preset threshold, it is determined that described to exempt from the excellent of authorization business First grade is higher than the priority of the UCI;
If the duration of the transmission for exempting from authorization business is greater than the 4th preset threshold, it is determined that described to exempt from authorization business Priority be lower than the UCI priority.
20. the method as described in claim 1, which is characterized in that when at least two uplink information includes SR, exempts to authorize industry Business and when UCI, at least one of type, transmission cycle, the duration of transmission based on uplink information, determine it is described at least The precedence information of two uplink informations, comprising:
The duration of transmission cycle or transmission based on uplink information determines the priority of at least two uplink information Information.
21. method as claimed in claim 20, which is characterized in that transmission cycle or transmission based on uplink information continue Time determines the precedence information of the uplink information of at least two specified type, comprising:
Transmission cycle based on uplink information determines the shortest uplink letter of transmission cycle from least two uplink information Breath;
By the shortest uplink information of the transmission cycle, it is determined as the uplink information of highest priority.
22. method as claimed in claim 20, which is characterized in that transmission cycle or transmission based on uplink information continue Time determines the precedence information of the uplink information of at least two specified type, comprising:
The duration of transmission based on uplink information determines the duration of transmission most from least two uplink information Short uplink information;
By the duration of the transmission shortest uplink information, it is determined as the uplink information of highest priority.
23. a kind of terminal device characterized by comprising
Determination unit, when there is conflict for the transfer resource when at least two uplink informations, type, biography based on uplink information At least one of defeated period, the duration of transmission determine the precedence information of at least two uplink information;
Transmission unit, for being based on the precedence information, highest priority is upper in transmission at least two uplink information Row information.
24. a kind of terminal device characterized by comprising
Processor;And
It is configured as the memory of storage computer executable instructions, the executable instruction makes the processor when executed Execute the method as described in any one of claim 1~22.
25. a kind of computer readable storage medium, the computer-readable recording medium storage one or more program, described one A or multiple programs are when the electronic equipment for being included multiple application programs executes, so that the electronic equipment is executed as right is wanted Method described in asking any one of 1~22.
CN201810136516.7A 2018-02-09 2018-02-09 Uplink information transmission method and terminal equipment Active CN110139384B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810136516.7A CN110139384B (en) 2018-02-09 2018-02-09 Uplink information transmission method and terminal equipment
PCT/CN2019/073165 WO2019154127A1 (en) 2018-02-09 2019-01-25 Uplink information transmission method and terminal device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810136516.7A CN110139384B (en) 2018-02-09 2018-02-09 Uplink information transmission method and terminal equipment

Publications (2)

Publication Number Publication Date
CN110139384A true CN110139384A (en) 2019-08-16
CN110139384B CN110139384B (en) 2022-08-19

Family

ID=67548129

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810136516.7A Active CN110139384B (en) 2018-02-09 2018-02-09 Uplink information transmission method and terminal equipment

Country Status (2)

Country Link
CN (1) CN110139384B (en)
WO (1) WO2019154127A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021056581A1 (en) * 2019-09-29 2021-04-01 富士通株式会社 Uplink signal sending and receiving method and apparatus
WO2021062804A1 (en) * 2019-09-30 2021-04-08 华为技术有限公司 Feedback information transmission method and apparatus
CN112929966A (en) * 2019-12-05 2021-06-08 维沃移动通信有限公司 Method and terminal for selecting uplink transmission resources

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021031042A1 (en) * 2019-08-16 2021-02-25 富士通株式会社 Methods and apparatus for sending and receiving signals

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107645785A (en) * 2016-07-22 2018-01-30 普天信息技术有限公司 A kind of random access processing method and device

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
ERICSSON: "Summary of CSI reporting v3", 《R1-1801069》 *
INTEL CORPORATION: "UL data transmission procedures in NR", 《R1-1717396》 *
NTT DOCOMO, INC.: "Multiplexing data with different transmission durations", 《R1-1800679》 *
VIVO: "Remaining issues on UCI multiplexing", 《R1-1800995》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021056581A1 (en) * 2019-09-29 2021-04-01 富士通株式会社 Uplink signal sending and receiving method and apparatus
CN114342535A (en) * 2019-09-29 2022-04-12 富士通株式会社 Method and device for transmitting and receiving uplink signal
CN114342535B (en) * 2019-09-29 2024-03-08 富士通株式会社 Method and device for transmitting and receiving uplink signals
WO2021062804A1 (en) * 2019-09-30 2021-04-08 华为技术有限公司 Feedback information transmission method and apparatus
CN114041303A (en) * 2019-09-30 2022-02-11 华为技术有限公司 Method and device for transmitting feedback information
CN114041303B (en) * 2019-09-30 2024-01-05 华为技术有限公司 Feedback information transmission method and device
CN112929966A (en) * 2019-12-05 2021-06-08 维沃移动通信有限公司 Method and terminal for selecting uplink transmission resources
CN112929966B (en) * 2019-12-05 2022-08-05 维沃移动通信有限公司 Method and terminal for selecting uplink transmission resources

Also Published As

Publication number Publication date
WO2019154127A1 (en) 2019-08-15
CN110139384B (en) 2022-08-19

Similar Documents

Publication Publication Date Title
TWI771494B (en) Methods, apparatus, storage medium and system for determining time-domain resource
CN110139384A (en) The transmission method and terminal device of uplink information
JP2021519045A (en) Uplink transmission method and equipment
JP7005738B2 (en) Data transmission method and terminal equipment
JP2022501967A (en) Channel status information CSI processing unit occupancy time determination method and terminal equipment
US11357027B2 (en) Uplink grant-free transmission method in URLLC, terminal side device and network side device
CN108282278B (en) Data transmission method, terminal equipment and network equipment
CN109392015A (en) A kind of resource selection method and device
CN109392101A (en) A kind of data transmission method, terminal and base station
CN110034865B (en) PUCCH resource determination method, PUCCH resource receiving method, terminal equipment and network side equipment
JP2021527997A (en) Data transmission method and terminal equipment
RU2757414C1 (en) Method and apparatus for wireless communication
CN111436136A (en) Authorization-free transmission method and device
EP3493637B1 (en) Resource scheduling method and apparatus for a logical channel
CN110324854A (en) Channel state information CSI report method, device and terminal device
CN111953458B (en) PUCCH resource determination method and communication equipment
JP2021513812A (en) Response information processing methods, devices, and storage media
WO2019075762A1 (en) Scheduling request transmission method and terminal device
CN113939023A (en) Conflict processing method and device
WO2020063266A1 (en) Harq process id determination method and apparatus, terminal, and medium
US11218997B2 (en) Uplink control channel transmission method, terminal, base station and device
JP7080904B2 (en) Wireless communication methods and devices
WO2019076226A1 (en) Method and apparatus for data transmission in multiple carriers
CN109842431A (en) Method, terminal device and the network equipment of transmitting feedback information
KR102506828B1 (en) Data transfer method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant