CN110139173A - A kind of network dividing area method reducing optical transfer network end-to-end time delay - Google Patents

A kind of network dividing area method reducing optical transfer network end-to-end time delay Download PDF

Info

Publication number
CN110139173A
CN110139173A CN201910376041.3A CN201910376041A CN110139173A CN 110139173 A CN110139173 A CN 110139173A CN 201910376041 A CN201910376041 A CN 201910376041A CN 110139173 A CN110139173 A CN 110139173A
Authority
CN
China
Prior art keywords
node
time delay
combination
network
end time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910376041.3A
Other languages
Chinese (zh)
Other versions
CN110139173B (en
Inventor
李慧
王文雯
占天顺
纪越峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Posts and Telecommunications
Original Assignee
Beijing University of Posts and Telecommunications
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Posts and Telecommunications filed Critical Beijing University of Posts and Telecommunications
Priority to CN201910376041.3A priority Critical patent/CN110139173B/en
Publication of CN110139173A publication Critical patent/CN110139173A/en
Application granted granted Critical
Publication of CN110139173B publication Critical patent/CN110139173B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q11/00Selecting arrangements for multiplex systems
    • H04Q11/0001Selecting arrangements for multiplex systems using optical switching
    • H04Q11/0062Network aspects
    • H04Q11/0067Provisions for optical access or distribution networks, e.g. Gigabit Ethernet Passive Optical Network (GE-PON), ATM-based Passive Optical Network (A-PON), PON-Ring
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q11/00Selecting arrangements for multiplex systems
    • H04Q11/0001Selecting arrangements for multiplex systems using optical switching
    • H04Q11/0062Network aspects
    • H04Q2011/0073Provisions for forwarding or routing, e.g. lookup tables
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q11/00Selecting arrangements for multiplex systems
    • H04Q11/0001Selecting arrangements for multiplex systems using optical switching
    • H04Q11/0062Network aspects
    • H04Q2011/0079Operation or maintenance aspects
    • H04Q2011/0083Testing; Monitoring

Abstract

The invention discloses a kind of network dividing area methods for reducing optical transfer network end-to-end time delay, belong to technical field of photo communication.Topology to be optimized, ideal number of partitions m and participation in the election node set N are inputted first;Optionally m node constructs combination of nodes from set N;Then topology area is repartitioned to each combination of nodes, obtains corresponding topological project;Calculate each average end-to-end time delay value for combining updated topological project;Point domain topological project for finally selecting the average the smallest topological project of end-to-end time delay value optimal as time delay.The present invention can be avoided business in the end-to-end transmission of carry out business and detour, both reduced chain-circuit time delay, decrease node time delay by the reasonable network planning, so that network delay performance boost, can preferably ensure the demand of low time delay and time delay sensitive traffic.

Description

A kind of network dividing area method reducing optical transfer network end-to-end time delay
Technical field
The invention belongs to technical field of photo communication, are related to optical transport network technology, and specifically a kind of reduction optical transfer network end is arrived The network dividing area method of terminal delay time.
Background technique
Universal with Internet application with the development of communication technology, part industry and business mention the delay performance of network Extremely harsh requirement is gone out, network delay performance is increasingly becoming one of emerging hot spot of the communications field.Optical transfer network (OTN) skill Art has merged the electric layer processing and network management energy of synchronous digital system (SDH) technology based on wavelength-division multiplex (WDM) technology Power has traffic scheduling flexibly and the advantage of high capacity transmission;Further, since business level is lower and transmits for rigid conduit, OTN technology also has the advantage of low time delay and low time delay shake, is the optimal selection for constructing low time delay network.
Traditional communication network generallys use the control mode in stratified set, splits the network into multiple regions, Mei Gequ Domain includes a server, is responded to the service request in the region, meanwhile, these region servers are again by the clothes of general headquarters Business device is regulated and controled.When business is to region server request content, if the server includes this content, by region server The request is responded, otherwise from the server to headquarters server send request, and by headquarters server to the request into Row response.Although OTN has time delay advantage, chain-circuit time delay is still inevitable.Under this layering centralized control, For larger Backbone Transport Network, part of nodes between headquarters server at a distance from it is excessive, cause chain-circuit time delay compared with Greatly, thus traffic affecting delay performance.
In order to improve network delay performance, the strategy of Ying Caiyong network flattening replaces tradition with multicenter Collaborative Control Layering centerized fusion, i.e., the function of original headquarters server is dispersed to each region server, by each regional service The scheduling of device Collaborative Control.Under multicenter Collaborative Control mode, in each region server other than storing local content, also store Contents list in other region servers searches for contents list when local zone server does not include requested content And request is initiated to comprising the content and apart from nearest region server, the service request is rung by the region server It answers.Multicenter Collaborative Control mode can effectively reduce the transmission range of business, to reduce end-to-end time delay.It is above-mentioned to realize Target first has to carry out region division to network and determines regional center.When network area division and central node selection do not conform to When reason, the problems such as business of will cause detours, so that end-to-end transfer delay be made to increase.Traditional communication network such as carrier network Usually it is foundation with administrative division to carry out network division and determines central node, it is this for network delay performance perspective Division mode is simultaneously non-optimal., need to be using end-to-end time delay as foundation in order to meet increasingly harsh delay requirement, algorithm for design comes real The now classifying rationally to network area and the optimal scheduling central node in determining each region.
Summary of the invention
The present invention in view of the above-mentioned problems, using traverse by the way of, by all possible network under specific input condition Point domain scheme carries out average end-to-end time delay and calculates, and the optimal network dividing area scheme of time delay under the input condition is obtained, so that net The region division of network and the determination of central node are more reasonable, reduce the possibility that business detours, to reach reduction business end To the technical effect of terminal delay time, there is the advantage for improving network delay performance, ensureing low time delay and time delay sensitive traffic demand Aspect has realistic meaning.
Specific step is as follows:
Step 1: topological G, ideal number of partitions m that input is to be optimized, and participation in the election node set N={ n1,n2,…,na};
It is integer that the number of element, which is a, a > 1, and a, in set N;Each subregion is by a node control, i.e. m≤a;Set Element in N is whole nodes in topology G or the part of nodes met certain condition.
Step 2: optional m node constructs a combination of nodes from a node of set N, form altogetherIt is a Combination of nodes.
Step 3: repartitioning topology area to each combination of nodes, corresponding topological project is obtained
It is divided into following steps:
Step 301, input topology G and i-th of combination of nodes C to be optimizedi={ n1,n2,…,nm}。
Step 302, for be not belonging in topological G combination CiSome node A, the section is successively calculated with dijkstra's algorithm Point A to combination CiIn end-to-end routed path between each node, and calculate separately the corresponding end-to-end time delay value in each path t1,t2,…,tm
The step of each routed path respectively corresponds an end-to-end time delay value, end-to-end time delay calculation method is as follows:
Step 1: being directed to some routed path, according to the bandwidth that network topology attribute and user specify, obtain the routing road The node and list of link that diameter passes through.
Step 2: according to the length of every section of link in list of link, calculating the time delay of each section of link, summation obtains link Overall delay Tl
Step 3: judge the location of each node that the routed path passes through, in conjunction with the time delay of each node of bandwidth calculation, Summation obtains node overall delay Tn
Step 4: further obtaining end-to-end overall delay Tt=Tl+Tn
Step 303, to be not belonging to combination CiNode A, select minimum value t from m end-to-end time delay valuek, and by time delay Minimum value tkNode n in corresponding combinationkCentral node as node A.
tk=min { t1,t2,…,tm}。
Step 304, similarly is each not belonging to combination CiNode, can be according to minimum end-to-end time delay value, in combination Ci Inside find respective central node.
Step 305 is directed to combination CiInterior certain node nk, the group is respectively not belonging to according to end-to-end minimal time delay value is corresponding The node of conjunction is as node nkSubordinate's node;
Step 306, by node nkIt is a region with its subordinate's node division, updates topology G, obtains combination CiIt is corresponding Topological project Gi
Topological project GiIn include m region, each region includes a central node and its whole subordinate node, node And the link between node is identical as original topology G.
Step 307, similarly, each combination of nodes is optimized respectively, and it is topological to obtain corresponding updates of each combination;
Including the central node in combination and each subordinate's node respectively connected in the topology of each update.
Step 4: calculating each average end-to-end time delay value for combining updated topological project;
It is divided into following steps:
First, it is directed to updated some topological project Gi, including node set are as follows:It is right Each node in set R calculates point domain routed path of the node into set R between other each nodes;
Each of set R node will be used as source node, and by other nodes in set R as destination node, successively Calculate corresponding point of domain routed path of sourcesink node;Detailed process is as follows:
Input divides the topological project G in regioni, source node src and destination node des;Obtain source node and destination node respectively Affiliated regional center node HsrcAnd Hdes.Then, judge source node src and destination node des regional center node whether phase Together, if so, source node src and destination node des belong to the same area, divide domain routed path using dijkstra's algorithm calculating Path: for src → Hsrc→des;Otherwise not same area carries out recycling dijkstra's algorithm after dividing as follows according to nodal community Calculate routed path:
Finally, a point domain routed path set is obtained
Then, each divide domain routed path corresponding end-to-end time delay value in set of computations P, and form set Q;
End-to-end time delay results set
Finally, according to end-to-end time delay results set Q, topological project G is calculatediThe whole network be averaged end-to-end time delay value Ti
Wherein j=1,2 ..., | Gi|×(|Gi|-1)。
Similarly, the whole network for obtaining each updated topological project is averaged end-to-end time delay value;
Step 5: point domain topological project for selecting the average the smallest topological project of end-to-end time delay value optimal as time delay.
The present invention has the advantages that
(1) a kind of network dividing area method for reducing optical transfer network end-to-end time delay, can be according to the number of regions of input and full The node of sufficient condition is that constraint carries out region division and selection area central node to network with time delay, can be effectively reduced industry The end-to-end transfer delay of business improves network delay performance.
(2) a kind of network dividing area method for reducing optical transfer network end-to-end time delay, is based on multicenter Collaborative Control feature, root Segmentation shortest path is carried out using classical dijkstra's algorithm according to the sourcesink node and affiliated area of business to calculate, and industry can be obtained The most short point of domain routing of business, reduces chain-circuit time delay.
(3) a kind of network dividing area method for reducing optical transfer network end-to-end time delay, the time delay based on OTN network are constituted, can The end-to-end time delay of business is obtained according to the bandwidth and router-level topology of OTN equipment feature and specific business, to obtain network Average end-to-end time delay is the basis for carrying out low time delay network dividing area.
Detailed description of the invention
Fig. 1 is a kind of step flow chart for the network dividing area method for reducing optical transfer network end-to-end time delay of the present invention;
Fig. 2 is a kind of step flow chart for dividing domain route computing method of the present invention;
Fig. 3 is a kind of step flow chart of OTN teleservice time-delay calculation method of the present invention;
Fig. 4 is the six node topology figures for not dividing domain used in the embodiment of the present invention;
Fig. 5 is the six node topology figures for having divided domain used in the embodiment of the present invention.
Specific embodiment
Below in conjunction with attached drawing and example, the present invention is described in further detail.
A kind of network dividing area method for reducing optical transfer network end-to-end time delay of the present invention, as shown in Figure 1, being divided into following step It is rapid:
Step 1: topological G, ideal number of partitions m that input is to be optimized, and participation in the election node set N={ n1,n2,…,na};
It is integer that the number of element, which is a, a > 1, and a, in set N;Each subregion is by a node control, i.e. m≤a;Set Element in N is whole nodes in topology G or the part of nodes met certain condition.
Step 2: optional m node constructs a combination of nodes from a node of set N, form altogetherIt is a Combination of nodes.
Wherein, m central node in participation in the election central node set N is included in each combination of nodes.
Step 3: repartitioning topology area to each combination of nodes, corresponding topological project is obtained;
It is divided into following steps:
Step 301, input topology G and i-th of combination of nodes C to be optimizedi={ n1,n2,…,nm}。
Step 302, for be not belonging in topological G combination CiSome node A, the section is successively calculated with dijkstra's algorithm Point A to combination CiIn end-to-end routed path between each node, and calculate separately the corresponding end-to-end time delay value in each path t1,t2,…,tm
Each routed path respectively corresponds an end-to-end time delay value, as shown in figure 3, the step of end-to-end time delay calculation method It is rapid as follows:
The first step, input topological diagram G and certain business traffic=(B, P);
Wherein, B is the bandwidth of business, user specified value;P is the routed path of the business, and each business has unique road By path.
Second step obtains the node set n that this routed path P is passed throughlist={ n1,n2,…,nkAnd link set llist ={ l1,l2,…,lk-1}。
Third step, according to llistThe chain-circuit time delay of calculating business;
To llistIn each of the links li, obtain the length of this link in topology GWhenWhen this The time delay of linkWhenWhen this link time delay
The then total link time delay of this businessWherein, i=1,2 ..., k-1.
4th step, according to nlistThe node time delay of calculating business;
To nlistIn each node ni, its time delay is calculated according to its present positionThen when total node of this business ProlongWherein, i=1,2 ..., k.
Node niTime delay valueIt is as follows with the relationship of its present position:
Wherein:
(1) time delay of intermediate node and the exchanged form of selection are related, if by light layer devices reality when signal passes through node Existing photosphere is through, thenFor light break-through time delay Tthrough;OtherwiseFor electric switching delay Tswitch
(2) electric switching delay TswitchWith light break-through time delay TthroughIt is related with specific capacity of equipment, it needs as the case may be To be arranged.
(3) time delay T is encapsulatedencapWith decapsulation time delay TdecapWith capacity of equipment, service bandwidth and specific mapping multiplexing road Diameter is related:
When service bandwidth is greater than capacity of equipment, mapping is packaged after need to splitting to business again;Every increase level-one Multiplexing, time delay increase 0.512us.It is inversely carried out when due to decapsulation according to encapsulation mapping multiplexed path, Tencap=Tdecap
If a) capacity of equipment meets service bandwidth, Tencap=Tdecap=0.512 × u, wherein u is business mapping multiplexing Series;
If b) capacity of equipment is unable to satisfy service bandwidth, former business is carried out to be split as v subservice and 1 remaining industry Business, so that original service bandwidth=equipment maximum rate × v+ surplus lines bandwidth, Tencap=Tdecap=0.512 × (u1×v+ u2), wherein u1And u2Respectively the mapping of subservice and surplus lines is multiplexed series.
(4) FEC coding delay TcodeWith fec decoder time delay TdecodeWith complexity, service bandwidth and the business of FEC algorithm Transmitting range is related, and specific time delay value should be determined according to selected FEC algorithm and specific application scenarios.
The corresponding end-to-end overall delay T of routed path of this business is calculated in 5th stept=Tl+Tn
Step 303, to be not belonging to combination CiNode A, select minimum value t from m end-to-end time delay valuek, and by time delay Minimum value tkNode n in corresponding combinationkCentral node as node A.
tk=min { t1,t2,…,tm}。
Step 304, similarly is each not belonging to combination CiNode, can be according to minimum end-to-end time delay value, in combination Ci Inside find respective central node.
Step 305 is directed to combination CiInterior certain node nk, the group is respectively not belonging to according to end-to-end minimal time delay value is corresponding The node of conjunction is as node nkSubordinate's node;
Step 306, by node nkIt is a region with its subordinate's node division, updates topology G, obtains combination CiIt is corresponding Topological project Gi
Topological project GiIn include m region, each region includes a central node and its whole subordinate node, node And the link between node is identical as original topology G.
Step 307, similarly, each combination of nodes is optimized respectively, and it is topological to obtain corresponding updates of each combination;
Including the central node in combination and each subordinate's node respectively connected in the topology of each update.
Step 4: calculating each average end-to-end time delay value for combining updated topological project;
To each combination of nodes CiTopology area is repartitioned, topological project G is obtainedi, and calculate its it is average end-to-end when Prolong value Ti.Topological project GiIt should make to be not belonging to combination C in former topology GiOther nodes to the central node time delay belonging to it most It is small.
It is divided into following steps:
First, it is directed to updated some topological project Gi, including node set are as follows:It is right Each node in set R calculates point domain routed path of the node into set R between other each nodes;
As shown in Fig. 2, detailed process is as follows: input divides the topological project G in regioni, source node src and destination node des; Obtain source node and destination node respectively affiliated regional center node HsrcAnd Hdes.Then, judge source node src and destination node Des whether same area, if so, source node src and destination node des central node having the same, utilize dijkstra's algorithm meter Point counting domain routed path path: for src → Hsrc→des;Otherwise not same area carries out sharp again after dividing as follows according to nodal community Routed path is calculated with Dijkstra algorithm:
Finally obtain final point domain routed path set
Then, each divide domain routed path corresponding end-to-end time delay value in set of computations P, and form set Q;
End-to-end time delay results set
Finally, according to end-to-end time delay results set Q, topological project G is calculatediThe whole network be averaged end-to-end time delay value Ti
Wherein j=1,2 ..., | Gi|×(|Gi|-1)。
Similarly, the whole network for obtaining each updated topological project is averaged end-to-end time delay value;
Step 5: point domain topological project for selecting the average the smallest topological project of end-to-end time delay value optimal as time delay.
Embodiment 1
It is illustrated by taking six node topologies as an example, it is assumed that whole nodes can be used as centromere in the network The network is divided into two regions by point, the specific steps are as follows:
1, six node topologies of input are as topology G, ideal number of partitions m=2 to be optimized, and participate in the election of central node set N= {n1,n2,n3,n4,n5,n6}。
2, it according to topology G to be optimized, ideal number of partitions m and participation in the election central node set N, obtains all altogether A central node combination.
Wherein, it is respectively as follows: in each central node combination comprising 2 central nodes in participation in the election central node set N
C1=(n1,n2),C2=(n1,n3),C3=(n1,n4),C4=(n1,n5),C5=(n1,n6),C6=(n2,n3),C7 =(n2,n4),C8=(n2,n5),C9=(n2,n6),C10=(n3,n4),C11=(n3,n5),C12=(n3,n6),C13=(n4, n5),C14=(n4,n6),C15=(n5,n6)。
3, C is combined to each central nodei, according to CiTopology area is repartitioned, topological project G is obtainedi, and calculate Its average end-to-end time delay value Ti
With C1=(n1,n2) topological project G1For, the specific steps are as follows:
A) topology G and central node to be optimized are inputted and combines C1=(n1,n2)。
B) C is not belonging to each in topological G1=(n1,n2) node, calling divide domain method for routing and end-to-end time delay Calculation method successively calculates the node to C1In two central nodes end-to-end time delay value, concrete outcome is as shown in the table:
Other nodes Central node Time delay value/us Central node Time delay value/us
n3 n1 1656.998 n2 1156.448
n4 n1 1907.048 n2 1406.498
n5 n1 1656.998 n2 1156.448
n6 n1 655.948 n2 905.948
C) C is not belonging to each in topological G1=(n1,n2) node, in C1In find a corresponding node p conduct Its central node makes the end-to-end time delay value ratio of node-to-node p to C1In other nodes it is small, it may be assumed that
Other nodes Central node Time delay value/us
n3 n2 1156.448
n4 n2 1406.498
n5 n2 1156.448
n6 n1 655.948
D) it is a region by each central node and its subordinate's node division, updates topology G, obtain topological project G1, That is:
4, whole topological project G are obtained according to the method described above1,G2,…,G15, to each topological project Gi, calculate its whole network Average end-to-end time delay value Ti
To calculate G1Time delay value T1For, the specific steps are as follows:
A) the topological project G of subregion is inputted1
B) R={ n1,n2,n3,n4,n5,n6, it is topology G1Node set.To each node in set R, calculating should Node other nodes into R divide domain routed path, obtain route results set:
P={ p12,p13,p14,p15,p16,p21,p23,p24,p25,p26,p31,p32,p34,p35,p36, p41,p42,p43,p45, p46,p51,p52,p53,p54,p56,p61,p62,p63,p64,p64}
C) according to route results set P, topology G is calculated1In each node to the end-to-end time delay value of other nodes, held To terminal delay time results set:
Q={ t12,t13,t14,t15,t16,t21,t23,t24,t25,t26,t31,t32,t34,t35,t36, t41,t42,t43,t45, t46,t51,t52,t53,t54,t56,t61,t62,t63,t64,t64}
D) according to end-to-end time delay results set Q, topological project G is calculated1The whole network be averaged end-to-end time delay value T1Pair, i.e., T1In all time delay values be averaged.
5, whole topological project G are obtained according to the method described above1,G2,…,G15Whole end-to-end time delay value T1,T2,…, T15, concrete outcome is as follows:
6, the average the smallest topological project G of end-to-end time delay value is selected15As optimization topological project Go, GoIt is as final to obtain To time delay it is optimal divide domain topological.As shown in figure 5, specifically dividing domain situation as follows:
Region Central node Other nodes
area1 n5 n3,n4
area2 n6 n1,n2
Embodiment 2
As shown in figure 5, six node topology G have divided region, node is calculated separately in this topology to (n3,n4),(n5, n6),(n5,n1),(n3,n6),(n4,n1) between divide domain routed path.
(A) source node src=n3, destination node des=n4
1, input has divided topological G, the source node src=n in region3, destination node des=n4
2, source is obtained according to the region division of G, the central node of destination node is respectively Hsrc=n5、Hdes=n5
3, area1 is belonged to according to the region division source of G, destination node, therefore D-algorithm is utilized to calculate src → Hdes→ des, Path=[n can be obtained3,n5,n4]。
(B) source node src=n5, destination node des=n6
1, input has divided topological G, the source node src=n in region5, destination node des=n6
2, source is obtained according to the region division of G, the central node of destination node is respectively Hsrc=n5、Hdes=n6
3, area1, area2, and node n are adhered to separately according to the region division source of G, destination node5、n6It is regional center Node, therefore D-algorithm is utilized to calculate src → des, path=[n can be obtained5,n6]。
(C) source node src=n5, destination node des=n1
1, input has divided topological G, the source node src=n in region5, destination node des=n1
2, source is obtained according to the region division of G, the central node of destination node is respectively Hsrc=n5、Hdes=n6
3, area1, area2, and node n are adhered to separately according to the region division source of G, destination node5For center node, node n1Non-central node, therefore dijkstra's algorithm is utilized to calculate src → HdesPath=[n can be obtained in → des5,n6,n1]。
(D) source node src=n3, destination node des=n6
1, input has divided topological G, the source node src=n in region3, destination node des=n6
2, source is obtained according to the region division of G, the central node of destination node is respectively Hsrc=n5、Hdes=n6
3, area1, area2, and node n are adhered to separately according to the region division source of G, destination node3Non-central node, node n6For center node, therefore D-algorithm is utilized to calculate src → HsrcPath=[n can be obtained in → des3,n5,n6]。
(E) source node src=n4, destination node des=n1
1, input has divided topological G, the source node src=n in region4, destination node des=n1
2, source is obtained according to the region division of G, the central node of destination node is respectively Hsrc=n5、Hdes=n6
3, area1, area2, and node n are adhered to separately according to the region division source of G, destination node4、n1Non-central node, Therefore D-algorithm is utilized to calculate src → Hsrc→HdesPath=[n can be obtained in → des4,n5,n6,n1]。
Embodiment 3
As shown in figure 5, six node topology G have divided region, it is known that business routed path P=[n4,n5,n6,n1], it is assumed that Service bandwidth B=1000MHz calculates in this topology node to (n4,n1) between business end-to-end time delay.It is false for convenience of narration If topological interior joint is 100Gbps OTN equipment, intermediate node is dispatched using photosphere.Specific step is as follows:
1, topology G, business traffic=(B, P)=(1000MHz, [n is inputted4,n5,n6,n1]);
2, this business institute is obtained through node set nlist={ n4,n5,n6,n1, link set llist={ (n4,n5), (n5,n6),(n6,n1)};
3, according to llistThe chain-circuit time delay of calculating business:
That is, the end-to-end link overall delay T of this businessl=1750.1us.
4, according to nlistThe node time delay of calculating business:
Node Present position Node time delay is constituted
n4 Source Tswitch+Tencap+Tcode
n5 It is intermediate Tthrough
n6 It is intermediate Tthrough
n1 Place Tswitch+Tdecap+Tdecode
Above-mentioned each value is described as follows:
(1) the electric switching delay of OTN equipment and light break-through time delay are related with specific capacity of equipment, and value is herein Tswitch=2us, Tthrough=0.05us;
(2) capacity of equipment is 100Gbps in this example, and service bandwidth 1000MHz is split without to business.
Specific business mapping path is traffic → ODU0 → ODU1 → OTU1, i.e. business mapping multiplexing series u=3, Therefore Tencap=Tdecap=0.512 × 3=1.536us.
(3) the FEC algorithm selected in this example it is long away from/ultra long haul transmission scene knit stitch to different business transmission rate not Together, transceiver overall latency measured value is as shown in the table:
Business packed maps to OTU1 in this example, i.e., the transmission rate in the line side OTN is 2.5Gbps, therefore has transmitting-receiving to set The sum of standby overall latency Tcode+Tdecode=149.4us.
That is, passing through the end-to-end node overall delay that can be calculated this business are as follows:
Tn=2 × Tswitch+2×Tthrough+Tencap+Tdecap+Tcode+Tdecode
=2 × 2+2 × 0.05+1.536+1.536+149.4=156.572us
5, the overall delay of this business is calculated:
Tt=Tl+Tn=1750.1+156.572=1906.672us.
Embodiment 1 is a kind of specific implementation case for the network dividing area method for reducing optical transfer network end-to-end time delay of the present invention Example.Embodiment 2,3 is one kind point domain route computing method used in the present invention and a kind of OTN teleservice time-delay calculation side The specific implementation case of method.Can be seen that a different point domain schemes from the data in embodiment 1 in table shown in step 5 will be right The end-to-end average delay of network generates different influences, when network dividing area and reasonable central node selection, can effectively reduce The end-to-end time delay value of network.The result final from embodiment 1 can be seen that through the invention a kind of reduction optical transfer network end to Optimal network dividing area scheme can be obtained in the network dividing area method of terminal delay time, keeps the average end-to-end time delay of network optimal, network Delay performance promoted, can preferably ensure the delay requirement of business.

Claims (3)

1. a kind of network dividing area method for reducing optical transfer network end-to-end time delay, which is characterized in that specific step is as follows:
Step 1: topological G, ideal number of partitions m that input is to be optimized, and participation in the election node set N={ n1,n2,…,na};
It is integer that the number of element, which is a, a > 1, and a, in set N;Each subregion is by a node control, i.e. m≤a;In set N Element be whole nodes or the part of nodes that meets certain condition in topology G;
Step 2: optional m node constructs a combination of nodes from a node of set N, form altogetherA node Combination;
Step 3: repartitioning topology area to each combination of nodes, corresponding topological project is obtained;
It is divided into following steps:
Step 301, input topology G and i-th of combination of nodes C to be optimizedi={ n1,n2,…,nm};
Step 302, for be not belonging in topological G combination CiSome node A, node A is successively calculated with dijkstra's algorithm and is arrived Combine CiIn end-to-end routed path between each node, and calculate separately the corresponding end-to-end time delay value t in each path1, t2,…,tm
Step 303, to be not belonging to combination CiNode A, select minimum value t from m end-to-end time delay valuek, and time delay is minimum Value tkNode n in corresponding combinationkCentral node as node A;
tk=min { t1,t2,…,tm};
Step 304, similarly is each not belonging to combination CiNode, can be according to minimum end-to-end time delay value, in combination CiInside look for To respective central node;
Step 305 is directed to combination CiInterior certain node nk, the combination is respectively not belonging to according to end-to-end minimal time delay value is corresponding Node is as node nkSubordinate's node;
Step 306, by node nkIt is a region with its subordinate's node division, updates topology G, obtains combination CiIt is corresponding to open up Flutter scheme Gi
Topological project GiIn include m region, each region includes a central node and its whole subordinate node, node and section Link between point is identical as original topology G;
Step 307, similarly, each combination of nodes is optimized respectively, and it is topological to obtain corresponding updates of each combination;
Including the central node in combination and each subordinate's node respectively connected in the topology of each update;
Step 4: calculating each average end-to-end time delay value for combining updated topological project;
Step 5: point domain topological project for selecting the average the smallest topological project of end-to-end time delay value optimal as time delay.
2. a kind of network dividing area method for reducing optical transfer network end-to-end time delay as described in claim 1, which is characterized in that institute In the step 302 stated, the step of each routed path respectively corresponds an end-to-end time delay value, end-to-end time delay calculation method, is such as Under:
Step 1: being directed to some routed path, according to the bandwidth that network topology attribute and user specify, obtain routed path warp The node and list of link crossed;
Step 2: according to the length of every section of link in list of link, calculate the time delay of each section of link, summation obtain link it is total when Prolong Tl
Step 3: the location of each node that the routed path passes through is judged, in conjunction with the time delay of each node of bandwidth calculation, summation Obtain node overall delay Tn
Step 4: further obtaining end-to-end overall delay Tt=Tl+Tn
3. a kind of network dividing area method for reducing optical transfer network end-to-end time delay as described in claim 1, which is characterized in that institute The step of stating four is divided for following steps:
First, it is directed to updated some topological project Gi, including node set are as follows:To set Each node in R calculates point domain routed path of the node into set R between other each nodes;
Each of set R node will be used as source node, and other nodes in set R are successively calculated as destination node Corresponding point of domain routed path of sourcesink node;Detailed process is as follows:
Input divides the topological project G in regioni, source node src and destination node des;It is respectively affiliated to obtain source node and destination node Regional center node HsrcAnd Hdes;Then, judge whether the regional center node of source node src and destination node des are identical, if It is that source node src and destination node des belong to the same area, divides domain routed path path using dijkstra's algorithm calculating: for src→Hsrc→des;Otherwise not same area carries out recycling dijkstra's algorithm to calculate routing after dividing as follows according to nodal community Path:
Finally, a point domain routed path set is obtained
Then, each divide domain routed path corresponding end-to-end time delay value in set of computations P, and form set Q;
End-to-end time delay results set
Finally, according to end-to-end time delay results set Q, topological project G is calculatediThe whole network be averaged end-to-end time delay value Ti
Wherein j=1,2 ..., | Gi|×(|Gi|-1);
Similarly, the whole network for obtaining each updated topological project is averaged end-to-end time delay value.
CN201910376041.3A 2019-05-07 2019-05-07 Network domain division method for reducing end-to-end time delay of optical transport network Active CN110139173B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910376041.3A CN110139173B (en) 2019-05-07 2019-05-07 Network domain division method for reducing end-to-end time delay of optical transport network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910376041.3A CN110139173B (en) 2019-05-07 2019-05-07 Network domain division method for reducing end-to-end time delay of optical transport network

Publications (2)

Publication Number Publication Date
CN110139173A true CN110139173A (en) 2019-08-16
CN110139173B CN110139173B (en) 2020-03-27

Family

ID=67576406

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910376041.3A Active CN110139173B (en) 2019-05-07 2019-05-07 Network domain division method for reducing end-to-end time delay of optical transport network

Country Status (1)

Country Link
CN (1) CN110139173B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113193993A (en) * 2021-04-19 2021-07-30 天津大学 Aerospace Ethernet topology optimization method
CN116346705A (en) * 2023-05-29 2023-06-27 广东省电信规划设计院有限公司 Optical transmission network intelligent deployment method and device based on time delay measurement and calculation

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102325039A (en) * 2011-06-09 2012-01-18 国网电力科学研究院 ASON (Automatically Switched Optical Network) optimization design method orienting to electric power control business
CN107070794A (en) * 2016-12-08 2017-08-18 航天东方红卫星有限公司 A kind of low rail information network optimal network benefit delay constraint method for routing

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102325039A (en) * 2011-06-09 2012-01-18 国网电力科学研究院 ASON (Automatically Switched Optical Network) optimization design method orienting to electric power control business
CN107070794A (en) * 2016-12-08 2017-08-18 航天东方红卫星有限公司 A kind of low rail information network optimal network benefit delay constraint method for routing

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
NADIA BRAHMI,OSMAN N. C. YILMAZ ,ETC.: ""Deployment Strategies for Ultra-Reliable and Low-Latency Communication in Factory Automation"", 《2015 IEEE GLOBECOM WORKSHOPS (GC WKSHPS)》 *
余景文,李俊杰: ""光网络低时延特性分析及优化思路"", 《电信网技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113193993A (en) * 2021-04-19 2021-07-30 天津大学 Aerospace Ethernet topology optimization method
CN113193993B (en) * 2021-04-19 2022-05-10 天津大学 Aerospace Ethernet topology optimization method
CN116346705A (en) * 2023-05-29 2023-06-27 广东省电信规划设计院有限公司 Optical transmission network intelligent deployment method and device based on time delay measurement and calculation
CN116346705B (en) * 2023-05-29 2023-09-19 广东省电信规划设计院有限公司 Optical transmission network intelligent deployment method and device based on time delay measurement and calculation

Also Published As

Publication number Publication date
CN110139173B (en) 2020-03-27

Similar Documents

Publication Publication Date Title
CN103650435B (en) Routing traffic method of adjustment, device and controller
US6882627B2 (en) Methods and apparatus for selecting multiple paths taking into account shared risk
US7889675B2 (en) Method and system for multi-layer network routing
CN106789707B (en) A kind of software definition Packet Transport Network overall situation service dynamic optimization method and device
CN103379032B (en) The acquisition methods and device, sub-route computational entity of cross-domain end-to-end route
CN103346979B (en) Flow distribution method and equipment in SPBM network
CN108111411B (en) Backbone network and dynamic path planning system and planning method thereof
CN101083548A (en) Multi-domain routing computation method and system
CN104518961B (en) It is grouped the leading method and device of optical transport network
CN105472484B (en) A kind of electric power backbone Optical Transmission Network OTN radio frequency channel proportional routing Wavelength allocation method
KR20100071855A (en) A resource management and recursive path computation for real-time automatic path setup at multi-layer transport network
CN108966053A (en) A kind of cross-domain route computing method of multiple-domain network dynamic domain sequence and device
CN110139173A (en) A kind of network dividing area method reducing optical transfer network end-to-end time delay
Zheng et al. Dependence-aware service function chain embedding in optical networks
CN108833142A (en) A kind of network plan method of multi-core optical fiber planning business
CN105007223A (en) Optical network dynamic multicast routing wavelength allocation method based on optical hierarchical structure
CN105430538B (en) A kind of inter-domain routing method based on optical-fiber network subtopology figure
CN103795641B (en) The optical network resource management method mapped based on multidimensional frame
CN108174446B (en) Network node link resource joint distribution method with minimized resource occupancy
CN104917677A (en) Data stream forwarding control method and system
CN101742366B (en) QOS-assuring parameterized label forwarding method for optical packet network
CN104702510B (en) Message forwarding method and device in a kind of RPR networks
CN114745227B (en) Electric power business network slicing time delay calculation method and device based on FlexE and SPN technologies
CN110062301A (en) Route selection method, device, equipment and storage medium
CN104506442A (en) Multipoint-to-multipoint multicast business optical grooming method for flexible grid optical network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant