CN110130881A - Method for rapidly identifying water plugging position of oil field horizontal well - Google Patents

Method for rapidly identifying water plugging position of oil field horizontal well Download PDF

Info

Publication number
CN110130881A
CN110130881A CN201910314148.5A CN201910314148A CN110130881A CN 110130881 A CN110130881 A CN 110130881A CN 201910314148 A CN201910314148 A CN 201910314148A CN 110130881 A CN110130881 A CN 110130881A
Authority
CN
China
Prior art keywords
water
horizontal well
oilfield horizontal
well
oilfield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910314148.5A
Other languages
Chinese (zh)
Other versions
CN110130881B (en
Inventor
朱洪征
姚建国
甘庆明
吕亿明
王百
崔文昊
常莉静
苏祖波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201910314148.5A priority Critical patent/CN110130881B/en
Publication of CN110130881A publication Critical patent/CN110130881A/en
Application granted granted Critical
Publication of CN110130881B publication Critical patent/CN110130881B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/10Locating fluid leaks, intrusions or movements

Landscapes

  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Geophysics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Production Of Liquid Hydrocarbon Mixture For Refining Petroleum (AREA)
  • Examining Or Testing Airtightness (AREA)

Abstract

The invention discloses a method for quickly judging and identifying the water plugging position of an oil field horizontal well, which comprises the following steps of firstly, determining the water breakthrough type according to the salt-containing data of a water breakthrough; secondly, collecting physical properties and production dynamic data of an oil well reservoir, and determining the lower limit of oil outlet of a well in the stratum and the development condition of a seam network of an injection well; then, the water well in the stratum analyzes the plane oil-containing condition by utilizing the lower limit standard of oil outlet, qualitatively judges the water outlet end by combining the actual production condition of the surrounding oil well, and determines the water outlet end by the dynamic response relation of the water well; finally, comprehensively utilizing the judged water outlet end, and determining the water outlet conditions of different layer sections to determine the water outlet section by combining the chromatographic value of each spray point of a single well; and the water plugging position is determined by combining the pressure and the transformation position. The method starts with the existing dynamic and static data of the horizontal well, quickly identifies the water layer section, and further adopts the measures of water control and oil stabilization; meanwhile, the method is suitable for two water-meeting types of the water-meeting injected water and the water-meeting stratum water.

Description

A kind of oilfield horizontal well water blockoff position quick recognition method
Technical field
The invention belongs to oilwell water shutoff fields, are related to a kind of oilfield horizontal well water blockoff position quick recognition method.
Background technique
The casing programme of horizontal well is different from straight well, it is made to be easier to the phenomenon that big volume production water, water occur in oil recovery process Horizontal well can bring about consumption stratum energy once being discharged, and reduce oil production, reduce oil well pump efficiency, aggravate the corrosion of pipeline, equipment And fouling, a series of problems, such as increasing the load of oil-water process system.The key of water plugging of horizontal well is to be quickly found out out water level It sets.
Oil field High water cut horizontal well inflow direction is surveyed mainly by water injection well dynamic authentication, dynamic monitoring, production profile at present The means of examination determine.Water injection well dynamic authentication is to judge water side by changing water injection well working system tracking well water To, but since horizontal well pair is answered, water injection well is more, proving period is longer, is only applicable to Fractured water breakthrough horizontal well.Dynamic monitoring side Method mainly utilizes waterflood front test, tracer monitoring to judge inflow direction, but by reservoir micro-fractures development and heterogeneity It influences, seam gateway system complexity, inflow direction is caused to judge that difficulty is big, the period is long, at high cost.Producing profile testing is to utilize external force Produced fluid cross section tester device is delivered to perforated interval by oil jacket annulus by (cable or coiled tubing, crawl device etc.), in pumping unit Do not stop using turbine flowmeter, water holdup tool real-time monitoring flow, aqueous in the case of taking out, but complex process, testing cost are high.
Summary of the invention
It is an object of the invention to overcome the above-mentioned prior art, it is quick to provide a kind of oilfield horizontal well water blockoff position Sentence knowledge method.
In order to achieve the above objectives, the present invention is achieved by the following scheme:
A kind of oilfield horizontal well water blockoff position quick recognition method, comprising the following steps:
Step 1: according to the water type after oilfield horizontal well water breakthrough, determining water breakthrough type;
Step 2: when water breakthrough type is to see water flooding, determining the fuel-displaced lower limit of oilfield horizontal well;When water breakthrough type is to see When injecting water, the seam net development condition of oilfield horizontal well is determined;
Step 3: practical raw according to the fuel-displaced lower limit and surrounding oil well of oilfield horizontal well when water breakthrough type is to see water flooding Situation is produced, determines the water outlet of oilfield horizontal well;When water breakthrough type is to see injection water, developed by the seam net of oilfield horizontal well Situation and dynamic response relationship, determine the water outlet of oilfield horizontal well;
Step 4: according to the chromatographic parameter value of each specking in water outlet, determining the water exit end of oilfield horizontal well;
Step 5: according to the water exit end of oilfield horizontal well, determining the water blockoff position of oilfield horizontal well.
A further improvement of the present invention lies in that:
Step 1 method particularly includes:
According to the water type after oilfield horizontal well water breakthrough, water breakthrough type is determined;Water type is CaCl after oilfield horizontal well water breakthrough2 When, water breakthrough type is to see water flooding;Water type after oilfield horizontal well water breakthrough is Na2SO4When, water breakthrough type is to see injection water.
The fuel-displaced lower limit of oilfield horizontal well is determined in step 2 method particularly includes:
According to the reservoir properties of oilfield horizontal well and Production development data, draw the resistance of oilfield horizontal well, interval transit time, Resistance, interval transit time, permeability and the oil reservoir of permeability and core intersection and aqueous relational graph and oilfield horizontal well The relational graph of thickness and production capacity determines the fuel-displaced lower limit of oilfield horizontal well.
The seam net development condition of oilfield horizontal well is determined in step 2 method particularly includes:
The corresponding relationship of long with depositing the liquid measure of pressure-break of oilfield horizontal well is obtained by underground microseism, and passes through measurement Ground liquid measure of depositing to obtain pressure-break long;Length is stitched according to transformation and draws seam net distribution map, is sentenced according to seam net distribution map and is known oil field level The water injection well of well is exchanged information;The seam net development condition for determining oilfield horizontal well of exchanging information with water injection well is grown according to pressure-break.
Dynamic response relationship in step 3 is the aqueous and Advance Water Injection amount of oilfield horizontal well, water injection intensity and adds up The relationship of water filling.
Step 4 method particularly includes:
According to the specking chromatography value of oilfield horizontal well water outlet, the water exit end of oilfield horizontal well is determined;When water breakthrough type is When seeing water flooding, the region that the specking chromatographic parameter value of oilfield horizontal well is lower than standard value is the water exit end of oilfield horizontal well;When Water breakthrough type is when seeing injection water, and the region that the specking chromatographic parameter value of oilfield horizontal well is higher than standard value is oilfield horizontal well Water exit end.
Step 5 method particularly includes:
It is pre- between water blockoff position and water exit end when water breakthrough type is to see water flooding according to the water exit end of oilfield horizontal well 50m is stayed, determines the water blockoff position of oilfield horizontal well;It is pre- between water blockoff position and water exit end when water breakthrough type is to see injection water 100m is stayed, determines the water blockoff position of oilfield horizontal well.
Compared with prior art, the invention has the following advantages:
Start with by using existing oilfield horizontal well dynamic and static data, determine the fuel-displaced lower limit of insight layer well and sees Inject the seam net development condition of well;And then determine water outlet, the chromatographic parameter of each specking is combined in determining water outlet Value, can quickly recognize water section, determine water blockoff position, and then take water and oil control measure;Meanwhile, it is capable to be suitable for seeing injection Water and see two kinds of water breakthrough types of water flooding, strong applicability.The existing theoretical foundation of this method, and have measured data support, Neng Gouzhun Really sentence and know horizontal well water exit position, provides foundation for the formulation of High water cut horizontal well control measures.
Detailed description of the invention
Fig. 1 is flow chart of the method for the present invention;
Fig. 2 is shown in water flooding horizontal well CP-X oil saturation isogram for of the invention;
Fig. 3 is that injection water horizontal well CP-Y adds up water filling distribution map for of the invention seeing.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
It should be noted that description and claims of this specification and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to the embodiment of the present invention described herein can in addition to illustrating herein or Sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that cover Cover it is non-exclusive include, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to Step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, product Or other step or units that equipment is intrinsic.
The invention will be described in further detail with reference to the accompanying drawing:
Referring to Fig. 1, a kind of oilfield horizontal well water blockoff of the invention position quick recognition method is provided according to water breakthrough well saliferous first Material determines water breakthrough type, collects oil reservoir physical property and Production development data, determines the fuel-displaced lower limit of insight layer well and sees injection Well stitches net development condition;Insight layer well utilizes fuel-displaced lower limit standard, analyzes plane oil-containing situation, in conjunction with surrounding oil well reality The condition of production, qualitatively judge water outlet;See that injection well by dynamic response relationship, determines water outlet.Then it comprehensively utilizes The water outlet judged determines different interval water outlet status in conjunction with each specking chromatography value height of individual well;Last combination pressure, Position is transformed, determines packer block-up position.
Specific technical solution is:
Step 1: according to the saliferous data after oilfield horizontal well water breakthrough, determining water breakthrough type;After oilfield horizontal well water breakthrough Water type is CaCl2When, water breakthrough type is to see water flooding;Water type after oilfield horizontal well water breakthrough is Na2SO4When, water breakthrough type is See injection water.
Step 2: when water breakthrough type is to see water flooding, according to the reservoir properties of oilfield horizontal well and Production development data, Resistance, interval transit time, permeability and the core intersection of drafting oilfield horizontal well and aqueous relational graph and oilfield horizontal well Resistance, interval transit time, permeability and core intersection and production capacity relational graph, determine the fuel-displaced lower limit of oilfield horizontal well;When Water breakthrough type is to obtain the corresponding pass of long with depositing the liquid measure of pressure-break of oilfield horizontal well when seeing injection water by underground microseism System, and to obtain pressure-break long for the ground liquid measure of depositing by measuring;Seam net distribution map is drawn according to pressure-break is long, according to seam net distribution map The water injection well for sentencing knowledge oilfield horizontal well is exchanged information;The seam for determining oilfield horizontal well of exchanging information with water injection well is grown according to transformation seam Net development condition;Wherein, long with depositing the liquid measure of pressure-break is positively correlated.
Step 3: when water breakthrough type is to see water flooding, according to the fuel-displaced lower limit of oilfield horizontal well, plane oil-containing situation is It is no be lower than fuel-displaced lower limit standard, it is no, be not discharged;It is, in conjunction with surrounding oil well practical condition, to determine the water outlet of oilfield horizontal well End;When water breakthrough type be see injection water when, by oilfield horizontal well seam net development condition and oilfield horizontal well it is aqueous and super The relationship of preceding water injection rate, water injection intensity and accumulative water filling, whether water injection intensity and accumulative water injection rate are excessive, no, are not discharged; It is the water outlet for determining oilfield horizontal well;
Step 4: according to the specking chromatography value of the water outlet of oilfield horizontal well, determining the water exit end of oilfield horizontal well;When seeing Water type is when seeing water flooding, and the specking chromatographic parameter value of oilfield horizontal well is going out for oilfield horizontal well lower than the region of standard value Water section;When water breakthrough type is to see injection water, the region that the specking chromatographic parameter value of oilfield horizontal well is higher than standard value is oil field The water exit end of horizontal well.
Step 5: according to the water exit end of oilfield horizontal well, when water breakthrough type is to see water flooding, water blockoff position and water exit end Between reserve 50m, determine the water blockoff position of oilfield horizontal well;When water breakthrough type is to see injection water, water blockoff position and water exit end Between reserve 100m, determine the water blockoff position of oilfield horizontal well.
Embodiment 1
Water breakthrough well data: more 10 sections of cluster pressure break of CP-X segmentation, add sand 335m3, acid adding 50m3, initial stage daily output liquid of going into operation 9.6m3, produce liquid 4.8t daily, aqueous 41.7%, saliferous 34486mg/l, water type CaCl after water breakthrough2
Step 1: water breakthrough type sentences knowledge.
Since the well saliferous is higher (general > 30000mg/l), water type CaCl2 is shown in water flooding.
Step 2: collecting CP-X well reservoir properties and Production development data.
Resistance, interval transit time, permeability and the core intersection of drafting oilfield horizontal well and aqueous relational graph, and oil Resistance, interval transit time, permeability and the core intersection of water in field horizontal well and the relational graph of production capacity determine the fuel-displaced offline of horizontal well Resistance is 30 Ω, and the velocity of sound is greater than 220 μm/m, and core intersection is greater than 10m.
Step 3: determining water outlet.
According to fuel-displaced lower limit standard, plane oil-containing situation is analyzed, in conjunction with the actual condition of production of surrounding oil well, referring to fig. 2, Determine that the well water outlet is southeastern direction.
Step 4: determining water exit end.
According to chromatography value, oiliness and the actual condition of production of surrounding oil well, judge on the south water exit end 2705m.
Step 5: determine water blockoff position: combination pressure, transformation position are reserved 50m, are determined between water blockoff position and water exit end Packer block-up position.
Embodiment 2
Water breakthrough well data: more 15 sections of cluster pressure break of CP-Y segmentation, add sand 491m3, acid adding 84m3, there is 3 mouthfuls of corresponding wells before operation Accumulative super note 7421m3;Operation initial stage produces liquid 14.03m daily3, produce liquid 0t, aqueous 100%, saliferous 9644mg/l, water type daily Na2SO4
Step 1: water breakthrough type sentences knowledge
Since the well saliferous is lower (general < 15000mg/l), water type is sodium sulphate, sees injection water.
Step 2: collecting CP-X well reservoir properties and Production development data.
The corresponding relationship of long with depositing the liquid measure of pressure-break of oilfield horizontal well is obtained by underground microseism, and passes through measurement Ground liquid measure of depositing to obtain pressure-break long;Seam net distribution map is drawn according to pressure-break is long, it is horizontal to sentence knowledge oil field according to seam net distribution map The water injection well of well is exchanged information;The seam net development condition for determining oilfield horizontal well of exchanging information with water injection well is grown according to transformation seam; Wherein, long with depositing the liquid measure of pressure-break is positively correlated.Pressure-break length=α deposits ground liquid measure, and α is positive correlation coefficient.
Step 3: determining water outlet.
By the seam net development condition and the aqueous and Advance Water Injection amount of oilfield horizontal well of oilfield horizontal well, water injection intensity with And the relationship of accumulative water filling, southern water breakthrough, is shown in Fig. 3 from the point of view of water drive distribution.
Step 4: determining water exit end.
The following chromatography value of well depth 3255m is high, physical property is good, Yi Jianshui;
Step 5: determining water blockoff position.
By water outlet fragment position and combination pressure and transformation situation, reserved between water blockoff position and water exit end 100m determines packer block-up position.
The above content is merely illustrative of the invention's technical idea, and this does not limit the scope of protection of the present invention, all to press According to technical idea proposed by the present invention, any changes made on the basis of the technical scheme each falls within claims of the present invention Protection scope within.

Claims (7)

1. a kind of oilfield horizontal well water blockoff position quick recognition method, which comprises the following steps:
Step 1: according to the water type after oilfield horizontal well water breakthrough, determining water breakthrough type;
Step 2: when water breakthrough type is to see water flooding, determining the fuel-displaced lower limit of oilfield horizontal well;When water breakthrough type is to see injection When water, the seam net development condition of oilfield horizontal well is determined;
Step 3: when water breakthrough type is to see water flooding, according to the fuel-displaced lower limit of oilfield horizontal well and surrounding oil well actual production feelings Condition determines the water outlet of oilfield horizontal well;When water breakthrough type is to see injection water, pass through the seam net development condition of oilfield horizontal well With dynamic response relationship, the water outlet of oilfield horizontal well is determined;
Step 4: according to the chromatographic parameter value of each specking in water outlet, determining the water exit end of oilfield horizontal well;
Step 5: according to the water exit end of oilfield horizontal well, determining the water blockoff position of oilfield horizontal well.
2. oilfield horizontal well water blockoff according to claim 1 position quick recognition method, which is characterized in that the step 1 Method particularly includes:
According to the water type after oilfield horizontal well water breakthrough, water breakthrough type is determined;Water type is CaCl after oilfield horizontal well water breakthrough2When, see Water type is to see water flooding;Water type after oilfield horizontal well water breakthrough is Na2SO4When, water breakthrough type is to see injection water.
3. oilfield horizontal well water blockoff according to claim 1 position quick recognition method, which is characterized in that the step 2 The fuel-displaced lower limit of middle determining oilfield horizontal well method particularly includes:
According to the reservoir properties of oilfield horizontal well and Production development data, resistance, the interval transit time, infiltration of oilfield horizontal well are drawn Resistance, interval transit time, permeability and the core intersection of rate and core intersection and aqueous relational graph and oilfield horizontal well With the relational graph of production capacity, the fuel-displaced lower limit of oilfield horizontal well is determined.
4. oilfield horizontal well water blockoff according to claim 1 position quick recognition method, which is characterized in that the step 2 The seam net development condition of middle determining oilfield horizontal well method particularly includes:
The corresponding relationship of long with depositing the liquid measure of pressure-break of oilfield horizontal well is obtained by underground microseism, and being deposited by what is measured It is long that ground liquid measure obtains pressure-break;Long draw is stitched according to transformation and stitches net distribution map, is sentenced according to seam net distribution map and is known oilfield horizontal well Water injection well is exchanged information;The seam net development condition for determining oilfield horizontal well of exchanging information with water injection well is grown according to pressure-break.
5. oilfield horizontal well water blockoff according to claim 1 position quick recognition method, which is characterized in that the step 3 In dynamic response relationship be the aqueous and Advance Water Injection amount of oilfield horizontal well, water injection intensity and the accumulative relationship filled the water.
6. oilfield horizontal well water blockoff according to claim 1 position quick recognition method, which is characterized in that the step 4 Method particularly includes:
According to the specking chromatography value of oilfield horizontal well water outlet, the water exit end of oilfield horizontal well is determined;When water breakthrough type is insight When layer water, the region that the specking chromatographic parameter value of oilfield horizontal well is lower than standard value is the water exit end of oilfield horizontal well;Work as water breakthrough Type is when seeing injection water, and the region that the specking chromatographic parameter value of oilfield horizontal well is higher than standard value is the water outlet of oilfield horizontal well Section.
7. oilfield horizontal well water blockoff according to claim 1 position quick recognition method, which is characterized in that the step 5 Method particularly includes:
It is reserved between water blockoff position and water exit end according to the water exit end of oilfield horizontal well when water breakthrough type is to see water flooding 50m determines the water blockoff position of oilfield horizontal well;When water breakthrough type is to see injection water, reserved between water blockoff position and water exit end 100m determines the water blockoff position of oilfield horizontal well.
CN201910314148.5A 2019-04-18 2019-04-18 Method for rapidly identifying water plugging position of oil field horizontal well Active CN110130881B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910314148.5A CN110130881B (en) 2019-04-18 2019-04-18 Method for rapidly identifying water plugging position of oil field horizontal well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910314148.5A CN110130881B (en) 2019-04-18 2019-04-18 Method for rapidly identifying water plugging position of oil field horizontal well

Publications (2)

Publication Number Publication Date
CN110130881A true CN110130881A (en) 2019-08-16
CN110130881B CN110130881B (en) 2022-05-06

Family

ID=67570403

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910314148.5A Active CN110130881B (en) 2019-04-18 2019-04-18 Method for rapidly identifying water plugging position of oil field horizontal well

Country Status (1)

Country Link
CN (1) CN110130881B (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4722394A (en) * 1986-06-12 1988-02-02 Shell Oil Company Determining residual oil saturation by radioactively analyzing injected CO2 and base-generating tracer-providing solution
US4876449A (en) * 1988-05-12 1989-10-24 Conoco Inc. Reservoir evaluation using partitioning tracer
US20010036667A1 (en) * 2000-04-26 2001-11-01 Davoud Tayebi Reservoir monitoring
CN1664575A (en) * 2005-03-14 2005-09-07 辽河石油勘探局 Method for monitoring petroleum reservoir performance by using biomarkers
US20060144588A1 (en) * 2004-10-22 2006-07-06 Core Laboratories Lp Method for determining tracer concentration in oil and gas production fluids
CN103132993A (en) * 2013-03-26 2013-06-05 西北大学 Method for gradually recognizing oil layer and water layer in low-permeability complex lithologic oil deposit
CN103615237A (en) * 2013-12-02 2014-03-05 天津大港油田圣达科技有限公司 Microelement interwell tracer agent and application thereof
CN104564006A (en) * 2015-02-04 2015-04-29 中国海洋石油总公司 Hypotonic gas well fracturing water-producing capacity judgment method
US20160003040A1 (en) * 2012-12-21 2016-01-07 Restrack As Tracers
US20160209391A1 (en) * 2015-01-21 2016-07-21 Baker Hughes Incorporated High temperature tracers for downhole detection of produced water
CN205778834U (en) * 2016-05-27 2016-12-07 西安百惠油气技术服务有限公司 Dragging water detection taken out by horizontal well twin packer double card list and production profile surveys process pipe string
CN106593425A (en) * 2016-12-08 2017-04-26 中国石油天然气股份有限公司 Method and device for identifying reservoir water top position and fluid type
CN106779229A (en) * 2016-12-26 2017-05-31 中国石油天然气股份有限公司 Prediction method for water plugging potential of high-water-cut horizontal well
CN108505990A (en) * 2018-07-05 2018-09-07 西南石油大学 A kind of down-hole oil tube tracer transmission groundwater prospecting method and device
US20180298274A1 (en) * 2015-04-30 2018-10-18 Johnson Matthey Public Limited Company Oil field chemical delivery fluids, methods for their use in the targeted delivery of oil field chemicals to subterranean hydrocarbon reservoirs and methods for tracing fluid flow

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4722394A (en) * 1986-06-12 1988-02-02 Shell Oil Company Determining residual oil saturation by radioactively analyzing injected CO2 and base-generating tracer-providing solution
US4876449A (en) * 1988-05-12 1989-10-24 Conoco Inc. Reservoir evaluation using partitioning tracer
US20010036667A1 (en) * 2000-04-26 2001-11-01 Davoud Tayebi Reservoir monitoring
US20060144588A1 (en) * 2004-10-22 2006-07-06 Core Laboratories Lp Method for determining tracer concentration in oil and gas production fluids
CN1664575A (en) * 2005-03-14 2005-09-07 辽河石油勘探局 Method for monitoring petroleum reservoir performance by using biomarkers
US20160003040A1 (en) * 2012-12-21 2016-01-07 Restrack As Tracers
CN103132993A (en) * 2013-03-26 2013-06-05 西北大学 Method for gradually recognizing oil layer and water layer in low-permeability complex lithologic oil deposit
CN103615237A (en) * 2013-12-02 2014-03-05 天津大港油田圣达科技有限公司 Microelement interwell tracer agent and application thereof
US20160209391A1 (en) * 2015-01-21 2016-07-21 Baker Hughes Incorporated High temperature tracers for downhole detection of produced water
CN104564006A (en) * 2015-02-04 2015-04-29 中国海洋石油总公司 Hypotonic gas well fracturing water-producing capacity judgment method
US20180298274A1 (en) * 2015-04-30 2018-10-18 Johnson Matthey Public Limited Company Oil field chemical delivery fluids, methods for their use in the targeted delivery of oil field chemicals to subterranean hydrocarbon reservoirs and methods for tracing fluid flow
CN205778834U (en) * 2016-05-27 2016-12-07 西安百惠油气技术服务有限公司 Dragging water detection taken out by horizontal well twin packer double card list and production profile surveys process pipe string
CN106593425A (en) * 2016-12-08 2017-04-26 中国石油天然气股份有限公司 Method and device for identifying reservoir water top position and fluid type
CN106779229A (en) * 2016-12-26 2017-05-31 中国石油天然气股份有限公司 Prediction method for water plugging potential of high-water-cut horizontal well
CN108505990A (en) * 2018-07-05 2018-09-07 西南石油大学 A kind of down-hole oil tube tracer transmission groundwater prospecting method and device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴晓明: "华庆地区长6油藏裂缝见水规律研究", 《中国优秀硕士学位论文全文数据库.工程科技Ⅰ辑》 *
王百等: "水平井井下取样找水技术", 《石油钻采工艺》 *

Also Published As

Publication number Publication date
CN110130881B (en) 2022-05-06

Similar Documents

Publication Publication Date Title
CN104915512B (en) It is a kind of to predict oil field produced degree and the method for moisture content
CN104879103B (en) Layered water injection effect analysis method
CN110056336A (en) A kind of shale air cleft network pressure splits operation pressure curve automatic diagnosis method
CN106522928B (en) Well testing method for unstable pressure drop of well logging head by stopping pump after acidizing and fracturing
CN108104801A (en) Horizontal well tracer liquid production profile testing pipe column and method
CN107092719A (en) Method and device for identifying water injection dominant channel and selecting microsphere plugging particle size
CN109707373B (en) Horizontal well-vertical well bidirectional tracing method based on fluid production profile test and inter-well tracing
CN105114061A (en) Multi-parameter combination test rapid water exploration pipe column and method for immobile pipe column of horizontal well
CN109236273A (en) Oil field development Production development data processing method
CN107066769A (en) Suitable for the efficient acidifying design method of ultra deep slit formation carbonate reservoir
CN104975827B (en) Predict the material balance method of carbon dioxide flooding oil reservoir index
CN105696985B (en) Four notes nine adopt the determination method and the efficient flooding method of combination flooding of the efficient flooding method of combination flooding under the conditions of well pattern
CN108241772A (en) Consider Tunnel Gushing method for determination of amount in the crack artesian aquifer of multiple factors
CN111075423A (en) Method for determining water injection development well spacing of low-permeability sandstone reservoir
CN105507887A (en) Process method for injecting tracer to make water exploration in high-water-content horizontal well and pipe column
CN106651158B (en) Quantitative evaluation method for water injection development effectiveness degree of ultra-low permeability tight reservoir horizontal well
CN103643928A (en) Step-by-step deep profile control method based on pressure field and flow velocity field distribution
CN110259421A (en) Fractured compact oil reservoir water injection energy supplementing method
CN102392636B (en) Underground fluid channel parameter description method for water drive development of sandstone reservoir
RU2318993C1 (en) Method for watered oil pool development
CN104632150B (en) The method that the offshore oilfield difference reasonable Liquid output of well group determines
CN109522619A (en) Low-permeability oilfield periodic oil extraction method
CN103048090A (en) Method for evaluating plugging action of plugging agent on crack
CN205445599U (en) High-water-content horizontal well tracer injection water exploration double-sealing single-clamp process pipe column
CN106150476A (en) A kind of system of the viscous suction bit freezing risk predicting drill string

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant