CN110106792A - Steel reinforcement cage binding device and manufacture craft - Google Patents
Steel reinforcement cage binding device and manufacture craft Download PDFInfo
- Publication number
- CN110106792A CN110106792A CN201910501134.4A CN201910501134A CN110106792A CN 110106792 A CN110106792 A CN 110106792A CN 201910501134 A CN201910501134 A CN 201910501134A CN 110106792 A CN110106792 A CN 110106792A
- Authority
- CN
- China
- Prior art keywords
- main reinforcement
- stirrup
- fixed
- piece
- stirrup piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Wire Processing (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
The invention discloses a kind of steel reinforcement cage binding device and manufacture crafts, it is related to constructing device field, steel reinforcement cage binding device includes fixed pedestal and bracket, side plate, positioning plate and baffle are provided on fixed pedestal, sleeve is fixed on baffle, it is provided with L-type main reinforcement locating piece on bracket, is provided with positioning groove on positioning plate;Manufacture craft is the following steps are included: S1: processing stirrup piece;S2: stirrup piece is fixed on fixed pedestal;S3: main reinforcement passes through every stirrup piece;S4: main reinforcement is fixedly connected with stirrup piece;First the stirrup piece made in advance can be fixed on fixed pedestal by fixed pedestal, main reinforcement is set to pass through stirrup piece again, main reinforcement and stirrup piece are fixed together again, main reinforcement is when passing through stirrup piece, stirrup will not cause to limit to main reinforcement, while stirrup piece can shift to an earlier date and be processed on the lathe of factory, then transport to construction site and carry out the making step of next step, the time for making stirrup at the construction field (site) can be saved, work efficiency is high.
Description
Technical field
The present invention relates to constructing device field more particularly to steel reinforcement cage binding device and manufacture crafts.
Background technique
With the development of bridge technology, the bridge of Long span gradually increases, and major diameter, overlength column and pile foundation steel bar cage are got over
It is applied come more, but is had the following problems in traditional fabrication of reinforcing cage technique in the design:
1, main reinforcement is first fixed, then passes through main reinforcement with stirrup, but due to more main reinforcement position restrictions, it can be very when wearing stirrup
Difficulty is worn;
It 2, is typically now to make steel reinforcement cage at the construction field (site), time consumption is long, and working efficiency is low.
Summary of the invention
The object of the invention is that devising a kind of steel reinforcement cage binding device and manufacture craft to solve the above-mentioned problems.
The present invention through the following technical solutions to achieve the above objectives:
A kind of steel reinforcement cage binding device, for the fixed stirrup piece made and main reinforcement, including fixed pedestal, fixed base
The two sides of seat upper surface are provided with two blocks of side plates being parallel to each other, and are additionally provided on fixed pedestal for positioning determining for stirrup piece
Position plate, positioning plate is parallel with side plate, and positioning plate is located between two blocks of side plates, the both ends of the stirrup piece side opposite with two blocks of side plates
Contact is squeezed, one end of fixed pedestal is fixed with baffle, and side surrounding of the baffle close to fixed pedestal center is fixed with multiple use
In the sleeve of positioning main reinforcement, one end of a main reinforcement is placed in a sleeve.
Further, steel reinforcement cage binding device further includes the bracket of multiple N-shapeds, and the lower end of each bracket is fixed on fixed base
On seat, two blocks of side plates are respectively positioned between the both sides of each bracket, and each bracket is equidistantly set close to the side at fixed pedestal center
It is equipped with multiple L-type main reinforcement locating pieces, the L-type main reinforcement of the sleeve for being located at baffle top or two sides and multiple bracket same positions
Locating piece in the same horizontal line, is placed through above baffle and the main reinforcement of two sides square socket middle part is determined with L-type main reinforcement is placed on
On the block of position.
Further, multiple positioning grooves are provided on positioning plate, it is recessed that the bottom of a stirrup piece is placed on a positioning
In slot.
Manufacture craft based on steel reinforcement cage binding device, which comprises the following steps:
S1: production stirrup piece;
S2: stirrup piece is fixed on fixed pedestal;
S3: main reinforcement passes through every stirrup piece, is placed on corresponding L-type main reinforcement locating piece;
S4: main reinforcement is fixedly connected with stirrup piece.
Further, in S3, main reinforcement is vertical with stirrup.
The beneficial effects of the present invention are: first the stirrup piece made in advance can be fixed by the effect of fixed pedestal
On fixed pedestal, then main reinforcement is made to pass through stirrup piece, finally main reinforcement and stirrup piece are fixed together again, change traditional fabrication
The mode of steel reinforcement cage, when passing through stirrup piece, stirrup will not cause to limit main reinforcement to main reinforcement, while stirrup piece can shift to an earlier date in work
It is processed on the lathe of factory, then transports to construction site and carry out the making step of next step, can be saved at the construction field (site)
The time of stirrup is made, work efficiency is high.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of steel reinforcement cage binding device of the present invention and manufacture craft;
Fig. 2 is the structural schematic diagram of fixed pedestal in steel reinforcement cage binding device of the present invention and manufacture craft;
Fig. 3 is the structural schematic diagram of bracket in steel reinforcement cage binding device of the present invention and manufacture craft;
Fig. 4 is the structural schematic diagram of stirrup piece in steel reinforcement cage binding device of the present invention and manufacture craft;
Wherein corresponding appended drawing reference are as follows:
1- fixed pedestal, 2- side plate, 3- main reinforcement, 4- stirrup piece, 5- baffle, 6- sleeve, 7- positioning plate, 8- positioning groove,
9- bracket, 10-L type main reinforcement locating piece.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings:
As shown in Figure 1, Figure 2, Figure 3, Figure 4, a kind of steel reinforcement cage binding device, for fixed 4 He of stirrup piece made
Main reinforcement 3, including fixed pedestal 1, the two sides of 1 upper surface of fixed pedestal are provided with two blocks of side plates 2 being parallel to each other, two blocks of side plates
2, for fixing the both ends of stirrup piece 4, are additionally provided with positioning plate 7, positioning plate 7 is for fixing and positioning stirrup piece on fixed pedestal 1
4 position, positioning plate 7 is parallel with side plate 2, and positioning plate 7 is located between two blocks of side plates 2, the both ends of stirrup piece 4 and two blocks of side plates 2
Opposite side squeezes contact, and one end of fixed pedestal 1 is fixed with baffle 5, side four of the baffle 5 close to 1 center of fixed pedestal
It is fixed with multiple sleeves 6 for being used to position main reinforcement 3 week, baffle 5 and sleeve 6 are used to the position that limitation main reinforcement 3 is installed, a master
One end of muscle 3 is placed in a sleeve 6.
As shown in Figure 1, Figure 2, Figure 3 shows, steel reinforcement cage binding device further includes the bracket 9 of multiple N-shapeds, bracket 9, each bracket 9
Lower end be fixed on fixed pedestal 1, two blocks of side plates 2 are respectively positioned between the both sides of each bracket 9, and each bracket 9 is close to fixed
The side at 1 center of pedestal is equidistantly provided with multiple L-type main reinforcement locating pieces 10, and L-type main reinforcement locating piece 10 is for positioning main reinforcement 3
Support is provided for main reinforcement 3 when position and installation, one is located at the sleeve 6 and multiple 9 same positions of bracket of 5 top of baffle or two sides
L-type main reinforcement locating piece 10 in the same horizontal line, be placed through 3 middle part of main reinforcement of the top of baffle 5 and two sides square socket 6 and put
It sets on L-type main reinforcement locating piece 10.
As shown in Fig. 2, being provided with multiple positioning grooves 8 on positioning plate 7, positioning groove 8 is for fixing and positioning stirrup piece 4
Position, the bottom of a stirrup piece 4 is placed in a positioning groove 8.
Manufacture craft based on steel reinforcement cage binding device, which comprises the following steps:
S1: production stirrup piece 4;
S2: stirrup piece 4 is fixed on fixed pedestal 1;
S3: main reinforcement 3 passes through every stirrup piece 4, is placed on corresponding L-type main reinforcement locating piece 10, main reinforcement 3 is vertical with stirrup;
S4: main reinforcement 3 is fixedly connected with stirrup piece 4.
The working principle of steel reinforcement cage binding device of the present invention and manufacture craft is as follows:
The unified processing stirrup piece 4 on the lathe of factory can be shifted to an earlier date, then transported again to construction site, by stirrup piece 4
Be fixed on fixed pedestal 1 by side plate 2 and positioning groove 8, after having fixed stirrup piece 4, then by main reinforcement 3 pass through fixinig plate, wear
It is positioned when main reinforcement 3 by the L-type main reinforcement locating piece 10 on bracket 9 and the sleeve 6 being fixed on baffle 5, finally by stirrup
Piece 4 and main reinforcement 3 are fixed together, and such erection sequence stirrup will not cause to limit to main reinforcement 3;Stirrup piece 4 can shift to an earlier date
It is processed on the lathe of factory, then transports to construction site and carry out the making step of next step, it can also be at the construction field (site)
Stirrup piece 4 is made, same processing stirrup piece 4 can save the time for making stirrup at the construction field (site), work on the lathe of factory
Make high-efficient.
Claims (5)
1. a kind of steel reinforcement cage binding device, for the fixed stirrup piece made and main reinforcement, it is characterised in that: including fixed base
Seat, the two sides of fixed pedestal upper surface are provided with two blocks of side plates being parallel to each other, are additionally provided on fixed pedestal for positioning
The positioning plate of stirrup piece, positioning plate is parallel with side plate, and positioning plate is located between two blocks of side plates, the both ends of stirrup piece and two blocks of side plates
Opposite side squeezes contact, and one end of fixed pedestal is fixed with baffle, and side surrounding of the baffle close to fixed pedestal center is solid
Surely there are multiple sleeves for being used to position main reinforcement, one end of a main reinforcement is placed in a sleeve.
2. steel reinforcement cage binding device according to claim 1, it is characterised in that: steel reinforcement cage binding device further includes multiple n
The lower end of the bracket of type, each bracket is fixed on fixed pedestal, and two blocks of side plates are respectively positioned between the both sides of each bracket, each
Bracket is equidistantly provided with multiple L-type main reinforcement locating pieces close to the side at fixed pedestal center, and one is located at baffle top or two
The L-type main reinforcement locating piece of the sleeve of side and multiple bracket same positions in the same horizontal line, is placed through above baffle and two
In the middle part of the main reinforcement of side sleeve and it is placed on L-type main reinforcement locating piece.
3. steel reinforcement cage binding device according to claim 1, it is characterised in that: it is recessed to be provided with multiple positioning on positioning plate
Slot, the bottom of a stirrup piece are placed in a positioning groove.
4. the manufacture craft based on steel reinforcement cage binding device described in claim 1-3, which is characterized in that including following step
It is rapid:
S1: production stirrup piece;
S2: stirrup piece is fixed on fixed pedestal;
S3: main reinforcement passes through every stirrup piece, is placed on corresponding L-type main reinforcement locating piece;
S4: main reinforcement is fixedly connected with stirrup piece.
5. manufacture craft according to claim 4, it is characterised in that: in S3, main reinforcement is vertical with stirrup.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910501134.4A CN110106792A (en) | 2019-06-11 | 2019-06-11 | Steel reinforcement cage binding device and manufacture craft |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910501134.4A CN110106792A (en) | 2019-06-11 | 2019-06-11 | Steel reinforcement cage binding device and manufacture craft |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110106792A true CN110106792A (en) | 2019-08-09 |
Family
ID=67494571
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910501134.4A Pending CN110106792A (en) | 2019-06-11 | 2019-06-11 | Steel reinforcement cage binding device and manufacture craft |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110106792A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001349061A (en) * | 2001-04-17 | 2001-12-21 | Kajima Corp | Method for vertically assembling cage for reinforced concrete column |
JP2010281113A (en) * | 2009-06-04 | 2010-12-16 | Okabe Co Ltd | Method for assembling reinforcement cage for cast-in-place concrete pile and device for assembling split reinforcement cage |
CN201738305U (en) * | 2010-07-10 | 2011-02-09 | 中铁六局集团有限公司 | Butt-joint precision control device for steel reinforcement joint of steel reinforcement cage |
CN104264590A (en) * | 2014-09-30 | 2015-01-07 | 中交二航局第四工程有限公司 | Pier column rebar prefabricating bed-jig capable of accurately positioning main rebars and stirrups simultaneously |
CN105908902A (en) * | 2016-05-17 | 2016-08-31 | 济南城建集团有限公司 | Positioning frame for prefabricated pier column reinforcing bar cages and construction method of pier column reinforcing bar cages |
CN205617664U (en) * | 2016-05-17 | 2016-10-05 | 济南城建集团有限公司 | Prefabricated pier stud locating rack for steel reinforcement cage |
CN108729353A (en) * | 2018-05-25 | 2018-11-02 | 成都交投建筑工业化有限公司 | A kind of General reinforced cage binding moulding bed |
CN109365696A (en) * | 2018-11-30 | 2019-02-22 | 中国冶集团有限公司 | A kind of fabrication of reinforcing cage mould bases and construction method |
CN210420876U (en) * | 2019-06-11 | 2020-04-28 | 成都交投建筑工业化有限公司 | Binding device for reinforcement cage |
-
2019
- 2019-06-11 CN CN201910501134.4A patent/CN110106792A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001349061A (en) * | 2001-04-17 | 2001-12-21 | Kajima Corp | Method for vertically assembling cage for reinforced concrete column |
JP2010281113A (en) * | 2009-06-04 | 2010-12-16 | Okabe Co Ltd | Method for assembling reinforcement cage for cast-in-place concrete pile and device for assembling split reinforcement cage |
CN201738305U (en) * | 2010-07-10 | 2011-02-09 | 中铁六局集团有限公司 | Butt-joint precision control device for steel reinforcement joint of steel reinforcement cage |
CN104264590A (en) * | 2014-09-30 | 2015-01-07 | 中交二航局第四工程有限公司 | Pier column rebar prefabricating bed-jig capable of accurately positioning main rebars and stirrups simultaneously |
CN105908902A (en) * | 2016-05-17 | 2016-08-31 | 济南城建集团有限公司 | Positioning frame for prefabricated pier column reinforcing bar cages and construction method of pier column reinforcing bar cages |
CN205617664U (en) * | 2016-05-17 | 2016-10-05 | 济南城建集团有限公司 | Prefabricated pier stud locating rack for steel reinforcement cage |
CN108729353A (en) * | 2018-05-25 | 2018-11-02 | 成都交投建筑工业化有限公司 | A kind of General reinforced cage binding moulding bed |
CN109365696A (en) * | 2018-11-30 | 2019-02-22 | 中国冶集团有限公司 | A kind of fabrication of reinforcing cage mould bases and construction method |
CN210420876U (en) * | 2019-06-11 | 2020-04-28 | 成都交投建筑工业化有限公司 | Binding device for reinforcement cage |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202225295U (en) | Integrally-forming mold base of steel reinforcement framework | |
CN110106792A (en) | Steel reinforcement cage binding device and manufacture craft | |
CN201850508U (en) | Non-strut bridge pier template | |
CN210420876U (en) | Binding device for reinforcement cage | |
CN205853051U (en) | A kind of band is magnetic the precast concrete production mould of dividing plate | |
CN205000633U (en) | Customization arc steel form | |
CN106150084A (en) | A kind of mold method wearing muscle template and formwork erecting structure thereof | |
CN203160428U (en) | Connecting structure of beam steel and steel rib at node position of framework beam column | |
CN214785903U (en) | Concrete building template for civil engineering | |
CN205836871U (en) | A kind of brickmaking fragment of brick transport trolleys | |
CN204568808U (en) | Push to rail mechanism | |
CN202411903U (en) | Clamp used in producing process of sliding block insert by using computerized numerical control (CNC) | |
CN209850217U (en) | Grid steel frame processor | |
CN207892243U (en) | A kind of template assembly system | |
CN206527585U (en) | Carrier detent mechanism | |
CN104723044B (en) | A kind of frame manufacture technique for concrete modular | |
CN101357737B (en) | Constant hoisting force conveying method for crane with multi-hoisting points | |
CN111576709A (en) | Prefabricated local coincide floor | |
CN212801231U (en) | Novel support base stone template | |
CN205394807U (en) | From special cushion of prefabricated pipeline cross reinforcing bar of steady type | |
IT8323048A1 (en) | SUPPORTING STRUCTURE FOR ARMING CONSTRUCTIONS | |
CN203613778U (en) | Concrete-filled steel tube pouring platform | |
CN207139333U (en) | Square steel blank saddle-shape stator milling both ends false boss frock | |
CN211256679U (en) | Vertical finish rolling screw-thread steel locating support in bridgehead fort steel-concrete combined section | |
CN211172729U (en) | Integrated steel bar protective layer cushion block |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |