CN110093944A - The online upgrading rebuilding construction method of heavy plate mill - Google Patents

The online upgrading rebuilding construction method of heavy plate mill Download PDF

Info

Publication number
CN110093944A
CN110093944A CN201910360378.5A CN201910360378A CN110093944A CN 110093944 A CN110093944 A CN 110093944A CN 201910360378 A CN201910360378 A CN 201910360378A CN 110093944 A CN110093944 A CN 110093944A
Authority
CN
China
Prior art keywords
steel
construction
platform
production
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910360378.5A
Other languages
Chinese (zh)
Other versions
CN110093944B (en
Inventor
李俊峰
汪钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201910360378.5A priority Critical patent/CN110093944B/en
Publication of CN110093944A publication Critical patent/CN110093944A/en
Application granted granted Critical
Publication of CN110093944B publication Critical patent/CN110093944B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B31/00Rolling stand structures; Mounting, adjusting, or interchanging rolls, roll mountings, or stand frames
    • B21B31/02Rolling stand frames or housings; Roll mountings ; Roll chocks
    • B21B31/06Fastening stands or frames to foundation, e.g. to the sole plate
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Abstract

The present invention relates to milling train maintenance field, the online upgrading rebuilding construction methods of specifically a kind of heavy plate mill;It is characterized in that: including step 1, preparation of construction;Step 2, steel platform production and foundation construction;Step 3, production periodical repair are shut down;Step 4, cold bed region used equipment and basis are removed;Step 5, steel platform installation;Step 6, the installation of interim roller-way;Step 8 is resumed production;Step 9, milling train pattern foundation pit supporting structure;Step 10, rolling mill for foundation engineering construction;Step 11, the installation of new milling equipment;It step 12, test running and puts into operation: after cold bed region used equipment and basis are removed, old workshop can be started and removed.This construction method is provided with interim roller-way and steel platform by milling train, removes used equipment and replacement roller-way using production repairing period, genuine room produces uninterrupted when realizing modifying rolling mill;Entire transformation process is divided into three parts construction, each section strict logic again can with parallel construction, work progress securely and reliably, economical and efficient.

Description

The online upgrading rebuilding construction method of heavy plate mill
Technical field
The present invention relates to milling train maintenance field, the online upgrading rebuilding construction methods of specifically a kind of heavy plate mill.
Background technique
As energy consumption and the requirement of environmental protection are increasingly strict, adjust structure, cost declining, superseded backward, promotion quality, exploitation high-end Product is becoming the target of domestic iron and steel enterprises pursuit.According to incompletely statistics, only in hot-strip field, the country go into operation with The hot strip rolling mill built nearly 90, production capacity is more than 300,000,000 tons, and excess capacity is more than 30%.In this 90 production lines, configuration life Producing mid and low-end products is more than half, mostly there is that dimensional accuracy is not high, performance is unstable, thin gauge produces difficulty etc. and asks jointly Topic.Competition in face of market, the technological transformation and upgrading of production line of rolling mill are a wise selections.Such as under existing roughing mill A finishing mill is added in trip, the quality of product can be improved, and make full use of existing apparatus, investment reduction.In general, production line of rolling mill Project of upgrading and rebuilding short time limit, construction space it is limited, mostly use shutdown to be transformed.But transformation is shut down 8-15 months, to production list Position is extremely disadvantageous.Rolling mill for foundation engineering foundation depth is more than 9m, such as using online transformation, how to guarantee new milling equipment base simultaneously Plinth construction is run with existing production line, is maximum technical problem in work progress.
Summary of the invention
The purpose of the present invention is to provide a kind of online upgrading rebuilding construction methods of heavy plate mill.
In order to achieve the above object, the present invention is implemented as follows:
A kind of online upgrading rebuilding construction method of heavy plate mill, including
Step 1, preparation of construction are replaced including reforming equipment and capable of being situated between for pipeline every discrete system;
Step 2, steel platform production and foundation construction;Steel platform includes column, two layers of platform and support system composition, -5.20m flat Platform includes middle girder and intermediate secondary beam, and ± 0.00m platform includes two elongated top layer girders and several support joist groups At, support joist between be connected with supporting welding between beam;Column is formed by section steel manufacture, the intermediate master of -5.20m platform Beam, intermediate secondary beam are formed by section steel manufacture, ± 0.00m top layer girder by section steel manufacture form, support joist by fashioned iron system It forms, support is by [10 channel steels are made, and column braces are formed by two angle steel chain intermittent welds between beam;Steel structure platform base Plinth uses shallow isolated footing, guarantees into rock stratum 2-3m;
Step 3, production periodical repair are shut down;
Step 4, cold bed region used equipment and basis are removed, and used equipment is removed using destructive, and basis is cut using pick machine;
Step 5, steel platform installation, steel platform can be installed in two times: production periodical repair installs steel platform column, cold bed region after shutting down After the completion of used equipment and basis are removed, then two layers of platform and support system are installed;
Step 6, the installation of interim roller-way;The interim roller-way of multiple groups is set, and interim roller-way and driving motor are each attached in steel platform;
Step 8 is resumed production, and the installation of isolation canopy above roller-way must be completed before resuming production, and isolation canopy is taken using color steel tile If;
Step 9, milling train pattern foundation pit supporting structure, foundation pit use miniature steel pipe pile reinforced supporting, and part basis uses coagulation with foundation pit height difference Soil spray Anchor Care slope;
Step 10, rolling mill for foundation engineering construction, rolling mill for foundation engineering are located at steel platform periphery, and when construction needs to pay attention to steel platform Protection;
Step 11, the installation of new milling equipment, after the completion of rolling mill for foundation engineering construction, dismountable interim roller-way and steel platform, new factory After the completion of room Steel Structure Installation, new milling equipment installation can be started;
It step 12, test running and puts into operation: after cold bed region used equipment and basis are removed, old workshop can be started and removed.Old workshop is Precast concrete, prefabricated post, fine strain of millet structure are removed using hydraulic shear cooperation truck crane;When prefabricated room panel is removed, first room Former design lifting lug is dug out on panel, if seriously corroded is not available lifting lug, bores Φ 100mm hole for hoist as suspension centre in lifting lug; Before old workshop is removed, must in old workshop colonnade pipeline carry out temporary support protection.
This construction method by milling train be provided with interim roller-way and steel platform, using production repairing period remove used equipment and Roller-way is replaced, genuine room produces uninterrupted when realizing modifying rolling mill;Entire transformation process is divided into three parts construction, respectively Part strict logic again can be with parallel construction, and work progress is safe and reliable, economical and efficient.
Detailed description of the invention
The process flow chart of the online upgrading rebuilding construction of Fig. 1 heavy plate mill.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
As shown in Figure 1, a kind of online upgrading rebuilding construction method of heavy plate mill, including
Step 1, preparation of construction are replaced including reforming equipment and capable of being situated between for pipeline every discrete system;
Step 2, steel platform production and foundation construction;Steel platform includes column, two layers of platform and support system composition, -5.20m flat Platform includes middle girder and intermediate secondary beam, and ± 0.00m platform includes two elongated top layer girders and several support joist groups At, support joist between be connected with supporting welding between beam;Column is formed by section steel manufacture, the intermediate master of -5.20m platform Beam, intermediate secondary beam are formed by section steel manufacture, ± 0.00m top layer girder by section steel manufacture form, support joist by fashioned iron system It forms, support is by [10 channel steels are made, and column braces are formed by two angle steel chain intermittent welds between beam;Steel structure platform base Plinth uses shallow isolated footing, guarantees into rock stratum 2-3m;
Step 3, production periodical repair are shut down;
Step 4, cold bed region used equipment and basis are removed, and used equipment is removed using destructive, and basis is cut using pick machine;
Step 5, steel platform installation, steel platform can be installed in two times: production periodical repair installs steel platform column, cold bed region after shutting down After the completion of used equipment and basis are removed, then two layers of platform and support system are installed;
Step 6, the installation of interim roller-way;The interim roller-way of multiple groups is set, and interim roller-way and driving motor are each attached in steel platform;
Step 8 is resumed production, and the installation of isolation canopy above roller-way must be completed before resuming production, and isolation canopy is taken using color steel tile If;
Step 9, milling train pattern foundation pit supporting structure, foundation pit use miniature steel pipe pile reinforced supporting, and part basis uses coagulation with foundation pit height difference Soil spray Anchor Care slope;
Step 10, rolling mill for foundation engineering construction, rolling mill for foundation engineering are located at steel platform periphery, and when construction needs to pay attention to steel platform Protection;
Step 11, the installation of new milling equipment, after the completion of rolling mill for foundation engineering construction, dismountable interim roller-way and steel platform, new factory After the completion of room Steel Structure Installation, new milling equipment installation can be started;
It step 12, test running and puts into operation: after cold bed region used equipment and basis are removed, old workshop can be started and removed.Old workshop is Precast concrete, prefabricated post, fine strain of millet structure are removed using hydraulic shear cooperation truck crane;When prefabricated room panel is removed, first room Former design lifting lug is dug out on panel, if seriously corroded is not available lifting lug, bores Φ 100mm hole for hoist as suspension centre in lifting lug; Before old workshop is removed, must in old workshop colonnade pipeline carry out temporary support protection.
This construction method by milling train be provided with interim roller-way and steel platform, using production repairing period remove used equipment and Roller-way is replaced, genuine room produces uninterrupted when realizing modifying rolling mill;Entire transformation process is divided into three parts construction, respectively Part strict logic again can be with parallel construction, and work progress is safe and reliable, economical and efficient.

Claims (1)

1. a kind of online upgrading rebuilding construction method of heavy plate mill, it is characterized in that: including
Step 1, preparation of construction are replaced including reforming equipment and capable of being situated between for pipeline every discrete system;
Step 2, steel platform production and foundation construction;Steel platform includes column, two layers of platform and support system composition, -5.20m flat Platform includes middle girder and intermediate secondary beam, and ± 0.00m platform includes two elongated top layer girders and several support joist groups At, support joist between be connected with supporting welding between beam;Column is formed by section steel manufacture, the intermediate master of -5.20m platform Beam, intermediate secondary beam are formed by section steel manufacture, ± 0.00m top layer girder by section steel manufacture form, support joist by fashioned iron system It forms, support is by [10 channel steels are made, and column braces are formed by two angle steel chain intermittent welds between beam;Steel structure platform base Plinth uses shallow isolated footing, guarantees into rock stratum 2-3m;
Step 3, production periodical repair are shut down;
Step 4, cold bed region used equipment and basis are removed, and used equipment is removed using destructive, and basis is cut using pick machine;
Step 5, steel platform installation, steel platform can be installed in two times: production periodical repair installs steel platform column, cold bed region after shutting down After the completion of used equipment and basis are removed, then two layers of platform and support system are installed;
Step 6, the installation of interim roller-way;The interim roller-way of multiple groups is set, and interim roller-way and driving motor are each attached in steel platform;
Step 8 is resumed production, and the installation of isolation canopy above roller-way must be completed before resuming production, and isolation canopy is taken using color steel tile If;
Step 9, milling train pattern foundation pit supporting structure, foundation pit use miniature steel pipe pile reinforced supporting, and part basis uses coagulation with foundation pit height difference Soil spray Anchor Care slope;
Step 10, rolling mill for foundation engineering construction, rolling mill for foundation engineering are located at steel platform periphery, and when construction needs to pay attention to steel platform Protection;
Step 11, the installation of new milling equipment, after the completion of rolling mill for foundation engineering construction, dismountable interim roller-way and steel platform, new factory After the completion of room Steel Structure Installation, new milling equipment installation can be started;
It step 12, test running and puts into operation: after cold bed region used equipment and basis are removed, old workshop can be started and removed;Old workshop is Precast concrete, prefabricated post, fine strain of millet structure are removed using hydraulic shear cooperation truck crane;When prefabricated room panel is removed, first room Former design lifting lug is dug out on panel, if seriously corroded is not available lifting lug, bores Φ 100mm hole for hoist as suspension centre in lifting lug; Before old workshop is removed, must in old workshop colonnade pipeline carry out temporary support protection.
CN201910360378.5A 2019-04-30 2019-04-30 On-line upgrading and reforming construction method of heavy plate mill Active CN110093944B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910360378.5A CN110093944B (en) 2019-04-30 2019-04-30 On-line upgrading and reforming construction method of heavy plate mill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910360378.5A CN110093944B (en) 2019-04-30 2019-04-30 On-line upgrading and reforming construction method of heavy plate mill

Publications (2)

Publication Number Publication Date
CN110093944A true CN110093944A (en) 2019-08-06
CN110093944B CN110093944B (en) 2021-03-26

Family

ID=67446506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910360378.5A Active CN110093944B (en) 2019-04-30 2019-04-30 On-line upgrading and reforming construction method of heavy plate mill

Country Status (1)

Country Link
CN (1) CN110093944B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114282289A (en) * 2021-11-30 2022-04-05 中国十七冶集团有限公司 Manufacturing and mounting method for movable safe passage platform of construction elevator

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002087666A (en) * 2000-09-12 2002-03-27 Dainippon Printing Co Ltd Web joining device
CN1900467A (en) * 2006-07-20 2007-01-24 上海市第一建筑有限公司 Horizontal force transfer method for underground building modification
CN101748758A (en) * 2008-12-04 2010-06-23 中国二十冶建设有限公司 Timbering method of foundation ditches for reforming on-line equipment foundations in factory buildings
CN102146492A (en) * 2011-05-24 2011-08-10 天津二十冶建设有限公司 Method for installing converter body equipment and tooling platform
CN103362152A (en) * 2012-04-09 2013-10-23 中冶赛迪工程技术股份有限公司 Method for transforming roller way foundation
CN103866784A (en) * 2014-03-28 2014-06-18 上海绿地建设(集团)有限公司 Adjustable tower crane steel platform foundation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002087666A (en) * 2000-09-12 2002-03-27 Dainippon Printing Co Ltd Web joining device
CN1900467A (en) * 2006-07-20 2007-01-24 上海市第一建筑有限公司 Horizontal force transfer method for underground building modification
CN101748758A (en) * 2008-12-04 2010-06-23 中国二十冶建设有限公司 Timbering method of foundation ditches for reforming on-line equipment foundations in factory buildings
CN102146492A (en) * 2011-05-24 2011-08-10 天津二十冶建设有限公司 Method for installing converter body equipment and tooling platform
CN103362152A (en) * 2012-04-09 2013-10-23 中冶赛迪工程技术股份有限公司 Method for transforming roller way foundation
CN103866784A (en) * 2014-03-28 2014-06-18 上海绿地建设(集团)有限公司 Adjustable tower crane steel platform foundation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114282289A (en) * 2021-11-30 2022-04-05 中国十七冶集团有限公司 Manufacturing and mounting method for movable safe passage platform of construction elevator
CN114282289B (en) * 2021-11-30 2023-03-10 中国十七冶集团有限公司 Manufacturing and mounting method for movable safe passage platform of construction elevator

Also Published As

Publication number Publication date
CN110093944B (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN101858222B (en) Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction
WO2021228189A1 (en) Reusable post-cast strip support replacement force transfer device and construction method therefor
CN107245951B (en) Mid-span and double-side simultaneous closure construction method for cable-stayed bridge
CN101899904B (en) Method for two-way hoisting construction of converter tower steel structure
CN114016552A (en) Pre-sealing construction method for basement roof settlement post-cast strip
CN106499226B (en) A kind of method of main building construction in layer
CN208965714U (en) A kind of prefabricated piping lane main frame structure of assembly concrete
CN110093944A (en) The online upgrading rebuilding construction method of heavy plate mill
CN110821159A (en) Steel-structure large-span adjustable floor support plate supporting structure and construction method thereof
Gong et al. A review of key technologies development of super high-rise building construction in China
CN202000644U (en) Movable bearing bracket platform
CN201560575U (en) Operation platform device
CN111322078B (en) Construction method for shield tunneling machine to pass through underground diaphragm wall
CN211647306U (en) Floor carrier plate bearing structure with adjustable steel construction large-span
CN205296197U (en) Prefabricated cushion cap of anticorrosive industry factory building concrete rim of a cup formula
CN103362152B (en) Method for transforming roller way foundation
CN201730626U (en) Concrete casting sliding die of flat hole of tunnel
CN102329903A (en) Construction method for restoring jacked blast furnace shell
CN106285028A (en) Reinforcement of factory building construction method in long-span heavy type crane girder based on BIM technology dismounting
CN205711786U (en) Big cross section porous overlength cast-in-place box culvert formwork system
CN103590419A (en) Assembled type adjustable high-voltage reactor foundation
CN115306397A (en) Unloading balance construction method for newly-built rectangular pipe-jacking upward-penetrating existing subway tunnel
CN102182320A (en) Mounting method of steel reinforced concrete steel skeleton of large metallurgical industrial factory
CN203594047U (en) Assembly type adjustable high-voltage electric reactor foundation
CN207485444U (en) A kind of modular is slagged tap platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant