CN110086149A - Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application - Google Patents

Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application Download PDF

Info

Publication number
CN110086149A
CN110086149A CN201910347453.4A CN201910347453A CN110086149A CN 110086149 A CN110086149 A CN 110086149A CN 201910347453 A CN201910347453 A CN 201910347453A CN 110086149 A CN110086149 A CN 110086149A
Authority
CN
China
Prior art keywords
unit
level
residual current
current protective
protective unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910347453.4A
Other languages
Chinese (zh)
Inventor
崔家才
马永
曹金芳
李坚
冷自超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaibei Mining Co Ltd
Original Assignee
Huaibei Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaibei Mining Co Ltd filed Critical Huaibei Mining Co Ltd
Priority to CN201910347453.4A priority Critical patent/CN110086149A/en
Publication of CN110086149A publication Critical patent/CN110086149A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H1/00Details of emergency protective circuit arrangements
    • H02H1/0061Details of emergency protective circuit arrangements concerning transmission of signals
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H3/00Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
    • H02H3/26Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to difference between voltages or between currents; responsive to phase angle between voltages or between currents
    • H02H3/32Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to difference between voltages or between currents; responsive to phase angle between voltages or between currents involving comparison of the voltage or current values at corresponding points in different conductors of a single system, e.g. of currents in go and return conductors
    • H02H3/33Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to difference between voltages or between currents; responsive to phase angle between voltages or between currents involving comparison of the voltage or current values at corresponding points in different conductors of a single system, e.g. of currents in go and return conductors using summation current transformers

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Emergency Protection Circuit Devices (AREA)

Abstract

The invention belongs to industrial and mineral technical fields, especially leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application, including the compatible malfunction module of leakage experiment leapfrog mode hopping block and mobile substation, the compatible malfunction module in mobile substation include for total power distribution unit, distribution electric unit, mobile voltage transformation unit and increase feed element, further include that leak(age) test bypasses the immediate leadership and jumps malfunction System Utilization Procedure compatible with mobile substation.The present invention utilizes the compatible malfunction module of the leakage experiment leapfrog mode hopping block of setting and mobile substation; entire significant effect; effectively the leapfrog of feeding switch is avoided to jump situation; it realizes mobile substation and feed compatibling problem, reduces scope of power outage, improve protector sensitivity; guarantee for reliability; influence time is reduced, safety accident is avoided, improves the security performance of bulk supply circuit.

Description

Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application
Technical field
The present invention relates to industrial and mineral technical field more particularly to leak(age) test bypass the immediate leadership jump malfunction compatible with mobile substation and Using.
Background technique
" safety regulations in coal mine " regulation Coal Mine Feeder Switch must do daily a leak(age) test with leak(age) test function, There can be no jump or the misactions of bypassing the immediate leadership.But global each mine occur the test of low voltage feeder creepage protection function bypass the immediate leadership jump and Misaction occurs, and there are also mobile substation and feed incompatibility problem, part mine takes shielding is mobile to become station leakage function, There are hidden troubles, and protective relaying device (requirement of four property) selectivity, speed, sensitivity, reliability is not achieved, and give supply lines Bring security risk in road.It cannot be guaranteed personal safety, can not prevent electric spark from generating.State Bureau and security bureau find more mines all It gives fine to put on record processing, needs leak(age) test to bypass the immediate leadership thus and jump malfunction compatible with mobile substation and application.
Summary of the invention
Leak(age) test proposed by the present invention, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application, solves the prior art There are the problem of.
To achieve the goals above, present invention employs following technical solutions:
Leak(age) test, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, including leakage experiment leapfrog mode hopping block and mobile substation Compatible malfunction module, the compatible malfunction module in the mobile substation include for becoming with total power distribution unit, distribution electric unit, movement It presses unit and increases feed element, the leakage experiment leapfrog mode hopping includes level-one residual current protective unit, second level earth leakage protective list Member, three-level residual current protective unit, level Four residual current protective unit, end residual current protective unit bypass the immediate leadership and jump signal acquisition unit, bypass the immediate leadership It jumps signal processing unit and regulation unit, total power distribution unit, distribution electric unit, mobile voltage transformation unit and increase feedback is jumped in leapfrog Electric unit is sequentially connected, and increases feed element, level-one residual current protective unit, second level residual current protective unit, level Four earth leakage protective list Member and end residual current protective unit are sequentially connected, and three-level residual current protective unit is connected with level Four residual current protective unit, are bypassed the immediate leadership and are jumped letter Number acquisition unit bypasses the immediate leadership to jump signal processing unit and bypass the immediate leadership and jumps regulation unit and be sequentially connected, and bypasses the immediate leadership and jumps signal acquisition unit and one Grade residual current protective unit, second level residual current protective unit, three-level residual current protective unit, level Four residual current protective unit and end electric leakage are protected Unit connection is protected, bypasses the immediate leadership and jumps regulation unit and level-one residual current protective unit, second level residual current protective unit, three-level earth leakage protective list Member, level Four residual current protective unit are connected with end residual current protective unit.
Leak(age) test, which is bypassed the immediate leadership, jumps malfunction System Utilization Procedure compatible with mobile substation, the steps include:
S1, determine mobile voltage transformation unit and increase at a distance from feed element and the output power of mobile voltage transformation unit feeder ear and Power supply line's length;
S2, the low pressure sampling plate in mobile voltage transformation unit is increased to electrolytic capacitor, while by increased electrolytic capacitor and increases feedback Electric unit is attached;
S3, signal acquisition unit real-time monitoring level-one residual current protective unit, second level residual current protective unit, three-level leakage are jumped using bypassing the immediate leadership The residual voltage current information of electric protection unit and level Four residual current protective unit operation, and the information of monitoring is transmitted to more Grade jumps signal processing unit, and the data that final leapfrog jump regulation unit is obtained according to processing are to level-one residual current protective unit, second level Residual current protective unit, the time delay condition of three-level residual current protective unit and level Four residual current protective unit at work are set, Mode is concurrently set to leak electricity according to level-one residual current protective unit to second level residual current protective unit, three-level residual current protective unit and level Four Gradually successively decrease in the direction of protection location.
Preferably, total power distribution unit carries out rectification seamless regulation to the alternating current of input, and distribution electric unit will be used for city Electricity electricity consumption adjusted is shunted, and the electricity consumption after shunting is carried out transformation regulation by mobile voltage transformation unit according to actual needs, is increased Add feed element for carrying out compatible allotment to mobile voltage transformation unit.
Preferably, the level-one residual current protective unit is used to carry out the electricity consumption after transformation level-one leakage protection, second level leakage Electric protection unit is used to carry out the electricity consumption after transformation second level leakage protection, and three-level residual current protective unit is used for the use after transformation Electricity carries out three-level leakage protection, and level Four residual current protective unit is used to carry out the electricity consumption after transformation level Four leakage protection, end leakage Electric protection unit is used to carry out isolating and protecting to the electricity consumption after transformation, and jump signal acquisition unit of bypassing the immediate leadership is protected for acquiring level-one electric leakage Protect the residual voltage of unit, second level residual current protective unit, three-level residual current protective unit and level Four residual current protective unit operation Current information bypasses the immediate leadership and jumps signal processing unit for the residual voltage current information of acquisition to be carried out processing conversion, bypasses the immediate leadership to jump and adjust Control unit is protected for controlling level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four electric leakage Protect the time delay condition of unit at work.
Preferably, the level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four leakage Electric protection unit is all made of model BKD20-400 Protection for Mine Vacuum Feed Switch, and end residual current protective unit uses KBZ20-400 Vacuum feed switch.
Preferably, total power distribution unit uses PBG-400 mineral high-voltage vacuum distribution device for explosion-proof type permanent, point Power distribution unit uses PBG-200 mineral high-voltage vacuum distribution device for explosion-proof type permanent, and mobile voltage transformation unit uses KBSGZY- 166 mobile substation.
In the present invention,
The compatible malfunction module of leakage experiment leapfrog mode hopping block and mobile substation of design utilization setting, entire significant effect, It effectively avoids the leapfrog of feeding switch from jumping situation, realizes mobile substation and feed compatibling problem, reduce scope of power outage, Protector sensitivity is improved, guarantees to reduce influence time for reliability, avoids safety accident, improve bulk supply circuit Security performance.
Detailed description of the invention
Fig. 1 is the structural schematic diagram that malfunction system compatible with mobile substation is jumped in leak(age) test proposed by the present invention leapfrog;
Fig. 2 is that malfunction system leakage experiment leapfrog mode hopping block compatible with mobile substation is jumped in leak(age) test proposed by the present invention leapfrog Structural schematic diagram.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Referring to Fig.1-2, leak(age) test, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, including leakage experiment leapfrog mode hopping The compatible malfunction module of block and mobile substation, the compatible malfunction module in mobile substation include for electric with total power distribution unit, distribution Unit, mobile voltage transformation unit and increase feed element, leakage experiment leapfrog mode hopping include level-one residual current protective unit, second level electric leakage Protection location, level Four residual current protective unit, end residual current protective unit, bypasses the immediate leadership and jumps signal acquisition list at three-level residual current protective unit Member bypasses the immediate leadership to jump signal processing unit and bypass the immediate leadership and jumps regulation unit, total power distribution unit, distribution electric unit, mobile voltage transformation unit and increasing Add feed element to be sequentially connected, increases feed element, level-one residual current protective unit, second level residual current protective unit, level Four electric leakage guarantor Shield unit and end residual current protective unit are sequentially connected, and three-level residual current protective unit is connected with level Four residual current protective unit, are bypassed the immediate leadership It jumps signal acquisition unit, leapfrog jump signal processing unit and jump regulation unit of bypassing the immediate leadership is sequentially connected, leapfrog jump signal acquisition unit It is leaked with level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit, level Four residual current protective unit and end Electric protection unit connection, bypasses the immediate leadership and jumps regulation unit and level-one residual current protective unit, second level residual current protective unit, three-level earth leakage protective Unit, level Four residual current protective unit are connected with end residual current protective unit.
Leak(age) test, which is bypassed the immediate leadership, jumps malfunction System Utilization Procedure compatible with mobile substation, the steps include:
S1, determine mobile voltage transformation unit and increase at a distance from feed element and the output power of mobile voltage transformation unit feeder ear and Power supply line's length;
S2, the low pressure sampling plate in mobile voltage transformation unit is increased to electrolytic capacitor, while by increased electrolytic capacitor and increases feedback Electric unit is attached;
S3, signal acquisition unit real-time monitoring level-one residual current protective unit, second level residual current protective unit, three-level leakage are jumped using bypassing the immediate leadership The residual voltage current information of electric protection unit and level Four residual current protective unit operation, and the information of monitoring is transmitted to more Grade jumps signal processing unit, and the data that final leapfrog jump regulation unit is obtained according to processing are to level-one residual current protective unit, second level Residual current protective unit, the time delay condition of three-level residual current protective unit and level Four residual current protective unit at work are set, Mode is concurrently set to leak electricity according to level-one residual current protective unit to second level residual current protective unit, three-level residual current protective unit and level Four Gradually successively decrease in the direction of protection location.
Further, total power distribution unit carries out rectification seamless regulation to the alternating current of input, and distribution electric unit will be used for alternating current Electricity consumption adjusted is shunted, and the electricity consumption after shunting is carried out transformation regulation by mobile voltage transformation unit according to actual needs, is increased Feed element is used to carry out compatible allotment to mobile voltage transformation unit.
Especially, level-one residual current protective unit is used to carry out the electricity consumption after transformation level-one leakage protection, and second level electric leakage is protected Protect unit be used for after transformation electricity consumption carry out second level leakage protection, three-level residual current protective unit be used for the electricity consumption after transformation into Row three-level leakage protection, level Four residual current protective unit are used to carry out the electricity consumption after transformation level Four leakage protection, and end electric leakage is protected It protects unit to be used to carry out isolating and protecting to the electricity consumption after transformation, bypasses the immediate leadership and jump signal acquisition unit for acquiring level-one earth leakage protective list The residual voltage electric current of member, second level residual current protective unit, three-level residual current protective unit and level Four residual current protective unit operation Information bypasses the immediate leadership and jumps signal processing unit for the residual voltage current information of acquisition to be carried out processing conversion, and bypassing the immediate leadership, it is single to jump regulation Member is for controlling level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four earth leakage protective list The time delay condition of member at work.
In addition, level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four earth leakage protective Unit is all made of model BKD20-400 Protection for Mine Vacuum Feed Switch, and end residual current protective unit is presented using KBZ20-400 vacuum Electric switch.
In addition to this, total power distribution unit uses PBG-400 mineral high-voltage vacuum distribution device for explosion-proof type permanent, distribution Electric unit uses PBG-200 mineral high-voltage vacuum distribution device for explosion-proof type permanent, and mobile voltage transformation unit uses KBSGZY- 166 mobile substation increases feed element and uses KBZ20-400 vacuum feed switch;
Embodiment one:
Output power determination mobile voltage transformation unit first and increase at a distance from feed element and move voltage transformation unit feeder ear With power supply line's length, when mobile voltage transformation unit and when increasing feed element and being arranged within 5 meters, by the leakage of mobile voltage transformation unit Electricity delay setting 0.2S increases electric leakage delay the setting 0.0S, residual voltage UO:1.5V, zero-sequence current IO of feed element: The 22UF/25V anode of increased electrolytic capacitor, is connect 17 lines for increasing feed element by 1.5A, and increased electrolytic capacitor cathode connects Increase by 18 lines of feed element;When 200 meters of feed element distance of mobile voltage transformation unit and increase or more, mobile voltage transformation unit leakage Electricity delay setting 0.2S increases feed element electric leakage delay setting 0.0S, residual voltage UO1.3V, zero-sequence current IO1.3mA;When When power supply line's length of mobile voltage transformation unit is more than the equipment that 800 meters and/or startup power are greater than 1200KW, increased electrolysis Capacitor carries out capacitor supplement voltage and springs up;
Embodiment two:
It is artificial to determine power supply line branch's capacitive sensing electric current and residual voltage over the ground according to power supply line's length, take zero sequence electric Stream and residual voltage value jump signal processing unit and bypass the immediate leadership as leapfrog jumps the foundation of unit comparison and regulation, utilizes leapfrog Jump signal acquisition unit real-time monitoring level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and four The residual voltage current information of grade residual current protective unit operation, then bypass the immediate leadership jump the numerical value that will test of signal processing unit with It is artificial to determine power supply line branch's capacitive sensing electric current and residual voltage numerical value carry out effect over the ground, bypass the immediate leadership jump regulation unit according to The data of comparison are to level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four earth leakage protective Data on unit are set, and concurrently set mode according to level-one residual current protective unit to second level residual current protective unit, three-level The direction of residual current protective unit and level Four residual current protective unit is gradually successively decreased, wherein one group of data setting are as follows: level-one earth leakage protective Unit delay setting 200ms(safety regulations in coal mine regulation, which leaks electricity to be delayed, must not exceed 0.2 second=200ms), second level earth leakage protective list Member, which is delayed, is arranged 130ms setting UO:1.2V, IO:1.2mA, three-level residual current protective unit delay setting 90ms setting UO:1.2V, IO:1.2mA, the delay of fourth stage residual current protective unit are that UO:1.3V, IO:1.3mA is arranged in 0ms.
Using the compatible malfunction module of the leakage experiment leapfrog mode hopping block of setting and mobile substation, entire effect is aobvious for the design It writes, the leapfrog of feeding switch is effectively avoided to jump situation, realize mobile substation and feed compatibling problem, reduce power failure model It encloses, improves protector sensitivity, guarantee to reduce influence time for reliability, avoid safety accident, improve bulk supply electricity The security performance on road.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", It is " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " suitable The orientation or positional relationship of the instructions such as hour hands ", " counterclockwise " is to be based on the orientation or positional relationship shown in the drawings, merely to just In description the present invention and simplify description, rather than the equipment of indication or suggestion meaning or element must have a particular orientation, with Specific orientation construction and operation, therefore be not considered as limiting the invention.
In addition, term " first ", " second " are used for description purposes only, it is not understood to indicate or imply relatively important Property or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Person implicitly includes one or more of the features.In the description of the present invention, the meaning of " plurality " is two or two with On, unless otherwise specifically defined.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (6)

1. leak(age) test, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, including leakage experiment leapfrog mode hopping block and mobile power transformation Stand compatible malfunction module, which is characterized in that the compatible malfunction module in the mobile substation include for total power distribution unit, distribution Electric unit, mobile voltage transformation unit and increase feed element, the leakage experiment leapfrog mode hopping includes level-one residual current protective unit, two Grade residual current protective unit, level Four residual current protective unit, end residual current protective unit, bypasses the immediate leadership and jumps signal at three-level residual current protective unit Acquisition unit bypasses the immediate leadership and jumps signal processing unit and leapfrog jump regulation unit, total power distribution unit, distribution electric unit, mobile change Pressure unit and increase feed element be sequentially connected, increase feed element, level-one residual current protective unit, second level residual current protective unit, Level Four residual current protective unit and end residual current protective unit are sequentially connected, three-level residual current protective unit and level Four residual current protective unit Connection, signal acquisition unit is jumped in leapfrog, signal processing unit is jumped in leapfrog and jump regulation unit of bypassing the immediate leadership is sequentially connected, and signal is jumped in leapfrog Acquisition unit and level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit, level Four residual current protective unit It is connected with end residual current protective unit, bypasses the immediate leadership and jump regulation unit and level-one residual current protective unit, second level residual current protective unit, three-level Residual current protective unit, level Four residual current protective unit are connected with end residual current protective unit.
2. leak(age) test, which is bypassed the immediate leadership, jumps malfunction System Utilization Procedure compatible with mobile substation, the steps include:
S1, determine mobile voltage transformation unit and increase at a distance from feed element and the output power of mobile voltage transformation unit feeder ear and Power supply line's length;
S2, the low pressure sampling plate in mobile voltage transformation unit is increased to electrolytic capacitor, while by increased electrolytic capacitor and increases feedback Electric unit is attached;
S3, signal acquisition unit real-time monitoring level-one residual current protective unit, second level residual current protective unit, three-level leakage are jumped using bypassing the immediate leadership The residual voltage current information of electric protection unit and level Four residual current protective unit operation, and the information of monitoring is transmitted to more Grade jumps signal processing unit, and the data that final leapfrog jump regulation unit is obtained according to processing are to level-one residual current protective unit, second level Residual current protective unit, the time delay condition of three-level residual current protective unit and level Four residual current protective unit at work are set, Mode is concurrently set to leak electricity according to level-one residual current protective unit to second level residual current protective unit, three-level residual current protective unit and level Four Gradually successively decrease in the direction of protection location.
3. leak(age) test according to claim 1, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, which is characterized in that institute It states total power distribution unit and rectification seamless regulation is carried out to the alternating current of input, distribution electric unit will be used for alternating current electricity consumption adjusted and carry out It shunts, the electricity consumption after shunting is carried out transformation regulation by mobile voltage transformation unit according to actual needs, is increased feed element and is used for shifting Dynamic voltage transformation unit carries out compatible allotment.
4. leak(age) test according to claim 1, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, which is characterized in that institute Level-one residual current protective unit is stated for carrying out level-one leakage protection to the electricity consumption after transformation, second level residual current protective unit is used for change Electricity consumption after pressure carries out second level leakage protection, and three-level residual current protective unit is used to carry out the electricity consumption after transformation three-level electric leakage anti- Shield, level Four residual current protective unit be used for after transformation electricity consumption carry out level Four leakage protection, end residual current protective unit for pair Electricity consumption after transformation carries out isolating and protecting, bypasses the immediate leadership and jumps signal acquisition unit for acquiring level-one residual current protective unit, second level electric leakage The residual voltage current information of protection location, three-level residual current protective unit and level Four residual current protective unit operation is bypassed the immediate leadership and is jumped Signal processing unit is used to carrying out the residual voltage current information of acquisition into processing conversion, bypasses the immediate leadership and jumps regulation unit for controlling one Grade residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four residual current protective unit are at work Time delay condition.
5. leak(age) test according to claim 1, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, which is characterized in that institute Level-one residual current protective unit, second level residual current protective unit, three-level residual current protective unit and level Four residual current protective unit is stated to be all made of Model BKD20-400 Protection for Mine Vacuum Feed Switch, end residual current protective unit use KBZ20-400 vacuum feed switch.
6. leak(age) test according to claim 1, which is bypassed the immediate leadership, jumps malfunction system compatible with mobile substation, which is characterized in that institute Total power distribution unit is stated using PBG-400 mineral high-voltage vacuum distribution device for explosion-proof type permanent, distribution electric unit uses PBG- 200 mineral high-voltage vacuum distribution device for explosion-proof type permanent, mobile voltage transformation unit use the mobile substation of KBSGZY-166.
CN201910347453.4A 2019-04-28 2019-04-28 Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application Pending CN110086149A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910347453.4A CN110086149A (en) 2019-04-28 2019-04-28 Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910347453.4A CN110086149A (en) 2019-04-28 2019-04-28 Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application

Publications (1)

Publication Number Publication Date
CN110086149A true CN110086149A (en) 2019-08-02

Family

ID=67417171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910347453.4A Pending CN110086149A (en) 2019-04-28 2019-04-28 Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application

Country Status (1)

Country Link
CN (1) CN110086149A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201478797U (en) * 2009-08-31 2010-05-19 莱芜市泰山阳光电器有限公司 Mine low voltage electric network flame-proof type timing sequence identification concentrate select-leakage protection device
CN102005745A (en) * 2010-12-07 2011-04-06 傅桂兴 IT power distribution system of 380/220V low voltage network and leakage protector thereof
CN202940556U (en) * 2012-09-04 2013-05-15 北京矿能科技有限公司 Mining explosion-proof type low-voltage power grid multi-level electric leakage protector
CN204441767U (en) * 2015-01-08 2015-07-01 西门子变压器(武汉)有限公司 Mobile substation
CN205377447U (en) * 2015-12-03 2016-07-06 鞍钢集团矿业公司 Mobile substation intelligence monitoring device
CN108983024A (en) * 2018-07-14 2018-12-11 山东工商学院 Mining earth leakage protective test and distant place closing device
CN208656407U (en) * 2018-05-14 2019-03-26 国电龙源电气有限公司 The protection system for preventing mediate contact from getting an electric shock

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201478797U (en) * 2009-08-31 2010-05-19 莱芜市泰山阳光电器有限公司 Mine low voltage electric network flame-proof type timing sequence identification concentrate select-leakage protection device
CN102005745A (en) * 2010-12-07 2011-04-06 傅桂兴 IT power distribution system of 380/220V low voltage network and leakage protector thereof
CN202940556U (en) * 2012-09-04 2013-05-15 北京矿能科技有限公司 Mining explosion-proof type low-voltage power grid multi-level electric leakage protector
CN204441767U (en) * 2015-01-08 2015-07-01 西门子变压器(武汉)有限公司 Mobile substation
CN205377447U (en) * 2015-12-03 2016-07-06 鞍钢集团矿业公司 Mobile substation intelligence monitoring device
CN208656407U (en) * 2018-05-14 2019-03-26 国电龙源电气有限公司 The protection system for preventing mediate contact from getting an electric shock
CN108983024A (en) * 2018-07-14 2018-12-11 山东工商学院 Mining earth leakage protective test and distant place closing device

Similar Documents

Publication Publication Date Title
CN209375132U (en) The full compensation device of single phase grounding current of electric power network is realized using Z-type compensator transformer
CN206248769U (en) A kind of electric automobile car body Insulation Inspection System
CN109193586A (en) A kind of both-end HVDC transmission line differential relaying algorithm
CN205263238U (en) Join in marriage power system fault travelling wave positioning system
CN103675591A (en) Multipoint insulation fault detection circuit of power battery output bus
CN102890185A (en) Grounding leakage current detecting device for train power supply system
CN207719893U (en) A kind of intelligent front end acquisition measure and control device
CN110086149A (en) Leak(age) test, which is bypassed the immediate leadership, jumps malfunction compatible with mobile substation and application
CN102004213A (en) Direct-detection type intelligent direct-current system insulation and state diagnosis instrument
CN102109557A (en) Real-time on-line monitoring device for power-frequency electromagnetic data
CN105529766B (en) A kind of anti-overcharge device applied to S4R type circuit
CN106782719A (en) Presurized water reactor power generator turbine has tripped sign signal generating method
CN205986095U (en) Earth fault protection system of track traffic DC traction system
CN203086106U (en) Low-voltage electric shock security apparatus
CN100389527C (en) Earthing compensation process for mine low-voltage electricity grid selective leakage protection system
CN101645594A (en) Synthetical leakage-selection module for longitudinal and horizontal timing sequence identification of industrial and mining low-voltage electric network
CN204479662U (en) A kind of lightning arrester service data pen recorder
CN106685090B (en) A kind of plug-in unit online test method of micro-capacitance sensor locality protection control integrated apparatus
CN207623458U (en) A kind of New insulated monitoring device with voltage compensation
CN201974485U (en) Power frequency electromagnetic data real-time online monitoring device
CN207732514U (en) A kind of direct current cabinet
CN103941082B (en) High-voltage electric energy direct metering device and method with double-channel data redundancy
CN201828640U (en) Direct-detecting intelligent apparatus for diagnosing insulation and status of direct-current (DC) system
CN105048631B (en) A kind of multi-functional Top-down design device towards interval
CN102061940A (en) Feed transducer for detecting differential mode leakage current of power cable

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190802

RJ01 Rejection of invention patent application after publication