CN110080801A - The repairing structure and its construction method of a kind of tunnel breakage section of jurisdiction - Google Patents

The repairing structure and its construction method of a kind of tunnel breakage section of jurisdiction Download PDF

Info

Publication number
CN110080801A
CN110080801A CN201910463278.5A CN201910463278A CN110080801A CN 110080801 A CN110080801 A CN 110080801A CN 201910463278 A CN201910463278 A CN 201910463278A CN 110080801 A CN110080801 A CN 110080801A
Authority
CN
China
Prior art keywords
jurisdiction
section
breaking point
tunnel
plugging plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910463278.5A
Other languages
Chinese (zh)
Other versions
CN110080801B (en
Inventor
郭旭东
毛武峰
徐文田
麦家儿
刘健美
郭敏
柳宪东
王建
史海欧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Metro Design and Research Institute Co Ltd
Original Assignee
Guangzhou Metro Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Metro Design and Research Institute Co Ltd filed Critical Guangzhou Metro Design and Research Institute Co Ltd
Priority to CN201910463278.5A priority Critical patent/CN110080801B/en
Publication of CN110080801A publication Critical patent/CN110080801A/en
Application granted granted Critical
Publication of CN110080801B publication Critical patent/CN110080801B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of repairing structure of tunnel breakage section of jurisdiction and its construction methods, and repairing structure includes inside repairing structure and outside repairing structure;It includes stiffener assembly and permanent plugging plate that structure is repaired in inside;Stiffener assembly is fixed on the inside of section of jurisdiction around breaking point, and the first waterproof filled layer is additionally provided between stiffener assembly and section of jurisdiction, and corresponding first waterproof filled layer is equipped with injected hole on stiffener assembly;Permanent plugging plate corresponds to breaking point setting and blocks breaking point;Outside repairing structure includes pouring cage and several joint bars, pours cage and is fixed on the outside of breaking point and blocks breaking point;Breaking point is inserted into one end of joint bar, and other end insertion pours cage, pours cage, joint bar and breaking point and pours fixed formed and pours building body;The outer surface for pouring building body is additionally provided with water repellent component;Method includes installation stiffener assembly;Slip casting blocks;Earth excavation;Permanent plugging plate is installed;Outside pouring molding;Construction waterproof component.Repairing structural strength of the invention is high, and waterproof performance is good, highly-safe.

Description

The repairing structure and its construction method of a kind of tunnel breakage section of jurisdiction
Technical field
The invention belongs to tunnel duct piece recovery technique fields, and in particular to a kind of repairing structure of tunnel breakage section of jurisdiction and its Construction method.
Background technique
As a city track traffic engineering new round is built, the subway transportation transport network to extend in all direction has been constructed for city, While bringing convenient trip further for citizen, the scale and difficulty of operation are increased, tunnel duct piece is by external environment operation Infringement is difficult to avoid that.
Such as some engineer operations of earth's surface cause the tunnel duct piece of underground impaired, borer drill rod or impact suffered by tunnel duct piece It is through and through wound that hammer, which destroys, by surface of a wound branch above tunnel horizontal center line 180 ° of range any positions, cause structure broken Damage range and situation most serious region, which are located on the outside of section of jurisdiction, meets native face, and side back soil face wound area is often only outside in section of jurisdiction 1/3~1/2.
Processing method in tunnel substantially by carrying out at present, processing sequence are as follows: cuts the coagulation that breakage does not fall or cracks Native fragment;Dregs dust is removed with pressure cleaning water at fragmentation surface;Segment damage range is measured, reinforced mesh is made;Pipe Piece steel planting, assembling reinforcement mesh sheet;It is pasted using cement mortar floating;Steel plate is reinforced in installation.
But due to the buried underground in tunnel, and it is limited by the influence of the external factor such as place, existing pipeline, traffic, often to pipe Meeting native face on the outside of piece can not be handled, but often not have section of jurisdiction outer surface treatment conditions in tunnel, lead to damaged model on the outside of section of jurisdiction It encloses and is exposed within the scope of the soil body, influenced by sulfate ion, Chloride Attack in the soil body and underground water, over time tunnel segment structure There are security risks for durability and stress.
Tunnel duct piece is bending stress component, and reinforcing bar and coagulation earth cooperation are held moment of flexure and shearing.Since breakage is original After structural concrete peels off, though being used as reinforcement measure after smoothing out using reinforced mesh and cement mortar filling, cement mortar is strong Degree, compactness, viscosity, durability etc. are often unable to reach original section of jurisdiction form concrete intensity (strength grade C50), and examine Consider Influence to operation, dynamic load is larger, and chip off-falling again easily occurs during long-term operation, causes safely to the train for having opened operation Greater risk.
Therefore, it is necessary to a kind of new technologies, and to solve in the prior art, to the damaged reparation of segment inside tunnel, there are relatively strong winds The problem of danger.
Summary of the invention
To solve the above problem in the prior art, the present invention provides a kind of repairing structure of tunnel breakage section of jurisdiction and its Construction method, structural strength is high after repairing, and waterproof performance is good, highly-safe.
The invention adopts the following technical scheme:
Structure is repaired in a kind of repairing structure of tunnel breakage section of jurisdiction, including inside repairing structure and outside, and the inside is repaired It mends structure and the inner side and outer side that structure is separately fixed at the breaking point of section of jurisdiction is repaired in outside;
The inside repairing structure includes stiffener assembly and permanent plugging plate;The stiffener assembly is around the damaged solid point It is scheduled on the inside of the section of jurisdiction, the first waterproof filled layer, the reinforcement group are additionally provided between the stiffener assembly and the section of jurisdiction The first waterproof filled layer is corresponded on part equipped with injected hole;The permanent plugging plate is arc-shaped and section of jurisdiction phase with the tunnel It adapts to, the permanent plugging plate corresponds to the breaking point setting and blocks breaking point, the permanent plugging plate and the reinforcement group Part is fixedly connected;
The outside repairing structure includes pouring cage and several joint bars, the outside for pouring cage and being fixed on the breaking point And the breaking point is blocked;The breaking point is inserted into one end of the joint bar, pours cage described in other end insertion, described to pour Cage, joint bar and breaking point pour fixed formed and pour building body;The outer surface for pouring building body is additionally provided with water repellent component.
It is further used as the improvement of technical solution of the present invention, and the stiffener assembly includes circumferential reinforcer and axial reinforcement Part;
The circumferential direction reinforcer is arranged circumferentially along the tunnel, and the circumferential direction reinforcer is bonded fixation, institute with the section of jurisdiction It states circumferential reinforcer and is equipped with the first notch being adapted with the permanent plugging plate, the circumferential direction reinforcer and the permanent closure Plate is fixedly connected in first indentation, there;
The axial direction reinforcer is axially arranged along the tunnel, the axial direction reinforcer be fixed on the section of jurisdiction and with institute It states inner wall to be adapted, the axial direction reinforcer is equipped with the second notch being adapted with the permanent plugging plate, described axially to reinforce Part is fixedly connected with the permanent plugging plate in second indentation, there.
It is further used as the improvement of technical solution of the present invention, and the circumferential direction reinforcer is in major arc type, the circumferential reinforcement The both ends of part pass through steel corbel respectively and are fixedly connected with the railway roadbed two sides in the tunnel.
It is further used as the improvement of technical solution of the present invention, and the steel corbel is equipped with groove, is equipped in the groove several Interlaced floor is additionally provided with the drainage hole being connected to the groove on steel corbel.
It is further used as the improvement of technical solution of the present invention, and the circumferential direction reinforcer includes several reinforced sheets, several described Reinforced sheet is successively arranged circumferentially along the tunnel, and bolt is fixedly connected with or passed through by groove welding between two adjacent reinforced sheets It is fixedly connected.
It is further used as the improvement of technical solution of the present invention, and the water repellent component includes being arranged in described to pour body surface face Waterproof coating pours the sealing rod and pour in the waterproof coating outer surface that building body is arranged with the section of jurisdiction joining place around described Build molding concrete cover.
It is further used as the improvement of technical solution of the present invention, and the waterproof coating is polyurethane water-proof coating.
The construction method of the repairing structure of tunnel breakage section of jurisdiction, comprising the following steps:
S10. first the filleting of the section of jurisdiction around the breaking point is blocked using the second waterproof filled layer, then institute is installed Stiffener assembly is stated, the stiffener assembly is fixedly connected with the section of jurisdiction;
S20. by the injected hole of stiffener assembly to carrying out waterproof material slip casting between the stiffener assembly and the section of jurisdiction, Form the first waterproof filled layer;
S30. drilling machine is circled round from ground excavation using all steel casing entirely, is converted when steel sleeve is apart from section of jurisdiction 1~2m of outer wall Hand excavation is to the exposure breaking point;
S40. permanent plugging plate is installed in the inside of breaking point to block the breaking point, permanent plugging plate is added with described Strong component is connected and fixed;
S50. interfacial agents are smeared on surface at the breaking point, then install it is described pour cage and the joint bar, and by institute It states to pour cage, joint bar and breaking point and pour to be formed and described pours building body;
S60. the water repellent component described in the appearance surface construction for pouring building body.
It is further used as the improvement of technical solution of the present invention, in the S10, the interim envelope of first construction before carrying out filleting and blocking Blocking component, the temporary plugging component include temporary plugging plate and third waterproof filled layer;The temporary plugging plate is fixed on brokenly Damage point inside blocks breaking point, and the temporary plugging plate is arc-shaped to be adapted with the section of jurisdiction;The third waterproof filled layer It is filled between the section of jurisdiction and the gap of the temporary plugging plate;
Between the S30 and S40, be additionally provided with S31, remove the temporary plugging component, and to the breaking point inside and outside It is cleaned and is dried in side.
It is further used as the improvement of technical solution of the present invention, the second waterproof filled layer/third waterproof filled layer material Matter is cement base epoxy.
Compared with prior art, the invention has the benefit that
The repairing structure of tunnel breakage section of jurisdiction of the invention, by permanent plugging plate to being blocked on the inside of breaking point, And reinforce the connection of permanent plugging plate and tunnel duct piece using stiffener assembly, form whole, cooperative bearing;Again by pour cage, Joint bar carries out pouring closure on the outside of breaking point, inside and outside waterproof is carried out by the first waterproof layer and water repellent component respectively, Waterproof is taken into account on the basis of guaranteeing its structural strength, it is whole impervious to improve at breaking point outside in section of jurisdiction;
In construction method of the invention, using all steel casing circle round full drilling machine cooperation hand excavation, compared with traditional vertical shaft spray Anchor supporting hand excavation's mode, impermeability, safety, efficiency of the practice, which have, to be greatly improved, particularly with layer of sand or Muddy Bottoms The poor stratas such as soil layer, safety is more secure, and the configuration of the present invention is simple, easy for construction, construction deviation is adaptable, uses spirit It is living.
Detailed description of the invention
Technology of the invention is described in further detail with reference to the accompanying drawings and detailed description:
Fig. 1 is overall structure diagram;
Fig. 2 is the schematic diagram that structure is repaired in inside and structure is repaired in outside;
Fig. 3 is that the planar development schematic diagram after structure installs is repaired in inside in tunnel;
Fig. 4 is the diagrammatic cross-section of circumferential reinforcer, the first waterproof filled layer and section of jurisdiction;
Fig. 5 is the floor map of steel corbel;
Fig. 6 is the diagrammatic cross-section in Fig. 5 along A-A;
Fig. 7 is that two neighboring reinforced sheet passes through groove welding connection schematic diagram;
Fig. 8 is the schematic diagram that two neighboring reinforced sheet is bolted;
Fig. 9 is that temporary plugging component is mounted on the schematic diagram at breaking point.
Appended drawing reference:
Structure is repaired on the inside of 1-;11- stiffener assembly;111- circumferential direction reinforcer;1111- reinforced sheet;The first notch of 1112-; 112- axial direction reinforcer, the second notch of 1121-;113- steel corbel;1131- groove;1132- floor;1133- drainage hole;
The permanent plugging plate of 12-;13- the first waterproof filled layer;
Structure is repaired on the outside of 2-;21- pours cage;22- joint bar;23- water repellent component;231- sealing rod;232- concrete is protected Sheath;233- waterproof coating;
The section of jurisdiction 3-;31- breaking point;
4- railway roadbed;
5- temporary plugging component;51- temporary plugging plate;52- third waterproof filled layer;53- channel steel.
Specific embodiment
It is carried out below with reference to technical effect of the embodiment and attached drawing to design of the invention, specific structure and generation clear Chu, complete description, to be completely understood by the purpose of the present invention, scheme and effect.It should be noted that the case where not conflicting Under, the features in the embodiments and the embodiments of the present application can be combined with each other.The identical attached drawing mark used everywhere in attached drawing Note indicates the same or similar part.
It should be noted that unless otherwise specified, when a certain feature referred to as " fixation ", " connection " are in another feature, It can directly fix, be connected to another feature, and can also fix, be connected to another feature indirectly.In addition, this The descriptions such as upper and lower, left and right used in invention are only the mutual alignment pass relative to each component part of the present invention in attached drawing For system.
Referring to figs. 1 to Fig. 8, a kind of repairing structure of tunnel breakage section of jurisdiction, including inside repairing structure 1 and outside repairing knot Structure 2, the inside repairing structure 1 and outside repairing structure 2 are separately fixed at the inner side and outer side of the breaking point 31 of section of jurisdiction 3.
Wherein, as shown in figures 1 and 3, the inside repairing structure 1 includes stiffener assembly 11 and permanent plugging plate 12.
The stiffener assembly 11 is fixed on the inside of the section of jurisdiction 3 around the breaking point 31 by multiple bolts, guarantees The stability that stiffener assembly 11 is connect with section of jurisdiction 3.
As shown in figure 4, the first waterproof filled layer 13 is additionally provided between the stiffener assembly 11 and the section of jurisdiction 3, it is described to add The first waterproof filled layer 13 is corresponded on strong component 11 equipped with injected hole.Wherein, the first waterproof filled layer 13 uses asphalt mixtures modified by epoxy resin Rouge is formed by the injected hole pressure injection.
The permanent plugging plate 12 is arc-shaped and is adapted with the section of jurisdiction in the tunnel 3, and the permanent plugging plate 12 is corresponding The setting of breaking point 31 blocks breaking point 31, the fixed company in edge of the permanent plugging plate 12 and the stiffener assembly 11 It connects, guarantees the bonding strength of permanent plugging plate 12 and stiffener assembly 11.
Specifically, as shown in figure 3, the stiffener assembly 11 includes circumferential reinforcer 111 and axial reinforcer 112, this reality It applies in example, circumferential reinforcer 111 is equipped with two groups, and front and back is arranged side by side.
The circumferential direction reinforcer 111 is arranged circumferentially along the tunnel, and the circumferential direction reinforcer 111 is affixed with the section of jurisdiction 3 More bolts of merga pass are fixed to each other, and the circumferential direction reinforcer 111 is equipped with first be adapted with the permanent plugging plate 12 Notch 1112, the circumferential direction reinforcer 111 pass through groove solid welding with the permanent plugging plate 12 at first notch 1112 It is bolted to connection after fixed connection or bending.
After circumferential reinforcer 111 is connected with permanent plugging plate 12, formed an arch adaptable with tunnel and with 3 phase of tunnel duct piece is fixed, and whole force structure is formed.
Such as Fig. 1 and Fig. 3, the circumferential direction reinforcer 111 is in major arc type, and for the ease of installation, circumferential reinforcer 111, which divides, is Several reinforced sheets 1111, several reinforced sheets 1111 are successively arranged circumferentially along the tunnel, two adjacent reinforced sheets 1111 Between be fixedly connected by groove welding, as shown in Figure 7;Or be bolted after adjacent two reinforced sheets 1111 bending, such as Fig. 8.The both ends of the circumferential direction reinforcer 111 pass through steel corbel 113 respectively and are fixedly connected with 4 two sides of railway roadbed in the tunnel.
Such as Fig. 1, Fig. 5 and Fig. 6, the steel corbel 113 is equipped with groove 1131, is equipped with several mutual friendships in the groove 1131 Wrong floor 1132 is additionally provided with the drainage hole 1133 being connected to the groove 1131 on steel corbel 113.
Such as Fig. 3, the axial direction reinforcer 112 is axially arranged along the tunnel, perpendicular with circumferential reinforcer 111.It is described Axial reinforcer 112 is fixed on the section of jurisdiction 3 by more bolts, and the shape and the inner wall phase of axial reinforcer 112 It adapts to.The axial direction reinforcer 112 is equipped with the second notch 1121 being adapted with the permanent plugging plate 12, the axial reinforcement Part 112 passes through spiral shell after being fixedly connected or bend also by groove welding at second notch 1121 with the permanent plugging plate 12 Bolt is fixedly connected.After axial reinforcer 112 is connected with permanent plugging plate 12, forms a strip along tunnel axial direction and add Strong structure.The purpose that stiffener assembly 11 is installed on the inside of section of jurisdiction 3 is to improve stress at breaking point 31, and enhancing structure rigidity makes Section of jurisdiction 3 and 11 cooperative bearing of stiffener assembly improve structure bending resistance, shear behavior.
It should be noted that circumferential reinforcer 111, axial reinforcer 112, steel corbel 113 use Q345B galvanized steel, Permanent plugging plate 12 is galvanized steel plain sheet.The bolt respectively connected uses galvanized bolt.
Wherein, the outside repairing structure 2 includes pouring cage 21 and several joint bars 22.
It such as Fig. 1 and Fig. 2, pours cage 21 and is equipped with the double-deck steel bar stress, the length for pouring cage 21 need to be greater than the broken of tunnel duct piece 3 31 edges of damage point, to block breaking point 31 completely.The cage 21 that pours is fixed on the outside of the breaking point 31 and by institute State the closure of breaking point 31;The breaking point 31 is inserted into one end of the joint bar 22, cage 21 is poured described in other end insertion, by inserting Muscle 22 realizes the positioning to cage 21 is poured.It is described pour cage 21, joint bar 22 and breaking point 31 and pour fixed formed pour building body;It is described The outer surface for pouring building body is additionally provided with water repellent component 23.
Specifically, the water repellent component 23 includes that the waterproof coating 233 for pouring body surface face is arranged in, pours around described The sealing rod 231 that building body and 3 joining place of section of jurisdiction are arranged and the coagulation in the 233 outer surface pouring molding of waterproof coating Protective soil layer 232.Wherein, sealing rod 231 is hydroexpansivity sealing rod, and the waterproof coating 233 is polyurethane water-proof coating.
Structure 2 is repaired based on above-mentioned inside repairing structure 1 and outside, circumferential reinforcer 111, axial reinforcer 112 will Permanent plugging plate 12 is fastened on 3 inside of section of jurisdiction of tunnel breaking point 31, ensure that the whole stress of tunnel duct piece 3, and And waterproof is carried out by the first waterproof filled layer 13, enhance impermeability;Structure 2 is repaired by outside, is realized to breaking point 31 filling, the closure in outside and waterproof;Realize the comprehensive repairing and reinforcement to outside in breaking point 31.
The present invention also provides the construction methods of the repairing structure of tunnel breakage section of jurisdiction, comprising the following steps:
S10. it first constructs temporary plugging component 5, influences the installation of repairing structure to prevent from occurring after breakage leak, it is described to face When blocking component 5 include temporary plugging plate 51 and third waterproof filled layer 52;The temporary plugging plate 51 is fixed on breaking point 31 Inside blocks breaking point 31, and the third waterproof filled layer 52 is filled in the seam of the section of jurisdiction 3 and the temporary plugging plate 51 Between gap.
Wherein, temporary plugging plate 51 is fixed by channel steel 53 and tunnel duct piece 3, the outside of temporary plugging plate 51 and channel steel 53 It is welded and fixed, and then axial setting is simultaneously bolted to connection with section of jurisdiction 3 channel steel 53.The temporary plugging plate 51 it is arc-shaped with The section of jurisdiction 3 is adapted, and material is Q345B galvanized steel, and size is greater than the size of breaking point 31 so that breaking point 31 is complete It is complete to block.The installation of blocking component is to cause tunnel circumferential because of 3 structural failure of section of jurisdiction, bolt failure in order to prevent and radial change Shape, unstability etc., while preventing the soil body and underground water on the outside of tunnel from coming down in torrents in tunnel.
After installing temporary plugging component 5, using the second waterproof filled layer to the embedding of the section of jurisdiction 3 around the breaking point 31 Seam is blocked, and prevents subsequent slip casting from leaking when forming the first waterproof filled layer 13, then install the stiffener assembly 11, will The stiffener assembly 11 is fixedly connected with the section of jurisdiction 3;First installation fixed circumferential reinforcer 111 when installation, then axial add, is installed Strong part 112;When circumferential reinforcer 111 is connected with axial reinforcer 112 using groove welding, it is anti-that commissure needs to smear epoxy zinc-rich Rust paint, prevents weld seam oxidation and rusting in subsequent use process.Wherein, the second waterproof filled layer and third waterproof filled layer 52 Material be cement base epoxy.
S20. waterproof material is carried out between the stiffener assembly 11 and the section of jurisdiction 3 by the injected hole of stiffener assembly 11 Slip casting forms the first waterproof filled layer 13, as the waterproof layer of inside, enhances impermeability, after installing as shown in Figure 9.
S30. the top progress place of 3 breaking point 31 of section of jurisdiction, which is enclosed, covers, is smooth, being compacted and being laid with load-bearing steel plate, and uses people Work carries out location of the core, circles round drilling machine entirely from ground excavation, after steel sleeve revolution is sunk, using mechanical gripping using all steel casing Bucket removes the earthwork in steel sleeve, and when steel sleeve is apart from 3 outer wall vertical 1~2m of clear distance of section of jurisdiction, conversion hand excavation is to completely cruelly In the case of exposing breaking point 31 ensures to control 3 overall deformation of tunnel duct piece, steel sleeve gradually sinks until when 0.3m is pushed up in section of jurisdiction 3 Stop, 3 top of section of jurisdiction is excavated to using artificial mark spraying anchor to the small range for not having steel bushing protection of pipe, interface seepage place is used Ejection for water plugging;Preferably, convert hand excavation when steel sleeve is apart from 3 outer wall vertical clear distance 1.5m of section of jurisdiction.
S31. the temporary plugging component 5 is removed, and the interior outside of the breaking point 31 is cleaned and dried, i.e., will Temporary plugging plate 51, channel steel 53 and third waterproof filled layer 52 are all removed, and convenient for the permanent plugging plate 12 of subsequent installation and are carried out It pours.
S40. permanent plugging plate 12 is installed in the inside of breaking point 31 to block the breaking point 31, by permanent plugging plate 12 It is connected and fixed with the stiffener assembly 11, when being attached according to groove welding, commissure needs to smear epoxy zinc-enriched antirust paint.
S50. interfacial agents are smeared on surface at the breaking point 31, then install it is described pour cage 21 and the joint bar 22, And by it is described pour cage 21, joint bar 22 and breaking point 31 and pour to be formed described pour building body;
S60. after building body to be poured reaches design strength, the water repellent component 23 described in the appearance surface construction for pouring building body, i.e., Polyurethane water-proof coating 233 is smeared on the surface for pouring building body, and building body and the closely connected hydroexpansivity sealing rod of 3 joining place of section of jurisdiction are poured in edge 231, then be laid with geotextiles on its outer surface and fixed with rivet and pour 100mm thickness C20 pea gravel concreten protective layer 232, shape At complete water-proof system.
By above-mentioned construction method, by the repairing structure construction of tunnel breakage section of jurisdiction of the invention by tunnel duct piece 3 Breaking point 31 is repaired, and construction method is safe, simple, and the structure stress effect after construction is preferable, and waterproof performance is good.
Other contents of the repairing structure of tunnel breakage of the present invention section of jurisdiction and its construction method referring to the prior art, Details are not described herein.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, therefore Without departing from the technical solutions of the present invention, according to the technical essence of the invention it is to the above embodiments it is any modification, Equivalent variations and modification, all of which are still within the scope of the technical scheme of the invention.

Claims (10)

1. a kind of repairing structure of tunnel breakage section of jurisdiction, it is characterised in that: repair structure including inside and structure, institute are repaired in outside It states inside repairing structure and the inner side and outer side that structure is separately fixed at the breaking point of section of jurisdiction is repaired in outside;
The inside repairing structure includes stiffener assembly and permanent plugging plate;The stiffener assembly is fixed on around the breaking point The inside of the section of jurisdiction, is additionally provided with the first waterproof filled layer between the stiffener assembly and the section of jurisdiction, on the stiffener assembly The corresponding first waterproof filled layer is equipped with injected hole;The permanent plugging plate is arc-shaped and mutually fits with the section of jurisdiction in the tunnel It answers, the permanent plugging plate corresponds to the breaking point setting and blocks breaking point, the permanent plugging plate and the stiffener assembly It is fixedly connected;
The outside repairing structure includes pouring cage and several joint bars, and the cage that pours is fixed on the outside of the breaking point and incites somebody to action The breaking point blocks;The breaking point is inserted into one end of the joint bar, pours cage described in other end insertion, it is described pour cage, Joint bar and breaking point pour fixed formed and pour building body;The outer surface for pouring building body is additionally provided with water repellent component.
2. the repairing structure of tunnel breakage according to claim 1 section of jurisdiction, it is characterised in that: the stiffener assembly includes ring To reinforcer and axial reinforcer;
The circumferential direction reinforcer is arranged circumferentially along the tunnel, and the circumferential direction reinforcer is bonded fixation, the ring with the section of jurisdiction The first notch being adapted with the permanent plugging plate is equipped with to reinforcer, the circumferential direction reinforcer and the permanent plugging plate exist First indentation, there is fixedly connected;
The axial direction reinforcer is axially arranged along the tunnel, the axial direction reinforcer be fixed on the section of jurisdiction and with it is described interior Wall be adapted, it is described axial direction reinforcer be equipped with the permanent plugging plate be adapted the second notch, it is described axial direction reinforcer with The permanent plugging plate is fixedly connected in second indentation, there.
3. the repairing structure of tunnel breakage according to claim 2 section of jurisdiction, it is characterised in that: the circumferential direction reinforcer is in Major arc type, the both ends of the circumferential direction reinforcer pass through steel corbel respectively and are fixedly connected with the railway roadbed two sides in the tunnel.
4. the repairing structure of tunnel breakage according to claim 3 section of jurisdiction, it is characterised in that: the steel corbel is equipped with recessed Slot, the groove is interior to be equipped with several interlaced floors, is additionally provided with the drainage hole being connected to the groove on steel corbel.
5. the repairing structure of tunnel breakage according to claim 2 section of jurisdiction, it is characterised in that: it is described circumferential direction reinforcer include Several reinforced sheets, several reinforced sheets are successively arranged circumferentially along the tunnel, pass through groove between two adjacent reinforced sheets Weldering is fixedly connected or is bolted to connection.
6. the repairing structure of tunnel breakage according to claim 1 section of jurisdiction, it is characterised in that: the water repellent component includes setting Set the waterproof coating for pouring body surface face, around the sealing rod for pouring building body and section of jurisdiction joining place setting and The concrete cover of waterproof coating outer surface pouring molding.
7. the repairing structure of tunnel breakage according to claim 6 section of jurisdiction, it is characterised in that: the waterproof coating is poly- ammonia Ester waterproof coating.
8. the construction method of the repairing structure of tunnel breakage according to any one of claim 1 to 7 section of jurisdiction, feature exist In, comprising the following steps:
S10. first the filleting of the section of jurisdiction around the breaking point is blocked using the second waterproof filled layer, then described add is installed The stiffener assembly is fixedly connected by strong component with the section of jurisdiction;
S20. it is formed by the injected hole of stiffener assembly to waterproof material slip casting is carried out between the stiffener assembly and the section of jurisdiction First waterproof filled layer;
S30. drilling machine is circled round from ground excavation using all steel casing entirely, is converted when steel sleeve is apart from section of jurisdiction 1~2m of outer wall artificial It is excavated to the exposure breaking point;
S40. permanent plugging plate is installed in the inside of breaking point to block the breaking point, by permanent plugging plate and the reinforcement group Part is connected and fixed;
S50. interfacial agents are smeared on surface at the breaking point, then install it is described pour cage and the joint bar, and poured described It builds cage, joint bar and breaking point and pours to be formed and described pour building body;
S60. the water repellent component described in the appearance surface construction for pouring building body.
9. the construction method of the repairing structure of tunnel breakage according to claim 8 section of jurisdiction, it is characterised in that:
In the S10, temporary plugging component of first constructing before carrying out filleting and blocking, the temporary plugging component includes temporary plugging Plate and third waterproof filled layer;The temporary plugging plate is fixed on the inside of breaking point and blocks breaking point, the temporary plugging plate It is arc-shaped to be adapted with the section of jurisdiction;The third waterproof filled layer is filled in the gap of the section of jurisdiction Yu the temporary plugging plate Between;
Between the S30 and S40, be additionally provided with S31, remove the temporary plugging component, and to the interior outside of the breaking point into Row cleaning and drying.
10. the construction method of the repairing structure of tunnel breakage according to claim 9 section of jurisdiction, it is characterised in that: described Two waterproof filled layers/third waterproof filled layer material is cement base epoxy.
CN201910463278.5A 2019-05-30 2019-05-30 Repair structure of damaged tunnel segment and construction method thereof Active CN110080801B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910463278.5A CN110080801B (en) 2019-05-30 2019-05-30 Repair structure of damaged tunnel segment and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910463278.5A CN110080801B (en) 2019-05-30 2019-05-30 Repair structure of damaged tunnel segment and construction method thereof

Publications (2)

Publication Number Publication Date
CN110080801A true CN110080801A (en) 2019-08-02
CN110080801B CN110080801B (en) 2024-10-01

Family

ID=67422636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910463278.5A Active CN110080801B (en) 2019-05-30 2019-05-30 Repair structure of damaged tunnel segment and construction method thereof

Country Status (1)

Country Link
CN (1) CN110080801B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485922A (en) * 2020-05-13 2020-08-04 陕西上坤蓝箭科技有限公司 E L F railway tunnel water leakage, block falling and grout turnover disease treatment method
CN113090291A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair and reinforcement complete equipment
CN113090292A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair reinforcement intelligent complete equipment
CN113090293A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repairing and reinforcing mechanical arm equipment
CN113431610A (en) * 2021-05-31 2021-09-24 中铁工程服务有限公司 Shield subway tunnel segment repair control method and device and storage medium
CN118601626A (en) * 2024-08-05 2024-09-06 济南轨道中铁管片制造有限公司 Tunnel segment unfilled corner repairing device and repairing process

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001295591A (en) * 2000-04-14 2001-10-26 Kawasaki Heavy Ind Ltd Repairing method for tunnel lining concrete
CN207568618U (en) * 2017-10-16 2018-07-03 广州地铁设计研究院有限公司 tunnel reinforcement structure
CN208718690U (en) * 2018-07-19 2019-04-09 北京建工土木工程有限公司 The reparation plugging structure of windowing in long range shield tunnel
CN210164483U (en) * 2019-05-30 2020-03-20 广州地铁设计研究院股份有限公司 Repair structure of damaged section of jurisdiction in tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001295591A (en) * 2000-04-14 2001-10-26 Kawasaki Heavy Ind Ltd Repairing method for tunnel lining concrete
CN207568618U (en) * 2017-10-16 2018-07-03 广州地铁设计研究院有限公司 tunnel reinforcement structure
CN208718690U (en) * 2018-07-19 2019-04-09 北京建工土木工程有限公司 The reparation plugging structure of windowing in long range shield tunnel
CN210164483U (en) * 2019-05-30 2020-03-20 广州地铁设计研究院股份有限公司 Repair structure of damaged section of jurisdiction in tunnel

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485922A (en) * 2020-05-13 2020-08-04 陕西上坤蓝箭科技有限公司 E L F railway tunnel water leakage, block falling and grout turnover disease treatment method
CN113090291A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair and reinforcement complete equipment
CN113090292A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair reinforcement intelligent complete equipment
CN113090293A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repairing and reinforcing mechanical arm equipment
CN113431610A (en) * 2021-05-31 2021-09-24 中铁工程服务有限公司 Shield subway tunnel segment repair control method and device and storage medium
CN118601626A (en) * 2024-08-05 2024-09-06 济南轨道中铁管片制造有限公司 Tunnel segment unfilled corner repairing device and repairing process
CN118601626B (en) * 2024-08-05 2024-10-01 济南轨道中铁管片制造有限公司 Tunnel segment unfilled corner repairing device and repairing process

Also Published As

Publication number Publication date
CN110080801B (en) 2024-10-01

Similar Documents

Publication Publication Date Title
CN110080801A (en) The repairing structure and its construction method of a kind of tunnel breakage section of jurisdiction
US20220145568A1 (en) Concrete inside interface processing structure and method for secant pile construction
CN105736001B (en) A kind of construction method using prefabricated parts subway station
CN101294447B (en) Buildings pile underpinning method
CN106050266A (en) Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN105256810B (en) Construction method for round underground continuous wall two-in-one structure
CN206189455U (en) Piping lane
CN107816117A (en) A kind of large-scale pressure current box culvert is not cut off the water outer restorative procedure
CN104806274A (en) Large-span long-distance underground space main body supporting integrated structure and construction method
CN113668612A (en) Modular combined prefabricated electric power working well and construction method thereof
CN110306559A (en) A kind of construction method of subway entrance support pile
CN104533468B (en) A kind of subway tunnel the wall of a borehole post-grouting method
KR101029311B1 (en) Non-excavation laying method for pipeline and tunnel using temporary composite pipe
CN114961788A (en) Construction method and construction structure for repairing damaged segments of shield tunnel
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
CN108808594A (en) The cable penetration sleeve structure and its construction method of slip casting sealing
CN210380191U (en) Lightweight power communication combination prefabricated cable channel
KR102103978B1 (en) Reinforcement and waterproof structure of vertical shafts for utility interface
CN210164483U (en) Repair structure of damaged section of jurisdiction in tunnel
CN105673933A (en) Waterproof sealing device for post-through-wall pipeline and construction method
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN110359450B (en) Assembled round pile structure and construction method
CN211598680U (en) Anti reinforced structure that floats of operation subway tunnel
CN210460663U (en) Detachable steel corrugated plate enclosure dado
CN209324383U (en) A kind of joint structure of Shield-bored tunnels and station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant