CN110080521A - Big section prestressed frame formwork system and construction method - Google Patents

Big section prestressed frame formwork system and construction method Download PDF

Info

Publication number
CN110080521A
CN110080521A CN201910419596.1A CN201910419596A CN110080521A CN 110080521 A CN110080521 A CN 110080521A CN 201910419596 A CN201910419596 A CN 201910419596A CN 110080521 A CN110080521 A CN 110080521A
Authority
CN
China
Prior art keywords
plate
baffle
bar
sliding
connect
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910419596.1A
Other languages
Chinese (zh)
Other versions
CN110080521B (en
Inventor
项光森
李益琍
赵银标
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENZHOU ZHONGSHUN BUILDING ENGINEERING Co Ltd
Original Assignee
WENZHOU ZHONGSHUN BUILDING ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENZHOU ZHONGSHUN BUILDING ENGINEERING Co Ltd filed Critical WENZHOU ZHONGSHUN BUILDING ENGINEERING Co Ltd
Priority to CN201910419596.1A priority Critical patent/CN110080521B/en
Publication of CN110080521A publication Critical patent/CN110080521A/en
Application granted granted Critical
Publication of CN110080521B publication Critical patent/CN110080521B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/22Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material with parts being prestressed
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor

Abstract

The present invention provides a kind of big section prestressed frame beam formwork system and construction method, it is characterised in that hole bracket is arranged between opposite hole plate;When Vierendeel girder strutting system is set up, 2 column sides hoop plate is circumferentially set on the outside of bolster stake, laterally supports beam and sliding support beam in the outside setting of the column side hoop plate of the upper and lower respectively;Beam bottom board is set on carrying platform plate, and reinforcing bar control position body is set on beam bottom board;After adjusting pressing plate regulation cock connect the connection step of Combined type pressing plate with beam side, fastening screw is set between pressing plate coupling bar;Shuttering supporting reinforcement is carried out by lateral compression bar, vertical compression bar;When Vierendeel girder maintenance construction, the top for controlling position baffle is set to be connected with sliding curing means, and downpipe is set between sliding curing means and water tank.The present invention can promote concreting and maintenance construction quality, the stress performance for improving constructing structure, the difficulty for reducing formwork erection and positioning, protection construction environment.

Description

Big section prestressed frame formwork system and construction method
Technical field
The present invention relates to building engineering field, in particular to a kind of stress performance that can improve constructing structure reduces mould The big section prestressed frame beam formwork system and construction method of difficulty, protection construction environment that plate is installed and positioned, are suitable for Big section prestressed frame beam construction work.
Background technique
With the stable and rapid development of Chinese national economy, concrete structure is gradually sent out to the direction of large span, big height There is a large amount of big section frame beam column construction in exhibition.Relative to conventional concrete beam column construction, it is characterized in that member section Size is big, formwork system bearing requirements are high, concrete pouring construction controls difficulty etc.
Have a kind of rc-frame-beam formwork-support, including horizontal support bar and longitudinal bracing in the prior art Bar, horizontal support bar and vertical supporting bar are located at same level and orthogonal;Horizontal support bar include horizontal extension bar and Two support side poles, support side pole include end connection vertical bar and transverse bar member, the both ends of horizontal extension bar respectively with Two transverse bar member ends are flexibly connected, and transverse bar member is connect with vertical supporting bar.The structure overcomes existing to a certain extent The support device of some rc-frame-beams is troublesome in poeration, and stability of strutting system is poor, is also easy to produce lacking for swollen mould, race mould and inclined mould It falls into, achieves preferable effect in suitable operating condition, but in climbing shuttering formwork system globality, the laying of reduction scene and positioning Difficulty etc. waits further to study.
In consideration of it, concreting and maintenance construction quality can be promoted, improve constructing structure by urgently inventing one kind at present Stress performance, reduce formwork erection and positioning difficulty, protect the big section prestressed frame beam formwork system of construction environment And construction method.
Summary of the invention
Concreting and maintenance construction quality can be not only promoted the purpose of the present invention is to provide a kind of, and can be with Improve the big section prestressed frame beam formwork of the stress performance of constructing structure, the difficulty that formwork erection and positioning can also be reduced System and construction method.
In order to realize any of the above goal of the invention, the present invention provides a kind of big section prestressed frame beam formwork system and applies Work method, comprising the following steps:
1) preparation of construction: the review of Vierendeel girder field position and concrete mix determine that the technique for determining site operation is quasi- The material and device that standby construction needs;
2) hole bracket is laid: one of outsourcing frid is respectively set on the sky side of facing of opposite hole plate, and makes to press spiral shell One end of bar is connect with slide plate coupling bar, and the other end is bolted with press, makes outsourcing frid and hole plate by pressing bolt It is connected firmly;Pressure-bearing crossbeam is placed in pressing between baffle on outsourcing frid, and by nestled bolt by pressure-bearing crossbeam and tightly Pressure transverse slat is connected firmly;In the bottom end of reinforcement dagger, dagger bottom plate is set;By spacer ferrule sleeve-board on reinforcement dagger, using hoop plate Two blocks of spacer ferrule plates are connected firmly by bolt by connection otic placode;The both ends of positioning supporting rod are made to pass through strut shaft and strut bottom Plate is connected with spacer ferrule plate;
3) Vierendeel girder strutting system is set up: be circumferentially arranged on the outside of bolster stake 2 column sides hoop plate, and column side hoop plate with Separate type cage plate and seam obturator are set between bolster stake;Beam is laterally supportted in the outside setting of the column side hoop plate on upper layer, makes cross It is welded to connect to the support side Liang Yuzhu hoop plate, and oblique strut and strut tune bolt laterally is being set between support beam and separate type cage plate; First strutbeam bottom plate is connected with longitudinal strutbeam in an entirety, and lateral connection pull rod and drawing are set between adjacent longitudinal strutbeam Bar regulation cock, then strutbeam bottom plate is placed on laterally support beam, the plan-position of longitudinal strutbeam is adjusted by pull rod regulation cock;In cross Falcon is limited to setting bottom plate between support beam and strutbeam bottom plate, and carrying platform plate and longitudinal strutbeam is made to pass through connection boots cap connection; The outside setting sliding support beam of hoop plate in the column side of lower layer, and keep the sliding beam drag-line on the outside of sliding support beam and separate type cage plate logical Cross the connection of guy anchor solid plate;Setting sliding conduit and sliding baffle on sliding support beam;Material storage box and sliding baffle it Between setting sliding strut, sliding support beam between be arranged bottom skid beam;
4) Vierendeel girder formwork erection positions: checking spatial position and the stability of longitudinal strutbeam and carrying platform plate;It is holding Setting limit upright bar on carrying platform plate, and upright bar diagonal brace is set between limit upright bar and carrying platform plate;In limit upright bar Bar top bracing plate| is arranged in top, and fagging stiffening plate is arranged between limit upright bar and bar top bracing plate|;It is arranged on carrying platform plate Beam bottom board, and beam side is placed in the inside of the side form bottom baffle of beam bottom board, and pass through the side form connecting rod of beam side bottom It is connect after side form bottom baffle with side form fastening bolt;The mould side coupling bar on the outside of beam side and limit upright bar is set to pass through transverse connecting rod Connection;First adjusting pressing plate regulation cock makes the connection step of Combined type pressing plate be connected firmly with beam side, then the pressure opposite in mirror image Fastening screw is set between plate coupling bar, and passes through the lateral position of tensioning fastening bolt control combination formula pressing plate;On beam bottom board Reinforcing bar control position body and bottom bracing embedded groove are set, and baffle is only starched in setting between reinforcing bar control position body and bottom bracing embedded groove, and in bottom bracing Bed die stiffening plate is arranged in the lower part of embedded groove;
5) shuttering supporting reinforcement: column side is set on bolster stake and binds round plate, and connection otic placode is connected by jail by hoop crab bolt Gu;The outside setting hoop side transverse slat of hoop plate in column side, and compression bar first baffle is set on hoop side transverse slat;In beam bottom board and carrying The seam crossing arranging plate end joint filling layer of column, compression bar second baffle is arranged in lower surface, in compression bar first baffle and compression bar second baffle Between lateral compression bar is set;Vertical compression bar is set between beam bottom board and hoop side transverse slat;
6) concrete pouring construction: scene review formwork erection quality, to concrete pouring construction, synchronously control Vierendeel girder The flatness on surface;
7) Vierendeel girder maintenance construction: setting support beam stanchion on the carrying platform plate at the top of longitudinal strutbeam, and make to support beam branch The top of column is connect with overhanging support beam, the setting support beam diagonal brace between overhanging support beam and carrying platform plate;In the upper of overhanging support beam Surface setting control position baffle and rope keep off pier, and the setting control position rope between control position baffle and rope gear pier;Make to control position baffle Top with sliding curing means be connected, and make sliding curing means on elastic connection plate be completely embedded with Vierendeel girder;In cunning It moves between curing means and water tank and downpipe is set.
According to another aspect of the present invention, the present invention provides a kind of big section prestressed frame beam formwork system, feature It is, is constructed and completed according to the construction method of the big section prestressed frame beam formwork system of any description above.
Compared with the prior art, the present invention has the following beneficial effects:
(1) top pressure screw rod of big section prestressed frame beam formwork system provided by the invention is connected with globality slide plate, It is convenient that scene is laid, and externally can apply lateral pressure on top surface by packet slot plate, improves the globality of structure;Meanwhile in bearing beam It is provided between outsourcing channel steel and presses baffle and press transverse slat, can effectively limit the deformation and displacement of pressure-bearing crossbeam;In reinforcement The spacer ferrule plate being connected with positioning supporting rod is set on dagger, the difficulty of reinforcement dagger positioning can be reduced.
(2) big section prestressed frame beam formwork system provided by the invention is provided with the double-deck column side and binds round plate, and in column side The inside for binding round plate is provided with separate type cage plate, can effectively promote the bonding strength of support construction and bolster stake;The cross of longitudinal strutbeam It can be adjusted to position as desired by pull rod regulation cock, reduce longitudinal strutbeam and carrying platform plate scene is laid and determined The difficulty of position;In addition, the present invention be provided with can horizontal sliding material storage box, material storage can reduced, collecting difficulty Meanwhile the construction environment that keeps the scene intact.
(3) reinforcing bar control position body is arranged on beam bottom board and can expire for big section prestressed frame beam formwork system provided by the invention The requirement of sufficient beam bottom steel bar cage protecting layer thickness dynamic control;Meanwhile the present invention is synchronous using side bottom baffle, lateral connection Bar, Combined type pressing plate and fastening bolt position beam side, can be while reducing formwork erection difficulty, and climbing shuttering is fixed The precision of position.
(4) present invention can apply vertically with lateral pressure on top surface beam bottom board by the way that vertical pressing plate is synchronous with lateral compression bar, keep away Exempt from the generation of the quick-fried modulus problem of beam-ends.
(5) present invention carries out wet curing to beams of concrete using sliding curing means, can promote concrete curing construction Quality;Meanwhile the frid that intercepts water of present invention sliding curing means is connected with water tank, can avoid maintenance environmental pollution by water Meanwhile realizing the recycling of curing water.
Detailed description of the invention
Fig. 1 is the construction process figure of the big section prestressed frame beam formwork system of an embodiment according to the present invention.
Fig. 2 is the structural schematic diagram that the hole bracket based on Fig. 1 is laid.
Fig. 3 is the structural schematic diagram that the monoblock type slide plate of Fig. 2 is connect with slide plate link slot.
Fig. 4 is the structural schematic diagram that the Vierendeel girder strutting system of Fig. 1 is set up.
Fig. 5 is the schematic cross-sectional view of longitudinal strutbeam portion structure of Fig. 4.
Fig. 6 is Fig. 4 bottom skid beam and sliding support beam attachment structure schematic diagram;
Fig. 7 is that the beam forms of Fig. 1 installs the schematic cross-sectional view of structure.
Fig. 8 is that the beam forms of Fig. 1 installs the schematic longitudinal section of structure.
Fig. 9 is the structural schematic diagram that the reinforcing bar control position body of Fig. 7 is connect with beam bottom board.
Figure 10 is the structural schematic diagram of the Combined type pressing plate of Fig. 7 and Fig. 8.
Figure 11 is the structural schematic diagram of the shuttering supporting reinforcing construction of Fig. 1.
Figure 12 is the structural schematic diagram of the Vierendeel girder maintenance construction of Fig. 1.
Figure 13 is the cross-sectional view of the sliding curing means of Figure 12.
In figure: 1- Vierendeel girder;The hole 2- plate;3- outsourcing frid;4- top pressure screw rod;5- slide plate coupling bar;6- presses bolt; 7- pressure-bearing crossbeam;8- presses baffle;9- nestled bolt;10- presses transverse slat;11- reinforcement dagger;12- dagger bottom plate;13- positioning Bind round plate;14- binds round crab bolt;15- connection otic placode;16- positioning supporting rod;17- strut shaft;18- strut bottom plate;Bind round plate in 19- column side; 20- bolster stake;21- separate type cage plate;22- seam obturator;23- laterally supports beam;The oblique strut of 24-;25- strut tune bolt;26- Strutbeam bottom plate;The longitudinal direction 27- strutbeam;28- lateral connection pull rod;29- pull rod regulation cock;30- water supply pump;31- bottom plate limits falcon; 32- carrying platform plate;33- connection boots cap;34- sliding support beam;35- sliding beam drag-line;36- guy anchor solid plate;37- slippage slot Road;38- slides baffle;39- material storage box;40- slides strut;41- bottom skid beam;42- limits upright bar;43- upright bar diagonal brace; 44- bar top bracing plate|;45- fagging stiffening plate;46- beam bottom board;47- beam side;48- side form bottom baffle;49- side form connecting rod;50- Filter residue plate;51- side form fastening bolt;52- mould side coupling bar;53- transverse connecting rod;54- pressing plate regulation cock;55- Combined type pressing plate; 56- connection step;57- pressing plate coupling bar;58- fastening screw;59- tensioning fastening bolt;60- reinforcing bar control position body;The insertion of 61- bottom bracing Slot;62- only starches baffle;63- bed die stiffening plate;64- binds round side transverse slat;65- compression bar first baffle;66- plate end joint filling layer;67- pressure Bar second baffle;68- transverse direction compression bar;The vertical compression bar of 69-;70- supports beam stanchion;71- overhanging support beam;72- supports beam diagonal brace;73- control Position baffle;74- rope keeps off pier;75- controls position rope;76- slides curing means;77- elastic connection plate;78- water tank;79- is fallen Water pipe;80- slide plate link slot;81- monoblock type slide plate;82- baffle side stay;83- slide plate limiting slot;84- fountain head;85- slide plate Connecting plate;86- cage plate connecting shaft;87- cage plate fastening rib;88- slides fagging;89- steel reinforcement cage bottom bracing;90- bottom bracing adjusting rod; 91- rotational handle;Bolt built in 92-;93- intercepts water frid;94- moves water pipe;95- combined closing plate;96- water pipe buttress;97- Water supplying pipe;The hole 98- bracket.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
It is understood that term " one " is interpreted as " at least one " or " one or more ", i.e., in one embodiment, The quantity of one element can be one, and in a further embodiment, the quantity of the element can be it is multiple, term " one " is no It can be interpreted as the limitation to quantity.
Fig. 1 is the big section prestressed frame beam formwork system construction process figure of an embodiment according to the present invention, reference Shown in Fig. 1, the construction method of big section prestressed frame beam formwork system, including following construction procedure:
1) preparation of construction: the review of Vierendeel girder (1) field position and concrete mix determine, determine the work of site operation Skill prepares material and device that construction needs;
2) hole bracket is laid: one of outsourcing frid (3) is respectively set on the sky side of facing of opposite hole plate (2), and makes One end of top pressure screw rod (4) is connect with the slide plate coupling bar (5) being placed on outsourcing frid (3), and the other end and press bolt (6) are even It connects, be connected firmly outsourcing frid (3) and hole plate (2);Pressure-bearing crossbeam (7) is placed on outsourcing frid (3) and presses baffle (8) Between, and fixed be placed on pressure-bearing crossbeam (7) presses transverse slat (10), specifically, can be horizontal by pressure-bearing by nestled bolt (9) Beam (7) is connected firmly with transverse slat (10) is pressed;Dagger bottom plate (12) are set in the bottom end of reinforcement dagger (11), are placed in pressure-bearing crossbeam (7) on;Spacer ferrule plate (13) is placed on reinforcement dagger (11) and is fixed, in an embodiment of the present invention, spacer ferrule plate (13) two pieces of spacer ferrule plates (13) are connected firmly by connection otic placode (15) using hoop crab bolt (14);Make positioning supporting rod (16) Both ends pass through strut shaft (17) and connect with strut bottom plate (18) and spacer ferrule plate (13), be placed on pressure-bearing crossbeam (7);
3) Vierendeel girder strutting system is set up: at least 2 column sides hoop plate (19) is circumferentially set on the outside of bolster stake (20), and Separate type cage plate (21) and seam obturator (22) are set gradually between column side hoop plate (19) and bolster stake (20);On upper layer Outside setting laterally support beam (23) of plate (19) is bound round in column side, in one embodiment of this invention, laterally supports beam (23) and column side is bound round Plate (19) is welded to connect, and oblique strut (24) and strut tune bolt laterally is being arranged between support beam (23) and separate type cage plate (21) (25);It is first that strutbeam bottom plate (26) and longitudinal strutbeam (27) connection is integral, and set between adjacent longitudinal strutbeam (27) Lateral connection pull rod (28) and pull rod regulation cock (29) are set, then strutbeam bottom plate (26) is placed in laterally support beam (23), passes through drawing Bar regulation cock (29) adjusts the plan-position of longitudinal strutbeam (27);In one embodiment of this invention, laterally support beam (23) with Bottom plate is set between strutbeam bottom plate (26) and limits falcon (31), and carrying platform plate (32) and longitudinal strutbeam (27) is made to pass through connection boots Cap (33) connection;Lower layer column side hoop plate (19) outside setting sliding support beam (34), and make sliding support beam (34) with separate Sliding beam drag-line (35) on the outside of formula cage plate (21) is connected by guy anchor solid plate (36);Sliding is set in sliding support beam (34) Conduit (37) and sliding baffle (38);Setting sliding strut (40) between material storage box (39) and sliding baffle (38), with cunning It moves between support beam (34) and bottom skid beam (41) is set, be placed in sliding conduit (37);
4) Vierendeel girder formwork erection positions: checking spatial position and the stabilization of longitudinal strutbeam (27) and carrying platform plate (32) Property;Setting limit upright bar (42) on carrying platform plate (32), in one embodiment of this invention, limit upright bar (42) and carrying Upright bar diagonal brace (43) are set between platform board (32);Bar top bracing plate| (44) are set on the top of limit upright bar (42), in the present invention An embodiment in, limit upright bar (42) and bar top bracing plate| (44) between setting fagging stiffening plate (45);In carrying platform plate (32) beam bottom board (46) are set on, and beam side (47) are placed in the inside of the side form bottom baffle (48) of beam bottom board (46), and make The side form connecting rod (49) of beam side (47) bottom passes through side form bottom baffle (48) and connect afterwards with side form fastening bolt (51);Make beam side Mould side coupling bar (52) on the outside of mould (47) is connect with limit upright bar (42) by transverse connecting rod (53);Pressing plate is first adjusted to adjust Bolt (54) makes the connection step (56) of Combined type pressing plate (55) be connected firmly with beam side (47), then connects in the opposite pressing plate of mirror image Setting fastening screw (58) between bolt (57) is connect, and passes through the lateral position of tensioning fastening bolt (59) control combination formula pressing plate (55) It sets;Reinforcing bar control position body (60) and bottom bracing embedded groove (61) are set on beam bottom board (46), it is embedding in reinforcing bar control position body (60) and bottom bracing Enter setting between slot (61) and only starch baffle (62), and bed die stiffening plate (63) are set in the lower part of bottom bracing embedded groove (61);
5) shuttering supporting reinforcement: being arranged column side on bolster stake (20) and bind round plate (19), and will even by hoop crab bolt (14) Ear connecting plate (15) is connected firmly;It is set in the outside of column side hoop plate (19) setting hoop side transverse slat (64), and on hoop side transverse slat (64) Set compression bar first baffle (65);Seam crossing arranging plate end joint filling layer (66) in beam bottom board (46) and bolster stake (20), lower surface It is arranged compression bar second baffle (67), lateral compression bar is set between compression bar first baffle (65) and compression bar second baffle (67) (68);Vertical compression bar (69) are set between beam bottom board (46) and hoop side transverse slat (64);
6) concrete pouring construction: scene review formwork erection quality, to concrete pouring construction, synchronously control Vierendeel girder (1) flatness on surface;
7) Vierendeel girder maintenance construction: setting support beam stanchion on the carrying platform plate (32) at the top of longitudinal strutbeam (27) (70), and make support beam stanchion (70) top with overhanging support beam (71) connect, form a L word structure, overhanging support beam (71) and Setting support beam diagonal brace (72) between carrying platform plate (32);In the upper surface of overhanging support beam (71) setting control position baffle (73) and restrict Rope keeps off pier (74), and setting control position rope (75) between control position baffle (73) and rope gear pier (74);Make to control position baffle (73) Top with sliding curing means (76) be connected, and make sliding curing means (76) on elastic connection plate (77) and Vierendeel girder (1) it is completely embedded;Downpipe (79) are set between sliding curing means (76) and water tank (78).
In step 2), hole bracket (98) is made of pressure-bearing crossbeam (7) and outsourcing frid (3);Outsourcing frid (3) cross section It is in U-shape, wraps up hole plate (2), slide plate link slot (80) are set in the opposite flank of outer packet slot plate (3) and press baffle (8), and Slide plate link slot (80) is set to be connected with monoblock type slide plate (81), baffle (8) are pressed in setting in the upside of outer packet slot plate (2), tight It presses and baffle side stay (82) is set between baffle (8) and outsourcing frid (3);
Slide plate limiting slot (83) are set on slide plate link slot (80);Slide plate coupling bar (5) are set on monoblock type slide plate (81), Slide plate connecting plate (85) are set with slide plate limiting slot (83) joint;Pressure-bearing crossbeam (7) is formed using rolling of sectional iron, upper surface It is arranged strut bottom plate (18).
In step 3), separate type cage plate (21) is formed by steel plate rolling, vertically whole to be set to the interior of column side hoop plate (19) Cage plate connecting shaft (86) are arranged between the separate type cage plate (21) to connect in side;Separate type cage plate (21) and column side hoop plate (19) are logical Cross cage plate fastening rib (87) connection;It is in a rectangular trapezoid that bottom plate limits falcon (31) cross section, and makes right-angle side and strutbeam bottom plate (26) Connect;Sliding support beam (34) is formed using steel plate rolling, is connect with bottom skid beam (41) by sliding fagging (88), and make to slide Fagging (88) is placed in sliding conduit (37).
Laterally support beam (23) perpendicular to column side hoop plate (19) outward be arranged, sliding support beam (34) vertical column side hoop plate (19) to Outer setting.
In step 4), outside setting side form connecting rod (49) of beam side (47) and mould side coupling bar (52);Bar top bracing plate| (44) it is connect with limit upright bar (42) vertical welding, pressing plate regulation cock (54) and Combined type pressing plate (55) is arranged in lower surface;Group The connection step (56) connecting with beam side (47) is arranged in box-like pressing plate (55) lower part, and pressing plate coupling bar (57) are arranged in inside;Steel Muscle control position body (60) is made of steel reinforcement cage bottom bracing (89), bottom bracing adjusting rod (90) and rotational handle (91), and makes steel reinforcement cage bottom bracing (89) it is connect respectively with bottom bracing adjusting rod (90) vertical welding with rotational handle (91);Only slurry baffle (62) uses rubber slab, Both ends are connect with steel reinforcement cage bottom bracing (89) and bottom bracing embedded groove (61) respectively;The plane width of bed die stiffening plate (63) is embedding compared with bottom bracing Enter slot (61) wide 10~20cm, the built-in bolt (92) connecting with bottom bracing adjusting rod (90) is set on bed die stiffening plate (63).
In step 7), the one end for controlling position rope (75) is connected with control position baffle (73), the other end after the rope baffle and Foreign volume draws equipment to be connected;Slide curing means (76) by the frid that intercepts water (93), mobile water pipe (94), combined closing plate (95) and Elastic connection plate (77) composition;Mobile water pipe (94) are connected to water supplying pipe (97), pass through water pipe buttress with the frid that intercepts water (93) (96) it connects, fountain head (84) are arranged in upper surface;Combined closing plate (95) is vertically arranged along the periphery for the frid (93) that intercepts water, Its top is connect with elastic connection plate (77);Filter residue plate (50) are set inside water tank (78), side wall and water supplying pipe (97) and confession Water pump (30) connection.
Fig. 2 is the hole Fig. 1 bracket layout stracture schematic diagram, and Fig. 3 is Fig. 2 monoblock type slide plate and slide plate link slot connection structure Schematic diagram, Fig. 4 are that Fig. 1 Vierendeel girder strutting system sets up structural schematic diagram, and Fig. 5 is that the longitudinal direction Fig. 4 strutbeam portion structure cross section shows It is intended to, Fig. 6 is Fig. 4 bottom skid beam and sliding support beam attachment structure schematic diagram, and Fig. 7 is that Fig. 1 beam forms installs structure transverse face and shows It is intended to, Fig. 8 is that Fig. 1 beam forms installs structure schematic longitudinal section, and Fig. 9 is that Fig. 7 reinforcing bar control position body shows with beam bottom board connection structure It is intended to, Figure 10 is Fig. 7 and Fig. 8 Combined type pressing plate structural schematic diagram, and Figure 11 is Fig. 1 shuttering supporting reinforcing construction structural schematic diagram, Figure 12 is Fig. 1 Vierendeel girder maintenance construction structural schematic diagram, and Figure 13 is Figure 12 sliding curing means cross-sectional view.
Vierendeel girder (1) width is 60cm, is highly 1.2m, strength grade of concrete C35.
Hole plate (2) is with a thickness of 120mm, strength grade of concrete C35.
Top pressure screw rod (4) is made of the stainless steel screw rod of diameter 30mm.
Slide plate coupling bar (5) and press bolt (6) are all made of the stainless steel bolt that internal diameter is 30mm.
Press baffle (8) and press transverse slat (10) and be all made of and is cut with a thickness of the steel plate of 10mm.
Nestled bolt (9) uses the stainless steel bolt of diameter 22mm.
Reinforcement dagger (11) is made of the steel pipe of diameter 100mm, wall thickness 2mm.
Dagger bottom plate (12) and spacer ferrule plate (13) are all made of and form with a thickness of the steel plate rolling of 2mm.
Bind round the high-strength bolt that crab bolt (14) use diameter 20mm.
Connection otic placode (15) and spacer ferrule plate (13) integrally roll, and are highly 5cm.
Positioning supporting rod (16) uses diameter to be made of the steel pipe of 30mm.
Strut shaft (17) uses the flexural pivot of diameter 30mm, is welded to connect with spacer ferrule plate (13).
Strut bottom plate (18) and column side hoop plate (19) are all made of and form with a thickness of the steel plate rolling of 2mm.
Bolster stake (20) planar dimension is 1000 × 1000mm, strength grade of concrete C40.
Separate type cage plate (21) is formed by steel plate rolling, vertically the whole inside for being set to column side hoop plate (19), using thickness Degree is that the steel plate rolling of 10mm forms.
Seam obturator (22) is used and is made with a thickness of the rubber material of 1mm.
Laterally support beam (23) use specification for 200 × 200 × 8 × 12 H profile steel.
Oblique strut (24) uses the stainless steel screw rod of diameter 60mm.
Strut tune bolt (25) uses internal diameter for the stainless steel bolt of 60mm.
Strutbeam bottom plate (26) is used and is made with a thickness of the steel plate of 2mm.
Longitudinal strutbeam (27) use specification for 150 × 150 × 7 × 10 H profile steel.
Lateral connection pull rod (28) uses the stainless steel screw rod of diameter 30mm.
Pull rod regulation cock (29) uses internal diameter for the stainless steel bolt of 30mm.
Water supply pump (30) uses 220v motor, and lift is the middle flow water pump of 24m.
Bottom plate limit falcon (31) cross section is in a rectangular trapezoid, forms using with a thickness of the steel plate rolling of 2mm.
Carrying platform plate (32) is used and is made with a thickness of the steel plate of 6mm.
Connection boots cap (33) is used and is formed with a thickness of the reinforcement welding of 10mm.
Using forming with a thickness of the steel plate rolling of 10mm, cross section is in rectangle for sliding support beam (34), and width 400mm is high Degree is 200mm.
Sliding beam drag-line (35) uses diameter for the wirerope of 26mm.
Guy anchor solid plate (36) is using the steel plate with a thickness of 10mm.
The width of sliding conduit (37) is 200mm, is highly 100mm;Baffle (38) are slid using the steel plate with a thickness of 2cm It rolls.
Material storage box (39) is used and is welded with a thickness of the steel plate of 1mm, volume 1.5m3.
Sliding strut (40) is made of the reinforcing bar of diameter 20mm.
Bottom skid beam (41) is welded to connect using forming with a thickness of the steel plate rolling of 10mm with sliding fagging (88);Sliding The steel body that it is 80mm for 160mm, highly with a thickness of width that fagging (88), which uses, strength grade Q235.
Limit the steel pipe that upright bar (42) use diameter 60mm.
Upright bar diagonal brace (43) is made of the steel pipe of diameter 30mm.
Bar top bracing plate| (44) and fagging stiffening plate (45) are all made of and form with a thickness of the steel plate rolling of 2mm.
Beam bottom board (46) and beam side (47) are all made of the alloy templates with a thickness of 3mm.
Side form bottom baffle (48) is cut using the steel plate of thickness 2mm.
Side form connecting rod (49) uses the screw rod of diameter 30mm.
The hole that diameter is 2mm is arranged using being made with a thickness of the steel plate of 1mm in filter residue plate (50) on filter residue plate (50).
Side form fastening bolt (51) uses the stainless steel bolt of internal diameter 30mm
Mould side coupling bar (52) and beam side (47) are welded to connect, the screw hole that inside setting internal diameter is 30mm.
Transverse connecting rod (53) uses diameter to form for the stainless steel screw rod of 30mm with bolt combination.
Pressing plate regulation cock (54) is made of length-adjustable bolt and bolt.
For Combined type pressing plate (55) using forming with a thickness of the steel plate rolling of 2mm, the height of connection step (56) is 2mm, long Degree is 5cm.
Pressing plate coupling bar (57) and tensioning fastening bolt (59) are all made of the bolt that internal diameter is 10mm.
Fastening screw (58) uses the screw rod of diameter 10mm.
Reinforcing bar control position body (60) is made of steel reinforcement cage bottom bracing (89), bottom bracing adjusting rod (90) and rotational handle (91);Wherein Steel reinforcement cage bottom bracing (89) and rotational handle (91) are all made of and form with a thickness of the steel plate rolling of 2mm;Bottom bracing adjusting rod (90) uses The screw rod of diameter 30mm is made.
The planar dimension of bottom bracing embedded groove (61) is identical as steel reinforcement cage bottom bracing (89);Only slurry baffle (62) using with a thickness of The sheet rubber of 1mm.
Bed die stiffening plate (63) with a thickness of the steel plate rolling of 10mm using forming, and plane width is compared with bottom bracing embedded groove (61) Wide 15cm.
Side transverse slat (64) are bound round using the steel plate with a thickness of 2cm, compression bar first baffle (65) and compression bar second baffle (67) are equal It is made of with a thickness of the steel plate of 10mm.
Plate end joint filling layer (66) is used and is cut with a thickness of the rubber slab of 10mm.
Lateral compression bar (68) and vertical compression bar (69) be respectively adopted diameter be 20mm and 30mm screw rod and bolt combination and At length is adjustable.
Support beam stanchion (70) and support beam diagonal brace (72) are all made of the H profile steel that specification is 150 × 150 × 7 × 10 and roll. Overhanging support beam (71) is all made of the H profile steel that specification is 100 × 100 × 6 × 8, with support beam stanchion (70) and support beam diagonal brace (72) weldering It connects in succession.
Control position baffle (73) is made of the steel plate of thickness 2mm.
Rope gear pier (74) is used and is formed with a thickness of the steel plate rolling of 2mm.
Control the wirerope that position rope (75) use diameter 10mm.
Curing means (76) are slid by the frid that intercepts water (93), mobile water pipe (94), combined closing plate (95) and elastic connection Plate (77) composition.Wherein elastic connection plate (77) is used and is made with a thickness of the rubber slab of 10mm;Mobile water pipe (94) use diameter For the steel pipe of 60mm;Frid (93) are intercepted water using with a thickness of 1mm steel plate;Combined closing plate (95) is using the steel plate with a thickness of 2mm It is made, is welded to connect with the frid that intercepts water (93).
Water tank (78) is used and is welded with a thickness of the iron sheet of 0.2mm, volume 1m3.
Downpipe (79) and water supplying pipe (97) are all made of the rubber tube that diameter is 60mm.
Slide plate link slot (80) and monoblock type slide plate (81) are all made of and form with a thickness of the steel plate rolling of 10mm.
Baffle side stay (82) uses diameter to cut for the spiral of 32mm.
The height of slide plate limiting slot (83) is 10mm, width 100mm;Slide plate connecting plate (85) is using with a thickness of 6mm's Steel plate is made, width 80mm.
Fountain head (84) uses water-saving spray head.
Cage plate connecting shaft (86) uses the shaft of diameter 10mm.
Cage plate fastening rib (87) uses diameter to be made of the stainless steel screw rod of 20mm.
Built-in bolt (92) uses the bolt of internal diameter 30mm.
Water pipe buttress (96) uses diameter to be made of the tube material of 100mm.
Hole bracket (98) is made of pressure-bearing crossbeam (7) and outsourcing frid (3).Pressure-bearing crossbeam (7) use specification for 300 × 300 × 10 × 15 H profile steel.Outsourcing frid (3) cross section is in U-shape, and forms using with a thickness of the steel plate rolling of 2mm.
The present invention is not limited to above-mentioned preferred forms, anyone can show that other are various under the inspiration of the present invention The product of form, however, make any variation in its shape or structure, it is all that there is skill identical or similar to the present application Art scheme, is within the scope of the present invention.

Claims (10)

1. a kind of construction method of big section prestressed frame beam formwork system, which is characterized in that including following construction procedure:
1) preparation of construction: the review of Vierendeel girder (1) field position and concrete mix determine that the technique for determining site operation is quasi- The material and device that standby construction needs;
2) hole bracket is laid: one of outsourcing frid (3) is respectively set on the sky side of facing of opposite hole plate (2), and makes to press One end of screw rod (4) is connect with the slide plate coupling bar (5) being placed on outsourcing frid (3), and the other end is connect with press bolt (6), Be connected firmly outsourcing frid (3) and hole plate (2);By pressure-bearing crossbeam (7) be placed on outsourcing frid (3) press baffle (8) it Between, and fixed be placed on pressure-bearing crossbeam (7) presses transverse slat (10);In the bottom end of reinforcement dagger (11), dagger bottom plate is set (12), it is placed on pressure-bearing crossbeam (7);Spacer ferrule plate (13) is placed on reinforcement dagger (11), and is fixed;Make positioning supporting rod (16) both ends pass through strut shaft (17) and connect with strut bottom plate (18) and spacer ferrule plate (13), are placed in pressure-bearing crossbeam (7) On;
3) Vierendeel girder strutting system is set up: at least 2 column sides hoop plate (19) being circumferentially arranged on the outside of bolster stake (20), and in column Ecto-entad sets gradually separate type cage plate (21) and seam obturator (22) between side hoop plate (19) and bolster stake (20);Upper Outside setting laterally support beam (23) of column side hoop plate (19) of layer;Strutbeam bottom plate (26) and longitudinal strutbeam (27) are first connected into one It is whole, and lateral connection pull rod (28) and pull rod regulation cock (29) are set between adjacent longitudinal strutbeam (27), then by strutbeam Bottom plate (26) is placed in laterally support beam (23), and the plan-position of longitudinal strutbeam (27) is adjusted by pull rod regulation cock (29);In cross Falcon (31) are limited to setting bottom plate between support beam (23) and strutbeam bottom plate (26), carrying platform plate (32) is made to be connected to longitudinal strutbeam (27) on;In the outside of the column side of lower layer hoop plate (19) setting sliding support beam (34), make sliding support beam (34) and separate type cage plate (21) the sliding beam drag-line (35) on the outside of is connected by guy anchor solid plate (36);The setting sliding conduit in sliding support beam (34) (37) and baffle (38) are slid;Setting sliding strut (40) between material storage box (39) and sliding baffle (38), with sliding It supports and bottom skid beam (41) is set between beam (34);
4) Vierendeel girder formwork erection positions: checking spatial position and the stability of longitudinal strutbeam (27) and carrying platform plate (32); Setting limit upright bar (42) on carrying platform plate (32);On the top of limit upright bar (42), bar top bracing plate| (44) are set;It is holding Beam bottom board (46) are set on carrying platform plate (32), and beam side (47) is placed in the interior of the side form bottom baffle (48) of beam bottom board (46) Side, and so that the side form connecting rod (49) of beam side (47) bottom is passed through side form bottom baffle (48) and connect afterwards with side form fastening bolt (51) It connects;It connect the mould side coupling bar (52) on the outside of beam side (47) by transverse connecting rod (53) with limit upright bar (42);First adjust Section pressing plate regulation cock (54) makes the connection step (56) of Combined type pressing plate (55) be connected firmly with beam side (47), then in mirror image phase Pair pressing plate coupling bar (57) between be arranged fastening screw (58), and pass through tensioning fastening bolt (59) control combination formula pressing plate (55) Lateral position;Reinforcing bar control position body (60) and bottom bracing embedded groove (61) are set on beam bottom board (46), in reinforcing bar control position body (60) Setting only starches baffle (62) between bottom bracing embedded groove (61), and bed die stiffening plate is arranged in the lower part of bottom bracing embedded groove (61) (63);
5) shuttering supporting reinforcement: fixed column side is set on bolster stake (20) and binds round plate (19);It is set on the outside of column side hoop plate (19) Hoop side transverse slat (64) is set, and compression bar first baffle (65) are set on hoop side transverse slat (64);It is arranged in beam bottom board (46) lower surface Lateral compression bar (68) is arranged in compression bar second baffle (67) between compression bar first baffle (65) and compression bar second baffle (67);? Vertical compression bar (69) are set between beam bottom board (46) and hoop side transverse slat (64);
6) concrete pouring construction: scene review formwork erection quality, to concrete pouring construction, synchronously control Vierendeel girder (1) The flatness on surface;
7) Vierendeel girder maintenance construction: setting support beam stanchion (70) on the carrying platform plate (32) at the top of longitudinal strutbeam (27), and It connect the top for supportting beam stanchion (70) with overhanging support beam (71), is arranged between overhanging support beam (71) and carrying platform plate (32) It supports beam diagonal brace (72);It is kept off in the upper surface of overhanging support beam (71) setting control position baffle (73) and rope gear pier (74), and in control position Setting control position rope (75) between plate (73) and rope gear pier (74);Make the top for controlling position baffle (73) and sliding curing means (76) it is connected, and is completely embedded the elastic connection plate (77) slid on curing means (76) with Vierendeel girder (1);It is conserved in sliding Downpipe (79) are set between device (76) and water tank (78).
2. the construction method of big section prestressed frame beam formwork system according to claim 1, it is characterised in that: in step 2) In, hole bracket (98) is made of pressure-bearing crossbeam (7) and outsourcing frid (3);Outsourcing frid (3) cross section is in U-shape, in outer packet slot Slide plate link slot (80) are set on plate (3) and press baffle (8), and make slide plate link slot (80) and monoblock type slide plate (81) phase Even, pressing setting baffle side stay (82) between baffle (8) and outsourcing frid (3);Slide plate is arranged on slide plate link slot (80) to limit Position slot (83);Slide plate coupling bar (5) are set on monoblock type slide plate (81), are connect with slide plate limiting slot (83) joint setting slide plate Plate (85);Pressure-bearing crossbeam (7) is formed using rolling of sectional iron, and strut bottom plate (18) are arranged in upper surface.
3. the construction method of big section prestressed frame beam formwork system according to claim 1, it is characterised in that: in step 2) In, pressure-bearing crossbeam (7) is connected firmly with transverse slat (10) is pressed by nestled bolt (9), using hoop crab bolt (14) by two pieces Spacer ferrule plate (13) is connected firmly by connection otic placode (15).
4. the construction method of big section prestressed frame beam formwork system according to claim 1, it is characterised in that: in step 3) In, vertically entirety is set to the inside that plate (19) are bound round in column side to separate type cage plate (21), sets between the separate type cage plate (21) to connect Set cage plate connecting shaft (86);Separate type cage plate (21) is connect with column side hoop plate (19) by cage plate fastening rib (87);Bottom plate limit Falcon (31) cross section is in a rectangular trapezoid, and right-angle side is made to connect with strutbeam bottom plate (26);Sliding support beam (34) and bottom skid beam (41) by sliding fagging (88) connection, and it is placed in sliding fagging (88) in sliding conduit (37).
5. the construction method of big section prestressed frame beam formwork system according to claim 1, which is characterized in that in step 3) In, it laterally supports beam (23) and column side hoop plate (19) is welded to connect, be laterally arranged between support beam (23) and separate type cage plate (21) Oblique strut (24) and strut tune bolt (25);Carrying platform plate (32) and longitudinal strutbeam (27) pass through connection boots cap (33) connection.
6. the construction method of big section prestressed frame beam formwork system according to claim 1, it is characterised in that: in step 4) In, outside setting side form connecting rod (49) of beam side (47) and mould side coupling bar (52);Bar top bracing plate| (44) and limit upright bar (42) vertical welding connects, and pressing plate regulation cock (54) and Combined type pressing plate (55) is arranged in lower surface;Under Combined type pressing plate (55) The connection step (56) connecting with beam side (47) is arranged in portion, and pressing plate coupling bar (57) are arranged in inside;Reinforcing bar control position body (60) by Steel reinforcement cage bottom bracing (89), bottom bracing adjusting rod (90) and rotational handle (91) composition, and make steel reinforcement cage bottom bracing (89) and rotational handle (91) it is connect respectively with bottom bracing adjusting rod (90) vertical welding;Only slurry baffle (62) use rubber slab, both ends respectively with reinforcing bar Cage bottom supports (89) and bottom bracing embedded groove (61) connection;The plane width of bed die stiffening plate (63) is wide compared with bottom bracing embedded groove (61), The built-in bolt (92) connecting with bottom bracing adjusting rod (90) is set on bed die stiffening plate (63).
7. the construction method of big section prestressed frame beam formwork system according to claim 1, it is characterised in that: limiting Upright bar diagonal brace (43) are set between position upright bar (42) and carrying platform plate (32), are limited between upright bar (42) and bar top bracing plate| (44) It is arranged fagging stiffening plate (45).
8. the construction method of big section prestressed frame beam formwork system according to claim 1, it is characterised in that: in step 7) In, the one end for controlling position rope (75) is connected with control position baffle (73), and the other end draws equipment phase with foreign volume after rope baffle Even;Curing means (76) are slid by the frid that intercepts water (93), mobile water pipe (94), combined closing plate (95) and elastic connection plate (77) Composition;Mobile water pipe (94) are connected to water supplying pipe (97), are connect with the frid that intercepts water (93) by water pipe buttress (96), upper surface It is arranged fountain head (84);Combined closing plate (95) is vertically arranged along the periphery for the frid (93) that intercepts water, top and elastic connection Plate (77) connection;Filter residue plate (50) are set inside water tank (78), side wall is connected to water supplying pipe (97) and water supply pump (30).
9. the construction method of big section prestressed frame beam formwork system according to claim 1, which is characterized in that in step It is rapid 5) in, column side hoop plate (19) by bind round crab bolt (14) connection otic placode (15) is connected firmly, beam bottom board (46) and bolster stake (20) seam crossing arranging plate end joint filling layer (66).
10. a kind of big section prestressed frame beam formwork system, which is characterized in that any described big to 9 according to claim 1 The construction method of section prestressed frame beam formwork system, which is constructed, to be completed.
CN201910419596.1A 2019-05-20 2019-05-20 Large-section prestressed frame beam formwork system and construction method Active CN110080521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910419596.1A CN110080521B (en) 2019-05-20 2019-05-20 Large-section prestressed frame beam formwork system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910419596.1A CN110080521B (en) 2019-05-20 2019-05-20 Large-section prestressed frame beam formwork system and construction method

Publications (2)

Publication Number Publication Date
CN110080521A true CN110080521A (en) 2019-08-02
CN110080521B CN110080521B (en) 2021-02-09

Family

ID=67420895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910419596.1A Active CN110080521B (en) 2019-05-20 2019-05-20 Large-section prestressed frame beam formwork system and construction method

Country Status (1)

Country Link
CN (1) CN110080521B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0547356A1 (en) * 1991-12-18 1993-06-23 Peri Gmbh Clamp for beam-moulding
JPH08118337A (en) * 1994-10-24 1996-05-14 Ando Corp Movable form for precast concrete member
DE102007016724B3 (en) * 2007-04-07 2008-10-02 Peri Gmbh Beam formwork with automatic de-shuttering of the inner shield
CN206562762U (en) * 2017-03-14 2017-10-17 上海嘉实(集团)有限公司 A kind of Fabricated Beam-Slab aluminum dipping form fast assembling disassembling structure
CN206599993U (en) * 2017-03-24 2017-10-31 杭州通达集团有限公司 A kind of cast-in-place tool-type erecting device for crossing beam forms
KR20180045562A (en) * 2016-10-26 2018-05-04 인하대학교 산학협력단 supporting system for formwork
CN108951840A (en) * 2018-08-08 2018-12-07 杭州江润科技有限公司 Based on setting bracket single side formwork basement arc external wall construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0547356A1 (en) * 1991-12-18 1993-06-23 Peri Gmbh Clamp for beam-moulding
JPH08118337A (en) * 1994-10-24 1996-05-14 Ando Corp Movable form for precast concrete member
DE102007016724B3 (en) * 2007-04-07 2008-10-02 Peri Gmbh Beam formwork with automatic de-shuttering of the inner shield
KR20180045562A (en) * 2016-10-26 2018-05-04 인하대학교 산학협력단 supporting system for formwork
CN206562762U (en) * 2017-03-14 2017-10-17 上海嘉实(集团)有限公司 A kind of Fabricated Beam-Slab aluminum dipping form fast assembling disassembling structure
CN206599993U (en) * 2017-03-24 2017-10-31 杭州通达集团有限公司 A kind of cast-in-place tool-type erecting device for crossing beam forms
CN108951840A (en) * 2018-08-08 2018-12-07 杭州江润科技有限公司 Based on setting bracket single side formwork basement arc external wall construction method

Also Published As

Publication number Publication date
CN110080521B (en) 2021-02-09

Similar Documents

Publication Publication Date Title
CN105386778B (en) Tunnel excavation lining construction chassis and tunnel excavation lining construction method
CN102251657B (en) Arching formwork erecting method for assembled framework beam plate
CN109056535A (en) Based on adjustable regularization template variable curvature construction of cast-in-situ box-beam method
CN110184921A (en) The construction method of steel box-concrete beam lifting system
CN110359595B (en) Prefabricated member spliced building block filler wall and construction method
CN111188459B (en) Construction process for bonding prestressed reinforced concrete beam
CN110359586A (en) Late poured band structure and construction method
CN111206506B (en) Construction method of bridge pier column
CN112227218A (en) Stainless steel-wood combined template applied to bare concrete and manufacturing method thereof
CN110080521A (en) Big section prestressed frame formwork system and construction method
CN204960300U (en) Steel bar truss template of steel bar truss floor and on --spot ligature floor
CN108930406B (en) Construction method for large-formwork narrow-space wall based on integral assembly
CN110847065A (en) Prefabricated assembled box channel and construction method
CN109972536A (en) The construction method of hollow slab girder reinforcing structure
CN113174854B (en) Construction method of large-span wide-body reserved post-cast-in-place box girder formwork system
CN205296821U (en) Oblique roofing formwork system of heavy grade cast in situ concrete
CN210288121U (en) Steel box-concrete composite beam concrete pouring system
CN105887922B (en) A kind of method that inwall construction is carried out using truss support device
CN109653088B (en) Construction method of cast-in-place reinforced concrete guardrail
CN211522933U (en) Temporary locking structure for midspan closure section of cantilever casting box beam
CN201343704Y (en) Movable scaffolding system for casting T-shaped beam bridge flange slabs in situ
CN109972537B (en) Construction method of composite reinforced structure of double-arch bridge
CN112746628A (en) Cast-in-place comprehensive pipe gallery formwork supporting structure and cast-in-place comprehensive pipe gallery construction method
CN113174869A (en) Construction method of large-span variable-section continuous cast-in-place box girder large-section support system
CN112813805A (en) Construction method of variable-section thin-wall hollow high pier of stiff framework

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant