- CN110047013A CN110047013A CN201810035653.1A CN201810035653A CN110047013A CN 110047013 A CN110047013 A CN 110047013A CN 201810035653 A CN201810035653 A CN 201810035653A CN 110047013 A CN110047013 A CN 110047013A
- Authority
- CN
- China
- Prior art keywords
- user
- stealing
- specially
- day
- line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000005611 electricity Effects 0.000 title claims abstract description 44
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000000605 extraction Methods 0.000 claims abstract description 4
- 238000012544 monitoring process Methods 0.000 claims abstract description 4
- 230000035772 mutation Effects 0.000 claims description 12
- 241001269238 Data Species 0.000 claims description 4
- 239000000284 extract Substances 0.000 claims description 3
- 238000001514 detection method Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The present invention provides a kind of anti-specially change user's discontinuous form stealing electricity method, comprising steps of, with monthly for the period, monitoring region within the jurisdiction includes the day line loss per unit △ P data for specially becoming each high voltage supply route of user 1. by power supply department power information acquisition system;Index △ P respectively is fluctuated containing the special high voltage supply route day line loss per unit for becoming user 2. calculatingbd, by the doubtful target line for thering is discontinuous form stealing specially to become user of criterion;3. determining that target line line loss per unit is mutated time point;4. extracting doubtful stealing in target line specially becomes user;5. specially becoming in user from the doubtful stealing of extraction, screens and lock stealing and specially become user;6. the stealing for calculating locking specially becomes the power-steeling quantity that user needs to remedy.The discontinuous form stealing that the present invention can in time, accurately lock in power supply line, which specially becomes user and can easily calculate stealing, specially becomes the power-steeling quantity that user need to remedy.
Description
Technical field
It opposes electricity-stealing method the present invention relates to power pack, and in particular to a kind of anti-specially to become user's discontinuous form stealing electricity method.
Background technique
It opposes electricity-stealing an important process of always power supply department.The traditional method of opposing electricity-stealing of power supply department, which relies primarily on, patrols
Inspection patrolman has found stealing clue, inefficiency, the timeliness opposed electricity-stealing, validity by power consumer site inspection
It cannot obviously meet the needs of, once especially specially becoming user's stealing, be more difficult to investigate and prosecute using existing means, because specially becoming user's
The equipment such as transformer are customer capital, and the installation site of metering device is in user's compass of competency, and are configured with and have mostly
The professional electrician of respective electric knowledge so that it is more hidden and professional specially to become user's electricity stealing, and mostly uses discontinuous form stealing
Method, once electricity stealing occurs, power-steeling quantity is big, and harm is serious.
In recent years, anti-discontinuous form stealing electricity method has been shown in research, such as the Chinese patent literature of Publication No. CN103455855B
A kind of intermittent electricity stealing prevention detection method based on the analysis of power information data is disclosed, the problem is that: first, calculating
Method is complicated, time-consuming and has certain limitation, second, being only applicable to the intermittent electricity stealing of detection meter power loss;
Third, not having automatic calculating power-steeling quantity function.
In recent years, carrying forward vigorously with state grid corporation of smart grid construction, Open3000 system, D5000 system
(upgrade version of Open3000), power information acquisition system and marketing system are built up and put into operation in succession, and power grid is in real time and non real-time
Information is highly integrated, shared and utilize, and provides comprehensive, complete and fine electric power industry for operations of power networks at different levels and administrative staff
Business data flow.Power supply management department can inquire the electric current of power supply line, electricity by Open3000 system and/or D5000 system
The real time datas such as pressure, electricity and historical data;The daily loss of inquiry power supply line is convenient to by power information acquisition system
Electricity, line loss per unit, the electricity consumption of each power consumer, electric current, voltage etc. in real time and history electricity consumption data information, pass through marketing system
It is convenient to the essential informations such as contract capacity, user location and the identity of inquiry power consumer.How above system is efficiently used
And information, it is that power supply department currently puts forth effort the technology for wanting to solve that building is timely and effectively anti-, which specially to become user's discontinuous form stealing electricity method,
Problem.
Summary of the invention
The object of the present invention is to provide a kind of anti-specially change user's discontinuous form stealing electricity method, this method in time, accurately to lock
Determine the discontinuous form stealing in power supply line and specially become user and can easily calculate stealing specially to become the power-steeling quantity that user need to remedy.
The technical scheme is that anti-special change user discontinuous form stealing electricity method of the invention, comprising the following steps:
1., with monthly for the period, monitoring region within the jurisdiction, which includes, specially becomes user by power supply department power information acquisition system
Each high voltage supply route day line loss per unit △ P data;
2. being calculated using formula (2) and respectively fluctuating index △ P containing the special high voltage supply route day line loss per unit for becoming userbdIf a certain
There is △ P containing the special high voltage supply route for becoming userbd>=3%, then it is doubtful for extracting this containing the special high voltage supply route for becoming user
Seemingly there is discontinuous form stealing specially to become the target line of user:
△Pbd=△ Pmax-△Pmin (2)
In formula, △ PmaxFor the monthly maximum day line loss per unit of high voltage supply route, △ PminFor the monthly of high voltage supply route
Minimum day line loss per unit;
3. determining that target line line loss per unit is mutated time point:
The first step, the day for transferring target line from power supply department D5000 system or Open3000 system and sell day power supply volume
Electricity data transfers the day line loss per unit data of target line from power supply department power information acquisition system, draws target line
Line loss per unit characteristic pattern;
Second step determines the line loss mutation day D of target line using the line loss per unit characteristic pattern of the target line of drafting;
4. extracting doubtful stealing in target line specially becomes user:
The first step transfers each special daily power consumption number for becoming user in target line from power supply department power information acquisition system
According to;
Second step is mutated the electricity consumption bust index of day D using each special change user in formula (3) calculating target line in line loss
△ W, if a certain special kilowatt hour of △ W >=1000 for becoming user, extracts the special change user as doubtful stealing and specially becomes user:
△ W=WD-1-WD (3)
In formula, WDThe electricity consumption of day D acquisition is mutated specially to become user in line loss;WD-1Day D is mutated specially to become user in line loss
Proxima luce (prox. luc) acquisition electricity consumption;
5. specially becoming in user from the doubtful stealing of extraction, screens and locks stealing and specially become user:
The first step transfers the target line and doubtful stealing of line loss mutation day D from power supply department power information acquisition system
24 hours current datas for specially becoming user, with 5 minutes for interval synchronization sampled targets line current inSpecially become use with doubtful stealing
Family electric current Ιn;
Second step calculates doubtful stealing using formula (4) and specially becomes user in the electric current bust value △ I of line loss mutation day Dn;It adopts
Doubtful stealing, which is calculated, with formula (5) specially becomes user in the electric current bust percentage K of line loss mutation day Dn:
△In=Ιn-1-In (4)
In formula, ΙnSpecially become user in the present sample current value of electricity bust day, I for doubtful stealingn-1It is special for doubtful stealing
Become user in electricity bust day and present sample current value ΙnAn adjacent upper sampled current value;
Third step, if a certain doubtful stealing, which specially becomes user, has △ In>=15 amperes or Kn>=10% situation, then count
Calculate the △ InThere is the current variation value of the affiliated power supply line of time point, if power supply line is in the △ InThere is the curent change of time point
Value does not occur △ InThe electric current bust of size, then lock the doubtful stealing and specially become user and specially become user into stealing;
6. specially becoming the power-steeling quantity that user needs to remedy using the stealing that formula (6) and formula (7) calculate locking:
In formula: η is specially to become user's stealing ratio, and △ I is the abovementioned steps 5. middle △ I calculatednMaximum value in value, ITFor
Stealing specially becomes the current value that user acquires after electric current bust, WFFor the special change user stealing period electricity of acquisition, specially become user
The stealing period terminates since selected electric current bust time point to there is electric current time point of uprushing, WQIt needs to remedy for the stealing period
Power-steeling quantity.
The present invention has the effect of positive: anti-special change user discontinuous form stealing electricity method of the invention, by power supply
Door relevant historical data, which carries out analysis, accurately automatic identification and the discontinuous form stealing locked in power supply line specially to become user,
And quickly, easily and accurately can determine that discontinuous form stealing specially becomes the power-steeling quantity that user need to remedy, accuracy and reliability is higher.
Detailed description of the invention
Fig. 1 is flow chart of the method for the present invention;
Fig. 2 is the line loss per unit feature schematic diagram of the doubtful target line for having discontinuous form stealing specially to become user.
Specific embodiment
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
(embodiment 1)
See that Fig. 1, the anti-special change user discontinuous form stealing electricity method of the present embodiment are implemented by following steps:
1., with monthly for the period, monitoring region within the jurisdiction includes specially by the existing power information acquisition system of power supply department
Become the day line loss per unit △ P data of each high voltage supply route of user:
In formula, WxgFor high voltage supply route day power supply volume;WxsFor high voltage supply route day electricity sales amount;Each high voltage supply line
The day line loss per unit △ P data on road can be directly acquired from power supply department by existing power information acquisition system.
2. being calculated using formula (2) and respectively fluctuating index △ P containing the special high voltage supply route day line loss per unit for becoming userbdIf a certain
High voltage supply route △ Pbd>=3%, then extracting this high voltage supply route is the doubtful target for having discontinuous form stealing specially to become user
Route:
△Pbd=△ Pmax-△Pmin (2)
In formula, △ PbdFor the day line loss per unit undulating value of high voltage supply route, △ PmaxFor the monthly maximum of high voltage supply route
Day line loss per unit, △ PminFor the monthly minimum day line loss per unit of high voltage supply route.
3. determining that target line line loss per unit is mutated time point:
The first step transfers the day power supply volume of target line from the existing D5000 system of power supply department or Open3000 system
With day electricity sales amount data, the day line loss per unit data of target line are transferred from the existing power information acquisition system of power supply department, are drawn
The line loss per unit characteristic pattern of the line loss per unit characteristic pattern of target line processed, the target line drawn is as schematically shown in Figure 2;
Second step determines the line loss mutation day D of target line using the line loss per unit characteristic pattern of the target line of drafting.
4. extracting doubtful stealing in target line specially becomes user:
The first step, from the existing power information acquisition system of power supply department transfer in target line it is each it is special become user it is daily
Electricity data;
Second step is mutated the electricity consumption bust index of day D using each special change user in formula (3) calculating target line in line loss
△ W, if a certain special kilowatt hour of △ W >=1000 for becoming user, extracts the special change user as doubtful stealing and specially becomes user:
△ W=WD-1-WD (3)
In formula, WDThe electricity consumption of day D acquisition is mutated specially to become user in line loss;WD-1Day D is mutated specially to become user in line loss
Proxima luce (prox. luc) acquisition electricity consumption.
5. specially becoming in user from the doubtful stealing of the target line of extraction, screens and locks stealing and specially become user:
The first step is transferred the target line of line loss mutation day D from the existing power information acquisition system of power supply department and is doubted
Specially become 24 hours current datas of user like stealing, with 5 minutes for interval synchronization sampled targets line current inWith doubtful stealing
Specially become user's electric current Ιn;
Second step calculates doubtful stealing using formula (4) and specially becomes user in the electric current bust value △ I of line loss mutation day Dn;It adopts
Doubtful stealing, which is calculated, with formula (5) specially becomes user in the electric current bust percentage K of line loss mutation day Dn:
△In=Ιn-1-In (4)
In formula, ΙnSpecially become user in the present sample current value of electricity bust day, I for doubtful stealingn-1It is special for doubtful stealing
Become user in electricity bust day and present sample current value ΙnAn adjacent upper sampled current value;
Third step, if a certain doubtful stealing, which specially becomes user, has △ In>=15 amperes or Kn>=10% situation, then count
Calculate the △ InThere is the current variation value of the affiliated power supply line of time point, if power supply line is in the △ InThere is the curent change of time point
Value does not occur △ InThe electric current bust of size, then lock the doubtful stealing and specially become user and specially become user into stealing.
6. specially becoming the power-steeling quantity that user needs to remedy using the stealing that formula (6) and formula (7) calculate locking:
In formula: η is specially to become user's stealing ratio, and △ I is the abovementioned steps 5. middle △ I calculatednMaximum value in value, ITFor
Stealing specially becomes the current value that user acquires after electric current bust, WFFor the special change user stealing period electricity of acquisition, specially become user
The stealing period terminates since selected electric current bust time point to there is electric current time point of uprushing, WQIt needs to remedy for the stealing period
Power-steeling quantity.
Above embodiments are the explanations to a specific embodiment of the invention, rather than limitation of the present invention, related technology
The technical staff in field without departing from the spirit and scope of the present invention, can also make various transformation and variation and obtain
To corresponding equivalent technical solution, therefore all equivalent technical solutions should be included into patent protection model of the invention
It encloses.
Claims (1)
1. a kind of anti-specially change user's discontinuous form stealing electricity method, which comprises the following steps:
1., with monthly for the period, monitoring region within the jurisdiction, which includes, specially becomes each of user by power supply department power information acquisition system
The day line loss per unit △ P data of high voltage supply route;
2. being calculated using formula (2) and respectively fluctuating index △ P containing the special high voltage supply route day line loss per unit for becoming userbdIf a certain containing special
There is △ P in the high voltage supply route for becoming userbd>=3%, then extracting this has containing the special high voltage supply route for becoming user to be doubtful
Discontinuous form stealing specially becomes the target line of user:
△Pbd=△ Pmax-△Pmin (2)
In formula, △ PmaxFor the monthly maximum day line loss per unit of high voltage supply route, △ PminFor the monthly minimum of high voltage supply route
Day line loss per unit;
3. determining that target line line loss per unit is mutated time point:
The first step transfers the day power supply volume and day electricity sales amount of target line from power supply department D5000 system or Open3000 system
Data transfer the day line loss per unit data of target line from power supply department power information acquisition system, draw the line loss of target line
Rate characteristic pattern;
Second step determines the line loss mutation day D of target line using the line loss per unit characteristic pattern of the target line of drafting;
4. extracting doubtful stealing in target line specially becomes user:
The first step transfers each special daily power consumption data for becoming user in target line from power supply department power information acquisition system;
Second step is mutated the electricity consumption bust index △ W of day D using each special change user in formula (3) calculating target line in line loss,
If a certain special kilowatt hour of △ W >=1000 for becoming user, extracts the special change user as doubtful stealing and specially becomes user:
△ W=WD-1-WD (3)
In formula, WDThe electricity consumption of day D acquisition is mutated specially to become user in line loss;WD-1Specially to become user before line loss is mutated day D
The electricity consumption of acquisition on the one;
5. specially becoming in user from the doubtful stealing of extraction, screens and locks stealing and specially become user:
The first step transfers the target line of line loss mutation day D from power supply department power information acquisition system and doubtful stealing specially becomes
24 hours current datas of user, with 5 minutes for interval synchronization sampled targets line current inSpecially become user's electricity with doubtful stealing
Flow Ιn;
Second step calculates doubtful stealing using formula (4) and specially becomes user in the electric current bust value △ I of line loss mutation day Dn;Using formula
(5) it calculates doubtful stealing and specially becomes user in the electric current bust percentage K of line loss mutation day Dn:
△In=Ιn-1-In (4)
In formula, ΙnSpecially become user in the present sample current value of electricity bust day, I for doubtful stealingn-1Specially become use for doubtful stealing
Family is in electricity bust day and present sample current value ΙnAn adjacent upper sampled current value;
Third step, if a certain doubtful stealing, which specially becomes user, has △ In>=15 amperes or Kn>=10% situation, then calculating should
△InThere is the current variation value of the affiliated power supply line of time point, if power supply line is in the △ InThere is the current variation value of time point not
There is △ InThe electric current bust of size, then lock the doubtful stealing and specially become user and specially become user into stealing;
6. specially becoming the power-steeling quantity that user needs to remedy using the stealing that formula (6) and formula (7) calculate locking:
In formula: η is specially to become user's stealing ratio, and △ I is the abovementioned steps 5. middle △ I calculatednMaximum value in value, ITFor stealing
Specially become the current value that user acquires after electric current bust, WFFor the special change user stealing period electricity of acquisition, specially become user's stealing
Period terminates since selected electric current bust time point to there is electric current time point of uprushing, WQThe stealing remedied is needed for the stealing period
Amount.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810035653.1A CN110047013B (en) | 2018-01-15 | 2018-01-15 | Anti-private-transformer user intermittent electricity stealing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810035653.1A CN110047013B (en) | 2018-01-15 | 2018-01-15 | Anti-private-transformer user intermittent electricity stealing method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110047013A true CN110047013A (en) | 2019-07-23 |
CN110047013B CN110047013B (en) | 2023-06-13 |
Family
ID=67273315
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810035653.1A Active CN110047013B (en) | 2018-01-15 | 2018-01-15 | Anti-private-transformer user intermittent electricity stealing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110047013B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111443237A (en) * | 2020-04-20 | 2020-07-24 | 北京中电普华信息技术有限公司 | Method and system for determining compensation electric quantity |
CN111650432A (en) * | 2020-07-14 | 2020-09-11 | 国网冀北电力有限公司 | Line loss-based electricity stealing determination method and device |
CN113311379A (en) * | 2021-05-26 | 2021-08-27 | 国网江苏省电力有限公司营销服务中心 | Low-voltage electricity stealing intelligent diagnosis method based on big data |
CN116070162A (en) * | 2023-03-06 | 2023-05-05 | 国网浙江省电力有限公司宁波供电公司 | Anti-electricity-stealing monitoring method and system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004340767A (en) * | 2003-05-16 | 2004-12-02 | Hitachi Ltd | Electric power transaction method and electric power transaction system prevented in stealing electricity |
CN103076476A (en) * | 2012-12-18 | 2013-05-01 | 广东电网公司汕头供电局 | On-line monitoring method of primary side shunt electric stealing of CT (current transformer) of 10kV special variable metering device |
CN103399186A (en) * | 2013-07-31 | 2013-11-20 | 深圳供电局有限公司 | Method and device for identifying electricity stealing and leakage users based on line loss monitoring |
CN105590166A (en) * | 2015-12-16 | 2016-05-18 | 国家电网公司 | Analytical judgment method for power consumption behavior of specific power transformer user in power distribution network |
CN106156269A (en) * | 2016-06-01 | 2016-11-23 | 国网河北省电力公司电力科学研究院 | One is opposed electricity-stealing precise positioning on-line monitoring method |
CN106645935A (en) * | 2016-12-27 | 2017-05-10 | 国网浙江象山县供电公司 | Electricity usage monitoring method and system |
-
2018
- 2018-01-15 CN CN201810035653.1A patent/CN110047013B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004340767A (en) * | 2003-05-16 | 2004-12-02 | Hitachi Ltd | Electric power transaction method and electric power transaction system prevented in stealing electricity |
CN103076476A (en) * | 2012-12-18 | 2013-05-01 | 广东电网公司汕头供电局 | On-line monitoring method of primary side shunt electric stealing of CT (current transformer) of 10kV special variable metering device |
CN103399186A (en) * | 2013-07-31 | 2013-11-20 | 深圳供电局有限公司 | Method and device for identifying electricity stealing and leakage users based on line loss monitoring |
CN105590166A (en) * | 2015-12-16 | 2016-05-18 | 国家电网公司 | Analytical judgment method for power consumption behavior of specific power transformer user in power distribution network |
CN106156269A (en) * | 2016-06-01 | 2016-11-23 | 国网河北省电力公司电力科学研究院 | One is opposed electricity-stealing precise positioning on-line monitoring method |
CN106645935A (en) * | 2016-12-27 | 2017-05-10 | 国网浙江象山县供电公司 | Electricity usage monitoring method and system |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111443237A (en) * | 2020-04-20 | 2020-07-24 | 北京中电普华信息技术有限公司 | Method and system for determining compensation electric quantity |
CN111650432A (en) * | 2020-07-14 | 2020-09-11 | 国网冀北电力有限公司 | Line loss-based electricity stealing determination method and device |
CN113311379A (en) * | 2021-05-26 | 2021-08-27 | 国网江苏省电力有限公司营销服务中心 | Low-voltage electricity stealing intelligent diagnosis method based on big data |
CN116070162A (en) * | 2023-03-06 | 2023-05-05 | 国网浙江省电力有限公司宁波供电公司 | Anti-electricity-stealing monitoring method and system |
CN116070162B (en) * | 2023-03-06 | 2023-08-29 | 国网浙江省电力有限公司宁波供电公司 | Anti-electricity-stealing monitoring method and system |
Also Published As
Publication number | Publication date |
---|---|
CN110047013B (en) | 2023-06-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110047013A (en) | It is anti-specially to become user's discontinuous form stealing electricity method | |
CN106093652B (en) | A kind of non-intrusive electrical load monitoring System and method for having self-learning function | |
CN107340492A (en) | Electric power meter failure analysis methods with scene anticipation are excavated based on big data | |
CN104200314B (en) | Electricity and line loss same period statistical method based on data remote synchronization acquisition technique | |
CN111650431B (en) | Ammeter region identification method | |
WO2020252785A1 (en) | Abnormal electricity use recognition method and device, and computer readable storage medium | |
CN110045194A (en) | High voltage supply route is opposed electricity-stealing method | |
CN110749784B (en) | Line electricity stealing detection method based on electric power data wavelet analysis | |
CN111600296A (en) | Power load prediction system based on edge calculation and prediction method thereof | |
CN109725219A (en) | A kind of electric energy meter platform area automatic identifying method | |
CN107194780A (en) | A kind of shared mobile phone lease operation system and its method | |
CN102289721A (en) | Carbon emission monitoring and measuring service system for daily life | |
CN109444800A (en) | Platform area recognition methods based on wireless communication acquisition | |
CN112307003A (en) | Power grid data multidimensional auxiliary analysis method, system, terminal and readable storage medium | |
CN111652761B (en) | Multi-source feature fusion electricity stealing behavior detection method based on evidence theory | |
CN103888731A (en) | Structured description device and system for mixed video monitoring by means of gun-type camera and dome camera | |
US20150088441A1 (en) | Energy usage estimation device and energy usage estimation method | |
Junaidi et al. | Big data applications in electric energy systems | |
EP3449267A1 (en) | A method for identifying the phases of a multi-phase distribution grid | |
CN112884228B (en) | Big data-based transformer area line loss management and control system | |
CN103606111A (en) | Integrated voltage qualified rate evaluation method | |
CN106127602B (en) | Electricity stealing identification method and device based on reduction outlier algorithm | |
CN110045196B (en) | High-voltage power supply line management line loss checking method | |
Li et al. | Implementation of load profile test for electricity distribution networks | |
CN110719445A (en) | Remote meter reading system and method based on image recognition |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |