CN110047013A - It is anti-specially to become user's discontinuous form stealing electricity method - Google Patents

It is anti-specially to become user's discontinuous form stealing electricity method Download PDF

Info

Publication number
CN110047013A
CN110047013A CN201810035653.1A CN201810035653A CN110047013A CN 110047013 A CN110047013 A CN 110047013A CN 201810035653 A CN201810035653 A CN 201810035653A CN 110047013 A CN110047013 A CN 110047013A
Authority
CN
China
Prior art keywords
user
stealing
specially
day
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810035653.1A
Other languages
Chinese (zh)
Other versions
CN110047013B (en
Inventor
张沂
潘志伟
潘峰
毛清
张腾
杭晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Changzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Changzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Changzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201810035653.1A priority Critical patent/CN110047013B/en
Publication of CN110047013A publication Critical patent/CN110047013A/en
Application granted granted Critical
Publication of CN110047013B publication Critical patent/CN110047013B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention provides a kind of anti-specially change user's discontinuous form stealing electricity method, comprising steps of, with monthly for the period, monitoring region within the jurisdiction includes the day line loss per unit △ P data for specially becoming each high voltage supply route of user 1. by power supply department power information acquisition system;Index △ P respectively is fluctuated containing the special high voltage supply route day line loss per unit for becoming user 2. calculatingbd, by the doubtful target line for thering is discontinuous form stealing specially to become user of criterion;3. determining that target line line loss per unit is mutated time point;4. extracting doubtful stealing in target line specially becomes user;5. specially becoming in user from the doubtful stealing of extraction, screens and lock stealing and specially become user;6. the stealing for calculating locking specially becomes the power-steeling quantity that user needs to remedy.The discontinuous form stealing that the present invention can in time, accurately lock in power supply line, which specially becomes user and can easily calculate stealing, specially becomes the power-steeling quantity that user need to remedy.

Description

It is anti-specially to become user's discontinuous form stealing electricity method
Technical field
It opposes electricity-stealing method the present invention relates to power pack, and in particular to a kind of anti-specially to become user's discontinuous form stealing electricity method.
Background technique
It opposes electricity-stealing an important process of always power supply department.The traditional method of opposing electricity-stealing of power supply department, which relies primarily on, patrols Inspection patrolman has found stealing clue, inefficiency, the timeliness opposed electricity-stealing, validity by power consumer site inspection It cannot obviously meet the needs of, once especially specially becoming user's stealing, be more difficult to investigate and prosecute using existing means, because specially becoming user's The equipment such as transformer are customer capital, and the installation site of metering device is in user's compass of competency, and are configured with and have mostly The professional electrician of respective electric knowledge so that it is more hidden and professional specially to become user's electricity stealing, and mostly uses discontinuous form stealing Method, once electricity stealing occurs, power-steeling quantity is big, and harm is serious.
In recent years, anti-discontinuous form stealing electricity method has been shown in research, such as the Chinese patent literature of Publication No. CN103455855B A kind of intermittent electricity stealing prevention detection method based on the analysis of power information data is disclosed, the problem is that: first, calculating Method is complicated, time-consuming and has certain limitation, second, being only applicable to the intermittent electricity stealing of detection meter power loss; Third, not having automatic calculating power-steeling quantity function.
In recent years, carrying forward vigorously with state grid corporation of smart grid construction, Open3000 system, D5000 system (upgrade version of Open3000), power information acquisition system and marketing system are built up and put into operation in succession, and power grid is in real time and non real-time Information is highly integrated, shared and utilize, and provides comprehensive, complete and fine electric power industry for operations of power networks at different levels and administrative staff Business data flow.Power supply management department can inquire the electric current of power supply line, electricity by Open3000 system and/or D5000 system The real time datas such as pressure, electricity and historical data;The daily loss of inquiry power supply line is convenient to by power information acquisition system Electricity, line loss per unit, the electricity consumption of each power consumer, electric current, voltage etc. in real time and history electricity consumption data information, pass through marketing system It is convenient to the essential informations such as contract capacity, user location and the identity of inquiry power consumer.How above system is efficiently used And information, it is that power supply department currently puts forth effort the technology for wanting to solve that building is timely and effectively anti-, which specially to become user's discontinuous form stealing electricity method, Problem.
Summary of the invention
The object of the present invention is to provide a kind of anti-specially change user's discontinuous form stealing electricity method, this method in time, accurately to lock Determine the discontinuous form stealing in power supply line and specially become user and can easily calculate stealing specially to become the power-steeling quantity that user need to remedy.
The technical scheme is that anti-special change user discontinuous form stealing electricity method of the invention, comprising the following steps:
1., with monthly for the period, monitoring region within the jurisdiction, which includes, specially becomes user by power supply department power information acquisition system Each high voltage supply route day line loss per unit △ P data;
2. being calculated using formula (2) and respectively fluctuating index △ P containing the special high voltage supply route day line loss per unit for becoming userbdIf a certain There is △ P containing the special high voltage supply route for becoming userbd>=3%, then it is doubtful for extracting this containing the special high voltage supply route for becoming user Seemingly there is discontinuous form stealing specially to become the target line of user:
△Pbd=△ Pmax-△Pmin (2)
In formula, △ PmaxFor the monthly maximum day line loss per unit of high voltage supply route, △ PminFor the monthly of high voltage supply route Minimum day line loss per unit;
3. determining that target line line loss per unit is mutated time point:
The first step, the day for transferring target line from power supply department D5000 system or Open3000 system and sell day power supply volume Electricity data transfers the day line loss per unit data of target line from power supply department power information acquisition system, draws target line Line loss per unit characteristic pattern;
Second step determines the line loss mutation day D of target line using the line loss per unit characteristic pattern of the target line of drafting;
4. extracting doubtful stealing in target line specially becomes user:
The first step transfers each special daily power consumption number for becoming user in target line from power supply department power information acquisition system According to;
Second step is mutated the electricity consumption bust index of day D using each special change user in formula (3) calculating target line in line loss △ W, if a certain special kilowatt hour of △ W >=1000 for becoming user, extracts the special change user as doubtful stealing and specially becomes user:
△ W=WD-1-WD (3)
In formula, WDThe electricity consumption of day D acquisition is mutated specially to become user in line loss;WD-1Day D is mutated specially to become user in line loss Proxima luce (prox. luc) acquisition electricity consumption;
5. specially becoming in user from the doubtful stealing of extraction, screens and locks stealing and specially become user:
The first step transfers the target line and doubtful stealing of line loss mutation day D from power supply department power information acquisition system 24 hours current datas for specially becoming user, with 5 minutes for interval synchronization sampled targets line current inSpecially become use with doubtful stealing Family electric current Ιn
Second step calculates doubtful stealing using formula (4) and specially becomes user in the electric current bust value △ I of line loss mutation day Dn;It adopts Doubtful stealing, which is calculated, with formula (5) specially becomes user in the electric current bust percentage K of line loss mutation day Dn:
△Inn-1-In (4)
In formula, ΙnSpecially become user in the present sample current value of electricity bust day, I for doubtful stealingn-1It is special for doubtful stealing Become user in electricity bust day and present sample current value ΙnAn adjacent upper sampled current value;
Third step, if a certain doubtful stealing, which specially becomes user, has △ In>=15 amperes or Kn>=10% situation, then count Calculate the △ InThere is the current variation value of the affiliated power supply line of time point, if power supply line is in the △ InThere is the curent change of time point Value does not occur △ InThe electric current bust of size, then lock the doubtful stealing and specially become user and specially become user into stealing;
6. specially becoming the power-steeling quantity that user needs to remedy using the stealing that formula (6) and formula (7) calculate locking:
In formula: η is specially to become user's stealing ratio, and △ I is the abovementioned steps 5. middle △ I calculatednMaximum value in value, ITFor Stealing specially becomes the current value that user acquires after electric current bust, WFFor the special change user stealing period electricity of acquisition, specially become user The stealing period terminates since selected electric current bust time point to there is electric current time point of uprushing, WQIt needs to remedy for the stealing period Power-steeling quantity.
The present invention has the effect of positive: anti-special change user discontinuous form stealing electricity method of the invention, by power supply Door relevant historical data, which carries out analysis, accurately automatic identification and the discontinuous form stealing locked in power supply line specially to become user, And quickly, easily and accurately can determine that discontinuous form stealing specially becomes the power-steeling quantity that user need to remedy, accuracy and reliability is higher.
Detailed description of the invention
Fig. 1 is flow chart of the method for the present invention;
Fig. 2 is the line loss per unit feature schematic diagram of the doubtful target line for having discontinuous form stealing specially to become user.
Specific embodiment
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
(embodiment 1)
See that Fig. 1, the anti-special change user discontinuous form stealing electricity method of the present embodiment are implemented by following steps:
1., with monthly for the period, monitoring region within the jurisdiction includes specially by the existing power information acquisition system of power supply department Become the day line loss per unit △ P data of each high voltage supply route of user:
In formula, WxgFor high voltage supply route day power supply volume;WxsFor high voltage supply route day electricity sales amount;Each high voltage supply line The day line loss per unit △ P data on road can be directly acquired from power supply department by existing power information acquisition system.
2. being calculated using formula (2) and respectively fluctuating index △ P containing the special high voltage supply route day line loss per unit for becoming userbdIf a certain High voltage supply route △ Pbd>=3%, then extracting this high voltage supply route is the doubtful target for having discontinuous form stealing specially to become user Route:
△Pbd=△ Pmax-△Pmin (2)
In formula, △ PbdFor the day line loss per unit undulating value of high voltage supply route, △ PmaxFor the monthly maximum of high voltage supply route Day line loss per unit, △ PminFor the monthly minimum day line loss per unit of high voltage supply route.
3. determining that target line line loss per unit is mutated time point:
The first step transfers the day power supply volume of target line from the existing D5000 system of power supply department or Open3000 system With day electricity sales amount data, the day line loss per unit data of target line are transferred from the existing power information acquisition system of power supply department, are drawn The line loss per unit characteristic pattern of the line loss per unit characteristic pattern of target line processed, the target line drawn is as schematically shown in Figure 2;
Second step determines the line loss mutation day D of target line using the line loss per unit characteristic pattern of the target line of drafting.
4. extracting doubtful stealing in target line specially becomes user:
The first step, from the existing power information acquisition system of power supply department transfer in target line it is each it is special become user it is daily Electricity data;
Second step is mutated the electricity consumption bust index of day D using each special change user in formula (3) calculating target line in line loss △ W, if a certain special kilowatt hour of △ W >=1000 for becoming user, extracts the special change user as doubtful stealing and specially becomes user:
△ W=WD-1-WD (3)
In formula, WDThe electricity consumption of day D acquisition is mutated specially to become user in line loss;WD-1Day D is mutated specially to become user in line loss Proxima luce (prox. luc) acquisition electricity consumption.
5. specially becoming in user from the doubtful stealing of the target line of extraction, screens and locks stealing and specially become user:
The first step is transferred the target line of line loss mutation day D from the existing power information acquisition system of power supply department and is doubted Specially become 24 hours current datas of user like stealing, with 5 minutes for interval synchronization sampled targets line current inWith doubtful stealing Specially become user's electric current Ιn
Second step calculates doubtful stealing using formula (4) and specially becomes user in the electric current bust value △ I of line loss mutation day Dn;It adopts Doubtful stealing, which is calculated, with formula (5) specially becomes user in the electric current bust percentage K of line loss mutation day Dn:
△Inn-1-In (4)
In formula, ΙnSpecially become user in the present sample current value of electricity bust day, I for doubtful stealingn-1It is special for doubtful stealing Become user in electricity bust day and present sample current value ΙnAn adjacent upper sampled current value;
Third step, if a certain doubtful stealing, which specially becomes user, has △ In>=15 amperes or Kn>=10% situation, then count Calculate the △ InThere is the current variation value of the affiliated power supply line of time point, if power supply line is in the △ InThere is the curent change of time point Value does not occur △ InThe electric current bust of size, then lock the doubtful stealing and specially become user and specially become user into stealing.
6. specially becoming the power-steeling quantity that user needs to remedy using the stealing that formula (6) and formula (7) calculate locking:
In formula: η is specially to become user's stealing ratio, and △ I is the abovementioned steps 5. middle △ I calculatednMaximum value in value, ITFor Stealing specially becomes the current value that user acquires after electric current bust, WFFor the special change user stealing period electricity of acquisition, specially become user The stealing period terminates since selected electric current bust time point to there is electric current time point of uprushing, WQIt needs to remedy for the stealing period Power-steeling quantity.
Above embodiments are the explanations to a specific embodiment of the invention, rather than limitation of the present invention, related technology The technical staff in field without departing from the spirit and scope of the present invention, can also make various transformation and variation and obtain To corresponding equivalent technical solution, therefore all equivalent technical solutions should be included into patent protection model of the invention It encloses.

Claims (1)

1. a kind of anti-specially change user's discontinuous form stealing electricity method, which comprises the following steps:
1., with monthly for the period, monitoring region within the jurisdiction, which includes, specially becomes each of user by power supply department power information acquisition system The day line loss per unit △ P data of high voltage supply route;
2. being calculated using formula (2) and respectively fluctuating index △ P containing the special high voltage supply route day line loss per unit for becoming userbdIf a certain containing special There is △ P in the high voltage supply route for becoming userbd>=3%, then extracting this has containing the special high voltage supply route for becoming user to be doubtful Discontinuous form stealing specially becomes the target line of user:
△Pbd=△ Pmax-△Pmin (2)
In formula, △ PmaxFor the monthly maximum day line loss per unit of high voltage supply route, △ PminFor the monthly minimum of high voltage supply route Day line loss per unit;
3. determining that target line line loss per unit is mutated time point:
The first step transfers the day power supply volume and day electricity sales amount of target line from power supply department D5000 system or Open3000 system Data transfer the day line loss per unit data of target line from power supply department power information acquisition system, draw the line loss of target line Rate characteristic pattern;
Second step determines the line loss mutation day D of target line using the line loss per unit characteristic pattern of the target line of drafting;
4. extracting doubtful stealing in target line specially becomes user:
The first step transfers each special daily power consumption data for becoming user in target line from power supply department power information acquisition system;
Second step is mutated the electricity consumption bust index △ W of day D using each special change user in formula (3) calculating target line in line loss, If a certain special kilowatt hour of △ W >=1000 for becoming user, extracts the special change user as doubtful stealing and specially becomes user:
△ W=WD-1-WD (3)
In formula, WDThe electricity consumption of day D acquisition is mutated specially to become user in line loss;WD-1Specially to become user before line loss is mutated day D The electricity consumption of acquisition on the one;
5. specially becoming in user from the doubtful stealing of extraction, screens and locks stealing and specially become user:
The first step transfers the target line of line loss mutation day D from power supply department power information acquisition system and doubtful stealing specially becomes 24 hours current datas of user, with 5 minutes for interval synchronization sampled targets line current inSpecially become user's electricity with doubtful stealing Flow Ιn
Second step calculates doubtful stealing using formula (4) and specially becomes user in the electric current bust value △ I of line loss mutation day Dn;Using formula (5) it calculates doubtful stealing and specially becomes user in the electric current bust percentage K of line loss mutation day Dn:
△Inn-1-In (4)
In formula, ΙnSpecially become user in the present sample current value of electricity bust day, I for doubtful stealingn-1Specially become use for doubtful stealing Family is in electricity bust day and present sample current value ΙnAn adjacent upper sampled current value;
Third step, if a certain doubtful stealing, which specially becomes user, has △ In>=15 amperes or Kn>=10% situation, then calculating should △InThere is the current variation value of the affiliated power supply line of time point, if power supply line is in the △ InThere is the current variation value of time point not There is △ InThe electric current bust of size, then lock the doubtful stealing and specially become user and specially become user into stealing;
6. specially becoming the power-steeling quantity that user needs to remedy using the stealing that formula (6) and formula (7) calculate locking:
In formula: η is specially to become user's stealing ratio, and △ I is the abovementioned steps 5. middle △ I calculatednMaximum value in value, ITFor stealing Specially become the current value that user acquires after electric current bust, WFFor the special change user stealing period electricity of acquisition, specially become user's stealing Period terminates since selected electric current bust time point to there is electric current time point of uprushing, WQThe stealing remedied is needed for the stealing period Amount.
CN201810035653.1A 2018-01-15 2018-01-15 Anti-private-transformer user intermittent electricity stealing method Active CN110047013B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810035653.1A CN110047013B (en) 2018-01-15 2018-01-15 Anti-private-transformer user intermittent electricity stealing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810035653.1A CN110047013B (en) 2018-01-15 2018-01-15 Anti-private-transformer user intermittent electricity stealing method

Publications (2)

Publication Number Publication Date
CN110047013A true CN110047013A (en) 2019-07-23
CN110047013B CN110047013B (en) 2023-06-13

Family

ID=67273315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810035653.1A Active CN110047013B (en) 2018-01-15 2018-01-15 Anti-private-transformer user intermittent electricity stealing method

Country Status (1)

Country Link
CN (1) CN110047013B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111443237A (en) * 2020-04-20 2020-07-24 北京中电普华信息技术有限公司 Method and system for determining compensation electric quantity
CN111650432A (en) * 2020-07-14 2020-09-11 国网冀北电力有限公司 Line loss-based electricity stealing determination method and device
CN113311379A (en) * 2021-05-26 2021-08-27 国网江苏省电力有限公司营销服务中心 Low-voltage electricity stealing intelligent diagnosis method based on big data
CN116070162A (en) * 2023-03-06 2023-05-05 国网浙江省电力有限公司宁波供电公司 Anti-electricity-stealing monitoring method and system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004340767A (en) * 2003-05-16 2004-12-02 Hitachi Ltd Electric power transaction method and electric power transaction system prevented in stealing electricity
CN103076476A (en) * 2012-12-18 2013-05-01 广东电网公司汕头供电局 On-line monitoring method of primary side shunt electric stealing of CT (current transformer) of 10kV special variable metering device
CN103399186A (en) * 2013-07-31 2013-11-20 深圳供电局有限公司 Method and device for identifying electricity stealing and leakage users based on line loss monitoring
CN105590166A (en) * 2015-12-16 2016-05-18 国家电网公司 Analytical judgment method for power consumption behavior of specific power transformer user in power distribution network
CN106156269A (en) * 2016-06-01 2016-11-23 国网河北省电力公司电力科学研究院 One is opposed electricity-stealing precise positioning on-line monitoring method
CN106645935A (en) * 2016-12-27 2017-05-10 国网浙江象山县供电公司 Electricity usage monitoring method and system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004340767A (en) * 2003-05-16 2004-12-02 Hitachi Ltd Electric power transaction method and electric power transaction system prevented in stealing electricity
CN103076476A (en) * 2012-12-18 2013-05-01 广东电网公司汕头供电局 On-line monitoring method of primary side shunt electric stealing of CT (current transformer) of 10kV special variable metering device
CN103399186A (en) * 2013-07-31 2013-11-20 深圳供电局有限公司 Method and device for identifying electricity stealing and leakage users based on line loss monitoring
CN105590166A (en) * 2015-12-16 2016-05-18 国家电网公司 Analytical judgment method for power consumption behavior of specific power transformer user in power distribution network
CN106156269A (en) * 2016-06-01 2016-11-23 国网河北省电力公司电力科学研究院 One is opposed electricity-stealing precise positioning on-line monitoring method
CN106645935A (en) * 2016-12-27 2017-05-10 国网浙江象山县供电公司 Electricity usage monitoring method and system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111443237A (en) * 2020-04-20 2020-07-24 北京中电普华信息技术有限公司 Method and system for determining compensation electric quantity
CN111650432A (en) * 2020-07-14 2020-09-11 国网冀北电力有限公司 Line loss-based electricity stealing determination method and device
CN113311379A (en) * 2021-05-26 2021-08-27 国网江苏省电力有限公司营销服务中心 Low-voltage electricity stealing intelligent diagnosis method based on big data
CN116070162A (en) * 2023-03-06 2023-05-05 国网浙江省电力有限公司宁波供电公司 Anti-electricity-stealing monitoring method and system
CN116070162B (en) * 2023-03-06 2023-08-29 国网浙江省电力有限公司宁波供电公司 Anti-electricity-stealing monitoring method and system

Also Published As

Publication number Publication date
CN110047013B (en) 2023-06-13

Similar Documents

Publication Publication Date Title
CN110047013A (en) It is anti-specially to become user's discontinuous form stealing electricity method
CN106093652B (en) A kind of non-intrusive electrical load monitoring System and method for having self-learning function
CN107340492A (en) Electric power meter failure analysis methods with scene anticipation are excavated based on big data
CN104200314B (en) Electricity and line loss same period statistical method based on data remote synchronization acquisition technique
CN111650431B (en) Ammeter region identification method
WO2020252785A1 (en) Abnormal electricity use recognition method and device, and computer readable storage medium
CN110045194A (en) High voltage supply route is opposed electricity-stealing method
CN110749784B (en) Line electricity stealing detection method based on electric power data wavelet analysis
CN111600296A (en) Power load prediction system based on edge calculation and prediction method thereof
CN109725219A (en) A kind of electric energy meter platform area automatic identifying method
CN107194780A (en) A kind of shared mobile phone lease operation system and its method
CN102289721A (en) Carbon emission monitoring and measuring service system for daily life
CN109444800A (en) Platform area recognition methods based on wireless communication acquisition
CN112307003A (en) Power grid data multidimensional auxiliary analysis method, system, terminal and readable storage medium
CN111652761B (en) Multi-source feature fusion electricity stealing behavior detection method based on evidence theory
CN103888731A (en) Structured description device and system for mixed video monitoring by means of gun-type camera and dome camera
US20150088441A1 (en) Energy usage estimation device and energy usage estimation method
Junaidi et al. Big data applications in electric energy systems
EP3449267A1 (en) A method for identifying the phases of a multi-phase distribution grid
CN112884228B (en) Big data-based transformer area line loss management and control system
CN103606111A (en) Integrated voltage qualified rate evaluation method
CN106127602B (en) Electricity stealing identification method and device based on reduction outlier algorithm
CN110045196B (en) High-voltage power supply line management line loss checking method
Li et al. Implementation of load profile test for electricity distribution networks
CN110719445A (en) Remote meter reading system and method based on image recognition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant