CN110045254A - A kind of multistation insulating bar segmented pressure test device - Google Patents
A kind of multistation insulating bar segmented pressure test device Download PDFInfo
- Publication number
- CN110045254A CN110045254A CN201910447235.8A CN201910447235A CN110045254A CN 110045254 A CN110045254 A CN 110045254A CN 201910447235 A CN201910447235 A CN 201910447235A CN 110045254 A CN110045254 A CN 110045254A
- Authority
- CN
- China
- Prior art keywords
- base
- rod
- withstand voltage
- segmented
- test platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/12—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing
- G01R31/1227—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials
- G01R31/1263—Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials of solid or fluid materials, e.g. insulation films, bulk material; of semiconductors or LV electronic components or parts; of cable, line or wire insulation
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Testing Relating To Insulation (AREA)
Abstract
本发明公开一种多工位绝缘杆分段耐压测试装置,在底座上设置多个接地电极座,利用底座的支撑杆固定均压环,将均压环与高压电源连接,在底座和均压环之间设置测试平台,测试平台上设置多个与底座上的多个接地电极座对应的高压输出电极,每个高压输出电极上设置一个泄漏电流采集装置,将每个所述高压输出电极与一个所述接地电极座相对应,将测试平台与所述均压环之间通过高压线电连接,能够同时安装多个待测绝缘杆,通过升降装置带动测试平台向下运动,实现绝缘杆的分段耐压测试或不同长度的耐压测试,通过每个泄漏电流采集装置采集每个待测绝缘杆的测试数据,本装置结构简单,能够同时测量多个待测绝缘杆,并且能够实现不同高度绝缘杆的测量。
The invention discloses a multi-station insulation rod segmented withstand voltage test device. A plurality of ground electrode seats are arranged on the base, and the support rods of the base are used to fix a voltage equalizing ring, and the voltage equalizing ring is connected with a high-voltage power supply. A test platform is arranged between the pressure rings, and a plurality of high-voltage output electrodes corresponding to the plurality of ground electrode seats on the base are arranged on the test platform, and a leakage current collection device is arranged on each of the high-voltage output electrodes, and each Corresponding to one of the ground electrode bases, the test platform and the pressure equalizing ring are electrically connected through a high-voltage line, and a plurality of insulating rods to be tested can be installed at the same time. Segmented withstand voltage test or withstand voltage test of different lengths, the test data of each insulation rod to be tested is collected through each leakage current acquisition device. The device has a simple structure, can measure multiple insulation rods to be tested at the same time, and can achieve different Measurement of highly insulated rods.
Description
技术领域technical field
本发明属于电力设备检测领域,尤其涉及一种多工位绝缘杆分段耐压测试装置。The invention belongs to the field of electric equipment detection, in particular to a multi-station insulation rod segmented withstand voltage test device.
背景技术Background technique
绝缘杆是电力系统操作和检修必备的安全工器具,根据DL/T1746-2015《电力安全工器具预防性试验规程》规定,绝缘杆每1年为周期,需按上述规程中试验方法做预防性试验,以检测其安全的有效性。在工频耐压检测时,需按规定要求设置两个加压电极之间的距离。由于绝缘杆属于大量使用工具,每年一次的检测量非常大,现有的绝缘杆测试设备通过在绝缘杆两端固定加压电极,如果需要改变绝缘杆的耐压测试的长度,就得在每个绝缘杆上重新固定加压电极,效率低下,不能满足对大量绝缘杆的耐压测试。The insulating rod is a necessary safety tool for the operation and maintenance of the power system. According to DL/T1746-2015 "Provisional Test Regulations for Electrical Safety Tools and Appliances", the insulating rod is a cycle every 1 year. sex trials to test its safety and effectiveness. In the power frequency withstand voltage test, the distance between the two pressure electrodes should be set according to the specified requirements. Since the insulating rod is a tool used in large quantities, the amount of testing once a year is very large. The existing insulating rod testing equipment fixes the pressure electrodes at both ends of the insulating rod. If the length of the withstand voltage test of the insulating rod needs to be changed, it must be Re-fixing the pressurized electrodes on each insulating rod is inefficient and cannot meet the withstand voltage test of a large number of insulating rods.
发明内容SUMMARY OF THE INVENTION
为解决以上问题,本发明提出多工位绝缘杆分段耐压测试装置,可一次性对大量绝缘杆进行分段耐压测试或不同长度的耐压测试。In order to solve the above problems, the present invention proposes a multi-position insulating rod segmented withstand voltage test device, which can perform segmental withstand voltage tests or different length withstand voltage tests on a large number of insulating rods at one time.
为了达到上述目的,本发明采用以下技术方案予以解决。In order to achieve the above object, the present invention adopts the following technical solutions to solve it.
一种多工位绝缘杆分段耐压测试装置,包括底座和测试平台,底座上设置有多个接地电极座,底座上竖直设置有支撑杆,支撑杆的上端设置有均压环,均压环与高压电源相连接;A multi-station insulation rod segmented withstand voltage test device, comprising a base and a test platform, a plurality of ground electrode bases are arranged on the base, a support rod is vertically arranged on the base, and a pressure equalizing ring is arranged on the upper end of the support rod. The pressure ring is connected with the high voltage power supply;
所述测试平台通过升降装置安装在底座和均压环之间,测试平台上设置有多个与底座上的多个接地电极座对应的高压输出电极,每个高压输出电极上设有一个泄漏电流采集装置,测试平台与所述均压环之间电连接;The test platform is installed between the base and the pressure equalizing ring through a lifting device. The test platform is provided with a plurality of high-voltage output electrodes corresponding to the plurality of ground electrode seats on the base, and each high-voltage output electrode is provided with a leakage current a collection device, the test platform is electrically connected with the voltage equalizing ring;
底座上设有与底座一端铰接的接地杆,接地杆能够相对底座转动与均压环接触。The base is provided with a grounding rod hinged with one end of the base, and the grounding rod can rotate relative to the base to be in contact with the pressure equalizing ring.
进一步的,接地电极座上设置有用于加持待测绝缘杆的环抱夹。Further, the ground electrode base is provided with an embracing clip for supporting the insulating rod to be tested.
进一步的,环抱夹与待测绝缘杆接触一侧设置有电泡棉。Further, electric foam is arranged on the side of the encircling clip in contact with the insulating rod to be tested.
进一步的,环抱夹采用两个对称设置的夹持杆,夹持杆的两端转动安装在底座上,夹持杆与底座转动连接处设有扭簧。Further, the embracing clip adopts two symmetrically arranged clamping rods, both ends of the clamping rods are rotatably mounted on the base, and a torsion spring is provided at the rotational connection between the clamping rod and the base.
进一步的,所述接地杆的下端与所述底座之间设置有摆动控制装置。Further, a swing control device is arranged between the lower end of the grounding rod and the base.
进一步的,摆动控制装置连杆和摆动电机,摆动电机的主轴上连接有曲柄,曲柄的端部与连杆的一端铰接,连杆的另一端铰接在接地杆上。Further, the swing control device has a connecting rod and a swing motor, the main shaft of the swing motor is connected with a crank, the end of the crank is hinged with one end of the connecting rod, and the other end of the connecting rod is hinged on the ground rod.
进一步的,升降装置包括垂直设置于底座上的丝杠,丝杠的两端分别与底座和均压环转动连接,底座上设有用于驱动丝杠转动的驱动电机,测试平台与丝杠螺纹配合传动。Further, the lifting device includes a lead screw vertically arranged on the base, two ends of the lead screw are respectively rotatably connected with the base and the pressure equalizing ring, the base is provided with a driving motor for driving the lead screw to rotate, and the test platform is threadedly matched with the lead screw. transmission.
进一步的,底座上设有两个平行设置的丝杠,两个丝杠均与测试平台螺纹配合传动,两个丝杠的下端均设有一个同步带轮,两个同步带轮之间通过同步传动带传动。Further, two parallel lead screws are arranged on the base, and the two lead screws are both threaded with the test platform for transmission, and the lower ends of the two lead screws are provided with a synchronous pulley. Belt drive.
进一步的,均压环上设置有水平架,水平架与支撑杆的上端固定连接,丝杠的上端转动连接在水平架上。Further, the pressure equalizing ring is provided with a horizontal frame, the horizontal frame is fixedly connected with the upper end of the support rod, and the upper end of the lead screw is rotatably connected to the horizontal frame.
进一步的,支撑杆上标有长度刻度,测试平台上设置有指针,指针指向支撑杆上的长度刻度。Further, a length scale is marked on the support rod, a pointer is provided on the test platform, and the pointer points to the length scale on the support rod.
与现有技术相比,本发明具有以下有益的技术效果:Compared with the prior art, the present invention has the following beneficial technical effects:
本发明一种多工位绝缘杆分段耐压测试装置,通过设置底座、测试平台和接地杆;在底座上设置多个接地电极座,利用底座的支撑杆固定有均压环,将均压环与高压电源相连接,在底座和均压环之间设置测试平台,在测试平台上设置多个与底座上的多个接地电极座对应的高压输出电极,并且在每个高压输出电极上设置一个泄漏电流采集装置,将每个所述高压输出电极与一个所述接地电极座相对应,将测试平台与所述均压环之间通过高压线电连接,能够同时安装多个待测绝缘杆,通过升降装置带动测试平台向下运动,能够实现绝缘杆的分段耐压测试或不同长度的耐压测试,通过每个泄漏电流采集装置采集每个待测绝缘杆的测试数据,本装置结构简单,使用方便,能够同时测量多个待测绝缘杆,并且能够实现不同高度绝缘杆的测量。The invention is a multi-station insulation rod segmented withstand voltage test device. By setting a base, a test platform and a grounding rod; a plurality of grounding electrode seats are arranged on the base, and a pressure equalizing ring is fixed by the support rod of the base, and the voltage equalizing The ring is connected with a high-voltage power supply, a test platform is set between the base and the pressure equalizing ring, a plurality of high-voltage output electrodes corresponding to the multiple ground electrode seats on the base are set on the test platform, and each high-voltage output electrode is set A leakage current collection device, each of the high-voltage output electrodes is corresponding to one of the ground electrode bases, and the test platform and the voltage equalizing ring are electrically connected through a high-voltage line, which can simultaneously install a plurality of insulating rods to be tested, The test platform is driven downward by the lifting device, which can realize the segmented withstand voltage test of the insulating rod or the withstand voltage test of different lengths. The test data of each insulating rod to be tested is collected through each leakage current acquisition device. The device has a simple structure. , easy to use, can measure a plurality of insulating rods to be tested at the same time, and can realize the measurement of insulating rods of different heights.
对绝缘杆进行耐压测试前,先通过摆动控制装置带动接地杆往内侧摆动,使接地杆的上端与均压环相接触,然后将多个绝缘杆分别竖直固定在接地电极座上,再通过升降装置带动测试平台向下运动,使所有绝缘杆的上端与测试平台上对应的高压输出电极相接触,再使接地杆的上端远离均压环,确保安装时接地电极座与高压输出电极之间电压平衡,确保安装安全,最后往均压环接通高压电,通过测试平台上的泄漏电流采集装置来监测每个绝缘杆上是否有泄漏电流,安全可靠。Before the withstand voltage test of the insulating rod, first drive the grounding rod to swing inward through the swing control device, so that the upper end of the grounding rod is in contact with the pressure equalizing ring, and then vertically fix multiple insulating rods on the grounding electrode holder, and then The test platform is driven downward by the lifting device, so that the upper ends of all insulating rods are in contact with the corresponding high-voltage output electrodes on the test platform, and then the upper ends of the grounding rods are kept away from the pressure equalizing ring to ensure that the grounding electrode seat and the high-voltage output electrode are connected during installation. The voltage is balanced between the two to ensure the safety of installation. Finally, the high-voltage power is connected to the voltage equalizing ring, and the leakage current collection device on the test platform is used to monitor whether there is leakage current on each insulating rod, which is safe and reliable.
进一步的,在接地电极座上设置环抱夹,实现不同规格和种类的绝缘杆的固定安装,给环抱夹通电后环抱夹可将绝缘杆的下端抱紧,使其与接地电机座接触良好。Further, an embracing clip is arranged on the grounding electrode base to realize the fixed installation of insulating rods of different specifications and types. After the embracing clip is energized, the embracing clip can hold the lower end of the insulating rod tightly so that it is in good contact with the grounding motor base.
本发明的多工位绝缘杆分段耐压测试装置可一次性可对大量绝缘杆进行测试,与绝缘杆的安装和拆卸比较方便,可随时调节绝缘杆的耐压测试长度。The multi-position insulating rod segment withstand voltage test device of the present invention can test a large number of insulating rods at one time, is more convenient to install and disassemble the insulating rods, and can adjust the withstand voltage test length of the insulating rods at any time.
进一步的,通过两个丝杠和同时控制测试平台的升降,保证升降平台的平稳性。Further, the lifting and lowering of the test platform is controlled simultaneously by two lead screws to ensure the stability of the lifting platform.
进一步的,所述支撑杆上标有长度刻度,所述测试平台上设置有指针,便于不同高度的精确调节,方便实验人员确定绝缘杆的耐压测试长度。Further, the support rod is marked with a length scale, and the test platform is provided with a pointer, which is convenient for precise adjustment of different heights, and it is convenient for the experimenter to determine the withstand voltage test length of the insulating rod.
附图说明Description of drawings
图1是本发明正向结构示意图;Fig. 1 is the forward structure schematic diagram of the present invention;
图2是图1的侧向结构示意图。FIG. 2 is a schematic side view of the structure of FIG. 1 .
图中:1、底座;101、接地电极座;102、环抱夹;2、支撑杆;3、均压环;301、水平架;4、测试平台;401、高压输出电极;5、接地杆;6、丝杠;7、驱动电机;8、同步带轮;9、同步传动带;10、连杆;11、摆动电机;12、指针。In the figure: 1. base; 101, ground electrode seat; 102, encircling clip; 2, support rod; 3, equalizing ring; 301, horizontal frame; 4, test platform; 401, high voltage output electrode; 5, ground rod; 6. Lead screw; 7. Drive motor; 8. Synchronous pulley; 9. Synchronous transmission belt; 10. Connecting rod; 11. Swing motor; 12. Pointer.
具体实施方式Detailed ways
下面结合附图对本发明做进一步详细描述:Below in conjunction with accompanying drawing, the present invention is described in further detail:
为了能更清楚地理解本发明的上述目的、特征和优点,下面结合附图和具体实施方式对本发明进行进一步的详细描述。In order to more clearly understand the above objects, features and advantages of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
参考图1和图2,一种多工位绝缘杆分段耐压测试装置,包括底座1、测试平台4和接地杆5;所述底座1上设置有多个接地电极座101,所述底座1上竖直设置有支撑杆2,支撑杆2的上端连接有均压环3,均压环3与高压电源相连接;所述测试平台4设置在底座1和均压环3之间,底座1上设有用于控制测试平台4升降的升降装置,所述测试平台4上设置有多个与底座1上的多个接地电极座101对应的高压输出电极401,每个高压输出电极401上设有一个泄漏电流采集装置,每个高压输出电极401都对应有一个接地电极座101,所述测试平台4与均压环3之间通过高压线电连接;接地杆5的下端铰接在底座1的一端,接地杆5的上端能够与均压环3外侧接触,接地杆5的下端与底座1之间设置有摆动装置。所述接地电极座101上设置有环抱夹102,所述环抱夹102的内侧设置有电泡棉。Referring to FIGS. 1 and 2, a multi-position insulating rod segmented withstand voltage test device includes a base 1, a test platform 4 and a grounding rod 5; the base 1 is provided with a plurality of grounding electrode bases 101, 1 is vertically arranged with a support rod 2, the upper end of the support rod 2 is connected with a pressure equalizing ring 3, and the pressure equalizing ring 3 is connected with a high-voltage power supply; the test platform 4 is arranged between the base 1 and the pressure equalizing ring 3, and the base 1 is provided with a lifting device for controlling the lifting and lowering of the test platform 4. The test platform 4 is provided with a plurality of high-voltage output electrodes 401 corresponding to the plurality of ground electrode holders 101 on the base 1, and each high-voltage output electrode 401 is provided with a plurality of high-voltage output electrodes 401. There is a leakage current collecting device, and each high-voltage output electrode 401 corresponds to a grounding electrode base 101 , and the test platform 4 and the voltage equalizing ring 3 are electrically connected through a high-voltage line; the lower end of the grounding rod 5 is hinged to one end of the base 1 , the upper end of the grounding rod 5 can be in contact with the outside of the pressure equalizing ring 3 , and a swing device is provided between the lower end of the grounding rod 5 and the base 1 . An embracing clip 102 is arranged on the ground electrode holder 101 , and electric foam is arranged on the inner side of the encircling clip 102 .
在以上实施例中,底座1、测试平台4均呈长方体状,测试平台4沿长度方向的两端与升降装置连接,多个接地电极座101对称设置在底座1的两侧,对应的,多个高压输出电极401对称设置在测试平台4的两侧。对绝缘杆进行耐压测试前,先通过摆动控制装置带动接地杆5往内侧摆动,使接地杆5的上端与均压环3相接触,然后将多个绝缘杆分别竖直固定在接地电极座101上,再通过升降装置带动测试平台4向下运动,使所有绝缘杆的上端与测试平台4上对应的高压输出电极401相接触,再使接地杆5的上端远离均压环3,最后往均压环3接通高压电,通过测试平台4上的泄漏电流采集装置来监测每个绝缘杆上是否有泄漏电流,判断绝缘杆是否合格。由于测试平台4可以上下移动,也可对绝缘杆进行的分段耐压测试或不同长度的耐压测试。为了保证试验人员安全,会另外设置一个与该测试装置相分离的实验控制台,泄漏电流采集装置可通过红外信号将测试数据传送到该实验控制台中。不同规格和种类的绝缘杆的粗细不同,为了使不同规格和种类的将绝缘杆的下端与接地电极座101接触紧密,可在接地电极座101上设置环抱夹102,环抱夹102可适应不同粗细的绝缘杆,给环抱夹102通电后环抱夹102可将绝缘杆的下端抱紧,使其与接地电机座接触良好。本发明的多工位绝缘杆分段耐压测试装置可一次性可对大量绝缘杆进行测试,与绝缘杆的安装和拆卸比较方便,可随时调节绝缘杆的耐压测试长度。In the above embodiment, the base 1 and the test platform 4 are both in the shape of a cuboid, the two ends of the test platform 4 along the length direction are connected to the lifting device, and the plurality of ground electrode holders 101 are symmetrically arranged on both sides of the base 1. Correspondingly, many The high-voltage output electrodes 401 are symmetrically arranged on both sides of the test platform 4 . Before the withstand voltage test of the insulating rod, first drive the grounding rod 5 to swing inward through the swing control device, so that the upper end of the grounding rod 5 is in contact with the pressure equalizing ring 3, and then vertically fix the plurality of insulating rods on the grounding electrode holder. 101, and then drive the test platform 4 to move downward through the lifting device, so that the upper ends of all insulating rods are in contact with the corresponding high-voltage output electrodes 401 on the test platform 4, and then the upper ends of the grounding rods 5 are kept away from the pressure equalizing ring 3, and finally go to The voltage equalizing ring 3 is connected to the high-voltage power, and the leakage current collecting device on the test platform 4 is used to monitor whether there is leakage current on each insulating rod, and judge whether the insulating rod is qualified. Since the test platform 4 can move up and down, it is also possible to perform a segmented withstand voltage test or a withstand voltage test of different lengths on the insulating rod. In order to ensure the safety of the test personnel, a separate experimental console will be set up from the test device, and the leakage current acquisition device can transmit the test data to the experimental console through infrared signals. Different specifications and types of insulating rods have different thicknesses. In order to make the lower end of the insulating rods and the grounding electrode base 101 in close contact with different specifications and types, an embracing clip 102 can be set on the grounding electrode base 101, and the embracing clip 102 can be adapted to different thicknesses. After the encircling clip 102 is energized, the encircling clip 102 can hold the lower end of the insulating pole tightly, so that it is in good contact with the grounded motor base. The multi-position insulating rod segment withstand voltage test device of the present invention can test a large number of insulating rods at one time, is more convenient to install and disassemble the insulating rods, and can adjust the withstand voltage test length of the insulating rods at any time.
参考图1,根据本发明的一个实施例,所述升降装置包括:两个丝杠6和一个驱动电机7,两个所述丝杠6分别转动装配在所述底座1和所述均压环3之间,所述测试平台4与两个所述丝杠6螺纹配合,每个所述丝杠6的下端分别设置有同步带轮8,两个所述同步带轮8之间套有同步传动带9,所述驱动电机7的主轴与其中一个所述丝杠6的下端相连接,通过两个丝杠同步传动,使测试平台平稳升降。Referring to FIG. 1 , according to an embodiment of the present invention, the lifting device includes: two lead screws 6 and a drive motor 7 , and the two lead screws 6 are respectively rotatably assembled on the base 1 and the pressure equalizing ring 3, the test platform 4 is threadedly matched with two of the lead screws 6, the lower ends of each of the lead screws 6 are respectively provided with a synchronous pulley 8, and a synchronous pulley is sleeved between the two synchronous pulleys 8. A transmission belt 9, the main shaft of the drive motor 7 is connected with the lower end of one of the lead screws 6, and the two lead screws are synchronously driven to make the test platform rise and fall smoothly.
在以上实施例中,驱动电机7通电后可通过主轴直接带动一个丝杠6转动,由于两个丝杠6通过同步带轮8以及同步传动带9传动连接,所以另一个丝杠6也会同时同向转动,当两个丝杠6原地同步转动时,与两个丝杠6同时螺纹配合的测试平台4在丝杠6上的螺纹的带动下沿着竖直方向上升或下降,以此调整测试平台4的竖直高度。In the above embodiment, after the driving motor 7 is powered on, it can directly drive one lead screw 6 to rotate through the main shaft. When the two lead screws 6 rotate synchronously in situ, the test platform 4 that is threadedly matched with the two lead screws 6 rises or falls in the vertical direction driven by the threads on the lead screws 6, so as to adjust The vertical height of the test platform 4 .
参考图1和图2,根据本发明的一个实施例,所述均压环3上设置有水平架301,所述水平架301与所述支撑杆2的上端固定连接,所述丝杠6的上端轴向转动连接在所述水平架301上。1 and 2 , according to an embodiment of the present invention, a horizontal frame 301 is provided on the pressure equalizing ring 3 , and the horizontal frame 301 is fixedly connected with the upper end of the support rod 2 . The upper end is axially rotatably connected to the horizontal frame 301 .
在以上实施例中,水平架301固定连接在均压环3的内侧,支撑杆2的上端与水平架301固定连接,丝杠6的上端与水平架301之间设置有轴承,丝杠6可相对水平架301原地转动。In the above embodiment, the horizontal frame 301 is fixedly connected to the inner side of the pressure equalizing ring 3, the upper end of the support rod 2 is fixedly connected to the horizontal frame 301, and a bearing is provided between the upper end of the lead screw 6 and the horizontal frame 301, and the lead screw 6 can be Rotate in place relative to the horizontal frame 301 .
参考图1,根据本发明的一个实施例,所述摆动控制装置包括:连杆10和一个摆动电机11,所述摆动电机11的主轴上连接有曲柄,所述曲柄的端部与所述连杆10的一端铰接,所述连杆10的另一端铰接在所述接地杆5上,电机在未通电情况下,可自由摆动,接地杆5在自身重力情况下向外侧倾斜,电机主轴上连接的曲柄通过连杆10与接地杆5相连接,使接地杆5的上端处于悬空和与均压环3相分离的状态,当电机接电后,电机通过曲柄和连杆10带动接地杆5往内侧摆动,使接地杆5的上端与均压环3相接触,使均压环3直接接地。1, according to an embodiment of the present invention, the swing control device includes: a connecting rod 10 and a swing motor 11, a crank is connected to the main shaft of the swing motor 11, and the end of the crank is connected to the connection One end of the rod 10 is hinged, and the other end of the connecting rod 10 is hinged on the grounding rod 5. The motor can swing freely when the motor is not powered on. The grounding rod 5 is inclined to the outside under its own gravity, and the motor is connected to the main shaft. The crank is connected with the grounding rod 5 through the connecting rod 10, so that the upper end of the grounding rod 5 is suspended and separated from the pressure equalizing ring 3. When the motor is powered on, the motor drives the grounding rod 5 through the crank and the connecting rod 10. The inner side swings so that the upper end of the grounding rod 5 is in contact with the pressure equalizing ring 3, so that the equalizing ring 3 is directly grounded.
参考图1,根据本发明的一个实施例,所述支撑杆2上标有长度刻度,所述测试平台4上设置有指针12。Referring to FIG. 1 , according to an embodiment of the present invention, the support rod 2 is marked with a length scale, and the test platform 4 is provided with a pointer 12 .
在以上实施例中,测试平台4再升降装置的带动下沿着丝杠6移动时,指针12指示在支撑杆2上的长度刻度处,方便实验人员确定绝缘杆的耐压测试长度。In the above embodiment, when the test platform 4 is moved along the lead screw 6 by the lifting device, the pointer 12 indicates the length scale on the support rod 2, which is convenient for the experimenter to determine the withstand voltage test length of the insulating rod.
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit and scope of the invention. Thus, provided that these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910447235.8A CN110045254A (en) | 2019-05-27 | 2019-05-27 | A kind of multistation insulating bar segmented pressure test device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910447235.8A CN110045254A (en) | 2019-05-27 | 2019-05-27 | A kind of multistation insulating bar segmented pressure test device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110045254A true CN110045254A (en) | 2019-07-23 |
Family
ID=67283768
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910447235.8A Pending CN110045254A (en) | 2019-05-27 | 2019-05-27 | A kind of multistation insulating bar segmented pressure test device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110045254A (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110716114A (en) * | 2019-11-28 | 2020-01-21 | 国网河北省电力有限公司沧州供电分公司 | Insulating rod withstand voltage test appurtenance |
| CN110907877A (en) * | 2019-11-13 | 2020-03-24 | 宁波荣集锦科技有限公司 | Current transformer production detection device |
| CN111856093A (en) * | 2020-06-11 | 2020-10-30 | 中国电力科学研究院有限公司 | A pendulum-type grounding rod design method and system for eliminating accumulated charges in space electric field measurement |
| CN112180167A (en) * | 2020-09-25 | 2021-01-05 | 广东电网有限责任公司 | A detection device and method of using the same |
| CN112946435A (en) * | 2021-02-02 | 2021-06-11 | 湖北清江水电开发有限责任公司 | Insulating rod voltage-withstanding detection device and method |
| CN113253080A (en) * | 2021-07-08 | 2021-08-13 | 广东电网有限责任公司东莞供电局 | Multi-station insulation rod subsection voltage-withstanding testing device |
| CN113295891A (en) * | 2021-04-15 | 2021-08-24 | 国网湖北省电力有限公司十堰供电公司 | Many insulator spindle withstand voltage test supports of electrodynamic type |
| CN114624552A (en) * | 2020-12-11 | 2022-06-14 | 河南平芝高压开关有限公司 | A kind of insulation rod segment withstand voltage test device |
| CN116067775A (en) * | 2023-02-20 | 2023-05-05 | 浙江华电器材检测研究院有限公司 | Segment detection device and workbench of an insulating tool |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201628755U (en) * | 2010-04-15 | 2010-11-10 | 浙江华特电气有限公司 | Insulating rope or insulating rod electric test frame |
| CN202210035U (en) * | 2011-08-11 | 2012-05-02 | 浙江大学台州研究院 | Automobile pedal control mechanism assembly performance test bench |
| CN203950014U (en) * | 2014-07-03 | 2014-11-19 | 厦门中唐电气有限公司 | A kind of test platform of UHV (ultra-high voltage) insulating safety tools |
| CN204044303U (en) * | 2014-09-03 | 2014-12-24 | 国家电网公司 | A kind of test apparatus for overpressure resistance of insulator spindle |
| CN204065336U (en) * | 2014-09-03 | 2014-12-31 | 国家电网公司 | A kind of test apparatus for overpressure resistance of insulator spindle |
| CN105158653A (en) * | 2015-08-14 | 2015-12-16 | 韩慧敏 | Automatic and retractable type insulation tool alternating-current withstand voltage test device and system thereof |
| CN106324294A (en) * | 2016-07-05 | 2017-01-11 | 国家电网公司 | Insulating rod voltage-withstanding test frame |
| CN207164098U (en) * | 2017-09-28 | 2018-03-30 | 保定市汇邦电气有限公司 | Horizontal insulating bar pressure test platform |
| CN207472919U (en) * | 2017-11-24 | 2018-06-08 | 广西电网有限责任公司崇左供电局 | A kind of convertible insulating bar test auxiliary stand |
| CN210109249U (en) * | 2019-05-27 | 2020-02-21 | 国家电网有限公司 | Multi-station insulating rod voltage-withstanding testing device |
-
2019
- 2019-05-27 CN CN201910447235.8A patent/CN110045254A/en active Pending
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201628755U (en) * | 2010-04-15 | 2010-11-10 | 浙江华特电气有限公司 | Insulating rope or insulating rod electric test frame |
| CN202210035U (en) * | 2011-08-11 | 2012-05-02 | 浙江大学台州研究院 | Automobile pedal control mechanism assembly performance test bench |
| CN203950014U (en) * | 2014-07-03 | 2014-11-19 | 厦门中唐电气有限公司 | A kind of test platform of UHV (ultra-high voltage) insulating safety tools |
| CN204044303U (en) * | 2014-09-03 | 2014-12-24 | 国家电网公司 | A kind of test apparatus for overpressure resistance of insulator spindle |
| CN204065336U (en) * | 2014-09-03 | 2014-12-31 | 国家电网公司 | A kind of test apparatus for overpressure resistance of insulator spindle |
| CN105158653A (en) * | 2015-08-14 | 2015-12-16 | 韩慧敏 | Automatic and retractable type insulation tool alternating-current withstand voltage test device and system thereof |
| CN106324294A (en) * | 2016-07-05 | 2017-01-11 | 国家电网公司 | Insulating rod voltage-withstanding test frame |
| CN207164098U (en) * | 2017-09-28 | 2018-03-30 | 保定市汇邦电气有限公司 | Horizontal insulating bar pressure test platform |
| CN207472919U (en) * | 2017-11-24 | 2018-06-08 | 广西电网有限责任公司崇左供电局 | A kind of convertible insulating bar test auxiliary stand |
| CN210109249U (en) * | 2019-05-27 | 2020-02-21 | 国家电网有限公司 | Multi-station insulating rod voltage-withstanding testing device |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110907877A (en) * | 2019-11-13 | 2020-03-24 | 宁波荣集锦科技有限公司 | Current transformer production detection device |
| CN110907877B (en) * | 2019-11-13 | 2021-10-22 | 常州金坛万杰电器有限公司 | A current transformer production detection device |
| CN110716114A (en) * | 2019-11-28 | 2020-01-21 | 国网河北省电力有限公司沧州供电分公司 | Insulating rod withstand voltage test appurtenance |
| CN111856093A (en) * | 2020-06-11 | 2020-10-30 | 中国电力科学研究院有限公司 | A pendulum-type grounding rod design method and system for eliminating accumulated charges in space electric field measurement |
| CN112180167A (en) * | 2020-09-25 | 2021-01-05 | 广东电网有限责任公司 | A detection device and method of using the same |
| CN114624552A (en) * | 2020-12-11 | 2022-06-14 | 河南平芝高压开关有限公司 | A kind of insulation rod segment withstand voltage test device |
| CN114624552B (en) * | 2020-12-11 | 2025-09-23 | 河南平芝高压开关有限公司 | A device for testing the segmented withstand voltage of an insulating pull rod |
| CN112946435A (en) * | 2021-02-02 | 2021-06-11 | 湖北清江水电开发有限责任公司 | Insulating rod voltage-withstanding detection device and method |
| CN113295891A (en) * | 2021-04-15 | 2021-08-24 | 国网湖北省电力有限公司十堰供电公司 | Many insulator spindle withstand voltage test supports of electrodynamic type |
| CN113253080A (en) * | 2021-07-08 | 2021-08-13 | 广东电网有限责任公司东莞供电局 | Multi-station insulation rod subsection voltage-withstanding testing device |
| CN113253080B (en) * | 2021-07-08 | 2021-09-14 | 广东电网有限责任公司东莞供电局 | Multi-station insulation rod subsection voltage-withstanding testing device |
| CN116067775A (en) * | 2023-02-20 | 2023-05-05 | 浙江华电器材检测研究院有限公司 | Segment detection device and workbench of an insulating tool |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210109249U (en) | Multi-station insulating rod voltage-withstanding testing device | |
| CN204575755U (en) | The sub-measuring robots of a kind of Intelligent insulation | |
| CN205620258U (en) | A test device for scratch resistance of cable insulation layer | |
| CN105866651B (en) | A method of using a withstand voltage detection device for an insulating rod-type safety tool | |
| CN219811036U (en) | Electric power instrument detection device | |
| CN211086375U (en) | A foldable insulating rod withstand voltage test bracket | |
| CN118425699A (en) | A handheld electric turn insulation test device for operation and maintenance of power supply equipment | |
| CN207036547U (en) | A kind of photovoltaic cable Kinetic penetration experimental provision | |
| CN109238087A (en) | One kind being based on monolithic processor controlled length-measuring appliance | |
| CN114062877A (en) | Insulation rod checking system and checking method | |
| CN208621694U (en) | A portable circuit testing equipment cabinet for electric power | |
| CN209296869U (en) | A kind of livewire work felt pad automatic detection device | |
| CN210894668U (en) | An electric meter detection mechanism for automatic wiring and disconnection | |
| CN216926974U (en) | Insulating rod calibration system | |
| CN220084919U (en) | Intelligent GIS partial discharge monitoring device | |
| CN208587741U (en) | A kind of gas pipeline wall defects detection device | |
| CN223487782U (en) | A quick-install wire fixing device | |
| CN219496560U (en) | Insulation detection device for power transmission equipment | |
| CN215005833U (en) | Automatic short circuit frock of fault indicator | |
| CN210954135U (en) | Combined electroscope test stand | |
| CN220542986U (en) | New energy battery detects with detection platform of convenient centre gripping | |
| CN221426838U (en) | Direct current battery detection device | |
| CN216694887U (en) | Double-motor shaft comprehensive detection tool | |
| CN204008922U (en) | A kind of experimental provision for detection of the cable life-span | |
| CN218098654U (en) | Workpiece detection device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190723 |