CN110043029A - The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing - Google Patents

The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing Download PDF

Info

Publication number
CN110043029A
CN110043029A CN201910416166.4A CN201910416166A CN110043029A CN 110043029 A CN110043029 A CN 110043029A CN 201910416166 A CN201910416166 A CN 201910416166A CN 110043029 A CN110043029 A CN 110043029A
Authority
CN
China
Prior art keywords
water tank
precompressed
monitoring
bracket
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910416166.4A
Other languages
Chinese (zh)
Inventor
张宏明
马德志
杨正成
刘扬辉
卢熙文
王雪岚
张弘
胡传贵
杨鸿祥
粟瑶
刘旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Construction Engineering Group Second Construction Engineering Co Ltd
Original Assignee
Guizhou Construction Engineering Group Second Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Construction Engineering Group Second Construction Engineering Co Ltd filed Critical Guizhou Construction Engineering Group Second Construction Engineering Co Ltd
Priority to CN201910416166.4A priority Critical patent/CN110043029A/en
Publication of CN110043029A publication Critical patent/CN110043029A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/02Details
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/08Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces
    • G01N3/10Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces generated by pneumatic or hydraulic pressure
    • G01N3/12Pressure testing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to technical field of building construction, and disclose the water tank pre-pressing process of huge laced beam steel pipe full framing, including following operating procedure: full framing is set up → selecting precompressed region → determine prefabricating load → water tank set up → monitoring point arrangement → monitoring instrument setting → water storage hierarchical loading → precompressed monitoring → settlement stability → draining unloads → adjusts rack template → next procedure.By using the standing simple device in building site, water tank is voluntarily configured, flexible and convenient, work efficiency is high, can shorten 1/3 or more than traditional preloading duration;Processing charges is low, it is easy to operate, it saves money, than 70 ~ 80% can be reduced investment outlay using prefabricated reinforced concrete block preloading method, 30 ~ 40% are reduced investment outlay than stacking sandbag precompressed, 20% ~ 30% can be reduced investment outlay compared with live bar material precompressed, this preloading method has construction equipment few, and construction efficiency is high, it gathers materials on the spot, the advantages that production is simple, environmental protection construction, and the actual forced status in simulation casting process is reasonable.

Description

The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing
Technical field
The present invention relates to technical field of building construction, the precompressed water tank of specially huge laced beam steel pipe full framing.
Background technique
In the huge laced beam concreting process of large-span cast-in-situ, the stability and deflection of bracket directly affect sky The safety and quality of web grider concreting.
The purpose of pre-pressing bracket is in order to which the safety of checking bracket and collection construction settlement data can be examined by precompressed Test the intensity, rigidity and safety of bracket, it is ensured that construction safety;The influence of bracket inelastic deformation can be eliminated, elasticity is grasped and becomes Graphic data keeps Application in Pre-camber reasonable, is conducive to laced beam rod piece alignment control, and the existing common selection of pre-pressing bracket load is prefabricated Reinforced concrete block precompressed, stacks the methods of sandbag precompressed or the bar material precompressed at scene at water bag precompressed, using pre-manufactured steel Reinforced concrete block precompressed needs that prefabricated reinforced concrete block precompressed is placed on bracket in batches with lifting machine, pre- in placement process Reinforced concrete block precompressed processed causes prefabricated reinforced concrete block precompressed discomfort to be evenly arranged in branch due to weight and area difference On frame, lead to the precompressed discontinuity of bracket, the phenomenon that local precompressed overload occurs, water bag precompressed also needs haulage equipment It is piled up on bracket, by the way of water bag precompressed, unbalance loading when be easy to causeing pre-pressing bracket, the precision after influencing test, Using the bar material precompressed at scene, need to expend a large amount of goods and materials and manpower, these methods need a large amount of people in summary Work, crane hoisting equipment, waste of material is serious, and the construction time is longer, not only time-consuming but also have a fixed limit to precompressed place System.
Summary of the invention
For the deficiency of above-mentioned background technique, the present invention provides the precompressed water tank of huge laced beam steel pipe full framing, Have and save resource, shorten construction period, advantage easy to operate, solves the problems, such as background technique proposition.
The invention provides the following technical scheme: the water tank pre-pressing process of huge laced beam steel pipe full framing, including it is following Operating procedure: full framing, which is set up, → selecting precompressed region → determines that prefabricating load → water tank sets up → monitoring point arrangement → monitoring Instrument setting → water storage hierarchical loading → precompressed monitoring → settlement stability → draining unloads → adjusts rack template → next procedure;
It has set up first and has designed and produced water tank on the steel pipe full framing of completion, directly carried out using live scaffold when setting up, Water tank main body is built using flitch, makes water tank bed die, in the production for carrying out two side templates;With perpendicular on the outside of two side template of water tank Secondary stupefied to flitch work, stupefied master is double steel pipe transversely strengthening, and paving waterproof cloth in cabinet, screw rod uses new waterproof Screw arbor with nut at both-ends (certainly Band waterproof blocks);It is tight that the closure such as rubber mat, marine glue are separately added at the perforation of screw rod both ends, cabinet uses wooden boards material, cabinet Monitoring point and placement monitoring instrument are arranged after completing as required, is directly poured water pressure to cabinet with water pump, every grade of load is applied It when adding into, monitors each monitoring point absolute altitude and calculates settling amount, after whole prefabricating loads apply, monitored at interval of 24 hours Once and each monitoring point absolute altitude is recorded, when pre-pressing bracket meets precompressed qualification, carries out bracket unloading, after unloading 6 hours, monitoring Each monitoring point absolute altitude, and the elastic deformation amount of each monitoring point of bracket is calculated, in loading procedure, pre-pressing bracket monitoring 36h cannot expire This regulation of foot should carry out checking computations and safety verification to bracket again, can extend according to the actual situation squeeze time or take other Processing method.
The precompressed water tank of huge laced beam steel pipe full framing, including steel pipe full framing, flitch, wooden boards, waterproof cloth, New waterproof Screw arbor with nut at both-ends, the flitch, wooden boards, waterproof cloth, new waterproof Screw arbor with nut at both-ends constitute water tank, and the flitch is located at The outermost of water tank, the wooden boards are located at the middle part of water tank, and the waterproof is laid in the most inner side of water tank, the flitch, wood Panel, waterproof cloth are connected by new waterproof Screw arbor with nut at both-ends, are equipped on the inside of water tank on the new waterproof Screw arbor with nut at both-ends Rubber ring, the two sides of the water tank, which are equipped with, throws bar, the monitoring dress being equipped with below water tank on the steel pipe full framing It sets.
Preferably, the water tank precompressed uses hierarchical loading, presses respectively by prefabricating load 0% → 60% → 80% → 100%, After the completion of every grade of load, first stops next stage load, and once monitored to bracket settling amount at interval of 12 hours, work as bracket When the 12 hours settling amount average value in top monitoring point is less than 2mm, next stage load can be carried out, every grade of load precompressed performs monitoring Data record can disposably drain unloading after precompressed detection data reaches design and the requirement in relation to standardizing.
Preferably, the water tank floor space is not less than the quasi- practical perspective plane of cast-in-place structural beam, and head height is by prefabricating load Conversion show that pre-pressing bracket loading range is no less than the practical perspective plane of cast-in-place concrete structure object.
Preferably, the pre-pressing bracket Load value is no less than the concrete structure dead load and template weight of bracket receiving The sum of 1.1 times, prepressing units internal loading intensity can be according to prefabricating load weight in its prepressing units divided by prepressing units face Product obtains.
Preferably, the settlement monitoring point arrangement of the bracket should be longitudinal every 1/4 span setting one along concrete structure Monitoring section, the monitoring point on each monitoring section should not be less than 5, and should be arranged symmetrically, bracket settlement monitoring point Ying Zhi It is respectively arranged on top of the trellis and bottom corresponding position.
The present invention have it is following the utility model has the advantages that
1, the precompressed water tank of the huge laced beam steel pipe full framing voluntarily configures water by using the standing simple device in building site Case, flexible and convenient, work efficiency is high, can shorten 1/3 or more than traditional preloading duration;Processing charges is low, easy to operate, section Province's expense, than 70 ~ 80% can be reduced investment outlay using prefabricated reinforced concrete block preloading method, 30 are reduced investment outlay than stacking sandbag precompressed ~ 40%, 20% ~ 30% can be reduced investment outlay compared with live bar material precompressed, this preloading method has construction equipment few, construction efficiency The advantages that height is gathered materials on the spot, and production is simple, environmental protection construction, and the actual forced status in simulation casting process is reasonable, it is preferable to solve The problem that support height of having determined is high, pre- pressure surface is long and narrow, meets the testing requirements of rack bearing power and deflection, shortens construction Duration saves expense.
2, the precompressed water tank of the huge laced beam steel pipe full framing examines the stability of bracket by precompressed, eliminates The inelastic deformation of bracket, and according to precompressed report in elastic deformation data, adjust bracket camber value, it is ensured that bracket exists Deflection in concreting process is in permissible range, and the present invention is in specific operating process, to construction material and work Skill does not have special requirement, and scene is set up, simple for production, and operation is easy, and applicability is preferable.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention;
Fig. 2 is use flow diagram of the present invention.
In figure: 1, steel pipe full framing;2, flitch;3, wooden boards;4, waterproof cloth;5, new waterproof Screw arbor with nut at both-ends;6, it throws Bar;7, monitoring device;8, rubber ring.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The water tank pre-pressing process of huge laced beam steel pipe full framing referring to FIG. 1-2, including following operating procedure: full Hall bracket set up → selecting precompressed region → determine prefabricating load → water tank set up → setting of monitoring point arrangement → monitoring instrument → Water storage hierarchical loading → precompressed monitoring → settlement stability → draining unloads → adjusts rack template → next procedure, props up using in original Precompressed water tank is made on frame, is preferably resolved the heap of high trestle ballast and stability under deck-siding limited circumstances and is asked Topic, the force simulation of entire support system is good, and pre-compaction process and actual forced status are close, and construction environmental protection is pollution-free, will not Surrounding enviroment are caused with big influence;
It has set up first and has designed and produced water tank on the steel pipe full framing of completion, it can be according to the practical projected area of longspan structure beam And upper part work structure type, load etc. lay water tank, have flexibility and adaptability, live foot is directly utilized when setting up Hand cradle carries out, and water tank main body is built using flitch, makes water tank bed die, in the production for carrying out two side templates;Two side form of water tank Stupefied with vertical flitch work time on the outside of plate, stupefied master is double steel pipe transversely strengthening, and paving waterproof cloth, screw rod use new waterproof pair in cabinet Draw screw rod (included waterproof blocks);It is tight that the closure such as rubber mat, marine glue are separately added at the perforation of screw rod both ends, cabinet uses wooden boards Material, cabinet arrange monitoring point and placement monitoring instrument as required after completing, directly poured water pressure to cabinet with water pump, water Pump lift is optionally about 1.15~1.20 times of water lift height, and water source, which can directly be derived from construction site collecting-tank also, may be derived from originally 75 tapping pipe of diameter is arranged in highest head position in water, and water level is more than automatic drainage when limiting height, and water tank both ends are set respectively It sets, pipeline can be connect with bottom end drainpipe, and when every grade of load applies completion, monitors each monitoring point absolute altitude and calculate settling amount, After whole prefabricating loads apply, at interval of monitoring primary within 24 hours and recording each monitoring point absolute altitude, when pre-pressing bracket meets When precompressed qualification, bracket unloading is carried out, adds unloading symmetrical, balanced in precompressed, is avoided that unbalance loading adversely affects bracket, unloads After carrying 6 hours, each monitoring point absolute altitude is monitored, and calculate the elastic deformation amount of each monitoring point of bracket, in loading procedure, pre-pressing bracket Monitoring 36h is not able to satisfy this regulation, checking computations and safety verification should be carried out to bracket again, when can extend precompressed according to the actual situation Between or take other processing methods.
The precompressed water tank of huge laced beam steel pipe full framing, including steel pipe full framing 1, to prevent bracket basis from meeting water After reduce bearing capacity, bracket basis should carry out waterproof, drainage works;Different types of bracket should according to engineering structure form, Load, support height, bracket basis situation etc. select representative region to carry out precompressed, determine precompressed range, flitch 2, wooden boards 3, waterproof cloth 4, new waterproof Screw arbor with nut at both-ends 5, water tank bed die, side form, the equal structural elements of new waterproof Screw arbor with nut at both-ends 5 It should be determined by calculating, bearing capacity, rigidity and stability requirement, flitch 2, wooden boards 3, waterproof cloth 4, new waterproof pair should be able to be met Screw rod 5 is drawn to constitute water tank, flitch 2 is located at the outermost of water tank, and wooden boards 3 are located at the middle part of water tank, and waterproof cloth 4 is located at water tank Most inner side, flitch 2, wooden boards 3, waterproof cloth 4 are connected by new waterproof Screw arbor with nut at both-ends 5, are installed on new waterproof Screw arbor with nut at both-ends 5 There is the rubber ring 8 being located on the inside of water tank, the two sides of water tank, which are equipped with, throws bar 6, is equipped with below water tank on steel pipe full framing 1 Monitoring device 7, monitoring device 7 can be used displacement meter and level synchronize be monitored, the content that monitoring device 7 monitors be plus Monitoring point absolute altitude before load, monitoring point absolute altitude after every grade of load, be loaded onto 100% after at interval of 24 hours monitoring point absolute altitudes, unloading Monitoring point absolute altitude after 6 hours determines head height (water weight takes 10KN/ cubic metres), water tank by the conversion to prefabricating load The height preferably specific head high 10CM~30CM of height, water tank floor space are pressed next not less than the practical perspective plane of cast-in-place concrete structure object It determines.
Wherein, water tank precompressed uses hierarchical loading, presses respectively by prefabricating load 0% → 60% → 80% → 100%, and every grade adds After the completion of load, first stop next stage load, and once monitored to bracket settling amount at interval of 12 hours, when cradle top is supervised When measuring point 12 hours settling amount average value is less than 2mm, next stage load can be carried out, every grade of load precompressed performs monitoring data note Record can disposably drain unloading, pre-pressing bracket Ying Zhi after precompressed detection data reaches design and the requirement in relation to standardizing It is carried out after the precompressed of frame basis is qualified.
Wherein, water tank floor space is not less than the quasi- practical perspective plane of cast-in-place structural beam, and head height is converted by prefabricating load Out, pre-pressing bracket loading range is no less than the practical perspective plane of cast-in-place concrete structure object.
Wherein, pre-pressing bracket Load value is no less than the concrete structure dead load and the sum of template weight of bracket receiving 1.1 times, prepressing units internal loading intensity can be obtained according to prefabricating load weight in its prepressing units divided by prepressing units area, Same prepressing units internal loading facilitates construction to load using uniformly distributed form.
Wherein, the settlement monitoring point arrangement of bracket should be longitudinal disconnected every 1/4 span setting one monitoring along concrete structure Face, the monitoring point on each monitoring section should not be less than 5, and should be arranged symmetrically, and bracket settlement monitoring point should be in cradle top It is respectively arranged on the corresponding position of bottom, monitoring precompressed qualification is that the initial 24 hours settling amount average value in each monitoring point is less than 1mm, each initial 72 hours settling amount average value in monitoring point are less than 5mm.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (6)

1. the water tank pre-pressing process of huge laced beam steel pipe full framing, it is characterised in that: including following operating procedure: Man Tangzhi Frame, which is set up, → selecting precompressed region → determines that prefabricating load → water tank sets up → monitoring point arrangement → monitoring instrument setting → water storage Hierarchical loading → precompressed monitoring → settlement stability → draining unloads → adjusts rack template → next procedure;
It has set up first and has designed and produced water tank on the steel pipe full framing of completion, directly carried out using live scaffold when setting up, Water tank main body is built using flitch, makes water tank bed die, in the production for carrying out two side templates;With perpendicular on the outside of two side template of water tank Secondary stupefied to flitch work, stupefied master is double steel pipe transversely strengthening, and paving waterproof cloth in cabinet, screw rod uses new waterproof Screw arbor with nut at both-ends (certainly Band waterproof blocks);It is tight that the closure such as rubber mat, marine glue are separately added at the perforation of screw rod both ends, cabinet uses wooden boards material, cabinet Monitoring point and placement monitoring instrument are arranged after completing as required, is directly poured water pressure to cabinet with water pump, every grade of load is applied It when adding into, monitors each monitoring point absolute altitude and calculates settling amount, after whole prefabricating loads apply, monitored at interval of 24 hours Once and each monitoring point absolute altitude is recorded, when pre-pressing bracket meets precompressed qualification, carries out bracket unloading, after unloading 6 hours, monitoring Each monitoring point absolute altitude, and the elastic deformation amount of each monitoring point of bracket is calculated, in loading procedure, pre-pressing bracket monitoring 36h cannot expire This regulation of foot should carry out checking computations and safety verification to bracket again, can extend according to the actual situation squeeze time or take other Processing method.
2. the precompressed water tank of huge laced beam steel pipe full framing, it is characterised in that: including steel pipe full framing (1), flitch (2), wooden boards (3), waterproof cloth (4), new waterproof Screw arbor with nut at both-ends (5), the flitch (2), wooden boards (3), waterproof cloth (4), New waterproof Screw arbor with nut at both-ends (5) constitutes water tank, and the flitch (2) is located at the outermost of water tank, and the wooden boards (3) are located at water tank Middle part, the waterproof cloth (4) is located at the most inner side of water tank, and the flitch (2), wooden boards (3), waterproof cloth (4) pass through novel Water-proof double-unit screw (5) connects, the rubber ring (8) being equipped on the inside of water tank on the new waterproof Screw arbor with nut at both-ends (5), institute The two sides for stating water tank, which are equipped with, throws bar (6), the monitoring device (7) being equipped with below water tank on the steel pipe full framing (1).
3. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described Water tank precompressed uses hierarchical loading, presses respectively by prefabricating load 0% → 60% → 80% → 100%, after the completion of every grade of load, first stops Only next stage loads, and is once monitored at interval of 12 hours to bracket settling amount, when cradle top monitoring point 12 is small When settling amount average value is less than 2mm, next stage load can be carried out, every grade of load precompressed performs monitoring data record, examines in precompressed Measured data can disposably drain unloading after reaching design and the requirement in relation to standardizing.
4. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described Water tank floor space is not less than the quasi- practical perspective plane of cast-in-place structural beam, and head height show that pre-pressing bracket adds by prefabricating load conversion Carry the practical perspective plane that range is no less than cast-in-place concrete structure object.
5. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described Pre-pressing bracket Load value is no less than 1.1 times of the concrete structure dead load that bracket is born and the sum of template weight, precompressed list First internal loading intensity can be obtained according to prefabricating load weight in its prepressing units divided by prepressing units area.
6. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described The settlement monitoring point arrangement of bracket should be longitudinal every 1/4 span setting, one monitoring section along concrete structure, and each monitoring is disconnected Monitoring point on face should not be less than 5, and should be arranged symmetrically, and bracket settlement monitoring point should be in cradle top and bottom corresponding position On be respectively arranged.
CN201910416166.4A 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing Pending CN110043029A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910416166.4A CN110043029A (en) 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910416166.4A CN110043029A (en) 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing

Publications (1)

Publication Number Publication Date
CN110043029A true CN110043029A (en) 2019-07-23

Family

ID=67282581

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910416166.4A Pending CN110043029A (en) 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing

Country Status (1)

Country Link
CN (1) CN110043029A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364759A (en) * 2020-03-18 2020-07-03 重庆交通建设(集团)有限责任公司 Prepressing device of full-scale support of giant open-web girder steel pipe and construction method thereof
CN111693366A (en) * 2020-05-27 2020-09-22 中冶建筑研究总院有限公司 Construction method for pre-loading structure in limited space
CN112030710A (en) * 2020-09-14 2020-12-04 武汉一冶建筑安装工程有限责任公司 Prepressing method and prepressing device for arch springing of arch ring bottom template
CN113931075A (en) * 2021-11-04 2022-01-14 中铁四局集团有限公司 Upper-pressing-down-hanging combined hydraulic-method prepressing and construction method for movable formwork
CN114427220A (en) * 2022-03-04 2022-05-03 中电建十一局工程有限公司 Porous arch bridge water bag prepressing construction method
CN114441307A (en) * 2021-12-29 2022-05-06 中铁二十局集团有限公司 Support pre-pressing method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3153291C2 (en) * 1980-10-10 1987-10-22 Peri-Werk Artur Schwoerer Gmbh & Co Kg, 7912 Weissenhorn, De Shuttering for concrete floor (ceiling) with joist
CN103225300A (en) * 2013-04-18 2013-07-31 贵州建工集团第二建筑工程有限责任公司 Process and equipment for reinforcing and strengthening concrete filling pile
WO2013166658A1 (en) * 2012-05-08 2013-11-14 Liu Chun Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork
CN103437549A (en) * 2013-09-16 2013-12-11 中铁四局集团建筑工程有限公司 Preloading structural part for high and large formwork support system
CN105155425A (en) * 2015-09-22 2015-12-16 深圳市市政工程总公司 Fluid analogue simulation preloading construction method of full framing
CN209976021U (en) * 2019-05-20 2020-01-21 贵州建工集团第二建筑工程有限责任公司 Prepressing water tank of giant open-web girder steel pipe full-scale support

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3153291C2 (en) * 1980-10-10 1987-10-22 Peri-Werk Artur Schwoerer Gmbh & Co Kg, 7912 Weissenhorn, De Shuttering for concrete floor (ceiling) with joist
WO2013166658A1 (en) * 2012-05-08 2013-11-14 Liu Chun Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork
CN103225300A (en) * 2013-04-18 2013-07-31 贵州建工集团第二建筑工程有限责任公司 Process and equipment for reinforcing and strengthening concrete filling pile
CN103437549A (en) * 2013-09-16 2013-12-11 中铁四局集团建筑工程有限公司 Preloading structural part for high and large formwork support system
CN105155425A (en) * 2015-09-22 2015-12-16 深圳市市政工程总公司 Fluid analogue simulation preloading construction method of full framing
CN209976021U (en) * 2019-05-20 2020-01-21 贵州建工集团第二建筑工程有限责任公司 Prepressing water tank of giant open-web girder steel pipe full-scale support

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364759A (en) * 2020-03-18 2020-07-03 重庆交通建设(集团)有限责任公司 Prepressing device of full-scale support of giant open-web girder steel pipe and construction method thereof
CN111693366A (en) * 2020-05-27 2020-09-22 中冶建筑研究总院有限公司 Construction method for pre-loading structure in limited space
CN112030710A (en) * 2020-09-14 2020-12-04 武汉一冶建筑安装工程有限责任公司 Prepressing method and prepressing device for arch springing of arch ring bottom template
CN113931075A (en) * 2021-11-04 2022-01-14 中铁四局集团有限公司 Upper-pressing-down-hanging combined hydraulic-method prepressing and construction method for movable formwork
CN114441307A (en) * 2021-12-29 2022-05-06 中铁二十局集团有限公司 Support pre-pressing method
CN114427220A (en) * 2022-03-04 2022-05-03 中电建十一局工程有限公司 Porous arch bridge water bag prepressing construction method

Similar Documents

Publication Publication Date Title
CN110043029A (en) The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing
CN201348570Y (en) Self-balanced static-load testing device for building structure
CN105297630A (en) Construction method for double-component steel tubes of main arch arcs
CN109779272A (en) A kind of high-altitude steel structure corridor construction method
CN109610834B (en) High-altitude construction method for multi-layer large-span heavy-load concrete structure
CN105155425A (en) Fluid analogue simulation preloading construction method of full framing
CN105369738A (en) Prepressing method of flushing type bridge rubber raft
CN105178604A (en) Construction method of assembly type superimposed floor slab
CN206581591U (en) A kind of inside wall formwork and roof plate template system
CN209976021U (en) Prepressing water tank of giant open-web girder steel pipe full-scale support
CN115369778A (en) Construction method of steel cross beam rotating body structure
CN212294351U (en) Water bag pre-pressing construction equipment for viaduct cast-in-place beam support system
CN109098314A (en) One kind being easily installed compact assembled lining
CN105756380A (en) Construction method of multi-layer large-span assembled integral space steel grid box-type structure factory building
CN101215968B (en) Inclined shaft sliding mode structure and inclined shaft pull-crawling construction process
CN111236632A (en) Construction method of heavy bracket and profile steel combined supporting system for super-thick top plate
CN206513016U (en) A kind of novel quick release frame
CN205296528U (en) String girder iron structure room lid is opened to firm type
CN205894732U (en) Reinforced structure of rowlock wall body
CN207862935U (en) A kind of steel construction plastering platform
CN2555292Y (en) Splicing water tank for detecting load of piling
CN105672135A (en) Simulation pre-pressing method for concrete box girder construction supporting frame
CN202153195U (en) Building balance test device
CN205046487U (en) Pre -compaction device of bath formula bridge rubber raft
CN220789448U (en) Bare concrete template for highway bridge pier stud

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination