CN109972624A - Subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction method - Google Patents

Subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction method Download PDF

Info

Publication number
CN109972624A
CN109972624A CN201910227484.6A CN201910227484A CN109972624A CN 109972624 A CN109972624 A CN 109972624A CN 201910227484 A CN201910227484 A CN 201910227484A CN 109972624 A CN109972624 A CN 109972624A
Authority
CN
China
Prior art keywords
layer
earthwork
foundation pit
campshed
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910227484.6A
Other languages
Chinese (zh)
Other versions
CN109972624B (en
Inventor
王明亮
郭建明
宋俊岭
王鑫
刘强
刘志永
侯克芳
梁肖然
孙朝硕
解咏平
付晓波
邰艳景
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Jike Engineering Project Management Co Ltd
Original Assignee
Hebei Jike Engineering Project Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Jike Engineering Project Management Co Ltd filed Critical Hebei Jike Engineering Project Management Co Ltd
Priority to CN201910227484.6A priority Critical patent/CN109972624B/en
Publication of CN109972624A publication Critical patent/CN109972624A/en
Application granted granted Critical
Publication of CN109972624B publication Critical patent/CN109972624B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention relates to subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction methods, comprising the following steps: excavates the number of plies and every layer of cutting depth according to enclosure structure of foundation pit of subway station crown beam, support drawing absolute altitude and the design of actual place absolute altitude relativeness;It excavates route and step divides quinquepartite, the first step excavates the hat above earthwork of bottom elevation, second step excavates campshed and punches part cubic metre of earth, third step is punched at campshed under crown beam using rope saw, 4th step punches the earthwork within the scope of facade foundation pit, and the 5th step punches lower part cubic metre of earth within the scope of facade foundation pit;The present invention transports ramp by increasing portal and slag-soil truck newly at the following campshed of foundation pit crown beam, earth excavation is carried out using common excavating machinery, reduce the investment of large excavator tool, the speed of construction is accelerated simultaneously, it reduces the duration and then saves cost, and the excavation working efficiency of the earthwork will not be limited because of the super large span of foundation pit, guarantee the progress of duration, convenient for the budget of duration.

Description

Subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction method
Technical field
The present invention relates to a kind of subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction methods, belong to Subway station open-cut field.
Background technique
Currently, urbanization is advanced by leaps and bounds, subway construction is such as emerged rapidly in large numbersBamboo shoots after a spring rain booming, subway work place periphery high building woods Vertical, heavy traffic, environment is increasingly complicated, requires controls such as construction noise, vibrations further stringent;It is carried on construction work at night in city to making an uproar Sound requires extremely harshness, a variety of large excavator tools, slag-soil truck is especially needed in earth excavation work progress, noise seriously surpasses Mark, increases subway foundation pit earth excavation difficulty.In addition, ordinary excavator tool can not be just since part foundation pit span, depth are big Earth excavation is often carried out, needs to excavate and to add in foundation pit many general using multiple large-sized long arm excavator tools above foundation pit Logical excavating machinery carries out the earthwork inside foundation pit to lead digging, further increases the difficulty of construction, in this regard, current this campshed+ There is also following defects for inner support huge ultradeep foundation pit digging mode:
(1) large-sized long arm excavator tool fuel consumption is big, purchase and lease expenses are high, it is mechanical to need to increase multiple auxiliary, increases Construction cost is added;
(2) the longer single excavated volume of large-sized long arm excavator tool arm is smaller, and the unit earth volume excavation used time is longer, and with The intensification of foundation depth, effect gradually decrease, and not can guarantee duration progress, influence duration budget.It can be seen that in the prior art Campshed+inner support huge ultradeep foundation pit earth excavation mode there are problems that construction cost is high and not can guarantee duration progress.
Summary of the invention
To solve the above-mentioned problems, the invention proposes a kind of subway station campshed and the inner support huge ultradeep foundation pit earthwork are fast Fast excavation construction method, to solve current huge ultradeep foundation pit earth excavation mode there are construction cost height and can not protect The problem of demonstrate,proving duration progress.
In order to solve the above-mentioned technical problem, present invention employs following technical solutions:
Subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction method, comprising the following steps:
Step 1, the drawing absolute altitude according to enclosure structure of foundation pit of subway station crown beam, support are opposite with actual place absolute altitude The number of plies and every layer of cutting depth are excavated in relationship and geological condition, design;
Route and excavation step are excavated in step 2, design, excavate route and step divides quinquepartite, the first step excavates crown beam The above first layer earthwork of bottom absolute altitude, second step excavation campshed punches in range and the earthwork of slope lane portion, third step row Stake punches, and the 4th step punches the second layer earthwork within the scope of facade foundation pit, under the 5th step punches within the scope of facade foundation pit Portion's third layer and the 4th layer of earthwork;
Step 3 excavates conventional excavating machinery and excavates the hat bottom elevation above section first layer earthwork, and the first layer earthwork is opened It digs successively to be excavated from the campshed place of punching to its opposite direction, increases bearing diagonal newly in crown beam, first of support and the range that punches at this time Synchronous construction;
Step 4 is completed when increasing bearing diagonal construction newly in crown beam, first of support and the range that punches, and excavates campshed and punch In range and after the completion of the earth excavation and slope protection of slope lane portion spray anchor, punched the row in range using rope saw cut , earth excavation and slope protection spray anchor are alternately constructed within the scope of slope lane;
Step 5 excavates first of support and lower part second branch using conventional excavating machinery after the completion of campshed punches The second layer earthwork between support, slag-soil truck haul volume outside slope lane, during excavation of earthwork, according to working face range Expansion is stepped up excavating machinery quantity and is excavated, and second layer earth excavation replaces construction with spraying anchor between piles at this time;
Step 6, after the completion of second layer earth excavation, the third layer earthwork, the 4th layer of earthwork that successively slope carries out lower part are opened Dig, the third layer earthwork and the 4th layer of earth excavation alternately, the third layer earthwork at this time, the 4th layer of earthwork, spraying anchor between piles and the Two support erection to replace with third road performs.
Further, in the step 1, same court absolute altitude is surveyed, the difference with hat bottom elevation is the first layer earthwork Cutting depth, the second layer, third layer earth excavation height between adjacent supports bottom distance, the 4th layer of earth excavation depth be Third road supports distance of the bottom away from foundation pit bottom.
Further, in the third step of the step 2, campshed is carried out using crane, rope saw and hand fit and is punched.
Further, in the step 5, when second layer earth excavation, digging, slag-soil truck are drawn into foundation pit with excavating machinery The haul volume outside slope lane.
Further, the step 6 punches most specifically, after the completion of second layer earth excavation from foundation pit with respect to campshed Inside carries out third layer earth excavation, and slag-soil truck is in the haul volume outside slope lane, earth excavation, support erection, spraying anchor between piles Intersection is constructed;Loop wheel machine, excavating machinery and hand fit's location and installation during support is set up;When foundation pit most inner side third layer Earth excavation to when meeting excavating machinery operating space, being put into the excavation that excavating machinery carries out the 4th layer of earthwork thereunder;The Four layers of earthwork are imported in third layer by excavating machinery, are packed into slag-soil truck by the excavating machinery of the excavation third layer earthwork and are transported outward, Loop wheel machine, excavating machinery and hand fit's location and installation during support is set up, circuit sequentially;The third layer earthwork at this time and the 4th layer Earth excavation is alternately;The third layer earthwork and the 4th layer of earthwork, support erection alternately to perform at spraying anchor between piles.
Further, each road support is bracing members.
Compared with the existing technology, the present invention has the following technical effect that
The present invention transports ramp by increasing portal and slag-soil truck newly at the following campshed of foundation pit crown beam, using conventional digging Pick is mechanical to carry out earth excavation, reduces the investment of large excavator tool, while accelerating the speed of construction, reduces the duration in turn Save artificial, machine cost, and the excavation working efficiency of the earthwork will not be limited because of the super large span of foundation pit, guarantee the duration into Degree, convenient for the budget of duration.
Detailed description of the invention
Fig. 1 is the plan view of the embodiment of the present invention;
Fig. 2 is the sectional view of the embodiment of the present invention.
Specific embodiment
Present invention is further described in detail by 1-2 with reference to the accompanying drawing, but not as a limitation of the invention.
Referring to Fig.1, Fig. 2, subway station campshed of the invention and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction party Method includes the following steps:
Step 1, the drawing absolute altitude according to enclosure structure of foundation pit of subway station crown beam, support are opposite with actual place absolute altitude The number of plies and every layer of cutting depth are excavated in relationship and geological condition, design;Same court absolute altitude is surveyed, the difference with hat bottom elevation For 10 cutting depth of the first layer earthwork, the height that the second layer earthwork 12, the third layer earthwork 13 are excavated is adjacent supports bottom spacing From the 4th layer of 14 cutting depth of the earthwork is 50 distance of the bottom away from foundation pit bottom of third road bracing members.
Route and excavation step are excavated in step 2, design, excavate route and step divides quinquepartite: the first step, excavate hat The above first layer earthwork 10 of bottom elevation;Second step, excavation campshed punches in coverage and the earthwork of slope lane portion 11;Third step, crane, rope saw and hand fit carry out campshed and punch 30;4th step, punch in excavation pit facade foundation pit range The interior second layer earthwork 12;5th step, the lower third layer earthwork 13 and the 4th layer of earthwork 14 within the scope of the facade foundation pit that punches.
Step 3 excavates the hat bottom elevation above section first layer earthwork 10 using excavating machinery 60, wherein comprising punching The earthwork of bottom elevation or more is preced at slope;Earth excavation be punch from campshed successively excavated to its opposite direction from 30, outer muck haulage Side, according in digging process in crown beam, first of bracing members 20 and the range that punches increase newly 80 face condition of bearing diagonal, timed delivery Fork construction.
Step 4, when the construction of bearing diagonal 80 completion newly-increased in crown beam, first of bracing members 20 and the range that punches and concrete After intensity reaches design requirement, carries out the earthwork 11 in coverage that punches of campshed in slope ramp and foundation pit and excavate;Earth excavation, Spraying anchor between piles and slope protection spray anchor 40 are alternately constructed, and the materials such as anchor cement to be painted, which reach, to carry out campshed after intensity requirement and punch cutting, Campshed punches 30 using loop wheel machine, rope saw, the artificial construction that cooperates.
Step 5 excavates first of bracing members 20 and the using conventional excavating machinery 60 when campshed punches after the completion of 30 The second layer earthwork 12 between two bracing members 50;When the second layer earthwork 12 is excavated, digging, slag are drawn into foundation pit with excavating machinery 60 The haul volume outside slope lane of navy barrow 70;During excavation of earthwork, excavator is stepped up according to the expansion of working face range 60 quantity of tool is excavated, and increases the outer haul volume of slag-soil truck 70, improves working efficiency, at this time earth excavation and spraying anchor between piles 40 Alternately construct.
Step 6 after the completion of second layer earth excavation, carries out third layer soil from foundation pit with respect to punch 30 most inner side of campshed Side is excavated, and slag-soil truck 70 is in the haul volume outside slope lane, earth excavation, second and the erection of third bracing members 50, spraying anchor between piles 40 intersections are constructed;Second and 50 erection process of third bracing members in loop wheel machine, excavating machinery 60 and hand fit's location and installation. When the foundation pit most inner side third layer earthwork 13, which is excavated to, meets 60 operating space of excavating machinery, it is put into excavating machinery 60 thereunder Carry out the excavation of the 4th layer of earthwork 14;The 4th layer of earthwork 14 is imported in third layer by excavating machinery 60, by the excavation third layer earthwork 13 excavating machinery is packed into slag-soil truck 70 and is transported outward, loop wheel machine, excavating machinery 60 and hand fit in 50 erection process of bracing members Location and installation circuits sequentially.The third layer earthwork at this time 13 and the 4th layer of earthwork 14 are excavated alternately, earth excavation 13,14, stake Between spray anchor 40, bracing members set up 50 alternately perform.
The present invention increases diagonal brace by increasing newly in the following campshed of foundation pit crown beam, ensure that the stabilization of foundation pit, increases newly at portal Portal effectively ensures that earth excavation efficiently promotes, while having excavating machinery cooperation in overlength bracing members erection process, improves Installation effectiveness effectively prevents casualties risk, improves support and sets up safety coefficient.
The present invention transports ramp by increasing portal and slag-soil truck newly at the following campshed of foundation pit crown beam, using conventional digging Pick is mechanical to carry out earth excavation, reduces the investment of large excavator tool, while accelerating the speed of construction, reduces the duration in turn Save artificial, machine cost, and the excavation working efficiency of the earthwork will not be limited because of the super large span of foundation pit, guarantee the duration into Degree, convenient for the budget of duration.
Above-described embodiment, which is intended merely to become apparent from, illustrates that technical solution of the present invention made enumerates, not to of the invention It limits, those skilled in the art are according to the common knowledge of this field to the accommodation of technical scheme also in this Shen Please be within protection scope, in short, above-described embodiment is only to enumerate, the protection scope of the application is with scope It is quasi-.

Claims (6)

1. subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction method, which is characterized in that including following Step:
Step 1, according to enclosure structure of foundation pit of subway station crown beam, the drawing absolute altitude of support and actual place absolute altitude relativeness And the number of plies and every layer of cutting depth are excavated in geological condition, design;
Route and excavation step are excavated in step 2, design, excavate route and step divides quinquepartite, the first step excavates crown beam bottom mark The high above first layer earthwork, second step excavation campshed punches in range and the earthwork of slope lane portion, third step campshed open Hole, the 4th step punch the second layer earthwork within the scope of facade foundation pit, and the 5th step punches lower part within the scope of facade foundation pit Three layers and the 4th layer of earthwork;
Step 3 excavates conventional excavating machinery and excavates the hat bottom elevation above section first layer earthwork, and first layer earth excavation is It is successively excavated from the campshed place of punching to its opposite direction, it is synchronous to increase bearing diagonal newly in crown beam, first of support and the range that punches at this time Construction;
Step 4 is completed when increasing bearing diagonal construction newly in crown beam, first of support and the range that punches, and excavates campshed and punch range After the completion of interior and slope lane portion earth excavation and slope protection spray anchor, is punched the campshed in range, put using rope saw cut Earth excavation and slope protection spray anchor are alternately constructed within the scope of the lane of slope;
Step 5 excavates first of support using conventional excavating machinery and supports it with lower part second after the completion of campshed punches Between the second layer earthwork, slag-soil truck haul volume outside slope lane, during excavation of earthwork, according to the expansion of working face range It is stepped up excavating machinery quantity to be excavated, second layer earth excavation replaces construction with spraying anchor between piles at this time;
Step 6, after the completion of second layer earth excavation, successively slope carries out the third layer earthwork of lower part, the 4th layer of earth excavation, The third layer earthwork and the 4th layer of earth excavation alternately, the third layer earthwork at this time, the 4th layer of earthwork, spraying anchor between piles and second with The support of third road, which is set up, alternately to be performed.
2. according to the method described in claim 1, it is characterized by: same court absolute altitude is surveyed, with crown beam in the step 1 The difference of bottom absolute altitude be first layer earth excavation depth, the second layer, third layer earth excavation height between adjacent supports bottom Distance, the 4th layer of earth excavation depth are that third road supports distance of the bottom away from foundation pit bottom.
3. according to the method described in claim 1, it is characterized by: in the third step of the step 2, using crane, rope saw and Hand fit carries out campshed and punches.
4. according to the method described in claim 1, it is characterized by: in the step 5, when second layer earth excavation, with excavation Machinery draws digging, slag-soil truck haul volume outside slope lane into foundation pit.
5. according to the method described in claim 1, it is characterized by: the step 6 is specifically, second layer earth excavation is completed Afterwards, third layer earth excavation is carried out from foundation pit with respect to the most inner side that campshed punches, slag-soil truck is in the haul volume outside slope lane, soil Side is excavated, support is set up, spraying anchor between piles intersection is constructed;Loop wheel machine, excavating machinery and hand fit are fixed during support is set up Position installation;When foundation pit most inner side third layer earth excavation is to when meeting excavating machinery operating space, it is put into excavator thereunder Tool carries out the excavation of the 4th layer of earthwork;The 4th layer of earthwork is imported in third layer by excavating machinery, by the digging of the excavation third layer earthwork The mechanical slag-soil truck that is packed into of pick is transported outward, and loop wheel machine, excavating machinery and hand fit's location and installation during support is set up successively are followed Ring;The third layer earthwork at this time and the 4th layer of earth excavation are alternately;The third layer earthwork and the 4th layer of earthwork, spraying anchor between piles, branch Support, which is set, alternately to be performed.
6. method according to any one of claims 1-5, it is characterised in that: each road support is bracing members.
CN201910227484.6A 2019-03-25 2019-03-25 Subway station row pile and inner support super-large and super-deep foundation pit earthwork rapid excavation construction method Active CN109972624B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910227484.6A CN109972624B (en) 2019-03-25 2019-03-25 Subway station row pile and inner support super-large and super-deep foundation pit earthwork rapid excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910227484.6A CN109972624B (en) 2019-03-25 2019-03-25 Subway station row pile and inner support super-large and super-deep foundation pit earthwork rapid excavation construction method

Publications (2)

Publication Number Publication Date
CN109972624A true CN109972624A (en) 2019-07-05
CN109972624B CN109972624B (en) 2021-04-30

Family

ID=67080387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910227484.6A Active CN109972624B (en) 2019-03-25 2019-03-25 Subway station row pile and inner support super-large and super-deep foundation pit earthwork rapid excavation construction method

Country Status (1)

Country Link
CN (1) CN109972624B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115125944A (en) * 2022-07-18 2022-09-30 中建八局第三建设有限公司 Deep foundation pit trenchless gate-type pile cutting and hole entering method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57193626A (en) * 1981-05-23 1982-11-29 Takenaka Komuten Co Ltd Excavation work for underground
CN101067300A (en) * 2007-06-01 2007-11-07 天津一建建筑工程有限公司 Deep foundation pits rampway structure
CN203716156U (en) * 2014-02-28 2014-07-16 中国建筑第四工程局有限公司 Pit-in-pit city gate hole type excavation construction structure in deep foundation pit

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57193626A (en) * 1981-05-23 1982-11-29 Takenaka Komuten Co Ltd Excavation work for underground
CN101067300A (en) * 2007-06-01 2007-11-07 天津一建建筑工程有限公司 Deep foundation pits rampway structure
CN203716156U (en) * 2014-02-28 2014-07-16 中国建筑第四工程局有限公司 Pit-in-pit city gate hole type excavation construction structure in deep foundation pit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋志成 等: "坑中坑开门式出土技术的研究及应用", 《城市建筑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115125944A (en) * 2022-07-18 2022-09-30 中建八局第三建设有限公司 Deep foundation pit trenchless gate-type pile cutting and hole entering method
CN115125944B (en) * 2022-07-18 2024-03-19 中建八局第三建设有限公司 Deep foundation pit trenchless gate-type pile cutting and hole entering method

Also Published As

Publication number Publication date
CN109972624B (en) 2021-04-30

Similar Documents

Publication Publication Date Title
CN101285385B (en) Undermining method for three-dimensional pipe-curtain
CN101666095B (en) Irregular foundation pit support and construction method
CN105298501A (en) Construction method for auxiliary air duct structure of underground excavation station
CN103061777B (en) Method for building urban underground tunnel shield cutter repairing space with preset reinforcing pile groups
CN105298507A (en) Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN106150508B (en) A kind of tunnel drilling operation method in karst strata
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN103410152B (en) A kind of construction method for long and narrow deep foundation pit earthwork digging
CN103590406A (en) Construction method for synchronously excavating ultra-large type deep foundation pits in partitioned mode
CN204098043U (en) After staying soil, excavation is in conjunction with inner support Retaining Structure with Double-row Piles
CN107190752A (en) A kind of design and construction method of the recyclable square-section Row Piles Supporting Structure of flexible compound antiseepage assembled
CN102758442A (en) Earth excavation method and open-cut tunnel construction method
CN104653188A (en) Method for arranging large-diameter shield receiving and originating well in underground-excavated air duct
CN107130611A (en) A kind of design and construction method of the recyclable circular section Row Piles Supporting Structure of flexible compound antiseepage assembled
CN112160755A (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN204825923U (en) Relay formula underground structure
CN104895079A (en) Reverse construction method for piling steel sheet piles
CN104863183A (en) Isolation damping pile structure used for construction of large cross-section tunnel closed-spaced building and construction method of isolation damping pile structure
CN103317603A (en) Method for applying wire saw to underground rock engineering through in-hole anchor guiders
CN109972624A (en) Subway station campshed and inner support huge ultradeep foundation pit earthwork Rapid Excavation construction method
CN209780906U (en) Tunnel hole-entering structure
CN110144903B (en) Construction method for foundation pit support in air defense cavity
CN114165268A (en) Grading coordination and reinforcement method for coal roadway tunneling broken surrounding rock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant