CN109967982A CN201910351448.0A CN201910351448A CN109967982A CN 109967982 A CN109967982 A CN 109967982A CN 201910351448 A CN201910351448 A CN 201910351448A CN 109967982 A CN109967982 A CN 109967982A
Authority
CN
China
Prior art keywords
thread
screw thread
nut
blank
circular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910351448.0A
Other languages
Chinese (zh)
Inventor
杨中桂
白洁
刘萍
丁永春
王家斌
崔建国
王海峰
李丹阳
赵令川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Hi Tech Co Ltd
Original Assignee
Zhengzhou Hi Tech Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Hi Tech Co Ltd filed Critical Zhengzhou Hi Tech Co Ltd
Priority to CN201910351448.0A priority Critical patent/CN109967982A/en
Publication of CN109967982A publication Critical patent/CN109967982A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass

Abstract

The invention discloses a kind of wind power generating set preparation methods of circular thread anchor component, and round steel bar and as desired scale or multiple length is selected to roll corresponding length as blank;Ultrasound+leakage field joint flaw detection is carried out to blank;Blank is heat-treated;Alignment processing is carried out to blank and removes surface scale;Vortex or magnetic powder inspection processing are carried out to blank;Circular thread is rolled at workpiece both ends by screw-rolling machine, obtains anchor bolt;Select round steel bar that sawing machine is used to carry out blanking to predetermined size as blank;Forging molding punching is carried out to blank;With lathe face work and inner hole, chamfering;With the threaded circular thread internal screw thread of screw tap;Workpiece is heat-treated with vacuum drying oven, obtains nut.Circular thread anchor bolt preparation method of the invention does not need removal material substantially, need to only be straightened removal surface scale, and the diameter tolerance control before anchor bolt rolled thread is in ± 0.3mm, and stock utilization is high, and production process is few, and production cost is low.

Description

A kind of preparation method of wind power generating set circular thread anchor component
Technical field
The invention belongs to wind-power electricity generation group pylons to be bolted, anchor bolts technical field, and in particular to a kind of wind-force hair The preparation method of motor group circular thread anchor component.
Background technique
Prestressing force blower foundation is the novel wind generator group base that the country such as the earlier 2000s U.S., Canada proposes Plinth technology, can effectively solve that traditional gravity type basis ring type foundation construction low efficiency, bending resistance resistance to capsizing be poor, application environment The problems such as adaptability for working condition is poor, hidden danger of quality is complicated difficult to control, has resistant slide, antidumping, environmental resistance excellent.It is high-intensitive Anchor bolt is the core component of prestressing force blower foundation, and prestressed anchor bolt assembly includes anchor bolt, nut etc., generallys use screw thread company It connects, existing threaded form of thread can be divided into triangle thread, saw-tooth thread, trapezoidal thread and pipe screw thread etc.." steel construction is used High-intensitive anchor bolts pair " the high-intensitive anchoring anchor bolts pair of M20-M64 steel construction is defined in (GB/T 33943-2017) Technical requirements and dimensions, all using the common metric thread of general service, i.e. angular thread." wind power generating set is high Strong threaded connection pair installation specification " M6-M64 bolt, spiral shell in wind-power electricity generation group are defined in (GB/T 33628-2017) The installation specification of the threaded connection pair of nail, stud and nut, also using the common metric thread of general service.State at present The precision that interior wind-powered electricity generation anchor bolt is threadedly engaged is 6g/6H, and there are three types of the process programs generallyd use: scheme one, blanking -- > thick school Directly -- > heat treatment -- > essence alignment -- > flaw detection -- > Vehicle Processing/grinding -- > rolled thread -- > anti-corrosion;Scheme two, blanking -- > thick Alignment -- > heat treatment -- > essence alignment -- > flaw detection -- > necking down -- > rolled thread -- > anti-corrosion;Scheme three, blanking -- > slightly alignment -- > annealing -- > drawing -- > heat treatment -- > essence alignment -- > flaw detection -- > Vehicle Processing/grinding -- > rolled thread -- > anti-corrosion.Using rice The screw thread pair being threadedly coupled is made, the diameter tolerance of anchor bolt material is generally required to be ± 0.1mm before rolled thread, and material is sharp It is low with rate.In actual use, screw thread once collides with, and will affect installing and using for normal threaded connection pair.The metric system Form of thread, the connection between bolts and nuts, anchor bolt and nut is not smooth enough, is easy to produce stress concentration phenomenon, in wind-force Under the inferior high-frequency reciprocating dynamic loads effect of generating set normal operating conditions, fracture easily occurs or loosens, once it loses It imitates, artificial repair and maintenance is difficult to find in time, and there are certain hidden dangers in project.In addition, domestic a part of anchor bolt producer uses intermediate frequency Quenching+intermediate frequency tempering heat treatment mode, the end effect of one side anchor bolt heat treatment cause waste of material, another aspect anchor bolt Surface hardness is higher, is unfavorable for later period rolling and processing.
Summary of the invention
To solve the above problems, the present invention provides a kind of preparation side of wind power generating set circular thread anchor component Method reduces difficulty of processing using continuous non-standard circle-arc screw-thread structure, reduces stress concentration phenomenon, and scene is adaptable, With excellent axial anti-pulling and fatigue behaviour.
The object of the present invention is achieved in the following manner:
A kind of preparation method of wind power generating set circular thread anchor component, the circular thread anchor component, including anchor bolt And nut, mutually matched inside and outside circular thread is provided on anchor screw bolt and nut,
The preparation method of the anchor bolt the following steps are included:
11) round steel bar and as desired scale or multiple length is selected to roll corresponding length as blank;
12) alignment processing, both ends chamfered edge are carried out to blank using straightener;
13) ultrasound+leakage field joint flaw detection is carried out to blank using defectoscope;
14) blank is heat-treated;
15) alignment processing is carried out to blank and removes surface scale;
16) vortex is carried out to blank using defectoscope or magnetic powder inspection is handled;
17) circular thread is rolled at workpiece both ends by screw-rolling machine, obtains anchor bolt;
18) preservative treatment is carried out to anchor bolt;
The preparation method of the nut the following steps are included:
21) select round steel bar that sawing machine is used to carry out blanking to predetermined size as blank;
22) forging molding punching is carried out to blank according to nut outer dimension;
23) lathe face work and inner hole, chamfering are used;
24) the threaded circular thread internal screw thread of screw tap is used;
25) workpiece is heat-treated with vacuum drying oven, obtains nut;
26) preservative treatment is carried out to nut.
In the range of ± 0.3mm, blank curvature is less than the diameter tolerance of blank described in step 13) and step 16 2mm/m, overall length curvature is less than 0.1%;Surface quality grades are that ultrasonic inspection is A grades, and magnetic leakage detection is 3 grades, and eddy current inspection is 6 grades, magnetic powder inspection is I grade.
Heat treatment described in step 14) includes quenching and tempering, carries out mid-frequency induction hardening using intermediate frequency furnace, uses Whole fiber well formula tempering furnace is tempered.
The inside and outside circular thread is the connection screw thread of face contact, and the continuous circular arc screw thread in anchor bolt is external screw thread, by upper Crest circular arc, straightway, lower tooth bottom circular arc, straightway are sequentially connected composition, the radius of upper tooth tip circle arc and lower tooth bottom circular arc Radius is equal, and straightway is tangent with upper tooth tip circle arc, lower tooth bottom circular arc respectively;Continuous circular arc screw thread on nut is internal screw thread, It is sequentially connected and is formed by upper half circular arc, tangential straightway, crest, crest is plane, and tangential straightway and upper half circular arc are tangent, spiral shell Female height is at least 7.5 times of screw pitch;Threaded connection pair is non-wide transverse tooth thickness, and external screw thread transverse tooth thickness is greater than internal screw thread transverse tooth thickness, outer spiral shell Line thread form angle is equal with internal screw thread thread form angle.
The stress sectional area of the circular thread anchor component is 1120mm2, screw pitch 6.35mm, external screw thread major diameter is 41.5mm, pitch diameter of external thread 39mm, external screw thread path are 36.5mm, a height of 2.5mm of external screw thread tooth, and upper radius of rounded crest is 1.5mm, lower radius of rounded root are 1.5mm, and internal screw thread path is 37.5mm, a height of 2.2mm of internal screw thread tooth;Nut diagonal distance For 74mm, nut opposite side distance is 65mm, and height of nut 48mm, external screw thread thread form angle and internal screw thread thread form angle are 60 °.
The stress sectional area of the circular thread anchor component is 1474mm2, screw pitch 8.5mm, external screw thread major diameter is 48.3mm, pitch diameter of external thread 45mm, external screw thread path are 41.7mm, a height of 3.3mm of external screw thread tooth, and upper radius of rounded crest is 2.0mm, lower radius of rounded root are 2.0mm, and internal screw thread path is 43.5mm, a height of 2.8mm of internal screw thread tooth;Nut diagonal distance For 80mm, nut opposite side distance is 70mm, and height of nut 64mm, external screw thread thread form angle and internal screw thread thread form angle are 60 °.
The method that preservative treatment is carried out to anchor bolt in step 18 are as follows: anchor pole overall length applies anti-corrosive grease, and anchor pole is located at wind-force hair Intermediate position inside motor group winds film cladding with PE, then PE pipe, PE pipe both ends are worn in the intermediate position of PE winding film cladding With the heat shrinking sleeve seal of tube, interim protective cap is not arranged by the both ends that PE winding film coats in anchor pole.
In step 26) to nut carry out preservative treatment method are as follows: nut use Dacroment or zincizing preservative treatment, it is resistance in Property the salt fog time be not less than 1000 hours.
The strength grade of the anchor bolt is 8.8 grades, and material is 42CrMoA or 35CrMoA, it is specified that plastic elongation intensity Rp0.2 >=660MPa, tensile strength Rm >=830MPa, elongation after fracture >=12%, anchor bolt hardness range 25-30HRC, anchor bolt surface and the heart The ballistic work average value KV of portion's difference of hardness control three samples in 2HRC, -40 DEG C2≥60J;Nut strength grade is 8 grades, material Matter is 42CrMoA or 35CrMoA, hardness 22-27HRC.
Compared with the existing technology, the beneficial effects of the present invention are:
(1) circular thread anchor bolt preparation method of the invention does not need removal material substantially, need to only be straightened removal surface oxidation Skin, the diameter tolerance control before anchor bolt rolled thread is in ± 0.3mm, and stock utilization is high, and production process is few, production cost It is low.
(2) anchor bolt of the invention uses the heat treatment process of mid frequency induction hardening and well furnace tempering, workpiece surface oxidation and decarbonization It is few, save raw material, working environment is good, pollution-free, low energy consumption;Tempering is not present end effect, anchor bolt end and intermediate position, Surface and center portion mechanical property are uniform, and the hardness of well furnace tempering is tempered low 2-3HRC than intermediate frequency, greatly reduce rolling and processing Difficulty reduces the loss of cylindrical die roll.
(3) circular thread auxiliary connection of the invention uses circular arc thread dental pattern, and internal screw thread and external screw thread are face contact, stress Uniformly, stress when can be effectively reduced screw thread carrying is concentrated, and anti-fatigue performance is good.Circular thread auxiliary connection of the invention is Non- wide transverse tooth thickness, axial fit clearance is big, and size is adaptable, is easy to in-site installation.Circular arc internal screw thread and externally threaded cooperation It is increasingly closer with the work of connected device, it is effectively prevented loosening.Circular thread uses big screw pitch circular thread, effectively Damage phenomenon caused by avoiding installation, the screw thread in use process from colliding with.Circular thread external screw thread crest of the invention is circular arc Shape, when rolled thread, metal plastic deformation region is small, and rolling power is small, and rolling and processing die life is high, greatly reduce rolling plus Work manufacture difficulty.
(4) anchor bolt overall length of the invention makes anti-corrosion grease using the flexible corrosion protection measure of PE winding film and preservation rouge It is reliably attached in anchor bolt, is easily achieved in engineering, not only solve the protection question in transhipment, transport and storage process, And corrosion-inhibiting coating is destroyed since prestressing force leads to the problem of surface elongation deformation when avoiding anchor bolt work, improve anti-corrosion Service life.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of circular thread auxiliary connection of the invention;
Fig. 2 is the cooperation schematic diagram of circular thread auxiliary connection in the present invention;
Fig. 3 is the externally threaded structural schematic diagram of circular thread in the present invention;
Fig. 4 is the structural schematic diagram of circular thread internal screw thread in the present invention;
Fig. 5 is the externally threaded scale diagrams of circular thread in the present invention;
Fig. 6 is the scale diagrams of circular thread internal screw thread in the present invention;
Fig. 7 is the scale diagrams of nut main view in the present invention;
Fig. 8 is the scale diagrams of nut side view in the present invention;
Fig. 9 is the mounting structure schematic diagram of anchor rod component of the present invention;
Figure 10 is anchor pole overall length anti-corrosion schematic diagram;
Figure 11 is the main view of head protector;
Figure 12 is the top view of head protector.
Wherein, 1 is bolt;2 be nut;3 be upper tooth tip circle arc;4 be straightway;5 be lower tooth bottom circular arc;6 be upper semi-circle Arc;7 be tangential straightway;8 be crest;9 be high-strength grout;10 be concrete;11 be PE pipe;12 be lower anchor slab;13 be PE Wind film;14 be interim protective cap;15 be nut II;16 be locking nut;17 be nut I;18 be head protector;19 be tower method It is blue;20 be thermal contraction casing tube;21 be gasket;L1 is threaded upper ends position;L2 is lower thread position;L3 is intermediate position.
Specific embodiment
A kind of preparation method of wind power generating set circular thread anchor component, the circular thread anchor component, including Mutually matched inside and outside circular thread is provided on anchor bolt 1 and nut 2, anchor bolt 1 and nut 2,
The preparation method of anchor bolt 1 the following steps are included:
11) round steel bar and as desired scale or multiple length is selected to roll corresponding length as blank;
12) alignment processing, both ends chamfered edge are carried out to blank using straightener;
13) ultrasound+leakage field joint flaw detection is carried out to blank using defectoscope;
14) blank is heat-treated;
15) alignment processing is carried out to blank and removes surface scale;
16) vortex is carried out to blank using defectoscope or magnetic powder inspection is handled;
17) circular thread is rolled at workpiece both ends by screw-rolling machine, obtains anchor bolt;
18) preservative treatment is carried out to anchor bolt;
The preparation method of nut 2 the following steps are included:
21) select round steel bar that sawing machine is used to carry out blanking to predetermined size as blank;
22) forging molding punching is carried out to blank according to nut outer dimension;
23) lathe face work and inner hole, chamfering are used;
24) the threaded circular thread internal screw thread of screw tap is used;
25) workpiece is heat-treated with vacuum drying oven, obtains nut;
26) preservative treatment is carried out to nut.
Quenching and tempering are carried out to nut workpiece using vacuum drying oven, eliminate the oxygen of workpiece surface in heating process Change, decarburization, can get the clean surface without metamorphic layer.
In the range of ± 0.3mm, blank curvature is less than the diameter tolerance of blank described in step 13) and step 16 2mm/m, overall length curvature can satisfy the requirement of circular thread rolling and processing less than 0.1%;Surface quality grades are ultrasonic inspection It is A grades, magnetic leakage detection is 3 grades, and eddy current inspection is 6 grades, and magnetic powder inspection is I grade.
Heat treatment described in step 14) includes quenching and tempering, carries out mid-frequency induction hardening, quenching using intermediate frequency furnace Temperature is 830 DEG C, and the type of cooling is water cooling, is tempered using Whole fiber well formula tempering furnace, and tempering temperature is 650 DEG C, heat preservation Time is 8h.Using mid-frequency induction hardening, induction heating speed is fast, since heat is being heated inside workpiece generation, rises Warm speed is fast, can improve low temperature impact properties with rapid refinement crystal grain, heating in medium frequency efficiency is up to 95%, and workpiece surface oxidation is de- Carbon is few, saves raw material, and working environment is good, pollution-free, low energy consumption.Using Whole fiber well formula tempering furnace, end is not present in tempering Effect, anchor bolt end and intermediate position, surface and center portion mechanical property are uniform, and hardness is tempered low 2~3HRC than intermediate frequency, significantly Rolling and processing difficulty is reduced, the loss of cylindrical die roll is reduced.Anchor bolt is placed in well formula tempering furnace with vertical state, on the one hand, anchor It deforms small after bolt heat treatment, ensure that the straightness of anchor bolt, for another aspect anchor bolt under thermal stress effect, anchor bolt can be slightly with stretching Long, stock utilization is high.
As shown in figures 1-8, inside and outside circular thread is the connection screw thread of face contact, and the continuous circular arc screw thread in anchor bolt 1 is outer Screw thread is sequentially connected and is formed by upper tooth tip circle arc 3, straightway 4, lower tooth bottom circular arc 5, straightway 4, the radius of upper tooth tip circle arc 3 Equal with the radius of lower tooth bottom circular arc 5, straightway 4 is tangent with upper tooth tip circle arc 3, lower tooth bottom circular arc 5 respectively;Company on nut 2 Continuous circular thread is internal screw thread, is sequentially connected and is formed by upper half circular arc 6, tangential straightway 7, crest 8, and crest 8 is plane, tangentially Straightway 7 and upper half circular arc 6 are tangent, and the height of nut 2 is at least 7.5 times of screw pitch;Threaded connection pair is non-wide transverse tooth thickness, outer spiral shell Line transverse tooth thickness is greater than internal screw thread transverse tooth thickness, and external screw thread thread form angle is equal with internal screw thread thread form angle.
In attached drawing, d is external screw thread major diameter, d2For pitch diameter of external thread, d3For external screw thread path, R1For upper radius of rounded crest, R2It is screw pitch, θ for lower radius of rounded root, P1For external screw thread thread form angle, H1For tooth height, D1For internal screw thread path, D2For internal screw thread Central diameter, D are internal screw thread major diameter, R3For upper half arc radius, H2For tooth height, θ2For internal screw thread thread form angle, s1For external screw thread transverse tooth thickness, s2 For internal screw thread transverse tooth thickness, m be height of nut, e is diagonal length, s is to edge lengths.
The stress sectional area of circular thread anchor component is 1120mm2, screw pitch 6.35mm, external screw thread major diameter is 41.5mm, pitch diameter of external thread 39mm, external screw thread path are 36.5mm, a height of 2.5mm of external screw thread tooth, and upper radius of rounded crest is 1.5mm, lower radius of rounded root are 1.5mm, and internal screw thread path is 37.5mm, a height of 2.2mm of internal screw thread tooth;Nut diagonal distance For 74mm, nut opposite side distance is 65mm, and height of nut 48mm, external screw thread thread form angle and internal screw thread thread form angle are 60 °.
The stress sectional area of circular thread anchor component is 1474mm2, screw pitch 8.5mm, external screw thread major diameter is 48.3mm, Pitch diameter of external thread is 45mm, and external screw thread path is 41.7mm, and a height of 3.3mm of external screw thread tooth, upper radius of rounded crest is 2.0mm, Lower radius of rounded root is 2.0mm, and internal screw thread path is 43.5mm, a height of 2.8mm of internal screw thread tooth;Nut diagonal distance is 80mm, nut opposite side distance is 70mm, and height of nut 64mm, external screw thread thread form angle and internal screw thread thread form angle are 60 °.
The method that preservative treatment is carried out to anchor bolt in step 18 are as follows: 1 overall length of anchor pole applies anti-corrosive grease, and anchor pole 1 is located at wind-force Intermediate position L3 inside generating set winds film 13 with PE and coats, then the intermediate position L3 that PE winding film 13 coats is worn PE pipe 11, PE pipe, 11 both ends are sealed with thermal contraction casing tube 15, and interim protective cap is not arranged by the both ends that PE winding film 13 coats in anchor pole 1 14.Anchor bolt overall length makes anti-corrosion grease be reliably attached to anchor using the flexible corrosion protection measure of PE winding film 13 and preservation rouge It on bolt 1, is easily achieved in engineering, not only solves the protection question in transhipment, transport and storage process, and avoid anchor bolt Corrosion-inhibiting coating is destroyed since prestressing force leads to the problem of surface elongation deformation when 1 work, improves anti-corrosion service life.
The method that preservative treatment is carried out to nut in step 26) are as follows: nut 2 uses Dacroment or zincizing preservative treatment, resistance to The neutral salt spray time is not less than 1000 hours.
The strength grade of the anchor bolt is 8.8 grades, and material is 42CrMoA or 35CrMoA, it is specified that plastic elongation intensity Rp0.2 >=660MPa, tensile strength Rm >=830MPa, elongation after fracture >=12%, anchor bolt 25~30HRC of hardness range, anchor bolt surface and The ballistic work average value KV of centre hardness difference control three samples in 2HRC, -40 DEG C2≥60J;Nut strength grade is 8 grades, Material is 42CrMoA or 35CrMoA, and hardness is 22~27HRC.
The anti-corrosion method of anchor component, anchor component include anchor bolt 1, nut I 17, nut II 15, locking nut 16 and pad Piece 21 carries out preservative treatment to it respectively according to the following steps as shown in figs. 9-10:
1) preservative treatment of anchor bolt 1: 1 overall length of anchor bolt applies anti-corrosive grease, and anchor bolt 1 is located at the intermediate position inside wind power generating set L3 PE winds film 13 and coats, then the intermediate position L3 that PE winding film 13 coats is worn PE pipe 11, and 11 both ends of PE pipe are heat-shrinked Casing 20 seals, and interim protective cap 14 is not arranged by the both ends that PE winding film 13 coats in anchor bolt 1;
2) preservative treatment of nut I 17, nut II 15, locking nut 16 and gasket 21: nut I 17 and gasket 21 use Dacroment Surface treatment, nut II 15 and locking nut 16 are using nigrescence or Dacroment surface treatment;
3) it installs: after anchor rod component is transported to scene, the interim protective cap 14 at 1 both ends of anchor bolt being removed, anchor bolt 1 successively penetrates down Anchor slab 12, locking nut 16 and tower drum flange 19 form anchor pole cage, and nut I 17 and nut II 15,10 He of casting concrete are put in rotation High-strength grout 9;
4) after anchor bolt tensioning, in the clearance portion for being threadedly engaged position, anchor bolt 1 and tower drum flange 19 of anchor bolt 1 and nut I 17 Position is sealed with waterproof silicone grease or anti-corrosive grease, exposed anchor bolt 1, nut I 17 and gasket at the top of foundation of wind-driven generator unit Place head protector 18 in 21 outsides.
Anti-corrosive grease is unbonded prestressing tendon anti-corrosion grease, the regulation of Ying Fuhe JG/T 430, with spray, dipping Or the mode that automatic oiling device is smeared coats, coating layer thickness is 0.1~0.3mm.Anti-corrosive grease is added by lube base oil Lubricating oil made from various antirust agent or lubricating grease, the rust-proof coating as metal part surface, rust-proof mechanism are antirust Agent is dissolved in grease at micella, forms firm adsorbed film in metal surface, the hydrocarbon chain in anti-corrosive grease component, then with antirust agent Mixing polymolecular layer is formed, to prevent the erosion of water and oxygen, prevents metal surface from getting rusty, is coated with anti-corrosion grease, outsourcing PE film With the anchor pole of protective sheath, there is dual anti-corrosion ability.
It is transportation and packing stretch wrap film, the regulation of Ying Fuhe BB/T 0024, with wrapping machine to anchor pole that PE, which winds film 13, The 1 intermediate position L3 for being located inside wind power generating set carries out the cladding of PE winding film 13, and the thickness of PE winding film 13 is not less than 25μm.Stretch wrap film is at normal temperature, to stretch generated deformation by force using mechanical tensioning devices or by hand by film and answer Cargo is wrapped a kind of packaging film for being readily transported, storing by power.Stretch package saves raw material than shrink-wraping, and does not need Thermal shrinking package machine saves the energy.Stretch wrap film has tensile property good, and tear-resistant, penetration-resistant is strong, and transparency is high, from The features such as sticky good and relaxation shrinkage is high, and packaging is close, will not be loose, effectively can be wrapped in anchor rod body for anti-corrosion grease On.
PE is wound film 13 and is coated using the method for spiral winding, facilitates large-scale industrial production, special winding can be used and set Standby to be rapidly completed, cladding degree of overlapping is not less than 50%, it can be ensured that anti-corrosion grease reliably wraps up.
The material of PE pipe 11 is polyvinyl resin, and the gap between PE pipe 11 and anchor bolt 1 is not less than 1mm, 11 wall thickness of PE pipe It not less than 3mm, can effectively completely cut off concrete, not influence anchor pole later period stretching construction.
The material of interim protective cap 14 is polyvinyl resin, and wall thickness is not less than 0.5mm, interim protective cap rain-proof, it is moisture-proof, Mould proof, antirust avoids 1 both ends screw thread colliding in transhipment, transport, installation, work progress of anchor bolt, can also prevent grease from expanding It dissipates, plays interim antisepsis.
The coating layer thickness of Dacroment preservative treatment is not less than 8 μm, and coating is zinc-chromium coating, is added simultaneously based on metal zinc metal sheet Enter the high dispersive water soluble paint that aluminium flake, chromic acid, deionized water make solvent, coating is stained on metallic matrix, follows by fully closed road Ring coating baking, forms very thin coating, Dacromet/steel successfully resists the erosion of chloride ion, and the resistance to neutral salt spray time is reachable 500 to 1000 hours.
The outer layer of thermal contraction casing tube 20 is cross-linked polyethylene resin, and internal layer is hot melt property adhesive, and wall thickness is not less than 0.5mm, temperature resistant range are -55 DEG C~105 DEG C, 115 DEG C of shrinkage temperature or more, have good cementability to metal and PE pipe Can, it can be to avoid the corrosion at 1 both ends of anchor pole and 9 contact site of concrete 10 and high-strength grout.
Waterproof silicone grease is made of organosiloxane thickening high-purity inorganic thickening agent, is translucent body of paste, temperature resistant range It is -60 DEG C~280 DEG C, there is good waterproof seal, high and low temperature, inoxidizability, it may have good mechanical stability And colloid stability, the disassembly and installation in later period is not influenced.
As depicted in figs. 11-12,18 top of head protector is tubular construction, and lower part is hexagonal tubular construction, and bottom turns up to be formed Skirt border structure, hexagonal tubular construction inner wall are adjacent to nut outer wall, and material is methyl vinyl silicone rubber, and wall thickness is not less than 2mm, adopts With injection molded, temperature resistant range is -50 DEG C~250 DEG C.Silicon rubber has good high temperature resistant, low temperature, oil resistance, is able to satisfy Outdoor use condition severe all the year round.
Major Diam is 42mm other than below, and for length is the anchor component of 3200mm, preparation process is as follows:
1. 42CrMoA round steel bar and as desired scale or multiple length is selected to roll corresponding length as blank, charge length one As be 3190mm, diameter specifications be 39 ± 0.3mm of Φ, blank curvature be less than 2mm/m, overall length curvature is less than 0.1%;
2. carrying out alignment processing to blank using straightener, surface scale, both ends chamfered edge are removed, chamfer dimesion is C3~C5;
3. carrying out ultrasound+leakage field joint flaw detection to blank using defectoscope, ultrasonic inspection is for detecting material internal defect, leakage field For detecting System of Detecting Surface Defects For Material, surface quality grades are that ultrasonic inspection is A grades for flaw detection, and magnetic leakage detection is 3 grades, and eddy current inspection is 6 grades, magnetic powder inspection is I grades;
4. being heat-treated to blank, mid-frequency induction hardening is carried out using intermediate frequency furnace, hardening heat is 830 DEG C, cooling side Formula is water cooling, is tempered using Whole fiber well formula tempering furnace, and tempering temperature is 65 DEG C, soaking time 8h, hard after heat treatment Degree is 25~30HRC;
5. carrying out alignment processing to blank and removing surface scale, the bolt diameter specification after alignment is 39 ± 0.3mm of Φ, base Expect that curvature is less than 2mm/m, overall length curvature is less than 0.1%;
6. carrying out vortex using defectoscope to blank or magnetic powder inspection being handled, vortex or magnetic powder inspection are used to detection material surface Defect, eddy current inspection are 6 grades, and magnetic powder inspection is I grades;
7. rolling circular thread, screw pitch 6.35mm, a height of 2.5mm of tooth at workpiece both ends by screw-rolling machine, Major Diam is 41.5mm, thread form angle θ1It is 60 °, rolling, which finishes rock-bolt length, becomes 3200mm;
8. carrying out preservative treatment to anchor bolt, anchor bolt 1 uses following preservative treatment measure, and 1 overall length of anchor bolt applies anti-corrosive grease, middle part PE pipe, the PE pipe both ends heat shrinking sleeve seal of tube, threaded upper ends position L1, lower thread are worn again with PE winding film cladding at the L3 of position Interim protective cap 14 is set at the L2 of position.
The preparation method of circular thread nut 2 the following steps are included:
1. selection 35CrMoA round steel bar carries out blanking to predetermined size with sawing machine, diameter specifications are Φ 45mm, and length is 102mm;
2. blank is selected to carry out forging molding punching according to nut outer dimension, nut diagonal distance e is 74mm, opposite side distance s For 65mm, height dimension 52mm, blanking inner hole is Φ 36mm;
3. three-jaw clamps, make height of nut size m 48mm, interior hole Φ 37.5mm, chamfering C2 with lathe face work;
4. with the threaded circular thread internal screw thread of screw tap, diameter of thread be Φ 37.5mm, pitch P 6.35mm, a height of 2.2mm of tooth, Thread form angle θ2It is 60 °;
5. being heat-treated with vacuum drying oven to workpiece, hardening heat is 830 DEG C, and the type of cooling is water cooling, tempering temperature 670 DEG C, soaking time 4h, hardness is 22~27HRC after heat treatment;
6. carrying out preservative treatment to nut 2, using Dacroment or zincizing preservative treatment, coating layer thickness is not less than 8 μm.
The structural parameters comparison of circular thread and regular screw threads of the invention is as shown in table 1, identical Major Diam specification Threaded connection pair, the two stress area and bearing capacity are almost the same, and circular thread is somewhat larger, since circular thread uses big spiral shell Away from non-wide transverse tooth thickness, be not only effectively reduced stress concentration, improve fatigue behaviour, axial fit clearance is big, processing and manufacturing It more easily realizes, processing cost is lower, and advantage is fairly obvious in the big specification threaded connection pair application of M36 or more specification.? With the screw thread bearing capacity of same specification it is comparable under the premise of, two kinds of helicitic texture parameters, through test and verifying repeatedly, load Optimum state can be belonged to processing performance.
What has been described above is only a preferred embodiment of the present invention, it is noted that for those skilled in the art, Without depart from that overall concept of the invention, several changes and improvements can also be made, these also should be considered as of the invention Protection scope.

Claims (9)

1. a kind of wind power generating set preparation method of circular thread anchor component, the circular thread anchor component, including anchor Mutually matched inside and outside circular thread is provided on bolt (1) and nut (2), anchor bolt (1) and nut (2), it is characterised in that:
The preparation method of the anchor bolt (1) the following steps are included:
11) round steel bar and as desired scale or multiple length is selected to roll corresponding length as blank;
12) alignment processing, both ends chamfered edge are carried out to blank using straightener;
13) ultrasound+leakage field joint flaw detection is carried out to blank using defectoscope;
14) blank is heat-treated;
15) alignment processing is carried out to blank and removes surface scale;
16) vortex is carried out to blank using defectoscope or magnetic powder inspection is handled;
17) circular thread is rolled at workpiece both ends by screw-rolling machine, obtains anchor bolt;
18) preservative treatment is carried out to anchor bolt;
The preparation method of the nut (2) the following steps are included:
21) select round steel bar that sawing machine is used to carry out blanking to predetermined size as blank;
22) forging molding punching is carried out to blank according to nut outer dimension;
23) lathe face work and inner hole, chamfering are used;
24) the threaded circular thread internal screw thread of screw tap is used;
25) workpiece is heat-treated with vacuum drying oven, obtains nut;
26) preservative treatment is carried out to nut.
2. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: For the diameter tolerance of blank described in step 13) and step 16 in the range of ± 0.3mm, blank curvature is less than 2mm/m, always Long curvature is less than 0.1%;Surface quality grades are that ultrasonic inspection is A grades, and magnetic leakage detection is 3 grades, and eddy current inspection is 6 grades, magnetic powder Flaw detection is I grade.
3. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: Heat treatment described in step 14) includes quenching and tempering, mid-frequency induction hardening is carried out using intermediate frequency furnace, using Whole fiber well Formula tempering furnace is tempered.
4. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: The inside and outside circular thread is the connection screw thread of face contact, and the continuous circular arc screw thread in anchor bolt (1) is external screw thread, by upper tooth tip circle Arc (3), straightway (4), lower tooth bottom circular arc (5), straightway (4) are sequentially connected composition, the radius and lower tooth of upper tooth tip circle arc (3) The radius of bottom circular arc (5) is equal, and straightway (4) is tangent with upper tooth tip circle arc (3), lower tooth bottom circular arc (5) respectively;On nut (2) Continuous circular arc screw thread be internal screw thread, be sequentially connected and formed by upper half circular arc (6), tangential straightway (7), crest (8), crest It (8) is plane, tangential straightway (7) and upper half circular arc (6) are tangent, and the height of nut (2) is at least 7.5 times of screw pitch;Screw thread connects Connecing secondary is non-wide transverse tooth thickness, and external screw thread transverse tooth thickness is greater than internal screw thread transverse tooth thickness, and external screw thread thread form angle is equal with internal screw thread thread form angle.
5. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: The stress sectional area of the circular thread anchor component is 1120mm2, screw pitch 6.35mm, external screw thread major diameter is 41.5mm, outside The pitch diameter of thread is 39mm, and external screw thread path is 36.5mm, and a height of 2.5mm of external screw thread tooth, upper radius of rounded crest is 1.5mm, under Radius of rounded root is 1.5mm, and internal screw thread path is 37.5mm, a height of 2.2mm of internal screw thread tooth;Nut diagonal distance is 74mm, Nut opposite side distance is 65mm, and height of nut 48mm, external screw thread thread form angle and internal screw thread thread form angle are 60 °.
6. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: The stress sectional area of the circular thread anchor component is 1474mm2, screw pitch 8.5mm, external screw thread major diameter is 48.3mm, outer spiral shell Line central diameter is 45mm, and external screw thread path is 41.7mm, and a height of 3.3mm of external screw thread tooth, upper radius of rounded crest is 2.0mm, lower tooth Bottom arc radius is 2.0mm, and internal screw thread path is 43.5mm, a height of 2.8mm of internal screw thread tooth;Nut diagonal distance is 80mm, spiral shell Female opposite side distance is 70mm, and height of nut 64mm, external screw thread thread form angle and internal screw thread thread form angle are 60 °.
7. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: The method that preservative treatment is carried out to anchor bolt in step 18 are as follows: anchor pole (1) overall length applies anti-corrosive grease, and anchor pole (1) is located at wind-power electricity generation Intermediate position (L3) inside unit winds film (13) cladding with PE, then the intermediate position (L3) of PE winding film (13) cladding is worn PE manages (11), and PE manages (11) both ends and sealed with thermal contraction casing tube (15), the both ends that anchor pole (1) is not coated by PE winding film (13) Interim protective cap (14) are set.
8. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: The method that preservative treatment is carried out to nut in step 26) are as follows: nut (2) uses Dacroment or zincizing preservative treatment, resistance to neutral salt The mist time is not less than 1000 hours.
9. the wind power generating set according to claim 1 preparation method of circular thread anchor component, it is characterised in that: The strength grade of the anchor bolt is 8.8 grades, and material is 42CrMoA or 35CrMoA, it is specified that plastic elongation intensity Rp0.2≥ 660MPa, tensile strength Rm >=830MPa, elongation after fracture >=12%, anchor bolt hardness range 25-30HRC, anchor bolt surface and center portion The ballistic work average value KV of difference of hardness control three samples in 2HRC, -40 DEG C2≥60J;Nut strength grade is 8 grades, material For 42CrMoA or 35CrMoA, hardness 22-27HRC.
CN201910351448.0A 2019-04-28 2019-04-28 A kind of preparation method of wind power generating set circular thread anchor component Pending CN109967982A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910351448.0A CN109967982A (en) 2019-04-28 2019-04-28 A kind of preparation method of wind power generating set circular thread anchor component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910351448.0A CN109967982A (en) 2019-04-28 2019-04-28 A kind of preparation method of wind power generating set circular thread anchor component

Publications (1)

Publication Number Publication Date
CN109967982A true CN109967982A (en) 2019-07-05

Family

ID=67086757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910351448.0A Pending CN109967982A (en) 2019-04-28 2019-04-28 A kind of preparation method of wind power generating set circular thread anchor component

Country Status (1)

Country Link
CN (1) CN109967982A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112427949A (en) * 2020-11-10 2021-03-02 青岛天能重工股份有限公司 Stock automated production assembly line
CN112681302A (en) * 2020-12-16 2021-04-20 深圳钜联锚杆技术有限公司 Anchor rod neck protection assembly, anchor rod and construction method
CN113420394A (en) * 2021-07-14 2021-09-21 中船重工海为郑州高科技有限公司 Design method of arc threaded connection pair
CN116877555A (en) * 2023-06-05 2023-10-13 中船海为高科技有限公司 Double-end stud for connecting wind turbine generator blade root and processing method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0428317A2 (en) * 1989-11-14 1991-05-22 Yugen Kaisha Shinjoseisakusho Method and apparatus for manufacturing an anchor bolt
CN103286246A (en) * 2013-05-16 2013-09-11 湖北德克特种异型高强螺栓有限公司 Method for manufacturing high-strength screws with fine threads for wind-driven generator foundations
CN104551561A (en) * 2014-12-11 2015-04-29 海盐三马标准件有限公司 Nut processing technology
CN106284345A (en) * 2016-10-18 2017-01-04 中国船舶重工集团公司第七�三研究所 A kind of prestressed anchor fastening system
CN106638657A (en) * 2016-10-18 2017-05-10 中国船舶重工集团公司第七�三研究所 Prestressed anchor rod assembly anti-corrosion method
CN107649837A (en) * 2017-09-25 2018-02-02 宁波埃索伦能源有限公司 A kind of processing method of wind-powered electricity generation ground anchor bolt

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0428317A2 (en) * 1989-11-14 1991-05-22 Yugen Kaisha Shinjoseisakusho Method and apparatus for manufacturing an anchor bolt
CN103286246A (en) * 2013-05-16 2013-09-11 湖北德克特种异型高强螺栓有限公司 Method for manufacturing high-strength screws with fine threads for wind-driven generator foundations
CN104551561A (en) * 2014-12-11 2015-04-29 海盐三马标准件有限公司 Nut processing technology
CN106284345A (en) * 2016-10-18 2017-01-04 中国船舶重工集团公司第七�三研究所 A kind of prestressed anchor fastening system
CN106638657A (en) * 2016-10-18 2017-05-10 中国船舶重工集团公司第七�三研究所 Prestressed anchor rod assembly anti-corrosion method
CN107649837A (en) * 2017-09-25 2018-02-02 宁波埃索伦能源有限公司 A kind of processing method of wind-powered electricity generation ground anchor bolt

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
中国石油天然气集团公司人事服务中心: "《管工》", 30 April 2007, 中国石油大学出版社 *
康庄等: "《深海工程中立管系统的设计分析》", 30 September 2018, 哈尔滨工程大学出版社 *
沪昆铁路客运专线湖南有限责任公司: "《客运专线铁路站前工程预留战后四电接口施工作业参考手册》", 31 January 2013, 中国铁道出版社 *
苑苓苓等: "《金工实习》", 31 July 2014, 东北师范大学出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112427949A (en) * 2020-11-10 2021-03-02 青岛天能重工股份有限公司 Stock automated production assembly line
CN112681302A (en) * 2020-12-16 2021-04-20 深圳钜联锚杆技术有限公司 Anchor rod neck protection assembly, anchor rod and construction method
CN113420394A (en) * 2021-07-14 2021-09-21 中船重工海为郑州高科技有限公司 Design method of arc threaded connection pair
CN113420394B (en) * 2021-07-14 2022-10-11 中船重工海为郑州高科技有限公司 Design method of arc threaded connection pair
CN116877555A (en) * 2023-06-05 2023-10-13 中船海为高科技有限公司 Double-end stud for connecting wind turbine generator blade root and processing method thereof

Similar Documents

Publication Publication Date Title
CN109967982A (en) A kind of preparation method of wind power generating set circular thread anchor component
CN103286246B (en) Method for manufacturing high-strength screws with fine threads for wind-driven generator foundations
CN106638657B (en) A kind of prestressed anchor bar assembly anti-corrosion method
CN102828915B (en) Host machine for marine anti-corrosion wind driven generator
CN202673954U (en) Anticorrosion anchoring bolt
CN102734297A (en) Anchoring bolt for offshore wind power foundation
CN103696448B (en) Anti-corrosion structure and anti-corrosion method of fan foundation prestressed component and fan foundation
CN213062422U (en) Anticorrosive type wind-powered electricity generation crab-bolt
CN203603175U (en) Anti-corrosion structure of wind power generator foundation prestress component and wind power generator foundation
CN202732239U (en) Wind generating set tower in ocean tidal zone
CN213478888U (en) Novel corrosion-resistant nut
CN211683486U (en) Anti-corrosion natural gas pipeline processing support
CN207021615U (en) A kind of anti-circular current hot-dip plastic steel pipe
CN212479860U (en) High-strength bolt
CN102678480B (en) Tower frame of wind turbine generator set
CN202789337U (en) Tower frame of offshore wind generating set
CN203362788U (en) Anti-corrosion structure of prestressed component and wind driven generator foundation
CN110872845A (en) Anti-corrosion anchor bolt piece, pre-stressed anchor bolt assembly and wind power supporting structure
CN107230955A (en) A kind of anti-circular current hot-dip plastic steel pipe
CN213478887U (en) Multiple anticorrosive structure of bolt fastener
CN211646448U (en) Anti-corrosion anchor bolt piece, pre-stressed anchor bolt assembly and wind power supporting structure
CN115787706B (en) Corrosion-resistant structure system for base of jacket fan of suction bucket and manufacturing method
CN216073939U (en) Iron tower angle steel cold and hot processing pool
CN110004971A (en) A kind of anti-corrosion method of foundation of wind-driven generator unit anchor rod component
CN215406559U (en) Building steel structure that oxidation resistance is strong

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination