CN109959162A CN201711402514.XA CN201711402514A CN109959162A CN 109959162 A CN109959162 A CN 109959162A CN 201711402514 A CN201711402514 A CN 201711402514A CN 109959162 A CN109959162 A CN 109959162A
Authority
CN
China
Prior art keywords
pipe
outlet pipe
heating
pipeline
combustion furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711402514.XA
Other languages
Chinese (zh)
Inventor
李芳芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711402514.XA priority Critical patent/CN109959162A/en
Publication of CN109959162A publication Critical patent/CN109959162A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H1/00Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters
    • F24H1/22Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating
    • F24H1/40Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating with water tube or tubes
    • F24H1/41Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating with water tube or tubes in serpentine form
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H9/00Details
    • F24H9/18Arrangement or mounting of grates or heating means
    • F24H9/1809Arrangement or mounting of grates or heating means for water heaters
    • F24H9/1832Arrangement or mounting of combustion heating means, e.g. grates or burners
    • F24H9/1836Arrangement or mounting of combustion heating means, e.g. grates or burners using fluid fuel

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Feeding And Controlling Fuel (AREA)
  • Spray-Type Burners (AREA)

Abstract

The invention discloses a kind of methanol wall-hung boiler and its installation methods, it is related to household appliance technical field, including sealing room, the sealing is indoor to be equipped with combustion chamber, heat exchanger is equipped in combustion chamber, the upper end of room is sealed equipped with the gas exchanges mouth with combustion chamber, coaxial smoke pipe is equipped in gas exchanges mouth, negative-pressure air fan is installed in coaxial smoke pipe, combustion furnace is equipped in combustion chamber, combustion furnace is equipped with nozzle, combustion furnace is equipped with ignition electrode, the lower end for hanging furnace shell is equipped with oil pump, the upper end of oil pump is connected to by pipeline one with the nozzle on combustion furnace, the lower end of oil pump is protruded by pipeline two in external methanol fuel holding vessel, the outer wall coenvelope of pipeline two has asbestos insulating layer, combustion furnace passes through pipeline one, oil pump and the pipeline two being connected to external methanol fuel holding vessel provide methanol fuel, to to the cold water Jing Guo heating tube into Row heating so that without natural gas area can also quickly, easily obtain hot water and heat source, it is easy to use.

Description

A kind of methanol wall-hung boiler and its installation method
Technical field
The present invention relates to household appliance technical fields, and in particular to a kind of methanol wall-hung boiler.
Background technique:
Wall-hung boiler is the abbreviation of burnt gas wall hanging furnace, and full name is " fuel wall hanging formula heating stove ".In some cold districts in the north, Important heating system is had become using the wall-hung boiler of gas-heating, more and more families are met life using wall-hung boiler and used The demand of water.
But for some more remote and backward in economy areas, combustion gas can not pass to these are more regional, cause People can not cause wall-hung boiler commonly used in the prior art can not be well at this in the winter of severe cold easily using hot water is arrived The area of sample is applied, and brings puzzlement to people's lives.
Summary of the invention
The purpose of the present invention is to provide a kind of methanol wall-hung boilers, caused by the prior art above-mentioned multinomial scarce to solve It falls into.
A kind of methanol wall-hung boiler, including sealing room, the sealing is indoor to be equipped with combustion chamber, is equipped with heat exchange in combustion chamber Device, the input end of the heating tube in heat exchanger be connected tos with external water inlet pipe, the outlet end of the heating tube in heat exchanger and External outlet pipe connection, the right end of the heat exchanger are equipped with heating water return pipe and heating outlet pipe, the end of heating water return pipe It holds and is connected to external expansion tank, heating outlet pipe is connected to external heating equipment, and the heating water return pipe is equipped with pressure Power valve, pressure gauge and water pump, are equipped with connecting pipe between the heating water return pipe and outlet pipe, connecting pipe is equipped with moisturizing Valve, the end of the heating outlet pipe are equipped with triple valve, and the water inlet pipe is equipped with flow control valve, is equipped in the outlet pipe Water flow sensor is additionally provided with flow stabilizing valve and filter on the outlet pipe, is all provided in the outlet pipe and heating outlet pipe There is water temperature sensor, the upper end of the sealing room is equipped with the gas exchanges mouth with combustion chamber, sets in the gas exchanges mouth There is coaxial smoke pipe, negative-pressure air fan is installed in coaxial smoke pipe, combustion furnace is equipped in the combustion chamber, combustion furnace is equipped with nozzle, The combustion furnace is equipped with ignition electrode, and combustion furnace is located at the underface of heat exchanger, and the lower end of the sealing room is equipped with oil pump, oil The upper end of pump is connected to by pipeline one with the nozzle on combustion furnace, and the lower end of oil pump protrudes into external methanol fuel by pipeline two In holding vessel, the outer wall coenvelope of the pipeline two has asbestos insulating layer.
Preferably, the heating tube in the heat exchanger is wavy or is helical form.
Preferably, strainer is equipped in the coaxial smoke pipe.
Preferably, the nozzle is equipped with multiple, and multiple nozzles are connected to the upper end of pipeline one.
A kind of installation method of methanol wall-hung boiler, including following installation steps:
Step 1: in a combustion chamber by heat exchanger and its combustion furnace installation, then sealing room is mounted on wall;
Step 2: water inlet pipe, outlet pipe, heating outlet pipe, heating water return pipe and pipeline two are successively installed;
Step 3: water temperature sensor is installed inside outlet pipe and heating outlet pipe, current stabilization is successively installed on outlet pipe Valve and filter;Then triple valve is installed in the end of heating outlet pipe;Connecting tube between heating water return pipe and outlet pipe Water compensating valve is installed on road;
One lower end of pipeline: being mounted on the upper end of oil pump by step 4, and one upper end of pipeline is mounted on the oil inlet on combustion furnace Mouthful;
Step 5: installing negative-pressure air fan in the combustion chamber, installs coaxial smoke pipe in the gas exchanges mouth of sealing room upper end.
The present invention has the advantages that combustion furnace is connected to by pipeline one, oil pump and with external methanol fuel holding vessel Pipeline two methanol fuel is provided, to be heated to the cold water Jing Guo heating tube so that without natural gas area can also it is quick, Hot water and heat source are easily obtained, it is easy to use.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
Wherein, 1- seals room, 2- gas exchanges mouth, the coaxial smoke pipe of 3-, 4- negative-pressure air fan, 5- heat exchanger, 6- heating Pipe, the combustion chamber 7-, 8- nozzle, 9- ignition electrode, 10- combustion furnace, 11- pipeline one, 12- oil pump, 13- pipeline two, 14- insulation stone Cotton layer, 15- water inlet pipe, 16- outlet pipe, 17- heating water return pipe, 18- heating outlet pipe, 19- expansion tank, 20- pressure valve, 21- pressure gauge, 22- water pump, 23- water compensating valve, 24- triple valve, 25- connecting pipe, 26- water temperature sensor, 27- water flow pass Sensor, 28- flow stabilizing valve, 29- filter, 30- flow control valve.
Specific embodiment
To be easy to understand the technical means, the creative features, the aims and the efficiencies achieved by the present invention, below with reference to Specific embodiment, the present invention is further explained.
As shown in Figure 1, a kind of methanol wall-hung boiler, including sealing room 1, the sealing room 1 is interior to be equipped with combustion chamber 7, combustion chamber 7 Interior to be equipped with heat exchanger 5, the input end of the heating tube 6 in heat exchanger 5 is connected to external water inlet pipe 15, in heat exchanger 5 The outlet end of heating tube 6 be connected to external outlet pipe 16, the right end of the heat exchanger 5 is equipped with heating water return pipe 17 and confession Warm outlet pipe 18, the end of heating water return pipe 17 are connected to external expansion tank 19, heating outlet pipe 18 and external heating Equipment connection, the heating water return pipe 17 are equipped with pressure valve 20, pressure gauge 21 and water pump 22, the heating water return pipe 17 with Connecting pipe 25 is equipped between outlet pipe 16, connecting pipe 25 is equipped with water compensating valve 23, and the end of the heating outlet pipe 18 is set There is triple valve 24, the water inlet pipe 15 is equipped with flow control valve 30, is equipped with water flow sensor 27 in the outlet pipe 16, It is additionally provided with flow stabilizing valve 28 and filter 29 on the outlet pipe 16, is equipped with water in the outlet pipe 16 and heating outlet pipe 18 Temperature sensor 26, the upper end of the sealing room 1 are equipped with the gas exchanges mouth 2 that is connected to combustion chamber 7, in the gas exchanges mouth 2 Equipped with coaxial smoke pipe 3, negative-pressure air fan 4 is installed in coaxial smoke pipe 3, in this way, external gas can be passed through to combustion chamber 7 It is interior, for combustion-supporting, while can be by 7 fuel combustion of combustion chamber when the gas discharge that generates, be equipped with burning in the combustion chamber 7 Furnace 10, combustion furnace 10 are equipped with nozzle 8, and the combustion furnace 10 is equipped with ignition electrode 9, the arteries and veins outside ignition electrode 9 and sealing room 1 Igniter (being not drawn into figure) connection is rushed, when igniting, presses the button on pulse igniter, pulse igniter work, ignition electrode 9 To light a fire to the fuel sprayed in nozzle 8, combustion furnace 10 is located at the underface of heat exchanger 5, described close for point discharge The lower end for sealing room 1 is equipped with oil pump 12, and the upper end of oil pump 12 is connected to by pipeline 1 with the nozzle 8 on combustion furnace 10, oil pump 12 Lower end protruded by pipeline 2 13 in external methanol fuel holding vessel, the outer wall coenvelope of the pipeline 2 13 has asbestos guarantor Warm layer 14, prevents in the winter of severe cold that pipeline 2 13 is freezing, plays a certain protective role.
In the present embodiment, the heating tube 6 in the heat exchanger 5 is wavy or is helical form.
In the present embodiment, strainer is equipped in the coaxial smoke pipe 2, negative-pressure air fan at work, prevents outside Gas under pressure from coaxial smoke pipe 2 enter combustion chamber 7 during by floaing in gas wad a quilt with cotton object bring burning into when 7 In.
In the present embodiment, the nozzle 8 is equipped with multiple, and multiple nozzles 8 are connected to the upper end of pipeline 1.
A kind of installation method of methanol wall-hung boiler, including following installation steps:
Step 1: heat exchanger 5 and its combustion furnace 10 are mounted in combustion chamber 7, and sealing room 1 is then mounted on wall On body;
Step 2: water inlet pipe 15, outlet pipe 16, heating outlet pipe 18, heating water return pipe 17 and pipeline two are successively installed 13;
Step 3: water temperature sensor 26 is installed inside outlet pipe 16 and heating outlet pipe 18, on outlet pipe 16 successively Flow stabilizing valve 28 and filter 29 are installed;Then triple valve 24 is installed in the end of heating outlet pipe 18;Heating water return pipe 17 with Water compensating valve 23 is installed in the connecting pipe between outlet pipe 16, is used for moisturizing;
One 11 lower end of pipeline: being mounted on the upper end of oil pump 12 by step 4, and one 11 upper end of pipeline is mounted on combustion furnace 10 On oil inlet on;
Step 5: installing negative-pressure air fan 4 in combustion chamber 7, and installation is coaxial in the gas exchanges mouth 2 of sealing 1 upper end of room Smoke pipe 3.
In the present invention, combustion furnace 10 is connected to by pipeline 1, oil pump 12 and with external methanol fuel holding vessel Pipeline 2 13 provide methanol fuel, to be heated to the cold water Jing Guo heating tube 6, so that can also be fast without natural gas area Speed easily obtains hot water and heat source, easy to use.
As known by the technical knowledge, the present invention can pass through the embodiment party of other essence without departing from its spirit or essential feature Case is realized.Therefore, embodiment disclosed above, in all respects are merely illustrative, not the only.Institute Have within the scope of the present invention or is included in the invention in the change being equal in the scope of the present invention.

Claims (5)

1. a kind of methanol wall-hung boiler, including sealing room (1), the sealing room (1) is interior to be equipped with combustion chamber (7), is set in combustion chamber (7) Have heat exchanger (5), the input end of the heating tube (6) in heat exchanger (5) is connected to external water inlet pipe (15), heat exchanger (5) outlet end of the heating tube (6) in is connected to external outlet pipe (16), and the right end of the heat exchanger (5) is equipped with heating Return pipe (17) and heating outlet pipe (18), the end of heating water return pipe (17) are connected to external expansion tank, heating water outlet Pipe (18) is connected to external heating equipment, which is characterized in that the heating water return pipe (17) is equipped with pressure valve (20), pressure Table (21) and water pump (22) are equipped with connecting pipe (25) between the heating water return pipe (17) and outlet pipe (16), connecting pipe (25) water compensating valve (23) are equipped with, the end of heating outlet pipe (18) is equipped with triple valve (24), on the water inlet pipe (15) Equipped with flow control valve (30), water flow sensor (27) are equipped in the outlet pipe (16), on the outlet pipe (16) also Equipped with flow stabilizing valve (28) and filter (29), water temperature sensor is equipped in the outlet pipe (16) and heating outlet pipe (18) (26), the upper end of sealing room (1) is equipped with the gas exchanges mouth (2) being connected to combustion chamber (7), the gas exchanges mouth (2) It is interior to be equipped with coaxial smoke pipe (3), it is equipped with negative-pressure air fan (4) in coaxial smoke pipe (3), combustion furnace is equipped in the combustion chamber (7) (10), combustion furnace (10) is equipped with nozzle (8), and the combustion furnace (8) is equipped with ignition electrode (9), and combustion furnace (10) is located at heat and hands over The lower end of the underface of parallel operation (5), sealing room (1) is equipped with oil pump (12), and the upper end of oil pump (12) passes through pipeline one (11) It is connected to the nozzle (8) on combustion furnace (10), the lower end of oil pump (12) protrudes into external methanol fuel storage by pipeline two (13) It deposits in tank, the outer wall coenvelope of the pipeline two (13) has asbestos insulating layer (14).
2. a kind of methanol wall-hung boiler according to claim 1, it is characterised in that: the heating tube in the heat exchanger (5) It (6) is wavy or be helical form.
3. a kind of methanol wall-hung boiler according to claim 1, it is characterised in that: be equipped in the coaxial smoke pipe (3) Strainer.
4. a kind of methanol wall-hung boiler according to claim 1, it is characterised in that: the nozzle (8) is equipped with multiple, multiple sprays Mouth (8) is connected to the upper end of pipeline one (11).
5. a kind of installation method based on methanol wall-hung boiler described in claim 1, which is characterized in that walked including following installation It is rapid:
Step 1: in a combustion chamber by heat exchanger and its combustion furnace installation, then sealing room (1) is mounted on wall;
Step 2: water inlet pipe (15), outlet pipe (16), heating outlet pipe (18), heating water return pipe (17) and pipe are successively installed Road two (13);
Step 3: water temperature sensor (26) are installed inside outlet pipe (16) and heating outlet pipe (18), on outlet pipe (16) Flow stabilizing valve (28) and filter (29) are successively installed;Then triple valve (24) are installed in the end of heating outlet pipe (18);It is supplying Water compensating valve (23) are installed in connecting pipe (25) between warm return pipe (17) and outlet pipe (16);
Pipeline one (11) lower end: being mounted on the upper end of oil pump (12) by step 4, and pipeline one (11) upper end is mounted on combustion furnace (10) oil inlet on;
Step 5: installing negative-pressure air fan (4) in combustion chamber (7), the installation in the gas exchanges mouth (2) of sealing room () upper end Coaxial smoke pipe (3).
CN201711402514.XA 2017-12-22 2017-12-22 A kind of methanol wall-hung boiler and its installation method Pending CN109959162A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711402514.XA CN109959162A (en) 2017-12-22 2017-12-22 A kind of methanol wall-hung boiler and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711402514.XA CN109959162A (en) 2017-12-22 2017-12-22 A kind of methanol wall-hung boiler and its installation method

Publications (1)

Publication Number Publication Date
CN109959162A true CN109959162A (en) 2019-07-02

Family

ID=67018995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711402514.XA Pending CN109959162A (en) 2017-12-22 2017-12-22 A kind of methanol wall-hung boiler and its installation method

Country Status (1)

Country Link
CN (1) CN109959162A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07109105A (en) * 1993-10-08 1995-04-25 Tokyo Gas Co Ltd Hydrogen-production apparatus
CN101561182A (en) * 2008-04-19 2009-10-21 广东万和集团有限公司 Fuel wall hanging stove with generating device
CN205481715U (en) * 2015-12-31 2016-08-17 朱新伟 Novel alcohol group hanging stove
CN106016690A (en) * 2016-07-06 2016-10-12 珠海格力电器股份有限公司 Fuel gas wall-hanging stove and control method thereof
EP3144275A1 (en) * 2015-09-21 2017-03-22 Air Products And Chemicals, Inc. Method of operating a catalytic stream-hydrocarbon reformer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07109105A (en) * 1993-10-08 1995-04-25 Tokyo Gas Co Ltd Hydrogen-production apparatus
CN101561182A (en) * 2008-04-19 2009-10-21 广东万和集团有限公司 Fuel wall hanging stove with generating device
EP3144275A1 (en) * 2015-09-21 2017-03-22 Air Products And Chemicals, Inc. Method of operating a catalytic stream-hydrocarbon reformer
CN205481715U (en) * 2015-12-31 2016-08-17 朱新伟 Novel alcohol group hanging stove
CN106016690A (en) * 2016-07-06 2016-10-12 珠海格力电器股份有限公司 Fuel gas wall-hanging stove and control method thereof

Similar Documents

Publication Publication Date Title
CN208566839U (en) A kind of methanol wall-hung boiler
CN207422353U (en) A kind of HVAC burnt gas wall hanging furnace branch thermostat
CN206073456U (en) A kind of horizontal burning oil fuel gas condensing boiler
CN207299528U (en) A kind of wall-hung boiler of condensed heat exchanger and the application condensed heat exchanger
CN201852197U (en) Single heating wall-mounted furnace
CN204214116U (en) Gas heater
CN208108491U (en) A kind of condensation type wall-mounted furnace apparatus
CN109959162A (en) A kind of methanol wall-hung boiler and its installation method
CN208349565U (en) A kind of water heater
CN209263337U (en) A kind of distribution energy-saving heater
CN209101568U (en) A kind of energy-saving, environmental protection boiler
CN2328940Y (en) Vertical steam water boiler
CN205174822U (en) Vacuum phase transition heating furnace
CN107764577A (en) A kind of hot performance test device of burner
CN204987439U (en) Warm dual -purpose boiler is bathed in full -automatic gas
CN205690669U (en) A kind of effective formula full water jacket numerical control boiler
CN208779700U (en) Direct combustion hotblast stove
CN220083342U (en) Anti-corrosion gas wall-mounted furnace
CN204757333U (en) Gas water heater
CN208765267U (en) A kind of heat-conducting oil furnace of high-energy utilization rate
CN207471816U (en) A kind of wall-hung boiler by water cooling burner
CN203190632U (en) Conduction oil scale-prevention pleuripotent furnace
CN206160470U (en) Hot blast stove device
CN201811195U (en) Energy-saving fuel gas steam boiler
CN209978386U (en) Gas water heater with flue gas heat exchange latent heat collection function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190702

WD01 Invention patent application deemed withdrawn after publication