CN109948239A CN201910199380.9A CN201910199380A CN109948239A CN 109948239 A CN109948239 A CN 109948239A CN 201910199380 A CN201910199380 A CN 201910199380A CN 109948239 A CN109948239 A CN 109948239A
Authority
CN
China
Prior art keywords
component
design document
bim
component design
professional user
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910199380.9A
Other languages
Chinese (zh)
Inventor
刘现
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mingsheng Drawin Technology Investment Co Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201910199380.9A priority Critical patent/CN109948239A/en
Publication of CN109948239A publication Critical patent/CN109948239A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of technological design progress exchange method, device, system and computer readable storage medium based on BIM, this method include the component design document for receiving user and uploading;Component design document is stored into default storage region;Downloading notice is sent to target professional user, so that target professional user is downloaded component design document.The application can store the design document after user uploads component design document, and send downloading notice in time to target professional user corresponding with the component design document, so that target professional user is in time downloaded the component design document.The application in use, can make subsequent professional staff understand component technological design progress in time, and obtain corresponding component design document in time, be conducive to the design efficiency for improving entire technological design.

Description

A kind of technological design progress exchange method, apparatus and system based on BIM
Technical field
The present embodiments relate to assembled architecture technical field, more particularly to it is a kind of based on the technological design of BIM into Spend exchange method, device, system and computer readable storage medium.
Background technique
BIM (Building Information Modeling, Building Information Model) is the items with construction-engineering project Based on relevant information data, it is established that three-dimensional buildings model, by possessed by digital information analogue simulation building Real information.
In assembled architecture design, the designer of most of subsequent profession needs with other being designed as of preamble profession Basis carries out the design work for oneself being responsible for designing part again after the completion of other designs, therefore there are the shared and works of data Coordination between work.
In the prior art, after the completion of the designer of preamble profession usually works be responsible for all industrial designs, The industrial design of completion can integrally be sent to the designer of subsequent profession, the staff of subsequent profession therefrom selecting and The related each technical papers of this profession carry out subsequent design operation.Since subsequent professional designer can not be in time to preamble The industrial design progress of profession is tracked, and causing will be corresponding with subsequent profession each even if the staff of preamble profession A technological design is completed, and follow-up work personnel can not get relevant design document in time, can only wait the work of preambles profession Make personnel for after the completion of all design documents, all technological designs could be sent to the staff of subsequent profession, thus Influence the design efficiency of entire technological design.
In consideration of it, how to provide the technological design progress exchange method based on BIM, the dress of a kind of solution above-mentioned technical problem It sets, system and computer readable storage medium become those skilled in the art's problem to be solved.
Summary of the invention
The purpose of the embodiment of the present invention is that provide a kind of technological design progress exchange method based on BIM, device, system and Computer readable storage medium, can make in use subsequent professional staff understand in time component technological design into Degree, and corresponding component design document is obtained in time, be conducive to the design efficiency for improving entire technological design.
In order to solve the above technical problems, the embodiment of the invention provides a kind of technological design progress interaction side based on BIM Method, comprising:
Receive the component design document that user uploads;
The component design document is stored into default storage region;
Downloading notice is sent to target professional user, so that the target professional user carries out the component design document Downloading.
Optionally, before transmission downloading notice to target professional user, further includes:
The file information corresponding with the component design document is obtained, the file information includes element type;
It is determined according to the element type pre-established with the mapping table of professional user corresponding with the element type Target professional user.
Optionally, further includes:
Record the upload number and download time of the component design document of the same element type;
Alarm prompt is issued when the download time and the upload number are inconsistent.
Optionally, further includes:
According to the element type of currently stored each component design document, the number of components currently submitted is counted.
The embodiment of the present invention provides a kind of technological design progress interactive device based on BIM accordingly, comprising:
Receiving module, for receiving the component design document of user's upload;
Memory module, for storing the component design document into default storage region;
Sending module, for sending downloading notice to target professional user, so that the target professional user is to the structure Part design document is downloaded.
Optionally, further includes:
Module is obtained, for obtaining the file information corresponding with the component design document, the file information includes structure Part type;
Matching module, for determined according to the mapping table of element type and professional user pre-established with it is described The corresponding target professional user of element type, and trigger the sending module.
Optionally, further includes:
Logging modle, for recording the upload number and download time of the component design document of the same element type;
Alarm module, for issuing alarm prompt when the download time and the upload number are inconsistent.
Optionally, further includes:
Statistical module is currently submitted for the element type according to currently stored each component design document, statistics The number of components.
The technological design progress interactive system based on BIM that the embodiment of the invention also provides a kind of, comprising:
Memory, for storing computer program;
Processor realizes that the technological design progress as described above based on BIM is handed over when for executing the computer program The step of mutual method.
The embodiment of the invention also provides a kind of computer readable storage medium, deposited on the computer readable storage medium Contain computer program, the computer program realized when being executed by processor it is as described above based on the technological design of BIM into The step of spending exchange method.
The embodiment of the invention provides a kind of technological design progress exchange method, device, system and computer based on BIM Readable storage medium storing program for executing, this method comprises: receiving the component design document that user uploads;Component design document is stored to default and is deposited In storage area domain;Downloading notice is sent to target professional user, so that target professional user is downloaded component design document.
As it can be seen that the application can store the design document after user uploads component design document, and send out in time Send downloading notice to target professional user corresponding with the component design document, so that target professional user is in time to the component Design document is downloaded.The application in use, can make subsequent professional staff understand component technique in time and set Meter progress, and corresponding component design document is obtained in time, be conducive to the design efficiency for improving entire technological design.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to institute in the prior art and embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of flow diagram of the technological design progress exchange method based on BIM provided in an embodiment of the present invention;
Fig. 2 is a kind of structural schematic diagram of the technological design progress interactive device based on BIM provided in an embodiment of the present invention.
Specific embodiment
The embodiment of the invention provides a kind of technological design progress exchange method, device, system and computer based on BIM Readable storage medium storing program for executing can make subsequent professional staff understand component technological design progress in time in use, and and When obtain corresponding component design document, be conducive to the design efficiency for improving entire technological design.
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Fig. 1 is please referred to, Fig. 1 is a kind of technological design progress exchange method based on BIM provided in an embodiment of the present invention Flow diagram.This method, comprising:
S110: the component design document that user uploads is received;
S120: component design document is stored into default storage region;
It should be noted that after the user of preamble profession designs one component design document of completion, it can be by the component Design document is uploaded, and system receives the component design document of user upload, and the component design document is stored to phase In the default storage region answered.
S130: downloading notice is sent to target professional user, so that target professional user carries out down component design document It carries.
It, can be with specifically, the component design document that uploads as the user that system receives preamble profession and after stored Downloading notice, downloading notice are sent to target professional user (namely the user for using the component design document in subsequent profession) In may include component design document the file information, notify that corresponding component design document has uploaded target professional user Success, can be downloaded, and after target professional user receives downloading notice, can enter system and be searched according to the file information And the component design document is downloaded, when target professional user will download with each component design document required for its profession After the completion, subsequent technological design can be entered, the preambles professional staff such as do not need and set all component design documents Subsequent professional is uniformly sent to after meter is good, subsequent professional component design document required for being screened out from it carries out Subsequent design.The staff (target professional user) of subsequent profession is capable of the work people of timely learning preamble profession in the application The design schedule of member, and component design document relevant to itself profession is obtained in time, be conducive to improve whole technological design Efficiency.
Further, before sending downloading notice to target professional user, further includes:
The file information corresponding with component design document is obtained, the file information includes element type;
Mapping table according to the element type and professional user that pre-establish determines mesh corresponding with element type Mark professional user.
Specifically, element type and the mapping table of professional user can be pre-established, also i.e. by the special of subsequent profession The industry user and its element type of required each component design document is mapped when carrying out technological design, wherein component Type may include component number information and component many types information, such as 1 counterpart member type A of professional user, component class Type B and element type C, 2 counterpart member type D of professional user, element type E and element type F, then when the component that user uploads When the element type of design document is A, then after being stored the component design document, downloading notice is sent to professional user 1, So that the professional user 1 downloads corresponding component design document after receiving downloading notice from system, can specifically pass through Component number information in element type searches component design document to be downloaded from system.
Further, this method further include:
Record the upload number and download time of the component design document of the same element type;
Alarm prompt is issued when download time and inconsistent upload number.
It should be noted that recording the component design document after the component design document of the same element type uploads Upload number, the component design document uploaded each time can store to last time upload component design document it is next , can also be using the last component design document uploaded of component design document covering that this is uploaded at storage location, this The component design document of upload is the component design document of latest edition.It is set in component of the target professional user to certain element type After counting file download, the current download time of the component design document of the element type is recorded, if the component of the element type The current download time of design document is not inconsistent with last time number, then after explanation is uploaded there are the component design document of new version, mesh Mark professional user is not downloaded the component design document of new version, carries out alarm prompt at this time, to remind target professional User downloads the component design document of new version, further increases the interaction of technological design progress, is more advantageous to subsequent profession Staff follows up to the work of the staff of preamble profession.
Further, this method further include:
According to the element type of currently stored each component design document, the number of components currently submitted is counted.
Specifically, can also be according to the element type of currently stored each component design document to current in the present embodiment The component total quantity submitted is counted, so that the staff of subsequent profession obtains the staff's of preamble profession in time Overall work progress.
As it can be seen that the application can store the design document after user uploads component design document, and send out in time Send downloading notice to target professional user corresponding with the component design document, so that target professional user is in time to the component Design document is downloaded.The application in use, can make subsequent professional staff understand component technique in time and set Meter progress, and corresponding component design document is obtained in time, be conducive to the design efficiency for improving entire technological design.
On the basis of the above embodiments, the embodiment of the present invention provide accordingly it is a kind of based on the technological design of BIM into Interactive device is spent, specifically referring to figure 2..The device includes:
Receiving module 21, for receiving the component design document of user's upload;
Memory module 22, for storing component design document into default storage region;
Sending module 23, for sending downloading notice to target professional user, so that target professional user designs component File is downloaded.
Further, further includes:
Module is obtained, for obtaining the file information corresponding with component design document, the file information includes element type;
Matching module, for being determined according to the mapping table of element type and professional user pre-established and component The corresponding target professional user of type, and trigger sending module.
Further, further includes:
Logging modle, for recording the upload number and download time of the component design document of the same element type;
Alarm module, for when download time and upload number it is inconsistent when issue alarm prompt.
Further, further includes:
Statistical module is currently submitted for the element type according to currently stored each component design document, statistics The number of components.
It should be noted that technological design progress interactive device provided in the present embodiment based on BIM have with it is upper The identical beneficial effect of technological design progress exchange method based on BIM provided in embodiment is stated, and for the present embodiment In specific introduce of the involved technological design progress exchange method based on BIM please refer to above-described embodiment, the application exists This is repeated no more.
On the basis of the above embodiments, the embodiment of the invention also provides a kind of, and the technological design progress based on BIM is handed over Mutual system, the system include:
Memory, for storing computer program;
Processor is realized when for executing computer program such as the above-mentioned technological design progress exchange method based on BIM Step.
For example, the processor in the present embodiment is for realizing the component design document for receiving user's upload;Component is designed File is stored into default storage region;Downloading notice is sent to target professional user, professional user sets component so as to target Meter file is downloaded.
On the basis of the above embodiments, the embodiment of the invention also provides a kind of computer readable storage mediums, calculate Computer program is stored on machine readable storage medium storing program for executing, when computer program is executed by processor realize as it is above-mentioned based on BIM The step of technological design progress exchange method.
The computer readable storage medium may include: USB flash disk, mobile hard disk, read-only memory (Read-OnlyMemory, ROM), random access memory (Random Access Memory, RAM), magnetic or disk etc. are various can store program The medium of code.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.For device disclosed in embodiment For, since it is corresponded to the methods disclosed in the examples, so being described relatively simple, related place is said referring to method part It is bright.
It should also be noted that, in the present specification, such as the terms "include", "comprise" or its any other variant meaning Covering non-exclusive inclusion, so that the process, method, article or equipment for including a series of elements not only includes that A little elements, but also including other elements that are not explicitly listed, or further include for this process, method, article or The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged Except there is also other identical elements in the process, method, article or apparatus that includes the element.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (10)

1. a kind of technological design progress exchange method based on BIM characterized by comprising
Receive the component design document that user uploads;
The component design document is stored into default storage region;
Downloading notice is sent to target professional user, so that the target professional user carries out down the component design document It carries.
2. the technological design progress exchange method according to claim 1 based on BIM, which is characterized in that in the transmission Before downloading notice to target professional user, further includes:
The file information corresponding with the component design document is obtained, the file information includes element type;
Mapping table according to the element type and professional user that pre-establish determines mesh corresponding with the element type Mark professional user.
3. the technological design progress exchange method according to claim 2 based on BIM, which is characterized in that further include:
Record the upload number and download time of the component design document of the same element type;
Alarm prompt is issued when the download time and the upload number are inconsistent.
4. the technological design progress exchange method according to claim 2 based on BIM, which is characterized in that further include:
According to the element type of currently stored each component design document, the number of components currently submitted is counted.
5. a kind of technological design progress interactive device based on BIM characterized by comprising
Receiving module, for receiving the component design document of user's upload;
Memory module, for storing the component design document into default storage region;
Sending module, for sending downloading notice to target professional user, so that the target professional user sets the component Meter file is downloaded.
6. the technological design progress interactive device according to claim 5 based on BIM, which is characterized in that further include:
Module is obtained, for obtaining the file information corresponding with the component design document, the file information includes component class Type;
Matching module, for being determined and the component according to the mapping table of the element type and professional user pre-established The corresponding target professional user of type, and trigger the sending module.
7. the technological design progress interactive device according to claim 6 based on BIM, which is characterized in that further include:
Logging modle, for recording the upload number and download time of the component design document of the same element type;
Alarm module, for issuing alarm prompt when the download time and the upload number are inconsistent.
8. the technological design progress interactive device according to claim 6 based on BIM, which is characterized in that further include:
Statistical module counts the component currently submitted for the element type according to currently stored each component design document Quantity.
9. a kind of technological design progress interactive system based on BIM characterized by comprising
Memory, for storing computer program;
Processor is realized as described in Claims 1-4 any one when for executing the computer program based on the work of BIM The step of skill design schedule exchange method.
10. a kind of computer readable storage medium, which is characterized in that be stored with computer on the computer readable storage medium Program is realized as described in Claims 1-4 any one when the computer program is executed by processor based on the technique of BIM The step of design schedule exchange method.
CN201910199380.9A 2019-03-15 2019-03-15 A kind of technological design progress exchange method, apparatus and system based on BIM Pending CN109948239A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910199380.9A CN109948239A (en) 2019-03-15 2019-03-15 A kind of technological design progress exchange method, apparatus and system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910199380.9A CN109948239A (en) 2019-03-15 2019-03-15 A kind of technological design progress exchange method, apparatus and system based on BIM

Publications (1)

Publication Number Publication Date
CN109948239A true CN109948239A (en) 2019-06-28

Family

ID=67010191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910199380.9A Pending CN109948239A (en) 2019-03-15 2019-03-15 A kind of technological design progress exchange method, apparatus and system based on BIM

Country Status (1)

Country Link
CN (1) CN109948239A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113077229A (en) * 2021-03-30 2021-07-06 贵州数智联云工程科技有限公司 Multi-party information interaction system and method based on BIM

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107644315A (en) * 2017-09-08 2018-01-30 泰州市抗震办公室(泰州市建设工程施工图设计审查中心) A kind of construction drawing joint review system
CN107846461A (en) * 2017-10-31 2018-03-27 广州市新誉工程咨询有限公司 File uploading method and management method and file designation method based on BIM models
CN108427696A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of acquisition methods and device of the design document based on BIM
CN108429781A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of file delivery method and file delivery system based on BIM
WO2018149373A1 (en) * 2017-02-16 2018-08-23 平安科技(深圳)有限公司 File interaction method and system, and terminal device and medium

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018149373A1 (en) * 2017-02-16 2018-08-23 平安科技(深圳)有限公司 File interaction method and system, and terminal device and medium
CN108427696A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of acquisition methods and device of the design document based on BIM
CN108429781A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of file delivery method and file delivery system based on BIM
CN107644315A (en) * 2017-09-08 2018-01-30 泰州市抗震办公室(泰州市建设工程施工图设计审查中心) A kind of construction drawing joint review system
CN107846461A (en) * 2017-10-31 2018-03-27 广州市新誉工程咨询有限公司 File uploading method and management method and file designation method based on BIM models

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113077229A (en) * 2021-03-30 2021-07-06 贵州数智联云工程科技有限公司 Multi-party information interaction system and method based on BIM
CN113077229B (en) * 2021-03-30 2024-04-30 贵州数智联云工程科技有限公司 Multiparty information interaction system and method based on BIM

Similar Documents

Publication Publication Date Title
CN105447174B (en) A kind of report generation method and device
CN110058856A (en) Page configuration method and device
CN105404507A (en) Process template construction method and system
EP3433732A1 (en) Converting visual diagrams into code
CN107491383A (en) Catching method, device and the mobile terminal of application crashes Operation Log
CN104267938B (en) A kind of method and device of the quick development deployment of the application of streaming computing
CN102368261A (en) Expandable running maintenance report generation method
CN109918435A (en) A kind of processing method and system of business interface
CN105095518B (en) A kind of data transfer device and device
CN110728123B (en) Report generation method, system and related equipment
CN103559323A (en) Database implementation method
CN110633331B (en) Method, system and related equipment for extracting data in relational database
CN107656729A (en) Updating device, method and the computer-readable recording medium of List View
CN109522324A (en) A kind of SQL scenario generation method, device and computer equipment
CN108984506A (en) A kind of generation method and device of configurable intelligent report forms
CN104281369A (en) Picture uploading processing method and device
CN108829653A (en) A kind of generation method of report, device, equipment and medium
CN104182436A (en) Method and device for cleaning databases
CN105404472A (en) Method and apparatus for compressing storage space of log time data
CN105653255A (en) Method arranging report template to automatically generate report files in office frame
CN105488210A (en) Batch data matching method and device
CN109948239A (en) A kind of technological design progress exchange method, apparatus and system based on BIM
CN106155719A (en) A kind of method and system utilizing USB device to realize openstack rapid deployment
CN109948238A (en) A kind of management method, device, system and the storage medium of assembled design document
CN107291746B (en) Method and equipment for storing and reading data

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190628

RJ01 Rejection of invention patent application after publication