CN109941933A - A kind of hoisting frame for workshop Pipe installing - Google Patents

A kind of hoisting frame for workshop Pipe installing Download PDF

Info

Publication number
CN109941933A
CN109941933A CN201910324920.1A CN201910324920A CN109941933A CN 109941933 A CN109941933 A CN 109941933A CN 201910324920 A CN201910324920 A CN 201910324920A CN 109941933 A CN109941933 A CN 109941933A
Authority
CN
China
Prior art keywords
frame body
main frame
hoisting
pipe installing
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910324920.1A
Other languages
Chinese (zh)
Inventor
杨杰
宗进营
常欢欢
文红宇
于朝辉
王岩
祝广龙
李彦稳
张保志
司永超
王卫生
邢瑞光
田雨
吴冰
安璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pingmei Shenma Construction and Engineering Group Co Ltd
Original Assignee
Pingmei Shenma Construction and Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pingmei Shenma Construction and Engineering Group Co Ltd filed Critical Pingmei Shenma Construction and Engineering Group Co Ltd
Priority to CN201910324920.1A priority Critical patent/CN109941933A/en
Publication of CN109941933A publication Critical patent/CN109941933A/en
Pending legal-status Critical Current

Links

Abstract

The present invention relates to Pipe installing operation auxiliary equipment technical fields, more particularly to a kind of hoisting frame for workshop Pipe installing, including main frame body, lift beam and hoisting mechanism, main frame body can be adjusted according to Working position, lift beam two sides at the top of frame body are arranged and can be adjusted according to working height, lift beam both ends are separately installed with a pulley blocks, the hinge rope of hand capstan is arranged across pulley blocks and the other end is connected with hook, lifting depth of beam is adjusted to adapt to working height, it adjusts to adjust pipeline to pre-installation height by hoisting mechanism and carries out installation connection, hoisting frame integrally has biggish weight and bearing capacity, it can guarantee the stability of work, there is very big help to the Pipe installing of the environment such as workshop.

Description

A kind of hoisting frame for workshop Pipe installing
Technical field
The present invention relates to Pipe installing operation auxiliary equipment technical fields, and in particular to a kind of for workshop Pipe installing Hoisting frame.
Background technique
General workshop, large-span industrial building, steel-structure factory building, garage, market, writes at the industrial premises of multilayer layer High variation The environment such as building and basement require the pipeline that installation sets up multiple use, especially fire protection pipeline, spray piping, due to not It is different with installation environment in structures, therefore can only be according to physical condition exact arrangement.At present in general pipe installation process, Usually artificial station adjustable shelf or ladder it is upper a segment pipe by the installation of one section of pipe fitting merogenesis later section, cannot whole section of pipe and The group on ground installs latter secondary property and is installed on bracket pipe fitting in batch, and this form of construction work speed is slower, to accelerate Speed of application then needs to increase adjustable shelf quantity, ladder quantity and artificial, and construction flexibility is weaker;When mounting height is excessively high, pipe Frame own wt increases, and difficulty of construction is opposite when erection will increase, and the labor intensity of each process also increases accordingly very much, and And during the installation process, forming the tube body of pipe support influences vulnerable to the unstable factors such as scratching, deform, and influences construction quality, brings Biggish security risk, therefore find one kind and can ensure construction quality, the technical method of progress and save the cost is extremely urgent.
Summary of the invention
To solve the above-mentioned problems, the present invention provides a kind of hoisting frames that pipeline is set up suitable for above-mentioned environment, including Main frame body, lift beam and hoisting mechanism, main frame body can be adjusted according to Working position, and lift beam two sides at the top of frame body are arranged And can be adjusted according to working height, lift beam both ends are separately installed with a pulley blocks, and the hinge rope of hand capstan is across cunning The setting of wheel group and the other end are connected with hook, and for adjusting lifting depth of beam to adapt to working height, being adjusted by hoisting mechanism will pipe Road adjusts to pre-installation height and carries out installation connection.
The present invention provides a kind of hoisting frame for workshop Pipe installing in order to solve the above problem, including main frame body, Lift beam and hoisting mechanism, the main frame body are cube shaped frame, including four vertical poles, four hyphen bars and two long transverse levers, Two long transverse levers and two hyphen bars connect into rectangle frame, and the upper portion pipe body of vertical pole is hollow and four vertical poles are respectively and vertically fixed at Four corners of rectangle frame, two hyphen bars, which respectively correspond, is fixed on vertical pole top;Construction platform, construction are equipped in the main frame body Platform is affixed with the body of rod of four vertical poles respectively for the quadrangle of horizontally disposed rectangular slab and platform of constructing, and main frame body front is equipped with and climbs Ladder, ladder top and the long side of construction platform are affixed, and ladder bottom end and a long transverse lever of main frame body bottom are affixed;The lift beam There are two and be separately mounted to the top two sides of main frame body, lift beam includes crossbeam and two adjustable interior bars, and adjustable interior bar is worn In vertical pole and its top is fixed on the body of rod of crossbeam, and the length of crossbeam is longer than greatly hyphen bar and crossbeam is parallel with hyphen bar, The both ends of crossbeam are separately installed with a hoisting mechanism, and the hoisting mechanism includes pulley blocks, hand capstan and hook, pulley Group is mounted on the end of crossbeam, and the vertical pole below pulley blocks installation place is equipped with hand capstan, and the hinge rope of hand capstan is across cunning The setting of wheel group and end and hook connect.
As a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention, the hollow space of the vertical pole The body of rod is spaced apart the bolt hole equipped with perforation along its length.
As a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention, the bottom four of the main frame body The adjustable rotary way roller of brake is provided at a angle.
As a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention, the side of the main frame body is solid It connects there are two reinforcing strip, two reinforcing strips fix as one in X-shaped to reinforce main frame body.
It is the vertical pole, long transverse lever, short as a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention Cross bar and adjustable interior bar are that coating steel pipe is made, and crossbeam and reinforcing strip are made of L shape angle bar.
As a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention, the manual hinge wheel is automatic The hand capstan of locking type.
As a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention, the hinge rope is 7*19 core 316 stainless steel wirerope.
As a kind of further scheme of the hoisting frame for workshop Pipe installing of the present invention, column is equipped at the top of the frame body Bar, railing is parallel with long transverse lever and both ends are connected to two vertical pole tops.
Beneficial effect
1, main frame body is cube shaped frame body, and horizontal construction platform is equipped in main frame body, is equipped with before main frame body and is used for worker The two sides of the ladder of construction platform, main frame body are equipped with lift beam, and lift beam includes crossbeam and two adjustable interior bars, and adjustable interior bar is worn It is equally spaced along its length on vertical pole to offer bolt hole, crossbeam in the upper section hollow lever of the vertical pole of composition main frame body It is set in parallel above main frame body by two adjustable interior bars and hyphen bar, is equipped in bolt hole and adjusts bolt, adjustable interior bar Bottom end in vertical pole, which is supported on, to be adjusted on bolt, adjusts the whole height of lift beam by adjusting bolt and bolt hole cooperation; Lift beam both ends are respectively provided with a pulley blocks, and the vertical pole below pulley blocks is equipped with matched hand capstan, hand capstan Hinge rope across pulley blocks setting and end be equipped with for riser tubing hook, the two sides of main frame body are equipped with a promotion Beam, the both ends of each lifting beam are equipped with a hoisting mechanism, according to Pipe installing direction and position, using the two of different directions Pipeline lift to mounting height is attached installation by a hoisting mechanism, is reduced the labor intensity of worker and is facilitated daily erector Make.
2, main frame body bottom is set there are four the adjustable polyurethane trundle of strap brake formula, and single brace has biggish load-bearing capacity, side Just the conversion of installation site, main frame body, lift beam are mainly made of coating steel pipe, and device integrally has stronger stability, hand Shaking capstan is the two-way anti-rotational hand capstan of automatic-locking type of 1200LBS type, guarantees the safety and stability of Pipeline lift, often A hook is suitable for the installation of the pipeline in a variety of directions, four sides of main frame body are equal by an individually hand capstan control Installation exercise can be individually carried out, the opposite side for carrying out installation exercise can hang weight to keep whole balance.
Detailed description of the invention
Fig. 1 is the forward sight structural schematic diagram of hoisting frame of the present invention;
Fig. 2 is the backsight structural representation of hoisting frame of the present invention;
Fig. 3 is the side structure schematic view of hoisting frame of the present invention;
Marked in the figure: 1, main frame body, 2, crossbeam, 3, vertical pole, 4, hyphen bar, 5, long transverse lever, 6, construction platform, 7, ladder, 8, adjustable Interior bar, 9, pulley blocks, 10, hand capstan, 11, hook, 12, adjustable rotary way roller, 13, reinforcing strip, 14, railing.
Specific embodiment
It is as shown in the figure: a kind of hoisting frame for workshop Pipe installing, including main frame body 1, lift beam and hoisting mechanism, it is main Frame body 1 includes that four vertical poles, 3, four hyphen bars 4 and two long transverse levers 5, two hyphen bars 4 are fixedly connected with two long transverse levers 5 For horizontal rectangle frame, four vertical poles 3 are respectively and vertically fixed at four corners of rectangle frame, the both ends of other two hyphen bar 4 Two 3 tops of vertical pole are separately connected, the both ends of railing 14 are respectively and fixedly connected to the top of two vertical poles 3 and railing 14 is located at main frame body The top at 1 back side, is equipped with the construction platform 6 for worker's installation exercise in main frame body 1, and the construction platform 6 is horizontally disposed with and four Angle is fixedly welded on respectively on the body of rod of four vertical poles 3, and 1 front of main frame body is equipped with the ladder 7 for platform 6 of constructing up and down, ladder 7 Upper and lower side connect respectively with construction platform 6 and long transverse lever 5, the two sides of main frame body 1 and back are respectively equipped with two reinforcing strips 13, two reinforcing strips 13 are in X-shaped cross-fixing, are connect with main frame body 1 and construction platform 6 to stablize main frame body 1 and the whole of platform 6 of constructing Body structure;1 bottom of main frame body is set there are four the adjustable rotary way roller 12 with brake, and preferably load-bearing capacity is stronger adjustable Polyurethane trundle, to adapt to working strength.
The top half body of rod of the vertical pole 3 is hollow, and hollow space equally spaced is provided with cross along the length direction of the body of rod To the bolt hole of perforation;Two lift beams are arranged in 1 top two sides of main frame body, and lift beam includes crossbeam 2 and two adjustable interior bars 8, two adjustable 8 activities of interior bar are threaded through in two vertical poles 3, and the crossbeam 2 is parallel with hyphen bar 4, are connect with adjusting crossbeam 2 Two adjustable interior bars 8 are threaded through the hollow space of vertical pole 3, are equipped with bolt, the bottom end branch of adjustable interior bar 8 in the bolt hole of vertical pole 3 Support is on bolt, and lifting depth of beam can be adjusted in the height and position by the way that bolt is arranged, and every one end of each crossbeam 2 is equal Equipped with a hoisting mechanism, hoisting mechanism includes pulley blocks 9, hand capstan 10 and hook 11, and pulley blocks 9 are mounted on crossbeam 2 End, hand capstan 10 is mounted on the lower section vertical pole 3 of 9 installation site of pulley blocks, and the pulley blocks 9 are single-wheel hanging-ring type H-type gin wheel, hand capstan 10 are the two-way anti-rotational hand capstan of automatic-locking type of 1200LBS type, the hinge of hand capstan 10 Rope is 316 stainless steel wirerope of 7*19 core, and the end for cutting with scissors rope passes through pulley blocks 9 and connect with hook 11.
The fast transfer to this programme hoisting frame can be facilitated by adjustable rotary way roller 12, worker is enterprising in construction platform 6 Row operation, for the height adjustment of face lift beam to adapt to different height job requirements, the people of lower section links up with tubing to be installed It is transported to mounting height after 11 fixations, top worker can install, and four hoisting mechanisms can control height respectively, to adapt to Different installation environments, the settable weight bearing in other side when unilateral side processes, prevent whole centre-of gravity shift;Main frame body 1 is mainly by galvanized steel Pipe is made, and the tubing of different tube diameters specification, lift beam and main frame body can be used according to 1 size of main frame body and applicable number 1 reinforcing strip 13 is made of the world L50 angle bar, and hoisting frame integrally has biggish weight and bearing capacity, can guarantee work Stability, there is very big help to the Pipe installings of the environment such as workshop.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification It is right according to the technical essence of the invention for the equivalent embodiment of equivalent variations, but without departing from the technical solutions of the present invention Any simple modification, equivalent change and modification made by above embodiments, all of which are still within the scope of the technical scheme of the invention.

Claims (8)

1. a kind of hoisting frame for workshop Pipe installing, it is characterised in that: including main frame body (1), lift beam and hoisting mechanism, The main frame body (1) is cube shaped frame, including four vertical poles (3), four hyphen bars (4) and two long transverse levers (5) are two long Cross bar (5) and two hyphen bars (4) connect into rectangle frame, and the upper portion pipe body of vertical pole (3) is hollow and four vertical poles (3) are respectively perpendicular Four corners of rectangle frame are fixed on, two hyphen bars (4), which respectively correspond, is fixed on vertical pole (3) top;In the main frame body (1) Equipped with construction platform (6), construction platform (6) be horizontally disposed rectangular slab and construct platform (6) quadrangle respectively with four vertical poles (3) The body of rod is affixed, and main frame body (1) front is equipped with ladder (7), and ladder (7) top and the long side of construction platform (6) are affixed, ladder (7) bottom It holds affixed with a long transverse lever (5) of main frame body (1) bottom;There are two the lift beams and is separately mounted to main frame body (1) Top two sides, lift beam include crossbeam (2) and two adjustable interior bars (8), and adjustable interior bar (8) is threaded through in vertical pole (3) and it is pushed up End is fixed on the body of rod of crossbeam (2), and the length of crossbeam (2) is longer than greatly hyphen bar (4) and crossbeam (2) is parallel with hyphen bar (4), The both ends of crossbeam (2) are separately installed with a hoisting mechanism, the hoisting mechanism include pulley blocks (9), hand capstan (10) with And hook (11), pulley blocks (9) are mounted on the end of crossbeam (2), the vertical pole (3) below pulley blocks (9) installation place is equipped with hand It shakes capstan (10), the hinge rope of hand capstan (10) is arranged across pulley blocks (9) and end is connect with hook (11).
2. a kind of hoisting frame for workshop Pipe installing as described in claim 1, it is characterised in that: the vertical pole (3) The hollow space body of rod is spaced apart the bolt hole equipped with perforation along its length.
3. a kind of hoisting frame for workshop Pipe installing as described in claim 1, it is characterised in that: the main frame body (1) The angle of bottom four at be provided with the adjustable rotary way roller (12) of brake.
4. a kind of hoisting frame for workshop Pipe installing as described in claim 1, it is characterised in that: the main frame body (1) Side it is affixed there are two reinforcing strip (13), two reinforcing strips (13) fix as one in X-shaped to reinforce main frame body (1).
5. a kind of hoisting frame for workshop Pipe installing as claimed in claim 4, it is characterised in that: the vertical pole (3), length Cross bar (5), hyphen bar (4) and adjustable interior bar (8) are that coating steel pipe is made, and crossbeam (2) and reinforcing strip (13) are by L shape angle bar It is made.
6. a kind of hoisting frame for workshop Pipe installing as described in claim 1, it is characterised in that: the manual hinge wheel is The hand capstan of automatic-locking type (10).
7. a kind of hoisting frame for workshop Pipe installing as described in claim 1, it is characterised in that: the hinge rope is 7*19 316 stainless steel wirerope of core.
8. a kind of hoisting frame for workshop Pipe installing as described in claim 1, it is characterised in that: set at the top of the frame body Have railing (14), railing (14) is parallel with long transverse lever (5) and both ends are connected to two vertical pole (3) tops.
CN201910324920.1A 2019-04-22 2019-04-22 A kind of hoisting frame for workshop Pipe installing Pending CN109941933A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910324920.1A CN109941933A (en) 2019-04-22 2019-04-22 A kind of hoisting frame for workshop Pipe installing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910324920.1A CN109941933A (en) 2019-04-22 2019-04-22 A kind of hoisting frame for workshop Pipe installing

Publications (1)

Publication Number Publication Date
CN109941933A true CN109941933A (en) 2019-06-28

Family

ID=67015802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910324920.1A Pending CN109941933A (en) 2019-04-22 2019-04-22 A kind of hoisting frame for workshop Pipe installing

Country Status (1)

Country Link
CN (1) CN109941933A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112828849A (en) * 2020-12-31 2021-05-25 云南交投公路建设第一工程有限公司 I-steel installation manipulator in tunnel
CN113503007A (en) * 2020-12-16 2021-10-15 中国建筑第二工程局有限公司 Operation platform for building wall construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203699789U (en) * 2014-03-07 2014-07-09 中建八局第一建设有限公司 Pipeline automatic lifting device
CN204675783U (en) * 2015-05-06 2015-09-30 国网河南禹州市供电公司 A kind of substation simple multifunctional tool car
CN108100896A (en) * 2017-12-27 2018-06-01 中国二十冶集团有限公司 A kind of Pipeline lift conveying device and method
DE202018003936U1 (en) * 2018-08-27 2018-09-11 Euroline Gmbh Podium ladder with central transport mechanism
KR200488597Y1 (en) * 2018-12-14 2019-02-26 김재일 Lifting apparatus for loading and unloading of plumbing
CN209989034U (en) * 2019-04-22 2020-01-24 平煤神马建工集团有限公司 A hoisting frame for factory building piping erection

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203699789U (en) * 2014-03-07 2014-07-09 中建八局第一建设有限公司 Pipeline automatic lifting device
CN204675783U (en) * 2015-05-06 2015-09-30 国网河南禹州市供电公司 A kind of substation simple multifunctional tool car
CN108100896A (en) * 2017-12-27 2018-06-01 中国二十冶集团有限公司 A kind of Pipeline lift conveying device and method
DE202018003936U1 (en) * 2018-08-27 2018-09-11 Euroline Gmbh Podium ladder with central transport mechanism
KR200488597Y1 (en) * 2018-12-14 2019-02-26 김재일 Lifting apparatus for loading and unloading of plumbing
CN209989034U (en) * 2019-04-22 2020-01-24 平煤神马建工集团有限公司 A hoisting frame for factory building piping erection

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113503007A (en) * 2020-12-16 2021-10-15 中国建筑第二工程局有限公司 Operation platform for building wall construction
CN112828849A (en) * 2020-12-31 2021-05-25 云南交投公路建设第一工程有限公司 I-steel installation manipulator in tunnel

Similar Documents

Publication Publication Date Title
CN107090968B (en) Lifting method of integrated attached lifting scaffold
CN105484502B (en) A kind of industrial premises steel structural roof purlin and support bar combined installation method
CN208792758U (en) A kind of huge column climbing apparatus
CN109941933A (en) A kind of hoisting frame for workshop Pipe installing
CN106193568A (en) Mobile steel truss operating platform
CN105781096B (en) A kind of safe Hanging Basket and its construction method for working at height
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN104674992A (en) Supporting method and structure of suspended steel bar truss deck
CN215803108U (en) Attached beam type hanging basket
CN214195484U (en) All-steel attached lifting scaffold
CN209989034U (en) A hoisting frame for factory building piping erection
CN106121252B (en) A kind of hydraulic stepping is from climbing material transfering device and method
CN211691525U (en) Construction device for overhanging type inclined curtain wall
CN108729644B (en) Suspension beam bracket and installation and use method thereof
CN2128653Y (en) Multi-function mutual rise and fall framing scaffold
CN2263161Y (en) Self-lifting scaffold
CN215829977U (en) A suspended door formula support for high altitude tower building vestibule fitment
CN116556666B (en) Construction method for special-part attached lifting scaffold
CN215558540U (en) Movable hanging basket
CN220080788U (en) Compensation system for attached part picking position of attached lifting scaffold
CN219118718U (en) Climbing frame horizontal protection
CN220014395U (en) Can have enough to meet need mounting bracket by intelligent integrated platform system bailey frame of equipping
CN217205242U (en) High altitude construction platform is used in building engineering construction
CN217897338U (en) Evaporate and press aerated concrete slab riser ware
CN220226207U (en) Anti-falling device for steel structure engineering construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination